Anda di halaman 1dari 18

Energy Conversion and Management 144 (2017) 322–339

Contents lists available at ScienceDirect

Energy Conversion and Management


journal homepage: www.elsevier.com/locate/enconman

Performance analysis of hybrid PV/diesel/battery system using HOMER:


A case study Sabah, Malaysia
Laith M. Halabi a,⇑, Saad Mekhilef a,⇑, Lanre Olatomiwa b, James Hazelton c
a
Power Electronics and Renewable Energy Research Laboratory (PEARL), Department of Electrical Engineering, Faculty of Engineering, University of Malaya, 50603 Kuala
Lumpur, Malaysia
b
Department of Electrical & Electronic Engineering, Federal University of Technology, PMB 65, Minna, Nigeria
c
School of Photovoltaics and Renewable Energy Engineering, University of New South Wales, Sydney, NSW 2052, Australia

a r t i c l e i n f o a b s t r a c t

Article history: This study considered two decentralized power stations in Sabah, Malaysia; each contains different com-
Received 9 November 2016 bination of photovoltaic (PV), diesel generators, system converters, and storage batteries. The work was
Received in revised form 4 April 2017 built upon previous related site surveys and data collections from each site. Verification of the site data
Accepted 22 April 2017
sets, simulation of different operational scenarios, and a comparison with the optimum design were all
Available online 2 May 2017
considered in the work. This includes all possible standalone diesel generators, hybrid PV/diesel/battery,
and 100% PV/battery scenarios for the proposed stations. HOMER software has been used in the modeling
Keywords:
entire systems. The operational behaviors of different PV penetration levels were analyzed to accurately
Hybrid system
Rural electrification
quantify the impact of PV integration. The performance of these stations was analyzed based on technical,
Fuel saving economic and environmental constraints, besides, placing emphasis on comparative cost analysis
HOMER between different operational scenarios. The results satisfied the load demand with the minimum total
Malaysia net present cost (NPC) and levelized cost of energy (LCOE). Moreover, sensitivity analysis was carried
out to represents the effects of changing main parameters, such as; fuel, PV, battery prices, and load
demand (load growth) on the system performance. Comparison of all operational behaviors scenarios
was carried out to elucidate the advantages/disadvantages of utilizing each scenario. The impact of dif-
ferent PV penetration levels on the system performance and the generation of harmful emissions is also
investigated. The results show more trends towards using renewable energy (RE) sources in energy gen-
eration and less dependence on standalone diesel generators. Hybrid PV/Diesel/Battery system is seen to
be the best technical performance compared to all other scenarios, while also reporting good economic
and environmental performance, which result in increased system sustainability. The 100% RE system
showed the best environmental characteristics with the highest costs. This study has demonstrated that
the presence of RE sources improves the performance of standalone systems and reduces energy storage
requirements.
Ó 2017 Elsevier Ltd. All rights reserved.

1. Introduction in various regions that have limited or no electricity access. In such


places, RE sources are considered a suitable solution for rural elec-
Out of all renewable energy (RE) technologies that can be used trification. This type of energy generation could play an important
in decentralized applications, solar energy has the widest applica- role in energy provision. Where the presence of electrical energy
tions in electricity generation. It provides reliable and low cost of access positively influences the human development index (HDI)
energy when employed in remote areas [1]. It also enhances local [3], a strong relation links the national energy consumptions and
development by creating new jobs and training opportunities. Fur- the gross national product (GDP) because electricity is a key
thermore, its environmental friendliness enhanced it is applicabil- requirement for societies’ development over economic, education,
ity [2]. This technology offers greater potential for developing and health sectors [4]. For example, in Malaysia, a certain portion
countries, where a significant percentage of the population lives of the population lives below the poverty line, this is mostly found
in remote places of Sabah and Sarawak, with poverty levels 67.05%
and 66.91%, respectively [5]. Malaysia has a good potential of solar
⇑ Corresponding authors.
energy, due to the abundance of solar radiation averaging
E-mail addresses: l.halabi@outlook.com (L.M. Halabi), saad@um.edu.my
(S. Mekhilef). 4.8–6.1 kW h/m2/day. Based on this, solar energy has always been

http://dx.doi.org/10.1016/j.enconman.2017.04.070
0196-8904/Ó 2017 Elsevier Ltd. All rights reserved.
L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339 323

