Project description The Environmental and Social Impact Assessment (ESIA) Report

has been prepared for the Project Remediation Activities on Coal


Elektroprivreda Crne Gore (EPCG) developed the Project of and Ash Disposal Facility Pljevlja following legal requirements of
remediation and reclamation activities of the coal and ash Montenegrin legislation as well as requirements of the World Bank
disposal facility in Pljevlja, which will contribute to improving Safeguard Policies.
the quality of environment in the area surrounding the thermal
power plant (TPP) Pljevlja. Implementation of the Project will The Project was the subject to previous public consultation during
ensure proper disposal and management of ash and slag in the the EIA procedure in accordance with national legislation and
upcoming period, and i t will also contribute to an increase in consultation activities have been conducted in developing the
efficiency of operation of the TPP Pljevlja. ESIA.

The remediation a n d r e c l a m a t i o n of the Cassette II This public consultation meeting is being organized in order to
a n d r elocation/diversion of the Paleški Stream is formu- inform public and different stakeholders including the population
lated as a “ Project” that will be financed by the funds obtained that would be potentially affected by the Project and to get
from the World Bank and the ESIA Report is mainly prepared comments and opinions on the Project and on the draft ESIA
for these two activities. The other elements ( r e m e d i a t i o n o f Report. ESIA Report can be viewed on the website:
the Cassette I, construction and remediation of the www.rio.org.me
C a s s e t t e I I I a n d c l o s i n g t h e M a l j e v a c l a n d f i l l ) will be
financed from the EPCG’s individual sources of financing
All the comments received during the public consultation will be
and are considered as associated activities in the ESIA Report
documented and addressed in the ESIA report including minutes
and approached accordingly for assessing the impacts.
with questions and answers from the public hearing.

Project components Remediation Activities


Contact details
1. Remediation of the Cassette II on Coal and Ash
By closing Cassette II , technical and biological reclamation and
landscaping of green areas are foreseen aiming to prevent ash
dispersion, to control pollution of surface runoff and to restoring Address: Disposal Facility Pljevlja
the damaged ecosystem.
Nature and Environmental Protection Agency
2. Relocation/diversion of the Paleski Stream
PIU for the RIO Project
For preventing further pollution of Paleški Stream caused by Podgorica, IV proleterske 19
drainage water from the ash and slag landfill, it is planned to
relocate the Paleški stream riverbed. Spring water and atmos- E-mail:
pheric water from this basin would be transported to the
Borovičko Lake as clean water through a n adequate channel of
epamontenegro@gmail.com PUBLIC CONSULTATION MEETING
1876m, with associated culverts and water containers for the almina.bucan@epa.org.me
cattle.
Phone: for the draft of ESIA Report
+382 20 446 527

