December 2017
Planning Department and Civil
Engineering and Development
Department
234834
December 2017
1 INTRODUCTION 11
1.1 Background 11
1.2 Study Area and Potential Development Areas 12
1.3 Study Flow and Methodology 13
4 Technical Assessments 67
4.1 Introduction 67
4.2 Geotechnical Assessment 68
4.3 Traffic and Transport Impact Assessment 72
4.4 Drainage, Sewerage, Water Supply and Utility Impact Assessment 77
4.5 Air Ventilation Assessment 84
4.6 Socio-Economic Impact Assessment 87
4.7 Sustainability Assessment 90
4.8 Green Initiative, Carbon Appraisal and “Wise City” Concept 92
4.9 Strategic Environmental Assessment 115
4.10 Landscape and Visual Impact Assessment 129
4.11 Broad Cost Estimation 145
7 Conclusion 149
Figures
Appendices
List of Figures
Figure 1.3.1 Study Area
Figure 1.4.1 Study Flow and Methodology
Figure 3.1.1 Summary of Opportunities for Developing the NTN
Figure 3.1.2 Summary of Key Issues & Constraints for Developing the NTN
Figure 3.3.1a-d Classification of Spatial Data, Scores and Categories in MCD Analysis
Figure 3.3.2 Delineation of PDA Boundaries
Figure 3.5.1 Option 1 – Contextual Clusters – Broad Land Use Plan
Figure 3.5.2 Option 2 – Productive Metropolis – Broad Land Use Plan
Figure 3.5.3 Option 3 – Polycentric Living – Broad Land Use Plan
Figure 3.6.1 Summary of 3 Development Scenarios – Scenario I, II and III
Figure 3.7.1 Concept Plan under Scenario I
Figure 3.7.2a Broad Land Use Concept Plan -LMC PDA Scenario I and II
Figure 3.7.2b Broad Land Use Concept Plan -MKT PDA Scenario I and II
Figure 3.7.2c Broad Land Use Concept Plan - HYW PDA Scenario I
Figure 3.7.2d Broad Land Use Concept Plan -TKL PDA Scenario I
Figure 3.7.2e Broad Land Use Concept Plan - QH PDA Scenario I
Figure 3.7.3 Location of Existing Brownfield Sites
Figure 3.7.4 The CP under Scenario I – Phase 1
Figure 3.7.5 The CP under Scenario I – Phase 2
Figure 3.7.6 Location of Existing “V” Zones and Existing Settlements
Figure 3.7.7 The CP under Scenario I – G/IC Facilities
Figure 3.8.1 Concept Plan under Scenario II
Figure 3.8.2c Broad Land Use Concept Plan - HYW PDA Scenario II
Figure 3.8.2d Broad Land Use Concept Plan - TKL PDA Scenario II
Figure 3.8.2e Broad Land Use Concept Plan - QH PDA Scenario II
Figure 3.8.3 The CP under Scenario II – Phase 1
Figure 3.8.4 The CP under Scenario II – Phase 2
Figure 3.8.5 The CP under Scenario II – Phase 3
Figure 3.8.6 The CP under Scenario II – G/IC Facilities
Figure 3.9.1 Concept Plan under Scenario I/II – Land Use Plan (with Possible SP/IE Site)
Figure 4.2.1 Published Solid and Superficial Geological Map at 1:20,000 scale (Map Sheets 2 and 3)
Figure 4.2.2 Published Solid Geological Map at 1:20,000 scale (Map Sheet 2)
Figure 4.2.3 Landslide Records – Heung Yuen Wai PDA
Figure 4.2.4 Landslide Records – Lok Ma Chau PDA
Figure 4.2.5 Landslide Records – Man Kam To PDA
Figure 4.2.6 Landslide Records – Ta Kwu Ling PDA
Figure 4.2.7 Landslide Records – Queen’s Hill PDA
Figure 4.2.8 Location of Existing Man-made Features – Heung Yuen Wai PDA
Figure 4.2.9 Location of Existing Man-made Features – Lok Ma Chau PDA
Figure 4.2.10 Location of Existing Man-made Features – Man Kam To PDA
Figure 4.2.11 Location of Existing Man-made Features – Ta Kwu Ling PDA
Figure 4.2.12 Location of Existing Man-made Features – Queen’s Hill PDA
Figure 4.2.13 Plan of Existing Ground Investigation – Heung Yuen Wai PDA
Figure 4.2.14 Plan of Existing Ground Investigation – Lok Ma Chau PDA
Figure 4.2.15 Plan of Existing Ground Investigation – Man Kam To PDA
Figure 4.2.16 Plan of Existing Ground Investigation – Ta Kwu Ling PDA
Figure 4.2.17 Plan of Existing Ground Investigation – Queen’s Hill PDA
Figure 4.2.18 Areas with Development Potential Limited by Geotechnical Constraints (Sheet 1 of 2)
Figure 4.2.19 Areas with Development Potential Limited by Geotechnical Constraints (Sheet 2 of 2)
Figure 4.2.20 Cavern Suitability Map of the Study Area
Figure 4.2.21 Natural Terrain Catchment Areas – Heung Yuen Wai PDA
Figure 4.2.22 Natural Terrain Catchment Areas – Lok Ma Chau PDA
Figure 4.2.23 Natural Terrain Catchment Areas – Man Kam To PDA
Figure 4.2.24 Natural Terrain Catchment Areas – Ta Kwu Ling PDA
Figure 4.2.25 Natural Terrain Catchment Areas – Queen’s Hill PDA
Figure 4.3.1 Possible Railway Line (To Be Studied)
Figure 4.3.2 Concept Plan for NTN Strategic Road Network
Figure 4.3.3 Concept Plan for NTN Proposed Cycle Network
Figure 4.4.1a Proposed Drainage System for Lok Ma Chau PDA
Figure 4.4.1b Proposed Drainage System for Man Kam To PDA
Figure 4.4.1c Proposed Drainage System for Heung Yuen Wai PDA
Figure 4.4.1d Proposed Drainage System for Ta Kwu Ling PDA (sheet 1 of 2)
Figure 4.4.1e Proposed Drainage System for Ta Kwu Ling PDA (sheet 2 of 2)
Figure 4.4.1f Proposed Drainage System for Queen’s Hill PDA
Figure 4.4.2 Proposed Alignment of Fresh Water Distribution Mains
Figure 4.4.3 Proposed Sewerage Infrastructure for NTN Development
Figure 4.4.4 Proposed Alignment of Flushing Water Distribution Mains
Figure 4.5.1 Wind Environment of Lok Ma Chau PDA
Figure 4.5.2 Wind Environment of Man Kam To PDA