considered as a sensible approach to sustainable green energy in Several literature have reported optimum systems of different
Malaysia [6,7]. Malaysia has lots of remote areas that are located hybrid combinations such as PV/Wind/Diesel/Battery systems
away from the main grid and, surrounded by rugged terrains and [18–21]. Meanwhile, PV systems had showed lower cost, and is
dense jungles. Grid extension through these remote locations is more applicable compared to wind turbines [22]. Hybrid PV/Diesel
not considered feasible or economical at present. Standalone diesel systems for rural electrification was recommended in most studies
generators are commonly used to provide electricity for these [7,8,16–18,23]. Some studies have discussed the optimized design-
areas [8,9]. Meanwhile, in a study carried out to investigate the ing methods of hybrid systems using different optimization soft-
potential of hybrid RE systems in various rural areas in Malaysia, ware such as HOMER and several other optimization algorithms
indicated high potential of RE (solar and micro-hydropower including artificial neural networks (ANN), differential evolution
resources) in electricity generation [10]. (DE), and particle swarm optimization (PSO) for assessments of
The Malaysian government adopted the National Energy Policy suitable sizing and appropriate operating strategies for different
in 1979 to achieve three primary objectives; adequacy of supply, configuration [24–30].
efficient utilization, and mitigating environmental effects. In Rehman and Al-Hadhrami [31] presented a study on PV/diesel
1981, the fossil fuel diversification strategy was introduced to hybrid power system with battery backup for a village in Saudi
reduce over dependence on oil, mainly in the power generation Arabia. The proposed hybrid system seems to be more favorable,
sector. This policy was aimed to provide a mix supply of natural especially when there is an increase in fuel price. In [32], a study
gas, hydropower, oil, and coal. It has drastically minimized oil conducted in Palestine indicated that utilizing PV/diesel hybrid
dependence from almost 90% in 1980, to less than 15% in 2000 system in remote locations is more economically feasible than
[11]. RE in Malaysia was introduced in 8th Malaysia Plan (8MP; standalone diesel generators or grid extension. Some studies have
2001–2005), where it expanded the Malaysian strategy towards also evaluated the techno-economic feasibility and potential of uti-
considering RE as the fifth source of power generation. The 8MP lization different hybrid system configurations in remote places
was originally intended to yield 5% (600 MW) of the country’s elec- [33–37]. Based on this fact, hybrid RE systems was considered a
tricity demand with RE by 2005, but only two plants with total promising technology and has the tendency to reduce environmen-
capacities of 12 MW were subsequently commissioned. Later, the tal pollution, and improve system stability while simultaneously
9th Malaysia Plan (9MP; 2006–2010) was intended to produce reducing the overall system cost. Up to date, many studies were
300 MW in Peninsular Malaysia and 50 MW in Sabah by 2010, performed to find the optimum solution for proposed projects
while energy efficiency was the focus of the 10th Malaysia Plan based on different methods. A study was carried out to find the
(10MP; 2011–2015) [12]. Malaysia aims to attain 2000 MW of RE cost benefits of standalone solar/battery/diesel in different part
production by 2020. The Malaysian Government is endorsing RE of the world using Geographic Information System (GIS) software
usage, especially in power generation throughout its comprehen- [38]. The result finds hybrid PV/battery/diesel reduced the leve-
sive policies and wide social support. This comes about as the lized cost of energy (LCOE) than standalone diesel generators in
country plans to be one of the leading RE producing countries in many regions. Another study analyzed the potential of hybrid solar
the world by 2020 [12,13]. Meanwhile, according to recent study and wind energy system in Saudi Arabia using HOMER and
[14], oil and natural gas are the most used sources for generating MATLAB software [39]. The results have found PV system generate
electrical energy with 87.4% from the total production. On the more and cheaper energy compared to wind turbine of the same
other hand, renewable energy penetrates only 9.4% from the total size. Besides, indicating the need for more reliable system would
production, despite the high availability of renewable energy result in increasing the overall system cost. Moreover, a study
resources in Malaysia. Whereas, hydropower shares 8.7% versus was performed in Egypt to examine the feasibility of introducing
all other renewable energy sources (such as solar and wind Fuel Cell (FC) in energy system along with PV, wind turbines, and
resources) as shown in Fig. 1. battery banks. Six different combinations where employed and
Currently, total replacement of conventional diesel generators tested using HOMER software and were compared to gird exten-
by RE sources in rural/remote communities is unfeasible due to sion solution. The results have found that hybrid system of PV/FC
unstable nature of RE resources [15,16]. Renewable and conven- offers the best LCOE and Net Present Cost (NPC) over all possible
tional hybrid energy systems could be a suitable solution to pro- solutions including grid extension and wind/battery systems. Dif-
vide the best in each system [16]. However, in designing of ferent surveys of about 800 samples were reported to measure
hybrid RE system several factors such as social, institutional, and the user’s willingness to pay in residential and commercial sectors
technical need to be consider in order to obtain the desired results as shown in [40–42]. Among all of the scenarios, higher willingness
otherwise, the system would be unreliable and inefficient [17]. to pay was found toward RE sources, particularly when it can dis-
place the need of diesel gensets completely in both sectors. Gener-
ally, users show greater satisfaction for better energy services
(such as fewer blackouts) and are found to be more willing to
pay for reliable RE sources [22].
Based on the above literature, it can be seen that most studies in
this field have been established to find the optimal deign, examine
the potential or investigate the techno-economic feasibility based
on different factors and comparison analysis for typical hybrid sys-
tems. Generally, these studies have shown hybrid systems offering
higher level of reliability as well as lower LCOE compared to single
source energy. However, analyzing the operational behavior of
hybrid systems once it is built and commissioned has not been
taken into consideration in previous studies, despite the high
importance associated with such practical evaluation. Therefore,
this research study and analyze the performance metrics of PV/
Diesel/Battery hybrid system in two locations; Pulau Banggi Island
and Tanjung Labian, Sabah, Malaysia. System evaluation is carried
Fig. 1. Electricity generation share from several sources in Malaysia [14] out based on technical, economical and environmental factors as
324 L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339

well as modeling of all possible scenarios that contain different obtained (NASA) could be employed in the event of unavailability
combinations. Within the study, a comparative analysis with the of sufficient measured data in the desired locations [45].
optimum design was performed to clarify whether the size of the Monthly solar radiation data for both locations is generally in
PV systems was optimally selected prior installations in both loca- the range of 4.41–6.65 kW h/m2/day, with an annual average of
tions. In addition to this, an examined hypothetical scenario using 5.43 and 5.57 kW h/m2/day for Pulau Banggi and Tanjung Labian,
100% RE generation were investigated. The results obtained were respectively.
compared to standalone diesel generator and existing hybrid PV/
diesel/battery systems to accurately quantify the impact of PV 2.2.2. Temperature
injection into the mini-grid in the considered communities. Finally, The NASA temperature data was also used in this work as
a conclusion on the findings and a summary of advantages and dis- shown in Fig. 3. The obtained data for both locations is generally
advantages of each system is presented. This study is expected to in the range of (25.64–27.38) °C with an annual average of
be very useful in decision making in any area with similar condi- 26.8 °C and 26.3 °C in Pulau Banggi and Tanjung Labian respec-
tions. All technical works in this study were accomplished using tively. However, it can be seen in some literature that the used of
HOMER software. artificial intelligence to predict ambient temperature by using
the direct relation between solar irradiation and temperature is
2. Methodology possible and could be employed as a proper solution for future
works [46–48].
In RE projects, successful evaluation requires appropriate crite-
ria to be applied on site data in order to correctly analyze the oper- 2.2.3. Load demand
ational behavior of all possible scenarios. The following analysis In rural areas, the majority of residents spend most of their time
framework were employed in this study: outside their homes for work purposes. At noon, increase in loads
can be observed, as some family members usually come home for
I. Site specification. lunch and other activities. However, maximum demand takes
II. Derivation and verification of modeled data sets. place at night, when the entire family is at home. Demand profiles
a. Solar energy were constructed using 2014 load data sets collected during the
b. Temperature site visits described in [43]. It was found that due to communica-
c. Load demand tion errors in measuring equipment, service interruptions and con-
III. System analysis and operational performance impact. tinuing load growth in these new energy access sites is prevalent.
Therefore, the datasets had to be modified to give a more accurate
The collected data from each site was illustrated and investi- representation of community demand for the modeled period.
gated under these criteria. Each were discussed and analyzed to Firstly, erroneous data points were identified – these could be as
describe the entire system. a result of communications and computation errors in the SCADA
system or incorrect equipment calibration. Filters were used to
eliminate values seems unreasonable (less than 10 kW and more
2.1. Site specifications
than 900 kW) before establishing the average profiles as shown
in Fig. 4.
Sabah, the second largest state in Malaysia, has an area that
To derive the demand input datasets in the models, the mea-
spans of about 72,500 km2. Sabah is located in the eastern part of
sured data also needed to be used to estimates data in months with
Malaysia, and is generally made up of mountainous hills with
no available data. This presented some challenges. Firstly, as differ-
dense jungles, hosting a diverse array of plant and animals, coupled
ent seasons will affect demand, there are some difficulties in
with an extensive network of river valleys. This study considered
approximating a full year based on size, therefore, monthly data
two stations in specific locations in Sabah named Pulau Banggi
would have to be done for Pulau Banggi site. Secondly, the sites
Island and Tanjung Labian. The general description for both loca-
were experiencing significant monthly load growth as new cus-
tions have been showed in a previous study [43]. The first location,
tomers receive access via expanding distribution lines. To account
Pulau Banggi is the third largest island in Malaysia, located on the
for these, a temperature dependent regression model was used to
northern coast of Sabah at a latitude 7.25°N/117.16667°E. Its main
take into account of the seasonal variation. From the measured
sources of income are agriculture, fishery, and tourism. Tanjung
datasets, the relationship between daily peak load and daily peak
Labian on the other hand is a small area located on the eastern side
temperature were correlated. Temperature variations for the
of Sabah, at a latitude 5.10°N/119.13°E, where major sources of
remaining months were taken from Section 2.2.2 and the average
income are timber, tourism, and seafood exports.
load scaled accordingly. Load growth was considered by taking
the most recent month as a baseline, then scaling this based on
2.2. Derivation and verification of modeled data sets sensitivity analysis in HOMER. The reduced loads at weekends
were accounted for by using the measured data sets and compar-
Site’s surveys described in [43] were carried out on both loca- ing peak and average load values. The resulting baseline cases for
tions to collect the required measured data for each site. It includes weekdays and weekends are shown in Fig. 5.
solar radiation, ambient temperature, and load profile data. In Once average load datasets were inputted into the model, vari-
order to assess system performance, real-time measurements of ability must be introduced using HOMER’s time step variability and
solar irradiation and ambient temperature data is needed. Unfortu- day to day variability functions. Appropriate values of these were
nately, the measured data was limited due to faulty sensors and determined to be 10.88% and 7.48%, respectively, in Pulau Banggi
measuring tools. To overcome these challenges, data obtained from and 14.22% and 16.26%, respectively, in Tanjung Labian.
National Aeronautics and Space Administration (NASA) [44] was
used as shown in the following sections. 2.3. System components

