TUGAS BESAR

ALAT BERAT
Dosen : Moch. Khamim, SST., MT.
NIP : 198407052012121002

Dikerjakan Oleh :
1. Ari Ifan Prasetyo (1731310070)
2. Ferian Saputra (1731310139)
3. Maulidya Annisa Paleky (1731310161)
4. Rosy Yulianto (1731310155)

JURUSAN TEKNIK SIPIL


POLITEKNIK NEGERI MALANG
2018

1
DAFTAR ISI

BAB I .................................................................................................................................. 3
DATA ALAT ..................................................................................................................... 3
1.1 Excavator Backhoe ..................................................................................................... 3
1.2 Dump Truck ................................................................................................................ 5
1.3 Bulldozer ...................................................................................................................... 7
1.4 Tabel Faktor konversi tanah...................................................................................... 9
1.5 Tabel. Efisiensi kerja ................................................................................................ 10
1.6 Volume Galian........................................................................................................... 10
BAB II .............................................................................................................................. 12
PERHITUNGAN ALAT BERAT .................................................................................. 12
2.1 Data Alat Berat ..................................................................................................... 12
2.1.1 Data Alat Penggali dan Pemuat ................................................................... 12
2.1.2 Data Alat Pengangkutan Material dan Pembuangan Tanah .................... 12
2.1.3 Data Alat Perata............................................................................................ 12
2.2 Hasil dan perhitungan .............................................................................................. 13
2.2.1 Data Pekerjaan Proyek .................................................................................. 13
2.3 Analisa Data ............................................................................................................. 13
2.4 Biaya penggunaan alat-alat berat per jam ................................................................ 17
2.5 Biaya yang harus dikeluarkan berdasarkan data perencanaan ................................ 18
2.6 Biaya yang harus dikeluarkan berdasarkan data realisasi di lapangan .................... 18
BAB III............................................................................................................................. 20
KESIMPULAN ............................................................................................................... 20

2
BAB I
DATA ALAT
1.1 Excavator Backhoe
No Uraian Kode Koefisien Satuan Keterangan
I BACKHOE
A Uraian Alat
1 Nama Alat Excavator Backhoe
2 Tipe Alat Komatsu PC 200-8
3 Kapasitas Bucket q1 0.97 m3
4 Status Alat Baik
5 Faktor Bucket K 0.7
6 Efisiensi Kerja E 0.75
7 Waktu Gali 9.2 Detik
8 Waktu Buang 7.2 Detik
9 Waktu Putar 5.8 Detik
B Produksi per siklus q 0.679 m3
C Waktu siklus cms 28 Detik
D Produksi per jam Q 65.475 m3 / jam
E Site out put per hari 523.8 m3 / hari alat bekerja 8 jam/hari
F Waktu kerja yang dibutuhkan 837 hari
G Jumlah alat yang dibutuhkan 3.5 unit
H Site out put per hari 4 unit backhoe 2095.2 m3 / hari
I Waktu kerja yang dibutuhkan 4 unit backhoe 209 hari
J Biaya penggunaan alat per jam
1 Biaya sewa alat 140000 Rp
2 Biaya Operator 18750 Rp
3 Biaya bahan bakar 180000 Rp 20liter/jam
4 Biaya minyak pelumas 36000 Rp 2liter/jam
biaya penggunaan backhoe per jam 374750 Rp
K Biaya berdasarkan data perencanaan
1 Biaya operasional per hari 2540000 Rp alat bekerja 8 jam/hari
2 Biaya operasional 300 hari 762000000 Rp perencanaan 300 hari
Biaya untuk 3 alat 2286000000 Rp alat yang digunakan 3 unit
L Biaya berdasarkan data real di lapangan
1 Biaya operasional per hari 2998000 Rp alat bekerja 8 jam/hari
2 Biaya operasional 209 hari 626582000 Rp perencanaan 209 hari
Biaya untuk 4 alat 2506328000 Rp alat yang digunakan 4 unit

Tabel Waktu gali (detik)

3
Kondisi Gali/Kedalaman
Ringan Sedang Agak sulit Sulit
Gali
0–2m 6 9 15 26
2–4m 7 11 17 28
4 – lebih 8 13 19 30

Tabel Waktu putar (detik)

