METHOD STATEMENT
Dr Naser Ghani
PhD, P.Eng, MIEM, MASCE, MACEM
anaser@usm.my
www.hbp.usm.my/naser
ROOM 104 E49
METHOD STATEMENT
Construction method planning should
begin at the tender stage
Money/Time
Background 3
Construction
Construction Method
Method Statements
Statements
4
Planning/Costing
Method Statement
Pre-tender
Planning/Costing
Method Statement
Planning/Costing
Method Statement
Planning/Costing
Method Statement
Submission
Method Statement
Submission
Method Statement
Work /Safety
Method Statement
Resources
Specifications
BQ
Drawings
14
Refer GnP full specs
Also refer drain and road bq in pdf
RM
material
Example:
Pre-Tender
MS
Pressure vessel
foundation
Submission/General Method Statement
refer Arup, Fairhurst, etc
Work
Work Method
Method Statement
Statement
1. Introduction
2. Scope of Works/Objectives
3. References/Standards
4. Resource Planning
5. Material and Delivery
6. Coordination
7. Methodology
8. Quality and Safety
Work
Work Method
Method Statement
Statement
Resource Planning
4.1 Material Planning
4.2 Manpower Planning
4.3 Machinery & Equipment Planning
Work
Work Method
Method Statement
Statement
Coordination
6.1 Coordination between Architecture works
6.2 Coordination between C&S works
6.3 Coordination between M&E works
6.4 Coordination between other specialist works
Work
Work Method
Method Statement
Statement
Methodology (example…)
7.1 Surface Preparation
7.2 Application of Water Proofing (PU Type)
7.3 Post-Application of Water Proofing (PU Type)
Work
Work Method
Method Statement
Statement