2.2.1. Solar resource Both stations were implemented in two phases and each con-
Solar radiation data obtained from NASA’s website [44] is sists of several components (PV arrays, batteries, converters and
shown in Fig. 2. Based on literature, satellite-based data such as diesel generation system) [43]. Pulau Banggi Island was commis-
L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339 325

Fig. 2. Solar irradiation comparison: (a) Pulau Banggi. (b) Tanjung Labian.

sioned in February 2014 and expected to serve about 1200 houses. 2.3.2. PV module
On the other hand, Tanjung Labian was commissioned in Novem- PV system is employed to supply electrical power during the
ber 2012 and expected to serve about 800 houses. Table 1 summa- day from 7 am to 7 pm ± 20 min, when there is sunshine, other-
rizes all components of each system in both locations. wise, the diesel generators or battery banks take the role to supply
A brief description of the system parameters and components the load. In this study, all specifications are shown in Table 2,
used in each location are presented as follows. where the capital cost and replacement costs of the PV, in addition
to a small maintenance cost of 10 $/year was considered to be 2000
$/kWp [50].
2.3.1. Diesel generators
Diesel generators are usually employed to meet the peak
2.3.3. Converter
demand, mainly when there is no output from the PV panels
Converters’ size is compatible with the PV arrays size to ensure
[49]. Capital and replacement costs in this study were regarded
full supply of PV power. Capital and replacement cost of the con-
to be 220 $/kW and 200 $/kW respectively, where the maintenance
verter are 890 $/kW and 800 $/kW, respectively, while 10 $/year
cost was 0.030 $/h [50] all specifications are shown in Table 2. The
is marked for maintenance. The operational lifetime was consid-
price of diesel depends on the location of each site, 2.9 RM/L in
ered to be 15 years [50].
Tanjung Labian and 3.3 RM/L in Pulau Banggi. In such rural areas,
fuel price could be more than 1.5 times the normal price because
of the high cost of fuel transportation and storage problems [51]. 2.3.4. Battery energy storage
However, the fuel prices in both locations are equal to 0.7 $/L Fiamm type batteries is employed in both sites (Pulau Banggi
and 0.8 $/L, respectively (according to an exchange rate of and Tanjung Labian). Each cell is made up of 2 V, and connected
$1 = RM4.08). as follows:
326 L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339

Fig. 3. Measured and NASA temperature comparison (a) Pulau Banggi. (b) Tanjung Labian.

I. In Pulau Banggi: Four strings, each string with a capacity of the batteries in the CC strategy. LF strategy seems to be the optimal
1500 A h and contains 240 units. strategy, as it helps to reduce excess energy and the total NPC [52],
II. In Tanjung Labian: Six strings, each string with a capacity of hence it is considered in this analysis. However, the flowchart
1500 A h and contains 240 units. The battery’s prices were shown in Fig. 6 illustrates the system operational behavior in var-
taken according to the local market of 1200 $/unit for capital ious cases of supplying the loads by the PV, diesel generators, and
cost and 1170 $/unit for replacement, where all specifica- batteries, in addition to the batteries charging cycles. According to
tions are shown in Table 2. Fig. 6, an overall energy management system is needed to control
the flow of energy, where the system operates in different modes
3. Operating strategies according to the surrounding atmospheric conditions. At normal
operating conditions, where the sun is available, the control sys-
There are two main operating strategies employed in the hybrid tem gives the PV arrays the highest priority to supply the loads.
RE systems, namely Load Following (LF) and Cycle Charging (CC) Meanwhile, in the case of excess energy the system will charge
dispatch strategies. In LF strategy, diesel generators are configured the battery, until it is fully charged (100% SOC), where any further
to supply the loads only in the event of unavailability of PV power excess energy can be used by dumped loads. In case of insufficient
output, while the PV arrays supply the load and charges the batter- energy from the PV system, the battery will supply the loads until
ies in the event of excess electricity. On the other hand, diesel gen- the minimum state of charge (40% SOC) is reached, then the con-
erators are used to meet loads demand and simultaneously charge ventional diesel generators will supply the loads. The decision of
L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339 327

Fig. 4. Measured average load profiles (a) Pulau Banggi. (b) Tanjung Labian.

the control system to operate any of the energy sources and charg- hypothetical standalone RE scenario (100% PV/Battery) systems
ing/ discharging the battery takes place every hour based on the were presented and discussed. Also included is the result of the
energy balance computation. sensitivity study applied to examine the effects of changes in fuel
The operating reserve is described by HOMER as the reliable cost, PV cost, battery prices and demand growth over the years.
amount of power that should supply if the RE supply suddenly Hybrid optimization model for electric renewable (HOMER)
decreased or the load demand suddenly increased. In this study, software were used in the simulation [53]. This entails establishing
the operating reserve values were set to 10% of hourly loads and a reference case as the first step, followed by the determination of
25% of solar output, while, the renewable fraction represents the operational behaviors of existing and hypothetical systems based
fraction of the energy delivered to the load which produced from on economical, technical, and environmental constraints. Fig. 7
renewable power sources. HOMER calculates the renewable frac- shows the existing system in both stations implemented by
tion as: HOMER. The results for each station analysis is presented sepa-
  rately in Sections 4.1 and 4.2.
Enon-ren þ Hnon-ren
RF ¼ 1   100% ð1Þ
Eserv ed þ Hserv ed
4.1. Pulau Banggi Island
where Enon-ren , Hnon-ren are respectively the electrical and thermal
energy produced by non-renewable energy sources (kW h/yr), while 4.1.1. Standalone diesel system (Baseline model)
Eserv ed , Hserv ed are the total served electrical and thermal loads This scenario was simulated based on the existing PV/Diesel/
(kW h/yr), respectively. Meanwhile, the renewable energy produc- Battery hybrid model using the available data. This is needed to
tion represents the total amount of electrical energy produced annu- accurately quantify the impact of injecting PV on NPC, LCOE, fuel
ally by the renewable energy components of the power system. consumption, running hours and other characteristics. Both electri-
cal penetration and diesel generator operation seems to be directly
4. Results influenced using PV and batteries.
In this site, the system depended on the largest generators (both
In this section, the results of technical, economical and environ- 400 kW) to deliver over 95% of the total energy production, as
mental analysis for different system configurations including stan- shown in Table 3. The LCOE is 0.276 $/kW h and NPC is
dalone diesel generators, existing hybrid PV/Diesel/Battery and $8,545,703 which is the lowest cost of energy compared to all
328 L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339

Fig. 5. Average load profiles (a) Weekdays. (b) Weekend.