Waktu
Sudut Putar Putar
45° – 90° 4–7
90° – 180° 5 8

Tabel Faktor bucket


Kondisi Pemuatan FAKTOR
Menggali dan memuat dari stockpile atau
material yang telah dikeruk oleh excavator
Ringan 0.8 – 1.0
lain, yang tidak membutuhkan gaya gali
dan dapat dimuat munjung dalam bucket.
Menggali dan memuat stockpile lepas dari
tanah yang lebih sulit untuk digali dan
Sedang 0.6 – 0.8
dikeruk tetapi dapat dimuat hamper
munjung.
Menggali dan memuat batu-batu pecah,
tanah liat yang keras, pasir campur kerikil,
tanah berpasir, tanah koloidal liat, tanah
Agak sulit liat dan tanah dengan kadar air tinggi yang 0.5 – 0.6
telah di stockpile oleh excavator lain. Sulit
untuk mengisi bucket dengan material
tersebut.
Bongkahan, batuan besar dengan bentuk
tak teratur dengan ruangan diantaranya
Sulit batuan hasil ledakan, batuan bundar, pasir 0.4 – 0.5
campur tanah liat, tanah liat yang sulit
dikeruk dengan bucket.

4
1.2 Dump Truck
No Uraian Kode Koefisien Satuan Keterangan
II DUMP TRUCK
A Uraian Alat
1 Nama Alat Dump Truck
2 Tipe Alat Hino FM 260 JD
3 Kapasitas Cd 20 m3
4 Status Alat baik
5 Kapasitas bucket q 0.97 m3
6 Faktor Bucket K 1
7 Cycle time backhoe cms 28 Detik
8 Efisiensi Kerja E 0.75
9 Jarak angkut dump truck D 500 m
10 Waktu pemuatan 18.33 menit
11 Waktu berangkat ke stockpile 7.5 menit
12 Waktu kembali 5.8 menit
13 Waktu buang 1.12 menit
14 Efisiensi Kerja
B Waktu Siklus cmt 32.75 menit
C Produksi per siklus q 20 m3
D Produksi per jam Q 27.48 m3 / jam
E Site out put per hari 219.85 m3 / hari alat bekerja 8 jam/hari
F Jumlah alat yang dibutuhkan 10 unit
G Biaya penggunaan alat per jam
1 Biaya sewa alat 162500 Rp
2 Biaya Operator 18750 Rp
3 Biaya bahan bakar 117000 Rp 13liter/jam
4 Biaya minyak pelumas 9000 Rp 0.5liter/jam
Biaya penggunaan dump truck per jam 307250 Rp
H Biaya berdasarkan data persencanaan
1 Biaya operasional per hari 2602000 Rp alat bekerja 8 jam/hari
2 Biaya operasional 300 hari 780600000 Rp perencanaan 300 hari
Biaya untuk 6 alat 4683600000 Rp alat yang digunakan 6 unit
I Biaya berdasarkan data real di lapangan
1 Biaya operasional per hari 2458000 Rp alat bekerja 8 jam/hari
2 Biaya operasional 209 hari 513722000 Rp perencanaan 209 hari
Biaya untuk 10 alat 5137220000 Rp alat yang digunakan 10 unit

5
Tabel Waktu muat dump truck

No. Waktu (menit)


1. 20,5
2. 18,6
3. 18,8
4. 19,3
5. 20,3
Rata-rata 18,33

Tabel Waktu berangkat dan kembali dump truck

Waktu (menit)
No. Berangkat Kembali
1. 7,2 5,7
2. 7,5 6,2
3. 7,2 5,9
4. 7,7 5,7
5. 7,9 5,9
Rata-rata 7,5 5,8

Tabel Waktu buang

No. Waktu (menit)