Protective Administration building of


layer on the Thermo-power plant “Pljevlja”
edge of the
www.rio.org.me January 15 2019 at 12 p.m.
Cassette II
Potential Impacts of the Project Summary of the Impact Assessment and Mitigation Measures Summary of Monitoring Activities
A large amount of ash and slag has been disposed at the Maljevac Issue Mitigation Measures Issue Parameter to be Monitored
Landfill for decades. The Project is aiming at the continued Land Use/
Slopes of embankments will be landscaped and planted.
Erosion control measures will be taken in all areas of works Erosion and
operation and reclamation of the Maljevac Landfill in phases in a Erosion
Landslide Slopes and relevant signs
against erosion risks.
sustainable and environmentally sound way. The Project provides Driving of machinery within surface waterbodies will be prevented. Risk
technical solutions for reducing, and where possible eliminating, Surface and
Maintenance, refuel, and construction machinery cleaning will be
the negative impacts of the landfill on the environment such as carried out at dedicated locations with proper containment and Surface Water
Ground Water quality parameters (sampling and analysis) as
drainage. and
relocation of Paleski stream and closure and remediation of water
Oil and fuel will be stored in places with secondary containment. Groundwater
required in relevant legislation
Resources
Cassette II, which would decrease the air, water and soil pollution Site specific emergency plans will be prepared to respond any
in the surrounding area. incidents and spillages. Number of spill/leakage incidents and corrective
Topsoil will be removed, stored, and handled in such a manner measures taken in accordance with national and
that it would be used during finishing works. Soil
international standards and soil quality parameters
Potential Area of Influence (AoI) Non-controlled and unplanned access road openings will be
(analysis) as required in relevant legislation
prevented.
Soil Quality
AoI of the Project includes the geographical area that potential im- Drainage channels will be constructed.
Air Quality Dust and PM 10
Operational plans for winter maintenance would be developed.
pacts of the Project could extend to. The AoI for physical and Soil quality will be monitored during operation stage including Noise Working hours and Noise levels (dB)
biological environment includes the Project footprint of the Cassette II control of the top soil in the village Gradac Donji.
reclamation area, the upstream and downstream of the Paleški Working sites will be frequently watered in land preparation and Waste Waste management plan, records and temporary
construction phase. Management waste storage areas
Stream and the new stream bed route reaching to the Borovičko Temporary spoil storage areas will be positioned not to be
Lake. In terms of the socioeconomic environment, the AoI in- Air Quality vulnerable to wind erosion. Landscape Related grievances records
cludes the close-by settlements mainly Zbljevo and Podrogatac EPCG will designate a liaison staff, in case of complaints related
with air quality that could be received from the neighborhood Flora and
as well as Pljevlja as the main settlement unit in the area. Survey for flora and fauna species
settlements. Fauna
Construction will be limited to day-hours (07:00-19:00).
Noise Socio- Having alternative access to the parcels close to the
Natural acoustic barriers and screens will be used.
Benefits from the Realization of the Project: Systematic collection of solid waste during construction and economy construction site, and related grievances records
Decreasing historical pollution - air, water, land Waste operation phases will be undertaken and wastes will be disposed
Generation at licensed facilities specified by national authorities or handed HS records (on accidents, employment, training)
Improved air quality over to a company authorized to collect the subject waste. Workers/ emergency preparedness plan, personnel
Preparation of a landscape restoration plan in line with the Occupational grievances, and periodical ESMP performance
Eliminating surface water pollution remediation design for Cassette II including the realistic Health and review and monitoring reports, existence and validity
Landscape requirements to minimize short term visual intrusion from the site
Safety of the legal environmental and health and safety
Remediation of the part of degraded land operations and to maximize the long term recovery potential of the
landscape. permits,
Increasing process security Clearing up and removal of vegetation will be minimized to the
extent necessary for the execution of works.
Achieving acceptable levels of discharge Measures will be taken to prevent animal deaths in the project Traffic Traffic management plan, selected route and time for
area and on access roads. transport of material
Ecosystem / Checks and photographic recording for germination success of
Flora and planted areas and for natural regeneration/vegetation will identify
Fauna locations and areas of disturbance, successes and failures.
Technical measures, such as fencing and intermediate cover, will
be taken to prevent the entrance of fauna to the landfill site.
Passages over the new Paleski Stream bed would be
formed/allowed as appropriate for the fauna species.
Land acquisition will be done in a manner which ensures
transparency and accountability, and which ensures that
compensation is paid in accordance to the law in force.
Relocation Socio- Appropriate disclosure of information, consultation, and the
economy informed participation of affected persons and community will be
implemented.
Mosaic
of Procurement of the land has been started on 'willing buyer/willing
seller' basis. EPCG has developed a Resettlement Action Plan. Distribution
Cultural Contractor will follow the national requirements with respect to
Paleski "chance finds" which may emerge during construction.
heritage
of Herbal
EPCG and the contractor of works are jointly responsible with
Stream regard to workers health and safety. This would include both
Occupation/ management measures and reporting and investigating any Culture on the
Works incidents, i.e. Implement international HSE standards in all
Health and contracts.
Safety A Health and Safety Management Plan would be developed as Cassette II
well as undertaking training programmes, inspections and
reward/penalty schemes to enforce safe working practices.
An Emergency Action Plan will be developed in line with the
Emergency emergency plan and procedures of the EPCG for the situations
Situations including fire, earthquake, flood and drought.