Figure 4.5.3 Wind Environment of Heung Yuen Wai PDA
Figure 4.5.4 Wind Environment of Ta Kwu Ling PDA
Figure 4.5.5 Wind Environment of Queen’s Hill PDA
Figure 4.8.1 Overall Effluent Reuse Strategy of Deep Bay Catchment
Figure 4.8.2 Locations of Various Infrastructure in Caverns
Figure 4.9.1 Habitat Map of Lok Ma Chau PDA and the Adjoining Areas
Figure 4.9.2 Habitat Map of Man Kam To PDA and the Adjoining Areas
Figure 4.9.3 Habitat Map of Ta Kwu Ling PDA and the Adjoining Areas
Figure 4.9.4 Habitat Map of Heung Yuen Wai PDA and the Adjoining Areas
Figure 4.9.5 Habitat Map of Queen’s Hill PDA and the Adjoining Areas
Figure 4.9.6a Representative Air Sensitive Receivers within the Lok Ma Chau PDA - Scenario II (Air
Quality)
Figure 4.9.6b Representative Air Sensitive Receivers within the Man Kam To, Ta Kwu Ling, Heung Yuen
Wai and Queen’s Hill PDA - Scenario II (Air Quality)
Figure 4.9.7 Contour Plot of 19th Highest 1-Hour NO2 Concentration (in µg/m3) within the Assessment
Area (Air Quality)
Figure 4.9.8 Contour Plot of Annual NO2 Concentration (in µg/m3) within the Assessment Area (Air
Quality)
Figure 4.9.9 Contour Plot of 10th Highest 24-Hour RSP Concentration (in µg/m3) within the Assessment
Area (Air Quality)
Figure 4.9.10 Contour Plot of Annual RSP Concentration (in µg/m3) within the Assessment Area (Air
Quality)
Figure 4.9.11 Contour Plot of 10th Highest 24-Hour FSP Concentration (in µg/m3) within the Assessment
Area (Air Quality)
Figure 4.9.12 Contour Plot of Annual FSP Concentration (in µg/m3) within the Assessment Area (Air
Quality)
Figure 4.9.13 Contour Plot of 4th Highest 10-Minute SO2 Concentration (in µg/m3) within the Assessment
Area (Air Quality)
Figure 4.9.14 Contour Plot of 4th Highest 24-Hour SO2 Concentration (in µg/m3) within the Assessment
Area (Air Quality)
Figure 4.9.15 Locations of Water Sensitive Receivers - All Options
Figure 4.9.16 Representative Existing Noise Sensitive Receivers for Road Traffic Noise Assessment
Figure 4.9.17 Representative Planned Noise Sensitive Receivers for Road Traffic Noise Assessment
Figure 4.9.18a Cultural Heritage Resources – Lok Ma Chau PDA
Figure 4.9.18b Cultural Heritage Resources – Queen’s Hill PDA & Ta Kwu Ling PDA
Figure 4.9.18c Cultural Heritage Resources – Heung Yuen Wai PDA & Ta Kwu Ling PDA
Figure 4.9.18d Cultural Heritage Resources – Man Kam To PDA
Figure 4.10.1 Aerial Photo – Overall
Figure 4.10.1a Aerial Photo – Enlargement Plan, Lok Ma Chau PDA (Sheet 1 of 5)
Figure 4.10.1b Aerial Photo – Enlargement Plan, Man Kam To PDA (Sheet 2 of 5)
Figure 4.10.1c Aerial Photo – Enlargement Plan, Heung Yuen Wai PDA (Sheet 3 of 5)
Figure 4.10.1d Aerial Photo – Enlargement Plan, Ta Kwu Ling PDA (Sheet 4 of 5)
Figure 4.10.1e Aerial Photo – Enlargement Plan, Queen’s Hill PDA (Sheet 5 of 5)
Figure 4.10.2 Landscape Resources Plan – Overall
Figure 4.10.2a Landscape Resources Plan – Enlargement Plan, Lok Ma Chau PDA (Sheet 1 of 5)
Figure 4.10.2b Landscape Resources Plan – Enlargement Plan, Man Kam To PDA (Sheet 2 of 5)
Figure 4.10.2c Landscape Resources Plan – Enlargement Plan, Heung Yuen Wai PDA (Sheet 3 of 5)
Figure 4.10.2d Landscape Resources Plan – Enlargement Plan, Ta Kwu Ling PDA (Sheet 4 of 5)
Figure 4.10.2e Landscape Resources Plan – Enlargement Plan, Queen's Hill PDA (Sheet 5 of 5)
Figure 4.10.3 Landscape Character Areas Plan – Overall
Figure 4.10.3a Landscape Character Areas Plan – Enlargement Plan, Lok Ma Chau PDA (Sheet 1 of 5)
Figure 4.10.3b Landscape Character Areas Plan – Enlargement Plan, Man Kam To PDA (Sheet 2 of 5)
Figure 4.10.3c Landscape Character Areas Plan – Enlargement Plan, Heung Yuen Wai PDA (Sheet 3 of 5)
Figure 4.10.3d Landscape Character Areas Plan – Enlargement Plan, Ta Kwu Ling PDA (Sheet 4 of 5)
Figure 4.10.3e Landscape Character Areas Plan – Enlargement Plan, Queen’s Hill PDA (Sheet 5 of 5)
Figure 4.10.4 Visually Sensitive Receiver Plan – Overall
Figure 4.10.5 Section 1 of Mitigation Measures - Urban / Green Belt Integration
Figure 4.10.6 Section 2 of Mitigation Measures - Main Road
Figure 4.10.7 Section 3 of Mitigation Measures - Urban / Agriculture Integration
Figure 4.10.8 Section 4 of Mitigation Measures - Green Stream
Figure 4.10.9 Integration of Landscape and SUDS Provisions
Figure 4.10.10 Sample Photomontage VSR3 Sheung Shui Wa Shan
Figure 7.1.1 Broad Land Use Concept of 3 PDAs as Extracted from the Booklet of Preliminary Concepts
for the NTN Development Promulgated in the Public Engagement of “Hong Kong 2030+”
List of Appendices
Appendix A Working Assumptions for Domestic and Non-domestic Uses
Appendix B Summary of Building Level Renewables and Energy Efficient Measures Proposed for NTN
Appendix C Municipal Solid Waste and Sludge Arising Forecast within NTN
Appendix D Broad Assessment of the Development Potential of the Fanling Golf Course Site
6
1 INTRODUCTION
1.1 Background
1.1.1 The New Territories North (NTN), broadly covering the area north of Hong
Kong's northern hill ranges viz. Kai Kung Leng, Pak Tai To Yan and Pat Sin
Leng, has been a relatively less developed part of the plains of the territory. Apart