1. 1,1
2. 1,1
3. 1,2
4. 1,1
5. 1,1
Rata-rata 1,12

6
1.3 Bulldozer
No Uraian Kode Koefisien Satuan Keterangan
III BULLDOZER
A Uraian Alat
1 Nama Alat Bulldozer
2 Tipe Alat Komatsu D31P-20
3 Ukuran Blade L=2.875m ; H=0.7m ;
4 Status Alat baik
5 Faktor blade a 0.7
6 Efisiensi Kerja E 0.75
7 Jarak gusur D 50 m
8 Waktu penggusuran maju 1.8 menit
9 Waktu mundur 1.1 menit
10 Waktu ganti persneling 0.11 menit
11 Faktor konversi tanah clay 1.35
B Produksi per siklus q 0.986 m3
C Waktu siklus cm 3 menit
D Produksi per jam Q 19.90 m3 / jam
E Site out put per hari 159.22 m3 / hari alat bekerja 8 jam/hari
F Waktu kerja yang dibutuhkan 145 hari
G Biaya penggunaan alat per jam
1 Biaya sewa alat 140000 Rp
2 Biaya Operator 18750 Rp
3 Biaya bahan bakar 189000 Rp 21liter/jam
4 Biaya minyak pelumas 36000 Rp 2liter/jam
Biaya penggunaan bulldozzer per jam 383750 Rp
H Biaya berdasarkan data persencanaan
1 Biaya operasional per hari 2076400 Rp alat bekerja 8 jam/hari
2 Biaya operasional 150 hari 311460000 Rp perencanaan 150 hari
Biaya untuk 1 alat 311460000 Rp alat yang digunakan 1 unit
I Biaya berdasarkan data real di lapangan
1 Biaya operasional per hari 3070000 Rp alat bekerja 8 jam/hari
2 Biaya operasional 145 hari 445150000 Rp perencanaan 145 hari
Biaya untuk 1 alat 445150000 Rp alat yang digunakan 1 unit

7
Tabel Waktu ganti persnelling bulldozer

Mesin Waktu ganti persneling


Mesin gerak langsung
tongkat tunggal 0.10 menit
tongkat ganda 0.20 menit
Mesin-mesin torqflow 0.05 menit

Tabel Faktor blade

Derajat Penggusuran Faktor Blade

Penggusuran dapat dilaksanakan dengan


sudut penuh tanah lepas;
Ringan Kadar air rendah, tanah berpasir tak 0.9 – 1.1
dipadatkan, tanah biasa, bahan material
untuk timbunan persediaan (stockpile).

Tanah lepas, tetapi tidak mungkin


menggusur dengan sudut penuh;
Sedang 0.7 – 0.9
Tanah bercampur kerikil atau split, pasir,
batu pecah.

Kadar air tinggi dan tanah liat, pasir


Agak sulit bercampur kerikil, tanah liat yang sangat 0.6 – 0.7
kering dan tanah asli.

Batu-batu hasil ledakan, batu-batu


Sulit 0.4 – 0.6
berukuran besar

8
1.4 Tabel Faktor konversi tanah

KONDISI TANAH YANG DIKERJAKAN

JENIS MATERIAL KONDISI KONDISI KONDISI KONDISI


AWAL ASLI LEPAS PADAT
(A) 1.00 1.11 0.95
(B) 0.90 1.00 0.86
Sand/Tanah Pasir (C) 1.05 1.17 1.00
(A) 1.00 1.25 0.90
(B) 0.80 1.00 0.72
Sand Clay/Tanah Biasa (C) 1.11 1.39 1.00
(A) 1.00 1.35 0.90
(B) 0.70 1.00 0.63
Clay/Tanah Liat (C) 1.11 1.59 1.00
(A) 1.00 1.18 1.08
(B) 0.85 1.00 0.91
Tanah Campur Kerikil (C) 0.93 1.09 1.00
(A) 1.00 1.13 1.03
(B) 0.88 1.00 0.91
Kerikil (C) 0.97 1.10 1.00
(A) 1.00 1.42 1.29
(B) 0.70 1.00 0.91
Kerikil Kasar (C) 0.77 1.10 1.00
(A) 1.00 1.65 1.22
Pecahan Cadas atau (B) 0.61 1.00 0.74
Batuan Lunak (C) 0.82 1.35 1.00
(A) 1.00 1.70 1.31
Pecahan Granit atau (B) 0.59 1.00 0.77
Batuan Keras (C) 0.76 1.30 1.00
(A) 1.00 1.75 1.40
(B) 0.57 1.00 0.80
Pecahan Batu (C) 0.71 1.24 1.00
(A) 1.00 1.80 1.30
(B) 0.56 1.00 0.72
Batuan Hasil Ledakan (C) 0.77 1.38 1.00

