08 February 2019
- Start injection at segment 19 A&B ( CJ 19A/19B , 2 boxes in 19B + EJ between 19A & 22B)
- EJ between 20B West side and 19A East side
To finalize and inspected by 11/02/2019
To spray at 13/02/2019
13 February 2019
- Injection for EJ between 19B and 18D at East side
- Injection for remaining part at segment 18 C&D at East side
To make inspection by 14/02/2019
To spray at 16/02/2019
16 February 2019
- Complete all injection remaining related to Road A1 at 20/02/2019.