Table 1
Summary of installed equipment.

PV hybrid station No. of connected houses Solar photovoltaic Diesel genset Battery bank
kWp Brand kW Brand kW h Brand
Pulau Banggi Phase 1 1200 200 Mitsubishi 2  200, 1  250 Cummins 720 Fiamm
Pulau Banggi Phase 2 1000 Mitsubishi 2  400 Caterpillar 2160 Fiamm
Tanjung Labian phase 1 800 700 Mitsubishi 2  500, 1  350 Cummins 4320 Fiamm
Tanjung Labian phase 2 500 Mitsubishi – – – –

Table 2
Technical parameters for system components.

Equipment Factor Value Equipment Factor Value


PV Rated power (kWp) 1200 Converter Rated power (kW) 1200
Temperature co-efficient (°C) 0.5 Lifetime (Years) 15
Derating factor (%) 80 Rectifier efficiency (%) 85
Operation temperature (°C) 47 Inverter efficiency (%) 90
Lifetime (Years) 25 Diesel generators Rated power (kW) 350, 400 & 500
Efficiency (%) 13 Load minimum ratio (%) 30
Nominal capacity (A h/Cell) 1500 Minimum running hours (h) 30,000
Battery Nominal capacity (kW h/Cell) 3
Nominal voltage (V/Cell) 2 Rated power (kW) 200 & 250
Lifetime per battery (Years) 7
Round trip efficiency (%) 80 Minimum running hours (h) 15,000

other scenarios using similar operating conditions of fuel and com- period are $319,000, $239,453, $1,428,387, $6,595,138, $643,548
ponent prices. The systems’ capital, replacement, operation and and $36,270 respectively, with 0% renewable penetration and
maintenance, fuel, operational and salvage costs over the project excess energy.
L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339 329

Fig. 6. Flowchart of system operation in various scenarios.

4.1.2. Existing hybrid PV/diesel with batteries $499,681 and $212,349 respectively, over the project period and
This scenario represents the existing system in both locations. It 50.4% renewable fraction was found with 9.3% of excess energy.
shows the advantages of including PV arrays in improving the sys-
tem performance in both sites. This scenario does not provide the 4.1.3. Optimized hybrid PV/diesel/batteries
best economical system in HOMER, but performed better in terms This scenario was performed to examine whether the existing
of technical and environmentally aspects, as well as lowest operat- hybrid PV/diesel/batteries scenario were optimally selected in both
ing cost. This system demonstrates the need of including storage locations prior to installation or not. The results of the optimized
system (batteries) to store excess energy from the PV. This scenario system in this location are shown in Table 3. The results showed
shows the effects of using PV/batteries in power generation. The the optimal selection for the PV, diesel generators, and battery
main operational characteristics is shown in Table 3. In this case, banks. The LCOE is 0.302 $/kW h and NPC is $ 9, 345,510, which
the system mainly depends on PV to produce 59.21% of the total are lower than the existing system by 0.064 $/kW h and
production, while the largest generators (400 kW) produce around $1,981,092 respectively with two strings of 1440 kW h batteries.
37%, while all other smaller generators provide only 3.54%. The However, the systems’ capital, replacement, operation and mainte-
LCOE is 0.366 $/kW h and NPC is $11,326,602, which is around nance, fuel, operational and salvage costs over the project period
1.5 times larger than the previous system. The systems’ capital, are $2,492,600, $1,098,347, $1,059,902, $4,772,016, $536,081 and
replacement, operation and maintenance, fuel, operational and sal- $77,351 respectively, with 34.8% renewable fraction and 6.2% of
vage costs were $4,939,000, $2,054,044, $1,179,342, $3,366,568, excess energy. As a consequence, it is clear that the optimum solu-
330 L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339

Fig. 7. Existing hybrid system in both location implemented in HOMER (a) Pulau Banggi. (b) Tanjung Labian.

Table 3
System operational behavior (Pulau Banggi).

Component Rated capacity (kW) Production (%) Running hours (h/yr) Fuel consumption (L/yr)
Standalone diesel generator
G1 400 48.75 4,314 309,142
G2 400 48.44 4,344 307,430
G3 250 2.04 672 19,715
G4 200 0.4 240 4406
G5 200 0.39 227 4201
Total 1450 100 9797 644,894
Hybrid PV/Diesel/Batteries
PV 1200 59.21 – –
G1 400 18.65 1950 143,342
G2 400 18.60 1976 143,137
G3 250 1.39 672 171,86
G4 200 1.13 575 134,26
G5 200 1.02 509 121,04
Total 2650 100 5682 329,195
Optimized Hybrid PV/Diesel/Batteries
PV 800 42.38 – –
G1 200 16.53 2367 115,769
G2 200 18.38 2756 129,098
G3 100 13.15 5339 122,562
G4 80 4.11 5314 46,275
G5 50 5.45 5736 52,920
Total 1430 100 21,512 466,624

tion system trends to depend more on the diesel generators com- price is dut to the high battery replacement costs. Meanwhile,
pared to the existing hybrid system, which results in a higher fuel the excess energy is 29.2% of the total production, with no capacity
consumption and operational cost. shortage found.

4.1.4. 100% PV and batteries (hypothetical model) 4.2. Tanjung Labian


Initiating this scenario required dramatic increment over the
rated values of PV and the batteries. As the existing rated capacity 4.2.1. Standalone diesel system (baseline model)
of the PV arrays in this site is 1200 kW and 4 strings batteries, The main operational characteristics of this scenario are shown
which consist of 960 battery cells and provides 2880 kW h. How- in Table 4. The system depends on the largest generators (both
ever, the optimum 100% renewable fraction system comes with 500 kW) to produce 78.55% of total energy production. The other
3000 kWp PV arrays and 50 strings batteries, which consist of generator acts as backup generator and works normally in the
12,000 battery cells and provide 36,000 kW h. The LCOE is 1.36 low loads period. The LCOE is 0. 3303 $/kW h and NPC is
$/kW h and NPC is $42,140,180 which is four times larger than $5,902,414 which is the lowest cost compared to all other scenar-
standalone diesel generators system and two times more than ios based on similar operating conditions. The systems’ capital,
existing hybrid PV/diesel/battery system. The systems’ capital, replacement, operation and maintenance, Fuel, operational and
replacement, operation and maintenance, operational and salvage salvage costs over the project lifetime (25 years) are $297,000,
costs over the project period are $21,468,000, $20,077,838, $309,371, $1,518,548, $3,806,995, $438,493 and $29,498 respec-
$, $2,070,905, $1,617,117 and $1,476,548 respectively. This high tively, with 0% renewable penetration but a small amount of excess
L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339 331

Table 4
System operational behavior (Tanjung Labian).