9
1.5 Tabel. Efisiensi kerja
Kondisi Operasi Alat Baik Sekali Baik Sedang Buruk Buruk Sekali

Baik Sekali 0.83 0.81 0.76 0.70 0.63


Baik 0.78 0.75 0.71 0.65 0.60
Sedang 0.72 0.69 0.65 0.60 0.54
Buruk 0.63 0.61 0.57 0.52 0.45
Buruk Sekali 0.52 0.50 0.47 0.42 0.32

1.6 Volume Galian


Luas Rata-
Area Jarak(m) Luas(m2) Volume
rata (m2)
1 2 3 4 5=2x4

STA 0+000 812,07

50 1046,8 26170,11

STA 0+050 1281,53

50 1362,06 34051,5

STA 0+100 1442,58

50 1434,5 35862,62

STA 0+150 1426,43

50 1268,77 31719,18

STA 0+200 1111,11

50 1117,98 27949,45

STA 0+250 1124,85

50 577,05 14426,24

STA 0+300 29,25

50 14,63 365,66

STA 0+350 0

50 63,91 1597,78

STA 0+400 127,82

50 516,13 12903,35

STA 0+450 904,45

10
50 1057,43 26435,72

STA 0+500 1210,41

50 1312,08 32802,12

STA 0+550 1413,76

50 1493,11 37327,81

STA 0+600 1572,47

50 1554,77 38869,28

STA 0+650 1537,07

50 1506,3 37657,39

STA 0+700 1475,52

50 1392,77 34819,34

STA 0+750 1310,03

50 1130,61 28265,33

STA 0+800 951,2

50 582,67 14566,69

STA 0+850 214,14

50 114,47 2861,68

STA 0+900 14,79

Total Galian 438651,23

11
BAB II
PERHITUNGAN ALAT BERAT

2.1 Data Alat Berat


Pada pelaksanaan pekerjaan jalan, digunakan alat-alat yang mendukung
pelaksanaan pekerjaan tesebut, meliputi :
2.1.1 Data Alat Penggali dan Pemuat
Untuk pekerjaan penggalian dan pemuatan material tanah digunakan alat
berat excavator, digunakan data sebagai berikut :
- Tipe alat : Excavator PC 200-8
- Merk alat : Komatsu
- Tahun alat : 2014
2.1.2 Data Alat Pengangkutan Material dan Pembuangan Tanah
Pekerjaan pengangkutan material maupun pembuangan tanah dibutuhkan
alat yang dapat menampung material dan pengangkutnya. Untuk menghitung
jumlah produksi per-jam dari dump truck yang melakukan pekerjaan secara terus
menerus digunakan data sebagai berikut:
- Tipe alat : dump truck FM 260 JD
- Merk alat : Hino
- Tahun alat : 2014
- Kapasitas dump truck : 20 m³
2.1.3 Data Alat Perata
Untuk mengerjakan perataan tanah maupun pembuangan tanah
dipakai alat bulldozer. Untuk menghitung jumlah produksi per-jam dari
bulldozer yang melakukan pekerjaan secara terus menerus digunakan data
sebagai berikut:
- Tipe alat : bulldozer D31P-20
- Merk alat : komatsu
- Tahun alat : 2014
- ukuran blade : H : 0,70 m L : 2,875 m