from the Fanling/Sheung Shui New Town, which had a population of about
255,000 in 2011, developments in the area are generally confined to rural
settlements or low-rise low-density residential estates, as well as open storage
yards or rural industries.
1.1.2 The relatively sparse development of the NTN is due to its large area of high
ecological significance, spanning from the Deep Bay and Mai Po Marshes in the
west, the fishponds in Hoo Hok Wai, the wet cultivation fields of Long Valley/Ho
Sheung Heung, and the woodlands of Robin's Nest (Hung Fa Leng), at the same
time north part of the Study Area was part of the Closed Area in the past.
Development of the NTN is also constrained by the lack of infrastructure support.
In terms of strategic transport networks, only part of the area is served by the East
Rail (ER) line and San Tin/Fanling Highways. These networks are already either
working at, or nearing capacity. In terms of sewerage, a large part of the area is
still unsewered.
1.1.3 Development in Shenzhen in the past three decades has resulted in a very
different urban landscape in the region. With town-centre-type developments just
across our northern boundary, the present rural NTN is a striking contrast. Other
than the physical disparity it creates between the two sides of the boundary,
development in Shenzhen, coupled with rapidly changing social and economic
conditions, has gradually turned the NTN from Hong Kong's frontier area to a
very dynamic portal where about 610,000 people and 42,000 vehicles passed
through on a daily basis in 2015. The NTN could be more than just a boundary
area. Its development potential should be better harnessed.
1.1.4 Apart from the North East New Territories (NENT) and Hung Shui Kiu (HSK)
New Development Areas (NDAs), there are vast tracts of undeveloped areas in
the NTN (including land already released from the Closed Area) that could be
considered for meeting the long-term development needs of Hong Kong, while
acknowledging that some areas mentioned above have high
ecological/conservation significance and are unsuitable for development.
1.1.5 The completed Study on Land Use Planning for the Closed Area points out that a
large portion of land within the Closed Area is worthy of conservation.
Nevertheless, development opportunities can still be found along the major cross-
boundary transport corridors such as those areas near Lok Ma Chau (LMC), Man
Kam To (MKT) and the future Liantang/Heung Yuen Wai (LT/HYW) Boundary
Control Points (BCPs).
1.1.6 The Ping Che (PC)/Ta Kwu Ling (TKL) NDA under the NENT Planning and
Engineering (P&E) Study is re-planned. Comprehensive planning of developable
areas released from the Closed Area together with the nearby areas in the NTN
would more effectively harness the development potential of the areas.
12
1.1.7 The 2013 Policy Address states that the feasibility of taking forward the further
development of the NTN should be studied with a view to developing a modern
new town there of a similar scale as the Fanling/ Sheung Shui New Town.
1.1.8 The Planning Department (PlanD) and the Civil Engineering and Development
Department (CEDD) of the Hong Kong Special Administrative Region (HKSAR)
commissioned Ove Arup and Partners Hong Kong Limited (Arup) on 30 January
2014 to undertake the Preliminary Feasibility Study on Developing the New
Territories North (the Study). The Study has formulated a Concept Plan (CP) for
the NTN and strategic infrastructure requirements supported by the Broad Land
Use Concept Plans (BLCPs), and examined the preliminary feasibility of
individual Potential Development Area (PDA) identified. The findings and
recommendations of this Study have formed the basis for detailed P&E Studies
for the PDAs in the future. Specifically, the Study has:
reviewed and examined how the Government’s strategic directions for
infrastructure provision could be taken forward in this Study;
established a baseline profile for the Study Area and to identify key
issues, constraints and opportunities of the PDAs and the Study Area;
reviewed and delineated the boundaries of the initial PDAs, taken into
account of comments from Government bureaux/departments, technical
feasibilities and development needs;
undertaken scenario testing to recommend the optimum population and
employment levels in the PDAs, substantiated by the series of broad
technical assessments in the formulation of preferred land use option;
examined how integration of urban development with rural
environment could be achieved;
examined innovative concepts to commensurate with the vision of
developing the NTN under the eco-city, low carbon city, wise city and
walkable city concepts;
ascertained the feasibility and acceptability of the Study proposals in
terms of traffic and other infrastructure capacities, urban design,
environment, landscape, air ventilation, etc.;
recommended the scope of the detailed P&E Studies for the PDAs to be
carried out in the next stage, and other issues to be resolved/tackled.