Component Rated capacity (kW) Production (%) Running hours (h/yr) Fuel consumption (L/yr)
Standalone diesel generator
G1 500 38.55 2938 152,634
G2 500 40.00 3020 158,178
G3 350 21.45 2802 114,628
Total 1350 100 8760 425,440
Hybrid PV/Diesel/Batteries
PV 1200 86.90 – –
G1 500 4.66 511 26,849
G2 500 4.76 516 27,368
G3 350 3.68 878 30,249
Total 2550 100 1905 84,466
Optimized Hybrid PV/Diesel/Batteries
PV 400 39.89 – –
G1 250 27.23 2510 107,062
G2 250 27.52 2480 108,007
G3 200 5.36 1877 33,238
Total 1100 100 6867 248,307

energy was observed, representing 1% of the total energy tional and salvage costs over the project period are $11,580,000,
production. $9,845,661, $1,119,823, $799,318 and $747,514 respectively, with
33.2% excess energy.
4.2.2. Existing hybrid PV/diesel with batteries
The main characteristics is shown in Table 4. In this case, PV 4.3. Sensitivity analysis
arrays produce 86.90% of the total energy production, where the
largest generators (500 kW) produced only 9.42% and the smaller Sensitivity analysis was performed to investigate the effects the
generators provide only 3.68%. The LCOE is 0.5352 $/kW h and changes in some factors such as; fuel price, PV cost, battery costs
NPC is $9,563,989 which is about two times more than standalone and load demand growth will have on the system performance.
diesel generator system. The systems’ capital, replacement, opera- In this study, the fuel price increased in a range from the current
tion and maintenance, fuel, operational and salvage costs over the price (0.7 $/L) until 3.3 $/L. The load demand growth was consid-
project period are $5,493,000, $2,787,715, $805,659, $755,828, ered 5% per year, while the cost of the PV and batteries opposed
$318,460 and $278,210 respectively. The PV arrays provide 80.7% to cost variation as a portion of the total initial cost in a range start-
of the renewable fraction while 17.4% of excess energy was ing from the current price to 60%. Diesel prices are expected to
observed in this scenario. increase and the current technological development would lead
to decrease PV and battery prices, as well as more utilization of
4.2.3. Optimized hybrid PV/diesel/batteries new electrical devices would increase the future loads. The results
The results of the optimized system in this location are shown of the sensitivity analysis in both sites are presented Figs. 8–11.
in Table 4. The optimal selection of PV, diesel generators and bat-
tery banks are found in lower rated values, where the LCOE was 4.3.1. Pulau Banggi Island
0.3118 $/kW h and NPC is $ 5, 571,168, which are lower than the In this location, it is seen from the comparison of Fig. 8 and
existing system by 0.2234 $/kW h and $3,992,821 respectively, Fig. 9 that the effects of increasing the load demand and fuel price
with two strings of 1440 kW h batteries. However, the systems’ would result in more dependence on the hybrid PV/diesel/battery
capital, replacement, operation and maintenance, fuel, operational system. Decreasing PV and battery prices have the highest impact
and salvage costs over the project period are $1,708,000, $978,872, on reducing the dependence on the standalone diesel generator
$760,444, $2,221,939, $302,203 and $98,085 respectively with systems and depending more on hybrid RE systems (PV has more
35.7% renewable fraction and 0.3% excess energy. It is clear that impact due to higher capital cost).
the optimum system shows a distinguished difference in the over-
all costs compared to the existing hybrid system, this occurred due 4.3.2. Tanjung Labian
to lower batteries, PV and diesel generators sizes. Figs. 10 and 11 show the effects of increasing the load demand
and fuel price on the operational behavior. This increment leads to
4.2.4. 100% PV and batteries (hypothetical model) more dependence on the hybrid system. In the same manner,
This scenario has been developed to examine the advantages/ decreasing PV and battery prices reduce the dependence on the
disadvantages of considering 100% RE system with different RE standalone diesel generators as well.
fractions in both locations based on the available data. The existing
rated capacity of PV arrays in this site is 1200 kW and 6 strings bat- 4.4. Storage system – batteries
teries, which consist of 1440 battery cells and provide 4320 kW h.
However, HOMER found the optimum 100% renewable fraction Battery roles in hybrid renewable energy system needs to the
system required an increment of the rated PV values and associ- highlighted, as it is usually charged at daytime and discharges at
ated batteries to be 1800 kW PV and 24 strings batteries, which the beginning of the night, where the loads dramatically increased.
consist of 5760 battery cells and provide 17,280 kW h. The LCOE The appearance of the batteries enhanced the system performance
is 1.22 $/kW h, and NPC is $21,797,966 making this system four in both locations. The battery state of charge (SOC) procedure in
times larger than standalone diesel generator system and around Pulau Banggi and Tanjung Labian are shown in Fig. 12. The lifetime
two times more than the existing hybrid PV/battery system. The of each battery is considered to be 7 years and the battery’s SOC
systems’ capital, replacement, operation and maintenance, opera- should be at least 40%, according to manufacturer specifications.
332 L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339

Fig. 8. Pulau Banggi sensitivity with fixed PV and Battery prices.

Fig. 9. Pulau Banggi sensitivity with varied PV and Battery prices.

However, the maximum loads occur between May and August. 4.5. Estimating reduction in fuel consumption and generators running
During this period, the batteries would have the minimum charg- hours
ing and maximum discharging limits.
The storage system is a very important towards ensuring sys- The analyzed data provide a clear idea about fuel consumption
tem stability, without which leads to large amount of excess and its related costs. Utilization of the hybrid system resulted in
energy. This energy is often regarded as losses, which could affect almost 49% and 80% fuel saving in Pulau Banggi and Tanjung
the operational behavior of the system. However, in both locations, Labian respectively. While, the utilization of 100% PV/battery sys-
the amount of excess energy was determined to be 9.3% in Pulau tem resulted in 100% fuel saving in both locations. However, from
Banggi and 17.4% in Tanjung Labian. 0% excess energy can only the sensitivity analysis, the system seems to relied more on the
be achieved by feeding the generated power to national grid in a hybrid scenario when fuel price and load growth is increased and
grid-connected system. On the other hand, in the 100% PV/ battery, components prices decrease as shown in Fig. 8 and 10 for both
the system totally relies on the battery banks to provide energy locations. This led to the fact that a 100% PV/Battery system would
when PV is unavailable. The SOC performance showed a higher be more feasible in the future in the case of increasing fuel prices,
range of charging cycles as shown in Fig. 13. load demand, and reducing in both PV and battery costs.
L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339 333

Fig. 10. Tanjung Labian sensitivity with fixed PV and Battery cost.

Fig. 11. Tanjung Labian sensitivity with varied PV and Battery cost.