12
- Data teknis di lapangan:
1. Waktu maju : 1,8 menit
2. Waktu mundur : 1,1 menit
3. Waktu ganti persneling : 0,11 menit
2.2 Hasil dan perhitungan
2.2.1 Data Pekerjaan Proyek
Pada pelaksanaan proyek pembangunan ruas jalan Lingkar Pulau Marsela
yang berlokasi di Provinsi Maluku di peroleh data sebagai berikut :
a) Volume tanah galian : 438.651,23 m3
b) Volume timbunan : 23.042,26 m3
c) Waktu pelaksanaan : 300 hari kerja kalender
d) Jam kerja/hari : 8 jam/hari
e) Jenis tanah : Clay/tanah liat
2.3 Analisa Data
A. Backhoe
o Nama alat = Backhoe
o Tipe alat = Komatsu PC 200-8
o Kapasitas bucket (q1) = 0,97 m3
o Status alat = Baik Faktor bucket (K) = 0,7(Tabel)
o Efisiensi kerja (E) = 0,75(Tabel)
o Waktu gali = 9,2 detik(Tabel)
o Waktu buang = 7,2 detik (Tabel)
o Waktu putar = 5,8 detik (Tabel)

1) Produksi per siklus


q = q1 × K
q = 0,97 × 0,7 = 0,68 m3

2) Waktu siklus
Cms = waktu gali + (waktu putar × 2) + waktu buang
Cms = 9,2 + (11,6) + 7,2 = 28 detik

13
3) Produksi per jam
𝑄 = 𝑞×3600×𝐸 𝐶𝑚
𝑄 = 0,68×3600×0,75 28 = 65,571 𝑚3/𝑗𝑎𝑚

4) Site out put per hari


Dalam satu hari alat bekerja selama 8 jam
= 8 × 65,571 = 524,57 m3/hari

5) Waktu kerja yang dibutuhkan


= 𝑉𝑜𝑙𝑢𝑚𝑒 𝑔𝑎𝑙𝑖𝑎𝑛 𝑡𝑎𝑛𝑎ℎ 𝑃𝑟𝑜𝑑𝑢𝑘𝑠𝑖 𝑝𝑒𝑟ℎ𝑎𝑟𝑖
= 438651,23 524,57 = 837 hari
6) Jumlah alat yang dibutuhkan = 𝑤𝑎𝑘𝑡𝑢 𝑘𝑒𝑟𝑗𝑎 𝑦𝑎𝑛𝑔 𝑑𝑖𝑏𝑢𝑡𝑢ℎ𝑘𝑎𝑛 𝑊𝑎𝑘𝑡𝑢
𝑝𝑒𝑙𝑎𝑘𝑠𝑎𝑛𝑎𝑎𝑛
= 837 hari 240 hari
= 3,48 ≈ 4 unit

7) Site out put per hari 4 unit backhoe


1 unit backhoe = 524,57 m3/hari
4 unit backhoe = 4 × 524,57 = 2098,28 m3/hari

8) Waktu kerja yang dibutuhkan 4 unit backhoe


= 𝑉𝑜𝑙𝑢𝑚𝑒 𝑔𝑎𝑙𝑖𝑎𝑛 𝑡𝑎𝑛𝑎ℎ 𝑃𝑟𝑜𝑑𝑢𝑘𝑠𝑖 𝑝𝑒𝑟ℎ𝑎𝑟𝑖
= 438651,23 2098,28 = 209 hari

14
B. Dump truck
o Nama alat = Dump truck
o Tipe alat = Hino FM 260 JD
o Kapasitas (Cd) = 20 m3
o Status alat = Baik
o Kapsitas bucket backhoe (q1) = 0,97 m3
o Faktor bucket (K) = 1
o Cycle time backhoe (Cms) = 28 detik
o Jarak angkut dump truck (D) = 500 m
o Waktu pemuatan = 18,33 menit (Tabel)
o Waktu berangkat ke stockpile = 7,5 menit (Tabel)
o Waktu buang = 1,12 menit (Tabel)
o Efisiensi Kerja (E) = 0,75 (Tabel)

1) Waktu Siklus (Cmt)


Cmt = Waktu pemuatan + Waktu berangkat ke stockpile + Waktu buang + waktu
kembali
18,33 + 7,5 + 1,12 + 5,8 = 32,75 menit

2) Produksi per siklus


q = Cd × K
Program Studi Teknik Sipil, Fakultas Teknik - Unpak 10
q = 20 × 1 = 20 m3