the area of influence (AOI) for conducting the various technical assessments, this
AOI, nevertheless has been extended during the course of the Study so as to
ensure satisfactory completion of tasks to be performed under the Study. In
particular, it was adjusted to cover those areas on which reviews and technical
assessments should be carried out due to new or upgrading of existing
infrastructure works outside the Study Area, which are needed for serving the
proposed developments in the PDAs.
and illustrative BLCPs for individual PDAs. Based on the PDA boundaries
delineated and different combination of population and employment, a total of
three broad land use options have been formulated at the early stage of the Study.
1.3.9 With further refinement and evaluation of the above mentioned broad land use
options, three development scenarios (Scenarios I, II and III) each with more
implementation details and infrastructure proposals have been generated for the
CP. Scenario I and Scenario II covering a spectrum of development thresholds
with different characteristics are considered more self-sustaining, and are
recommended to be examined in the next stage of the Study. In addition to CP for
NTN, a set of illustrative BLCPs has also been prepared for each of the PDAs.
Broad Technical Assessments in Support of the Concept Plan
1.3.10 A total of three rounds of broad technical assessments have been carried out
throughout the Study, as an iterative process to support the formulation of the CP.
The broad technical assessments embrace various aspects, including
environment, geotechnics, traffic and transport, drainage, sewage, water supply,
utility, air ventilation, socio-economic, sustainability, green initiatives, carbon
appraisal and “wise city concept”, landscape and visual, etc.
Formulation of Implementation Strategy and Development Timeframe
1.3.11 Towards the end of the Study, broad development timeframe has been
recommended, taking into account of required statutory procedures, consultancy
tendering, detailed design, contract tendering etc.
1.3.12 In summary, please refer to Figure 1.4.1 for the Study Flow and Methodology of
the Study.
1.3.13 The purpose of this Final Report (FR) is to document the study flow &
methodology, key findings, recommendations and conclusion of the Study. It also
includes the land use proposals of the CP, as well as the summary of broad
technical assessments undertaken in the Study.
15
Legend:
1
According to the names of villages on the list of village representatives for the Village Representative Election
2011-2014 excluding those squatter areas
22
provision of new public and community facilities and new information and
communication technology.
3.3.4 Upon completion of the MCD analysis, areas with high development potential
have been identified under 4 development scenarios adopting different
infrastructural combinations, which were then used as the basis for the
delineation of PDA boundaries. Areas with “High Development Potential” are
listed in Table 3.3.1 below.
26
3.3.5 Table 3.3.1 Area with “High Development Potential” under the 4 Scenarios
Scenarios 0 1 2 3
(Existing) (+Proposed (+Proposed (+Proposed
NOL) NOL+ NOL NOL + NOL
Extension2) Extension+
Possible north-
south railway)3
Area with High About About About About
Development 270 ha 508 ha 1,016 ha 1,019 ha
Potential
3.3.6 In summary, the MCD Analysis has confirmed the areas with development
opportunities, covering lands with low, medium and high development potentials.
Taking into account the result from the analysis, PDAs covering three areas,
namely LMC, MKT, and HYW/TKL/Queen’s Hill (QH), have been identified for
the NTN development, with a total area of about 1,400 ha (Figure 3.3.2 refers).
This figure is greater than 1,019 ha under Scenario 3 because existing villages,
existing settlements, existing residential/community facilities, agriculture and
green belt located in proximity to areas with high development potential have
also been included within the PDA boundaries for comprehensive planning.
2
The idea of NOL extension is to connect the TKL and Fanling North areas from Kwu Tung.
3
During the formulation of the CP at the later stage of the Study, the idea of NOL extension is replaced by the
concept of a possible north-south railway (A possible alignment connecting from HYW, TKL, PC, HLH to the
nearby new town and further extension to other new town and/or urban area.).
27
Population Estimate
3.4.2 The population level for the future NTN development was estimated based on
three approaches with different considerations, namely ‘Environmental
Capacity’, ‘Engineering Infrastructure Capacity’ (including transport and
effluent re-use) and ‘Employment Generating Capacity’.
Environmental Capacity
3.4.3 To determine the appropriate development capacity in the 5,300 ha NTN Study
Area, with the vision to achieve eco-city, low carbon city, wise city and walkable
city concepts and create a “new” generation new town beyond year 2030,
references has been made to eco-city standards as benchmarks.
3.4.4 EIU Green City Index - Firstly, the Study adopted top-rated cities in the
Economist Intelligence Unit (EIU) Green City Index (Copenhagen, Singapore,
and San Francisco) as benchmarks: These cities were assumed to have an optimal
population density, as this metric is one of the key drivers in reducing energy use
and emissions through allowing efficient public transit systems to develop. It is
noted that population density of these cities ranged between 69-75 persons per ha,
which multiplied by the 5,300ha of NTN implies a population range of about
366,000 -398,000.
3.4.5 China Eco-Cities - Similarly, best practices in Eco-Cities in China was also used
as a reference. It is noted that population density of these cities ranged between
83-125 persons per ha, which multiplied by NTN land area implies a population
of about 442,000 -663,000. However, as many of China’s Eco-Cities are largely
still under development rather than successfully populated and operating, this
density remains a hypothetical guideline rather than one that has been proven to
work well in practice.