Furthermore, the simulation has shown that decreasing the manufacturers recommended that their product to work at least
running hours of the generators could lead to minimizing the 30–40% of the rated power. In the same manner, Tanjung Labian
dependence on the larger generators, thereby reducing the wear/ generators’ running was greatly reduced. G1, G2, and G3 were
tear, and leading to overall efficiency improvement. In Pulau reduced by 83%, 83%, and 67%, respectively, as seen in Fig. 14. In
Banggi, Fig. 14 shows the reduction in the running hours of all gen- summary, it should be pointed out that the generators are not only
erators. G1 and G2 were reduced by 54% and 54%, respectively. G3 working less, but also running at lower loads.
reports similar running hours and G4 and G5 running hours
increased by 58% and 55%. This results in maximized lifetime of 4.6. Economic analysis
the system component i.e. no need for component replacement
at early stages of the project lifetime. Lower loading on the gener- Table 5 summarizes the NPC, operating and LCOE costs of all
ator is generally regarded to be good for fuel consumption and scenarios. As seen from this table, standalone diesel generators
reducing wear/tears, but within a limit specified by the manufac- provide the lowest NPC and LCOE, followed by the optimized and
turer, otherwise, the system would be inefficient. Most generator’s existing hybrid then 100% RE system. The 100% PV/battery system
334 L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339

Fig. 12. Batteries SOC performance in (a) Pulau Banggi. (b) Tanjung Labian.

has the highest operating cost due to high battery replacement prices in the future, which endorses the idea of implementing
costs. It was assumed to be replaced every 7 years (battery life- totally RE projects.
time). No fuel is required by this system (100% RE). Meanwhile,
the optimized and existing hybrid systems report lower operating 4.7. Reduction of pollutant emissions
cost compared to standalone diesel generator, as less usage of the
diesel generators is required, yet reported higher LCOE than stan- The addition of PV in the standalone power systems would sig-
dalone diesel generator system. From the sensitivity analysis in nificantly reduce harmful carbon emission. This reduction justifies
Section 4.4, it is clear that when the loads and fuel price increased, eliminating the inefficient use of diesel generators, based on the
the system tends to depend more on the hybrid system, which pro- results reported in Table 6. The utilization of PV and battery banks
vides a good indicator of the availability towards using such sys- in the system enhanced the reduction of carbon emissions by 49% in
tem in future projects. Furthermore, referring to current Pulau Banggi, and 80% in Tanjung Labian. This shows that upgrading
technologies, it is expected to see decreasing in PV and battery’s standalone diesel generation systems in mini-grids with PV and
L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339 335

Fig. 13. Batteries 100% PV operational behavior in (a) Pulau Banggi. (b) Tanjung Labian.

batteries reduced harmful emissions, as well as fuel consumption. 5. Discussion on the operational analysis in both locations
However, 100% PV/Battery system offer zero emissions, and is con-
sidered as the best system from an environmental perspective, In this section, the main findings of Section 4 are discussed and
while the standalone diesel generators system is regarded as the explained. The results are connected together to show the relation
worst, as it generates the highest amount of the harmful emissions. between different system components and the effects of changes in
In this study, no penalties over CO2 emissions was considered. the main system parameter on the system performance. In addi-
336 L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339

Fig. 14. Pulau Banggi and Tanjung Labian generators running hours before and after adding PV/Batteries.

Table 5
Economic summary of existing and hypothetical scenarios.

Site System description NPC ($) Operational cost ($) LCOE ($/kW h)
Pulau Banggi Standalone diesel (0% RE) 8,545,703 643,458 0.2761
Hybrid PV/DG/Battery (59.21% RE) 11,326,602 499,681 0.366
Optimized Hybrid PV/DG/Battery (42.38% RE) 9,345,510 536,081 0.302
PV/Battery (100% RE) 42,140,180 1,617,117 1.36
Tanjung Labian Standalone diesel (0% RE) 5,902,414 438,493 0.3303
Hybrid PV/DG/Battery (86.90% RE) 9,563,989 318,460 0.5352
Optimized Hybrid PV/DG/Battery (39.89% RE) 5,571,168 302,203 0.3118
PV/Battery (100% RE) 21,797,966 799,318 1.22

tion, this study place emphasis on comparative cost and environ- trast to the 100% PV/Battery system that reports the highest cost.
mental analysis of each scenario. However, hybrid PV/diesel/battery system shows the best techni-
Four different scenarios were analyzed in Sections 4.1 and 4.2. cal and a very good economic characteristics based on the overall
These include the standalone diesel generators, existing hybrid system cost. The hybrid PV/diesel/battery system is costlier than
PV/diesel/battery, 100% PV/battery, and the optimum solution sce- the standalone diesel system over capital, replacement, operation
narios. The effects of changing major parameters, such as fuel price and maintenance, fuel, operational and salvage costs. Where,
and load growth on the system operation were investigated hybrid PV/diesel/battery system shows lower costs compared to
throughout the sensitivity analysis (Section 4.3). Each scenario 100% PV/battery system as shown in Fig. 15(a) and (b). The results
shows and quantifies the impact of injecting PV on NPC, LCOE, of both locations indicate that using 100% PV/battery would
power penetration, excess energy, fuel consumption, running involve high cost due to high capital and battery replacement
hours and other characteristics. costs. But, if a price reduction is found for these component, it
would be a feasible solution.
5.1. Techno-economic impact A comparison with the optimized scenarios shows that both
existing PV systems are not optimally selected prior to installation
The results obtained showed that standalone diesel system for the same load profiles, solar irradiation, and temperature data.
offers the best economic properties over the project period, in con- Due to the extreme remote location of both areas, the designers of

Table 6
System pollutant harmful emissions.

Site Description Emissions (kg/yr)


Carbone Carbone Unburned Particular Sulfur Nitrogen
dioxide monoxide hydrocarbons matters dioxide oxide
Pulau Banggi Standalone diesel (0% RE) 1,705,774 289.04 23.66 18.75 3486.60 3762.70
Existing hybrid PV/DG/Battery 870,387 326.41 32.27 23.19 1776.30 3462.5
(59.21% RE)
PV/Battery (100% RE) No Emissions
Tanjung Standalone diesel (0% RE) 1,124,134 797 84.18 58.62 2288.3 7717.10
Labian Existing hybrid PV/DG/Battery 223,090 205.85 22.07 15.25 453.38 1940.90
(86.90% RE)
PV/Battery (100% RE) No Emissions
L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339 337

Fig. 15. Cost analysis over all combinations: (a) Pulau Banggi. (b) Tanjung Labian.

these projects prefer to depend more on the PV and batteries than diesel generator particularly when the fuel prices and loads
the diesel generators for the existing systems. Thus, the optimal increase. Furthermore, reducing PV and battery banks costs would
systems show lower PV penetration levels, where the RE share is enhance the use of PV arrays and battery as lower NPC and LCOE
42.38% in Pulau Banggi and 39.89% in Tanjung Labian from the would associate with such system.
total production. Furthermore, the batteries strings are reduced The storage battery system is crucial towards the stability of the
to two strings in both locations. This is compared to 59.21% of RE of the system. The battery system offers a sufficient technique to
sharing with four strings and 86.9% of RE sharing with six strings minimize excess energy. Thus, the utmost usage of this energy to
in the existing hybrid systems of Pulau Banggi and Tanjung Labian, the current design is found. Meanwhile, the SOC of the battery sys-
respectively. tem reports high charging cycles for both systems, but higher
The sensitivity analysis examined the effect of changes in major cycles are found in the 100% PV/battery system, where the system
parameters, such as fuel price, load growth, PV, and battery banks depends mainly on the batteries to provide adequate energy to
prices on the overall system performance. The results show more loads when the PV is unavailable. Furthermore, the hybrid system
trend towards using hybrid systems that include PV, battery, and is compared to the standalone diesel generators to quantify the
338 L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339

