ABSTRACT
Road construction requires heavy equipment in its work, one of them is road layer. Heavy
equipments which currently use is dump truck, excavator, motor greder, water tank truck,
tandem roller and wheel loader. The number of heavy equipment to itemized work selected
heap, Class B aggregate and A class aggregate are 1 unit excavator, 1 unit wheel loader, 15
unit dump trucks, 1 unit grader motor, 2 unit tandem rollers, 1 unit water tank, selected heap
work which use the provisions of the owner is 9 days and the contractor 11 days, class B
aggregate work using the provisions of the owner are 7 days and 9 days contractor, A class
aggregate work using the provisions of the owner are 5 days and 7 days contractor. The
differences in the cost of heavy equipment is Rp.121.650.532 or higher by using contractor's
heavy equipment. To determine the heavy equipment with a more efficient cost with a saving
percentage of 12.93% then, the contractor must meet the provisions made by the owner with
the economical life tool, the condition of the machine and eligible labor.
Wheel
1 26 807.062,62 20.983.628,12
Loader2,1m3
Alat HPS owner = = 47 jam
Dump Truck
15 8 567.632,43 68.115.891,60
10 T
Alat kontraktor = = 60 jam
Motor
1 10 770.847,63 7.708.476,30
Jumlah hari yang dibutuhkan (h) : Grader10.800
F. DAFTAR PUSTAKA.
Abdul, G. (2007). Analisa Perhitungan
Produktivitas Alat Berat pada
Pelaksanaan Pematangan Lahan untuk
Pembuatan Work Shop di Kab.
Malindau. Kalimantan Timur :
Universitas Samarinda.
Peraturan Mentri Pekerjaan Umum No. 09,
2013, Tentang Persyaratan Kompetisi
Untuk Subkualifikasi Tenaga Ahli dan
Tenaga Terampil Bidang Jasa
Kontruksi.
Peraturan Mentri PUPR No. 28, 2016,
Tentang Alat Berat.
Rachmanhadi. (1992). Alat – alat Berat
dan Penggunaannya. Jakarta : Bada
Penerbit Pekerjaan Umum.
Rima, M. S. (2016) Analisis Produktivitas
dan Biaya Alat Berat Pekerjaan
Penghamparan Hotmix Proyek
Pembangunan Ruas Jalan Wawar-
Congot.
Yogyakarta : Universitas Gajah Mada
Spesifikasi Umum Bina Marga Revisi 3.
(2010). Panduan Analisa Harga Satuan.
Pemerintah Provinsi Riau Dinas
Pekerjaan Umum Dan Penataan Ruang.
Rostiyanti, Susy Fatena. 2008. Alat Berat
Untuk Proyek Konstruksi. Edisi 2. PT
Rineka Cipta. Jakarta.
Shalahuddin, Muhammad. 2009. Alat
Berat dan Pemindahan Tanah Mekanis.
Pusbangdik. Pekanbaru.
Stefi, P. T. (2013). Analisis Biaya
Penggunaan Alat Berat Pada
Pekerjaan Tanah (Studi Kasus
Perencanaan Bandar Udara Lokasi
Desa Pusungi Kec. Ampana Tete Kab.
Tojo Una-una, Sulawesi Tengah).
Manado : Universitas Sam Ratulangi.
Wigroho,H.Y.,& Suryadharma, 1993,
”Pemindahan Tanah Mekanis”. Bagian
I. Yogyakarta.