3.4.6 NTN Land Resources - Thirdly, the MCD analysis output was categorised into
levels of suitability for development, mirroring the zoning categories for
residential development in Hong Kong. Prevailing development densities were
applied to the identified land resources in the vast area of the Study Area, based
on the Hong Kong Planning Standard and Guidelines (HKPSG) and plot ratio
ranges of existing New Towns. Using a range of average flat sizes, and typical
household sizes, an implied population was then extrapolated from the buildable
area of each category. A maximum population of about 400,000 can be
supported by the whole NTN land resources according to this methodology.
28
With reference to the MCD analysis and the comparable NDAs, a similar
housing to developable area ratio for the whole NTN land resources has been
adopted to determine the residential area in different types of density in
development.
3.4.7 In summary, the population estimated using the land resources capacity, 400,000,
was chosen as the unifying estimate. This estimation is considered valid as it is
close to the benchmark of the Green City Index. Although the China Eco City
benchmark imply a higher population could be desirable, the standards are
derived from a broad range of urban developments, where the contexts may be
very different from the NTN.
Engineering Infrastructure Capacity
3.4.8 A total of two infrastructure scenarios were developed, which is minimum
infrastructure and maximum infrastructure.
3.4.9 Minimum Infrastructure Scenario - The additional population that could be
supported is the combination of population that can be supported by existing
spare capacity on existing ER and WR Lines by 2041 and by the potential bus
29
Employment-Generating Capacity
3.4.12 The third methodology for forecasting a sustainable population in NTN is by
estimating its employment generating capacity. The maximum core employment
figure estimated (to be covered in the next section) was chosen as a starting point,
in order to create a population-employment pair in line with the planning
principle of creating opportunities for people and businesses for consideration.
Core jobs are hypothesized to exist on day 1 and induce a residential population
in the NTN. 4 In turn, the residential population creates more employment,
4
This is a highly simplified characterisation of the longer-term location choices that workers make: As with
many economic models, it starts from a completely unrealistic simplifying assumption, but the stripped down
simplification makes the process of how equilibrium is reached easier to comprehend. In reality, jobs emerge
over time and each new job causes the iterative process to take longer to come to equilibrium.
30
Source: (a) Arup assumption; (b) Inverse of 55% forecast from Planning Department Territorial Population and
Employment Data Matrices, 2041forecast for Northwest New Territories
Note: Total population induced have been rounded so the totals may differ slightly
5
Assumptions: (1) 50% of workers in NTN will chose to live in the Study Area; (2) Each worker supports a
household size of 1.82 in line with existing demographics; (3) population-serving jobs (in education, health,
basic infrastructure, building maintenance etc.) typically equivalent to 6.5% of district population in typical HK
districts.
31
Maximum:
as capped by NTN
Land Resources
Employment Estimates
3.4.14 Instead of adopting the conventional employment forecasting methods, an
alternative employment forecasting method, namely a sector-based forecast
(bottom-up approach) has been adopted in this Study. This approach has an
advantage that specific floor space requirement can be worked out for individual
employment sectors, and the process is illustrated in Diagram 3.4.2. The key
steps in the process are:
1) Creating a core employment forecast on a sector-by-sector basis; and
2) Assigning a share of jobs in each sector to the NTN
Diagram 3.4.2: Supply-led employment forecast methodology
3.4.15 The shortlisted sectoral industries, listed in Table 3.4.5, were used to generate a
bottom-up employment forecast for the territory as a whole, based on long term
GDP forecasts for real GDP growth over the 2014-2041 period, as well as the
GDP forecasts by sectors, using the annual sector output data and employment
figures for the 4 key and 6 pillar industries, as well as the forecasted growth of
tourism (specialized retail) and urban agriculture industries.
3.4.16 After job growth in key industries is forecasted, shares of new jobs in each
industry were then assigned to NTN according to the suitability of NTN to house
activity in that sector.
32
3.4.17 Table 3.4.6 summarizes the range of sectors that were assigned to the NTN under
the three different employment scenarios (i.e. weak, moderate and strong
economic linkages with PRD), with their rationales for locating in the NTN
elaborated.
3.4.18 Having rearranged job demand by type of space, we looked at the suitability of
the NTN as a location for specific job spaces as well as the drivers for each
specific industry to allocate a target range of share of jobs that could be located in
the NTN. The share of jobs going to the NTN will vary according to the
employment forecast scenario. Various percentage shares ranging from 3% to
50% were assigned using a combination of desktop research on existing industry
clusters or agglomeration patterns and stakeholder consultation.
33
3.4.19 Applying the different employment shares under different scenarios resulted in a
core jobs forecast for NTN ranging from about 99,000-184,000 as listed in
Tables 3.4.7 and 3.4.8.
34
3.4.23 These combinations were then applied as a basis for formulation of broad land
use options to be discussed in the next section of this FR.
3.5.2 The NTN is developed into a transition area between Hong Kong and the
Mainland, adopting the role of an urban fringe that supports commerce and trade
in the region while broadening the dependence of local residents on the existing
employment hubs in the wider territory. Option 1 is estimated to house a
population and employment of 219,000 and 124,000 respectively, which is a
scenario of minimum provision of new infrastructure with weak economic
linkage with the PRD.
3.5.3 New urban cores are carefully located to minimise impact on existing settlements
and are adapted to the local context in terms of development intensity. With
limited residential development, the NTN retains much of its scenic character
solidifying the perception of a rural and recreational region.
3.5.4 The limited development minimizes the requirements for additional railway
infrastructure, spurring development around the possible intermediate station on
NOL at LMC PDA, and the possible station at Chau Tau north of the San Tin
Highway.