3) Produksi per jam


𝑄 = 𝑞 × 60 × 𝐸 𝐶𝑚𝑡
𝑄 = 20 × 60 × 0,75 32,75
= 27,48 m3/jam

4) Site out put per hari


Dalam satu hari alat bekerja selama 8 jam
= 8 × 27,48 = 219,84 m3/hari

15
5) Jumlah dump truck yang dibutuhkan
= 𝑠𝑖𝑡𝑒 𝑜𝑢𝑡 𝑝𝑢𝑡 𝑝𝑒𝑟 ℎ𝑎𝑟𝑖𝑏𝑎𝑐𝑘ℎ𝑜𝑒 𝑠𝑖𝑡𝑒 𝑜𝑢𝑡 𝑝𝑢𝑡 𝑝𝑒𝑟 ℎ𝑎𝑟𝑖 𝑑𝑢𝑚𝑝 𝑡𝑟𝑢𝑐𝑘
= 2098,28 219,84 = 9,4 ≈ 10 unit

C. Bulldozer
o Nama alat = Bulldozer
o Tipe alat = Komatsu D31P-20
o Ukuran blade = L = 2,875 m ; H = 0,7 m
o Status alat = Baik Faktor blade (a) = 0,7(Tabel)
o Efisiensi kerja (E)= 0,75 (Tabel)
o Jarak gusur (D) = 50 m
o Waktu penggusuran (maju) = 1,8 menit (Tabel)
o Waktu mundur = 1,1 menit (Tabel)
o Waktu ganti persneling (Z) = 0,11 menit (Tabel)
o Faktor konversi tanah clay = 1,35 (Tabel)

1) Produksi per siklus


𝑞 = 𝐿 ×𝐻2 ×𝑎
= 2,875×0,72 ×0,7 = 0,986 m3

2) Waktu siklus
Cm = Waktu penggusuran (maju) + Waktu mundur + Waktu ganti persneling
Cm = 1,8 + 1,1 + 0,11 = 3 menit

3) Produksi per jam


𝑄 = 𝑞 × 60 ×𝐸 ×𝑓𝑎𝑘𝑡𝑜𝑟 𝑘𝑜𝑛𝑣𝑒𝑟𝑠𝑖 𝑡𝑎𝑛𝑎ℎ 𝐶𝑚
= 0,986 × 60 ×0,75 ×1,35 3 = 19,96 m3/jam

4) Site out put per hari


Dalam satu hari alat bekerja selama 8 jam
= 8 × 19,967 = 159,73 m3/hari

16
5) Waktu kerja yang dibutuhkan
= 𝑉𝑜𝑙𝑢𝑚𝑒 𝑡𝑖𝑚𝑏𝑢𝑛𝑎𝑛 𝑡𝑎𝑛𝑎ℎ 𝑆𝑖𝑡𝑒 𝑜𝑢𝑡 𝑝𝑢𝑡 𝑝𝑒𝑟 ℎ𝑎𝑟𝑖
= 23042,26 159,73 = 144,2 ≈ 145 hari

2.4 Biaya penggunaan alat-alat berat per jam


A. Backhoe
Biaya sewa alat = Rp. 140.000,00/jam
Biaya operator = Rp. 18.750,00/jam
Biaya bahan bakar 20 Liter/jam × Rp. 9.000,00 = Rp. 180.000,00/jam
Biaya minyak pelumas 2 Liter/jam × Rp. 18.000,00 = Rp. 36.000,00/jam

Biaya penggunaan backhoe perjam adalah (Biaya sewa alat + Biaya operator +
Biaya bahan bakar + Biaya minyak pelumas) = Rp. 374.750,00/jam

B. Dump truck
Biaya sewa alat = Rp. 162.500,00/jam
Biaya operator = Rp. 18.750,00/jam
Biaya bahan bakar 13 Liter/jam × Rp. 9.000,00 = Rp. 117.000,00/jam
Biaya minyak pelumas 0,5 Liter/jam × Rp. 18.000,00 = Rp. 9.000,00/jam
Program Studi Teknik Sipil, Fakultas Teknik - Unpak 11