Fig. 16. PV penetration level VS CO2 emissions in both locations.

effects of using such systems on fuel consumption, diesel genera- put emphasis on all costs associated with the systems through
tors running hours, harmful emission and economic aspects. comparative cost analysis between different configurations.
The results indicate that hybrid systems would reduce the fuel The comparison with the optimal system indicates that the
consumption and generate less harmful emission to the surround- existing systems were not optimally selected prior to installation.
ing environment. Diesel generators’ running hours would also Hybrid PV/Diesel/Battery system shows the best performance
reduce, as the system depends more on smaller generator units compared to all other scenarios in terms of the technical aspects
to supply the loads at different times during the day. The genera- as well as supporting 24-h energy access. Meanwhile, the stan-
tors are working less at lower loads, which results in decreasing dalone diesel generator system shows the best economical sce-
the replacement, maintenance, operational, fuel costs and the nario. However, 100% RE scenario is regarded as the best system
overall wear/tear of the system, hence leading to reduction in total for the provision of clean energy with no emissions. The results
NPC and LCOE. of sensitivity analysis carried out based on variation on some
parameters including fuel, PV, battery prices and load demand
(load growth), shows trends towards using RE sources in energy
5.2. Environmental impact
generation and less dependence on standalone diesel generators.
The inclusion of RE resources in power generation has resulted in
The results showed that standalone diesel system offers the
improving the system performance and minimizing the depen-
highest rate of harmful emissions into the surrounding environ-
dence on fossil fuel and harmful emissions as well. It also resulted
ment, in contrast to the 100% PV/Battery system that reports the
in increasing system sustainability. This study has demonstrated
best environmental properties with no harmful emissions to the
the importance of including storage system (batteries) to store
environment. However, hybrid PV/diesel/battery system shows a
excess energy and reducing losses. Furthermore, it shows the ben-
very good economical and environmental characteristic. The rela-
efits of RE projects in local communities in enhancing the socio-
tion between the PV penetration and CO2 emissions is shown in
economic developments by creating new job opportunities for
Fig. 16 for both locations.
the local residents. On the other hand, 100% RE system seems to
As seen in Fig. 16 that increasing the energy produced by RE
be uneconomically feasible, due to the high PV and battery capital
sources would result in reducing the harmful emissions generated
and replacement costs. However, with further research in PV and
by the system. It is also clear that the reduction of harmful emis-
battery production technologies, projected decrease of the costs
sion depends on the system configuration and the amount of the
are expected to make this approach feasible in the near future.
generated energy.

Acknowledgement
6. Conclusion
The authors would like to acknowledge the financial support
This study investigates the performance matrices of the current
from the University of Malaya, Malaysia, through the Postgraduate
and proposed scenarios of two power stations located in Pulau
Research Grant (PPP) PG338-2016A and PG192-2016A.
Banggi and Tanjung Labian, Sabah, Malaysia. It showed the impact
of injection of PV into mini-grids based on important operational
procedures over different RE penetration levels (0%, 39.89%, References
42.38%, 59.21%, 86.90% and 100%). The existing systems in both
locations were compared to the optimum sizing of the PV system [1] Zhou W, Lou C, Li Z, Lu L, Yang H. Current status of research on optimum sizing
of stand-alone hybrid solar–wind power generation systems. Appl Energy
in order to examine whether the systems are optimally selected
2010;87:380–9.
prior the installation for the same load profiles, solar radiation [2] Lovins AB. Small is profitable: the hidden economic benefits of distributed
and temperature data sets. The effects of changing RE penetration generation (and other distributed resources). In: Australian eco generation
levels on NPC, LCOE and associated technical properties, the influ- conference; 2002.
[3] Kanagawa M, Nakata T. Assessment of access to electricity and the socio-
ence of different PV penetration levels on the harmful emissions economic impacts in rural areas of developing countries. Energy Policy
generation were also shown and discussed. In addition, the study 2008;36:2016–29.
L.M. Halabi et al. / Energy Conversion and Management 144 (2017) 322–339 339