3.5.5 Please refer to Figure 3.5.1 for the Broad Land Use Plan for Option 1.
3.5.6 Given NTN’s strategic location being adjacent to the major market in the
Mainland, this option seeks to redefine the region as a self-sufficient Productive
Metropolis that balances a significant provision of new employment places with
residential areas with strong economic linkage with the PRD. Option 2 is
estimated to house a population and employment of 200,000 and 215,000
respectively.
3.5.7 The option is supported by the extension of the NOL8 eastwards to the TKL area,
shifting the centre of the NTN to the TKL area which will develop into a major
commercial and residential area.
3.5.8 New urban cores already established in Option 1 are intensified to provide a mix
of commercial activities and housing that will function as working/living
environments minimizing the dependence on other hubs in the territory.
3.5.9 Please refer to Figure 3.5.2 for the Broad Land Use Plan for Option 2.
8
During the formulation of the CP at the later stage of the Study, NOL Extension is recommended to be
replaced by the concept of possible north-south railway.
9
During the formulation of the CP at the later stage of the Study, NOL Extension is recommended to be
replaced by the concept of possible north-south railway.
38
railway southwards to other new towns and/or urban areas would be required,
triggering a total of 3 phases of development. Besides, with the increased road
traffic, the need for and the practicality of more stringent traffic demand
management measures and/or a possible new highway would have to be explored.
3.6.7 Scenario III (Highest Population, Lowest Employment to Population Ratio)
is developed based on Broad Land Use Option 3 – Polycentric Living, with the
intention to explore a highest residential development scenario with the lowest
employment to population ratio, with same infrastructure provision compared to
Scenario II. Similarly, development by 3 phases is recommended. The
population/job combination is about 397,000/165,000. Compared to Scenario I
and II, it is necessary to designate more land at the PDAs in the east NTN for
residential uses in replace of a more diverse land use, with the maximum PR still
at 7.5. The scenario is skewed towards population increase, thus will generate
even more commuting trips to the urban area than that in Scenario II. Although
strategic transport infrastructure proposed is similar to Scenario II, the traffic
impact is expected to be much greater.
3.6.8 Evaluation of the pros and cons for the three development scenarios has been
conducted. Scenario III is not recommended for consideration in the next stage of
the Study. This is mainly due to its low employment level, which the planning
principle of creating opportunities for people and businesses can hardly be
achieved. Although Scenario III has a comparatively merit of housing high level
of residential use and population, the population density is even higher than that
of the Tseung Kwan O New Town and problem of incompatibility with nearby
rural settlements and setting of the rural NT is also anticipated.
3.6.9 Comparatively, Scenario I and II, which are considered more self-sustaining and
covering a spectrum of development thresholds with different characteristics, are
recommended to be further developed in the Study and should form the basis for
detailed planning and design for the CP to be discussed in the next section of this
Report.
10
There are changes in broad land uses presented in this section in view of the identification of site near
LT/HYW BCP for the development of Science Park (SP) and/or Industrial Estate (IE) as per the 2016 Policy
Address (please refer to Section 3.9 for details).
41
*Including the planned QH Development which will provide a population of about 40,000.
of the site will be restricted to 4 storeys. There is also an intention to enhance the
cross-boundary access to the LMC BCP, and the existing San Tin Public
Transport Interchange (PTI) for yellow buses will be improved by integrating into
this commercial area with multi-storey car parking which will be directly
accessible from the nearby the possible station in Chau Tau. District cooling
system (DCS) plants are proposed to be developed as part of the “C” site to the
southeast of the possible station in San Tin and at the “C” site that accommodate
the cross-boundary retail park, to provide chilled water to the air-conditioning
system for cooling purpose and for achieving energy efficiency, whereas exact
location and scale (whether it is a standalone building/ incorporated within the
future commercial building) will be subject to detailed design.
3.7.16 At the HYW PDA, “C” sites are designated with PR 6 intended to provide cross-
boundary retail facilities around a possible station and connectivity to the HYW
BCP.
3.7.17 At the TKL PDA, “C” sites which are proposed around a possible station in PC
are designated with a PR of 4. A site at the north of a possible station in HLH is
designed with a PR of 3, while another site at PC is designated with a lower PR
of 3. The proposed zone is intended to support the residential communities and
provide an employment node for the locality, serving as nodes for retail, office,
hotel and other commercial activities. A strip of land is also designated towards
the south of the TKL PDA, along the Sha Tau Kok Road, with a lower PR of 3.
The designated site will interact with the “C” zone in the opposite of the Sha Tau
Kok Road (at the QH’s PDA) to form a strip of commercial nodes which serves
for local retail, dinning and other activities.
3.7.18 Within the QH PDA, various sites locating along Sha Tau Kok are designated
with a PR of 3.5, serving as a buffer from the traffic noise and air pollution from
the Sha Tau Kok Road for residential areas to the south. The designated “C” sites
also interact with the commercial zone in the TKL PDA (as mentioned above) to
form a strip of commercial activity corridor which serves local retail, dinning and
other activities.
Mixed Use (“MU”) – 23 ha
3.7.19 “Mixed Use” sites are proposed among the LMC PDA, QH PDA and TKL PDA.
All sites are located near the possible railway stations to maximise development
potential for development of the core centre for each PDA. The planning
intention of “MU” is for a mixed residential and commercial uses. A combination
of various types of compatible uses including commercial, residential,
educational, cultural, recreational and entertainment uses, either vertically within
a building or horizontally over a spatial area is allowed. People movement are
spanned both under and above the possible stations creating the necessary
pedestrian connection across the at-grade or underground railway line.
3.7.20 “MU” sites with domestic PR of 5 and non-domestic PR of 1 are proposed at
LMC PDA. The sites will comprise both retail and residential above the possible
stations and be reaching a total of PR6 to optimize the benefits of transit-oriented
development (TOD) forming a new urban core and will be accompanied with
high-density commercial areas.