Biaya penggunaan backhoe perjam adalah (Biaya sewa alat + Biaya operator +
Biaya bahan bakar + Biaya minyak pelumas) = Rp. 307.250,00/jam

C. Bulldozer

Biaya sewa alat = Rp. 140.000,00/jam


Biaya operator = Rp. 18.750,00/jam
Biaya bahan bakar 21 Liter/jam × Rp. 9.000,00 = Rp. 189.000,00/jam
Biaya minyak pelumas 2 Liter/jam × Rp. 18.000,00 = Rp. 36.000,00/jam

17
Biaya penggunaan backhoe perjam adalah (Biaya sewa alat + Biaya operator +
Biaya bahan bakar + Biaya minyak pelumas) = Rp. 383.750,00/jam

2.5 Biaya yang harus dikeluarkan berdasarkan data perencanaan

a. Backhoe

Biaya operasional per hari Rp. 317.500,00 × 8 = Rp. 2.650.000,00 Biaya


operasional 300 hari Rp. 2.650.000,00 × 300 = Rp. 762.000.000,00 Alat yang
digunakan 3 unit Rp. 762.000.000,00 × 3 = Rp. 2.286.000.000,00

b. Dump truck

Biaya operasional per hari Rp. 325.250,00 × 8 = Rp. 2.602.000,00 Biaya


operasional 300 hari Rp. 2.602.000,00 × 300 = Rp. 780.600.000,00 Alat yang
digunakan 6 unit
Rp. 780.600.000,00 × 6 = Rp. 4.683.600.000,00

c. Bulldozer

Biaya operasional per hari Rp. 259.550,00 × 8 = Rp. 2.076.400,00 Biaya


operasional 150 hari Rp. 2.076.400,00 × 150 = Rp. 311.460.000,00 Alat yang
digunakan 1 unit Rp. 311.460.000,00 × 1 = Rp. 311.460.000,00

2.6 Biaya yang harus dikeluarkan berdasarkan data realisasi di lapangan

a. Backhoe

Biaya operasional per hari Rp. 374.750,00 × 8 = Rp. 2.998.000,00 Biaya


operasional 209 hari Rp. 2.998.000,00 × 209 = Rp. 626.582.000,00 Alat yang
digunakan 4 unit Rp. 626.582.000,00 × 4 = Rp. 2.506.328.000,00

18
b. Dump truck

Biaya operasional per hari Rp. 307.250,00 × 8 = Rp. 2.458.000,00 Biaya


operasional 209 hari Rp. 2.458.000,00 × 209 = Rp. 513.722.000,00 Alat yang
digunakan 6 unit Rp. 513.722.000,00 × 10 = Rp. 5.137.220.000,00

c. Bulldozer

Biaya operasional per hari Rp. 383.750,00 × 8 = Rp. 3.070.000,00 Biaya


operasional 145 hari Rp. 3.070.000,00 × 145 = Rp. 445.150.000,00 Alat yang
digunakan 1 unit Rp. 445.150.000,00 × 1 = Rp. 445.150.000,00
Program Studi Teknik Sipil, Fakultas Teknik - Unpak 12

19
BAB III
KESIMPULAN

Hasil dari perbandingan antara perhitungan perencanaan dan realisasi di


lapangan diperoleh 3 unit backhoe, 6 unit dump truck, 1 unit bulldozer pada
perhitungan perencanaan. Sedangkan realisasi di lapangan diperoleh 4 unit
backhoe, 10 unit dump truck, 1 unit bulldozer. Ditinjau dari waktu pelaksanaan
pemakaian alat berat backhoe dan dump truck dari 300 hari menjadi 209 hari lebih
cepat 91 hari, sedangkan bulldozer dari 150 hari menjadi 145 hari lebih cepat 5 hari.
Selisih biaya pemakaian alat antara perhitungan perencanaan dan realisasi di
lapangan Rp. 8.088.698.000,00 – Rp. 7.281.060.000,00 = Rp. 807.638.000,00.
Biaya pada saat di lapangan lebih boros Rp. 807.638.000,00 karena jumlah alat
berat yang tidak sesuai perencanaan, tetapi dari segi waktu pelaksanaan menjadi
lebih cepat.