[4] Doll CN, Pachauri S. Estimating rural populations without access to electricity [30] Olatomiwa L, Mekhilef S, Ismail M, Moghavvemi M. Energy management
in developing countries through night-time light satellite imagery. Energy strategies in hybrid renewable energy systems: a review. Renew Sustain
Policy 2010;38:5661–70. Energy Rev 2016;62:821–35.
[5] Borhanazad H, Mekhilef S, Saidur R, Boroumandjazi G. Potential application of [31] Rehman S, Al-Hadhrami LM. Study of a solar PV-diesel-battery hybrid power
renewable energy for rural electrification in Malaysia. Renew Energy 2013;59 system for a remotely located population near Rafha, Saudi Arabia. Energy Dec
(November):210–9. 2010;35:4986–95.
[6] Lau KY, Yousof MFM, Arshad SNM, Anwari M, Yatim AHM. Performance [32] Mahmoud MM, Ibrik IH. Techno-economic feasibility of energy supply of
analysis of hybrid photovoltaic/diesel energy system under Malaysian remote villages in Palestine by PV-systems, diesel generators and electric grid.
conditions. Energy 2010;35(August):3245–55. Renew Sustain Energy Rev Apr 2006;10:128–38.
[7] Wong SY, Chai A. An off-grid solar system for rural village in Malaysia. In: 2012 [33] Karakoulidis K, Mavridis K, Bandekas D, Adoniadis P, Potolias C, Vordos N.
Asia-Pacific power and energy engineering conference (Appeec); 2012. Techno-economic analysis of a stand-alone hybrid photovoltaic-diesel–
[8] Ajan CW, Ahmed SS, Ahmad HB, Taha F, Zin AABM. On the policy of battery-fuel cell power system. Renew Energy 2011;36:2238–44.
photovoltaic and diesel generation mix for an off-grid site: East Malaysian [34] Rajkumar R, Ramachandaramurthy V, Yong B, Chia D. Techno-economical
perspectives. Sol Energy 2003;74:453–67. optimization of hybrid pv/wind/battery system using Neuro-Fuzzy. Energy
[9] Nandi SK, Ghosh HR. Prospect of wind–PV-battery hybrid power system as an 2011;36:5148–53.
alternative to grid extension in Bangladesh. Energy 2010;35:3040–7. [35] Saheb-Koussa D, Haddadi M, Belhamel M. Economic and technical study of a
[10] Izadyar N, Ong HC, Chong WT, Mojumder JC, Leong K. Investigation of potential hybrid system (wind–photovoltaic–diesel) for rural electrification in Algeria.
hybrid renewable energy at various rural areas in Malaysia. J Clean Prod Appl Energy 2009;86:1024–30.
2016;139:61–73. [36] Ohijeagbon O, Ajayi OO. Solar regime and LVOE of PV embedded generation
[11] Mustapa SI, Peng LY, Hashim AH. Issues and challenges of renewable energy systems in Nigeria. Renew Energy 2015;78:226–35.
development: a Malaysian experience. Proceedings of the international [37] Baneshi M, Hadianfard F. Techno-economic feasibility of hybrid diesel/PV/
conference on energy and sustainable development: issues and strategies wind/battery electricity generation systems for non-residential large
(ESD) 2010;2010:1–6. electricity consumers under southern Iran climate conditions. Energy
[12] Mekhilef S, Safari A, Mustaffa W, Saidur R, Omar R, Younis M. Solar energy in Convers Manage 2016;127:233–44.
Malaysia: current state and prospects. Renew Sustain Energy Rev [38] Cader C, Bertheau P, Blechinger P, Huyskens H, Breyer C. Global cost
2012;16:386–96. advantages of autonomous solar–battery–diesel systems compared to diesel-
[13] Ahmad S, Ab Kadir MZA, Shafie S. Current perspective of the renewable energy only systems. Energy Sustain Develop 2016;31:14–23.
development in Malaysia. Renew Sustain Energy Rev 2011;15:897–904. [39] Ramli MA, Hiendro A, Al-Turki YA. Techno-economic energy analysis of
[14] NEB. Suruhanjaya Tenaga (Energy Commission), National Energy Balance. wind/solar hybrid system: case study for western coastal area of Saudi Arabia.
Available: <meih.st.gov.my>; 2013. Renew Energy 2016;91:374–85.
[15] Phuangpornpitak N, Kumar S. PV hybrid systems for rural electrification in [40] Dagher L, Harajli H. Willingness to pay for green power in an unreliable
Thailand. Renew Sustain Energy Rev 2007;11(September):1530–43. electricity sector: Part 1. The case of the Lebanese residential sector. Renew
[16] Olatomiwa L, Mekhilef S, Huda A, Sanusi K. Techno-economic analysis of Sustain Energy Rev 2015.
hybrid PV–diesel–battery and PV–wind–diesel–battery power systems for [41] Harajli H, Gordon F. Willingness to pay for green power in an unreliable
mobile BTS: the way forward for rural development. Energy Sci Eng; 2015. electricity sector: Part 2. The case of the Lebanese commercial sector. Renew
[17] Lena G. Rural electrification with PV hybrid systems. St. Ursen: International Sustain Energy Rev 2015;50:1643–9.
Energy Agency Photovoltaic Power Systems Programme; 2013. [42] Mahmud AM. Evaluation of the solar hybrid system for rural schools in Sabah,
[18] Khatib T, Mohamed A, Sopian K, Mahmoud M. Optimal sizing of building Malaysia. In: IEEE international conference on power and energy (PECon),
integrated hybrid PV/diesel generator system for zero load rejection for 2010; 2010. p. 628–33.
Malaysia. Energy Build 2011;43(December):3430–5. [43] Hazelton J, Bruce A, MacGill I. Improving risk management for utility PV-
[19] Olatomiwa L, Mekhilef S, Huda A, Ohunakin OS. Economic evaluation of hybrid battery-diesel mini-grid projects in Sabah, Malaysia; 2015.
energy systems for rural electrification in six geo-political zones of Nigeria. [44] NASA. Surface meteorology and solar energy. Available: <http://eosweb.
Renew Energy 2015;83:435–46. larc.nasa.gov/sse/>.
[20] Olatomiwa L, Mekhilef S, Huda A. Optimal sizing of hybrid energy system for a [45] Sinha S, Chandel S. Review of recent trends in optimization techniques for
remote telecom tower: a case study in Nigeria. In: IEEE conference on energy solar photovoltaic–wind based hybrid energy systems. Renew Sustain Energy
conversion (CENCON), 2014; 2014. p. 243–47. Rev 2015;50:755–69.
[21] Olatomiwa L. Optimal configuration assessments of hybrid renewable power [46] Olatomiwa L, Mekhilef S, Shamshirband S. Global solar radiation forecasting
supply for rural healthcare facilities. Energy Rep 2016;2:141–6. based on SVM-wavelet transform algorithm. Int J Intell Syst Appl (IJISA)
[22] Hazelton J, Bruce A, MacGill I. A review of the potential benefits and risks of 2016;8: 19.
photovoltaic hybrid mini-grid systems. Renew Energy 2014;67:222–9. [47] Shamshirband S, Mohammadi K, Chen H-L, Samy GN, Petković D, Ma C. Daily
[23] Neves D, Silva CA, Connors S. Design and implementation of hybrid renewable global solar radiation prediction from air temperatures using kernel extreme
energy systems on micro-communities: a review on case studies. Renew learning machine: a case study for Iran. J Atmos Solar Terr Phys
Sustain Energy Rev 2014;31(March):935–46. 2015;134:109–17.
[24] Olatomiwa L, Mekhilef S, Ohunakin OS. Hybrid renewable power supply for [48] Mohammadi K, Shamshirband S, Danesh AS, Abdullah MS, Zamani M.
rural health clinics (RHC) in six geo-political zones of Nigeria. Sustain Energy Temperature-based estimation of global solar radiation using soft computing
Technol Assess 2016;13:1–12. methodologies. Theor Appl Climatol; 2015: 1–12.
[25] Banos R, Manzano-Agugliaro F, Montoya F, Gil C, Alcayde A, Gómez J. [49] Nfah E, Ngundam J. Modelling of wind/Diesel/battery hybrid power systems
Optimization methods applied to renewable and sustainable energy: a for far North Cameroon. Energy Convers Manage 2008;49:1295–301.
review. Renew Sustain Energy Rev 2011;15:1753–66. [50] Hossain M, Mekhilef S, Olatimiwa L. Performance evaluation of a stand-alone
[26] Belfkira R, Zhang L, Barakat G. Optimal sizing study of hybrid wind/PV/diesel PV-wind-diesel-battery hybrid system feasible for a large resort center in
power generation unit. Sol Energy 2011;85:100–10. South China Sea, Malaysia. Sustain Cities Soc 2016.
[27] Erdinc O, Uzunoglu M. Optimum design of hybrid renewable energy systems: [51] Anwari M, Rashid M, Muhyiddin H, Ali A. An evaluation of hybrid wind/diesel
overview of different approaches. Renew Sustain Energy Rev energy potential in Pemanggil Island Malaysia. In: International conference on
2012;16:1412–25. power engineering and renewable energy (ICPERE), 2012; 2012. p. 1–5.
[28] Haidar AM, John PN, Shawal M. Optimal configuration assessment of [52] Ngan MS, Tan CW. Assessment of economic viability for PV/wind/diesel hybrid
renewable energy in Malaysia. Renew Energy 2011;36:881–8. energy system in southern Peninsular Malaysia. Renew Sustain Energy Rev
[29] Zahboune H, Zouggar S, Krajacic G, Varbanov PS, Elhafyani M, Ziani E. Optimal 2012;16:634–47.
hybrid renewable energy design in autonomous system using Modified [53] Lambert T, Gilman P, Lilienthal P. Micropower system modeling with HOMER.
Electric System Cascade Analysis and Homer software. Energy Convers Integr Altern Sources Energy 2006;1:379–418.
Manage 2016;126:909–22.

Anda mungkin juga menyukai