3.7.21 “MU” sites with domestic PR5 and non-domestic PR1 are proposed near the
possible stations at QH and PC. The sites will comprise both retail and residential
45
uses and be reaching a total of PR6 to optimize the benefits of TOD. At TKL
PDA, the “MU” site will form the new urban core near a possible station in PC
and will be surrounded by high density commercial areas up to PR4. At the QH
PDA, “MU” sites are designated immediately north of the planned QH
Development (which will be comprised high-density public housing, medium-
density private housing and an international school development housing nearly
40,000 population). The intention of this “MU” zone is to serve as a centre to
enhance the pedestrian connectivity of the planned QH Development towards the
possible station in QH, such as requiring at-grade public pedestrian corridor,
retail podium and etc., to reduce reliance on road-based transport.
Residential (“R”) – 224 ha
3.7.22 In general there are about 224 ha of land designated for residential uses. These “R”
zone clusters are mainly located around the possible railway stations and density
gradually reduces away from the station, with PR ranging from PR6 to PR1.5.
3.7.23 In the LMC PDA, residential uses are ranging from PR 3.5 to PR6. They are
generally located at the periphery of the PDA. PR6 residential uses are located
near to the proposed San Tin commercial core around the possible station, from
which the density descends gradually to PR5 and 3.5 towards the western and
southern fringe of the PDA. Further away from the possible station, towards the
eastern part of the PDA, medium-rise rural type residential development of PR3.5
are proposed, which creates a transitional increase of development intensity from
the rural context and the existing village-type development near the Ki Lun Shan
area to the cross boundary retail facilities at the north of the site.
3.7.24 In the TKL PDA, residential uses are ranging from PR1.5 to PR6. They are
generally located around the two possible stations, i.e. in PC and HLH and nearby
the proposed road network. Surrounding the central area of HLH, where the
possible station in HLH, a commercial area and various district G/IC facilities are
located, residential development of PR6 at the west gradually descending to PR
3.5 at the east forming a new residential neighbourhood at HLH of the PDA.
Around the possible station in PC and at the periphery of the commercial core,
medium-density residential area with PR3 are planned for gentle transition with
PR 1.5 at the west, while low-rise rural type residential development of PR1.5 are
generally scattered nearby existing villages and towards the southern part of the
TKL PDA which corresponds and respect to the rural context.
3.7.25 In the QH PDA, the proposed “R” zones are located to the south and east of the
planned QH development 11 . Developments immediately south and east to the
planned QH development are at PR 4.5 and 3.5 respectively. Another residential
site towards the northeast of the QH PDA, along Sha Tau Kok Road is planned
for PR1.5 to respect the local rural context and village settlements near the Ko Po
and San Tong Po area.
Villages (“V”) – 86 ha
11
The sites for the planned public housing (13.77 ha) and private housing (3.97) at QH have not been included
in the entries of “R” zones but a separate entry “Queen’s Hill Development (planned )” in Table 3.7.2.
46
belt and “AGR” zone in order to provide and maintain a rural setting environment,
buffered from new high-rise developments, to the low rise village houses.
Existing Settlements – 94 ha
3.7.32 Existing Settlements refer to established village settlements and squatter houses
which fall outside “V” zones and existing residential zones. They are usually
scattered near the existing “V” zones (Figure 3.7.6 refers). In order to respect
local established squatters and settlements, conservative approaches are taken to
minimize the encroachment to these existing settlements identified as far as
possible. The existing locations and size of Existing Settlements are recorded
based on survey plan, aerial photo interpretation and verified by site inspection,
subject to review in detailed design stage.
3.7.33 The boundary of the “Existing Settlements” is drawn by a general rule of 5m
from the Existing Settlements identified. For these “Existing Settlements”, as part
of the PDAs in the future, our intention is to provide incentives for these villagers
to upgrade the condition of these village houses and benefit from improvements
to infrastructure such as sewage, utilities and accessibility to enhance their living
standard. The area of “Existing Settlements” is therefore about 94 ha. Currently,
there is no statutory zoning for the recommended rural improvements for
“Existing Settlements” zone, which is a new concept proposed under this Study to
foster urban-rural-nature integration. Nevertheless, reference could be made to
the “Residential (Group D)” “(R(D))” or “OU(‘Rural Use’). The “R(D)” zone is
intended to improve and upgrade temporary structure within the rural areas
through redevelopment of existing temporary structures into permanent structure.
It is also intended for low-rise, low-density residential developments subject to
planning permission from the Town Planning Board. A similar zoning can be
provided with a determined development potential given to the site; while
“OU(“RU’)” zone is intended primarily for preservation of the character of the
rural area, and uses/development compatible with rural landscape may be allowed
on application to the Town Planning Board, with a view to upgrading or
improving the area or providing support to the local communities. These zonings
provide incentives for rural enhancement by providing some PR incentives, e.g.
PR0.4 for both “R(D)” and “OU(‘RU’)” zones, to tailor-make to these residential-
base village settlements and provide adequate incentives to organically improve
the entire rural environment and living standard. Thus, this new concept for rural
improvements needs to be further explored in detailed design stage of the Study.
Agriculture (“AGR”) – 172 ha
3.7.34 Agricultural land has been identified in the PDAs based on information received
from Agriculture, Fisheries and Conservation Department (AFCD) and PlanD on
location, size and status (active/abandoned) of agricultural land, which is further
modified by aerial photo interpretation and site inspection.
3.7.35 About 172 ha of land in the CP is zoned as “AGR”. Existing “AGR” land which
is currently actively farmed is preserved with the greatest effort unless major
infrastructural development is colliding with the existing “AGR” land.
3.7.36 Relatively large area of “AGR” land is planned in the TKL PDA and HYW PDA,
where areas of active agriculture and its surrounding abandoned farmland that are
with opportunities to be rehabilitated as a whole are proposed. Much of these
“AGR” land are located near to the “V” and “Existing Settlements” area which
helps to maintain a rural context to these village clusters. Several “AGR” land is
48
12
A site of about 0.86ha locating along main road has been reserved for a vehicle depot which is requested by
the FEHD, and the scale and location is subject to further discussion with FEHD.
49
3.7.43 In the TKL PDA, preserved existing G/IC uses include Wun Chuen Sin Koon,
Government farm, existing schools, rural committee building, existing pumping
stations, existing elderly homes and nursery school and Government Offices,
most of which are clustered along PC Road. Opportunities could be explored on
enhancing the use of these existing G/IC facilities in serving the future
development in the PDA, subject to discussion with the relevant Government
departments. For instance, opportunities could be explored to adaptive reuse of
the abandoned schools for agriculture/tourism related use. A range of new G/IC
facilities are proposed in the TKL PDA, which includes 12 primary schools and
10 secondary school, a swimming pool complex, a district police station, 3 sports
centres, a sports ground, a clinic, a hospital, a fire station cum ambulance depot
and a vehicle depot for Food and Environmental Hygiene Department (FEHD).
Most of the G/IC facilities are located at the edge of development hub, the only
difference is at HLH area. It is located at the centre of the population as this
location can reach the optimum population within the PDA. It should be noted
that a hospital, which is a regional facility is proposed in the TKL PDA at the
eastern edge of the TKL PDA yet with good access to the possible station in PC.
Moreover, similar to the LMC PDA, a site of about 1.6 ha locating along main
road has been reserved for a vehicle depot requested by FEHD. The scale and
location of these regional facilities are to be further discussed with the relevant
Government departments.
3.7.44 Within the QH PDA, existing and planned G/IC facilities includes the Kwan Ti
Public School, Agricultural Station, a church and a planned fire station cum
ambulance depot located along the Sha Tau Kok Road. New G/IC facilities
include 4 primary schools. It should be noted the planned QH Development will
also include 2 additional primary schools and an international school. The “G/IC”
zones are located at area where they can serve the population at the core of the
hub and also the population at villages/ existing settlements.
Open Space (“O”) – 85 ha
3.7.45 About 85 ha of land is designated as “Open Space” within the PDAs. Open space
corridors comprising landscaped routes, existing active agricultural uses and
preserved natural landscapes are therefore strategically configured to maximise
mobility linkages (including pedestrian and cycling routes) and preservation of
the rural character within larger urban development zones. One example is the
“green mobility loop” that surrounds the TKL PDA, which is a continuous linear
park of 30m in width to include a cycle track, pedestrian path and greenery. The
7.5km loop encourages existing and future residents to walk to work or access to
public facilities. For recreational purposes, it can be well equipped with a
potential jogging track and several linear playgrounds. As the loop intersects with
some possible railway stations and is linked with the proposed open space
systems within the PDAs with existing walking routes, it is highly connected on
both a regional and a local level.
3.7.46 At the same time, preserving interstitial access and visual links to important areas
in the vicinity, such as burial grounds and the agricultural landscape, will enhance
the integration of new development with the rural surroundings and minimise the
disruption to existing residents.
Logistics Industry – 24 ha
3.7.47 About 24 ha of land is designated as Logistics/ Light Industry use. PR3 are
applied in the zones at LMC PDA, TKL PDA and HYW PDA. The intention of
50
will maximize the synergy between research and production and will form the
west edge of the industrial corridor that begins with the 22 ha industrial areas
across the planned LT/HYW BCP Link Road to the east. The Science Park area
envelops part of an EIS that will be protected in the new development and
utilized as an open space resource.
Enterprise Park (“EP”) – 13 ha
3.7.53 About 13 ha of land with PR of 3 is reserved for “EP” at the LMC PDA along the
San Tin Highway. It is envisioned that this development will provide both work
space and the type of support and networking services more typically associated
with incubators and innovation districts. This facility would be targeted at a
broader range of industries, and cater to the needs of the local population. Social
enterprises could be a particular focus of this space.
Planned Queen’s Hill Development – 20 ha
3.7.54 About 20ha of land is for the planned QH Development. This includes a planned
public housing development (13.77 ha site) which will be developed with a PR6,
a private housing site (3.97 ha), assuming a PR3.6, and a “G/IC” site (2.34 ha)
planned for international school use. It is estimated that the planned QH
Development will provide a total population of about 40,000 13 . Within the
planned public housing site, 2 primary schools, a public transport terminus and a
community hall will also be provided.
Other Specified Use (“OU”) and Others – 151 ha
3.7.55 About 25 ha and 8 ha of land are planned as “OU” in the HYW PDA, for the
planned HYW BCP and a railway depot planned for accommodating the railway-
related facilities for the possible north-south railway .
3.7.56 Besides, about 118 ha of land in the CP are designated for other uses such as
roads, which include about 64 ha for existing/planned roads and 54 ha new roads.
13
Source: North District Council Paper No. 49/2014 discussed on 9 Oct 2014 and RNTPC Paper No. 7/15, on 8.5.2015 on
the proposed amendments to the Draft Lung Yeuk Tau and Kwan Tei South Outline Zoning Plan No. S/NE-LYT/15.
52
also shown in our CP that the proposed open space is located near proposed
population centre, easily accessible by both new and existing population, as well
as serving as linkage of future activity centres throughout NTN.
3.7.63 Thus, a total of about 85 ha of open space14 will be provided in the CP under
Scenario I.
3.7.64 For comparison purpose, the overall provision of open space per new population
is approx. 3.3m2 per person, which is comparable to open space provision
proposed in recent planning studies such as Tung Chung New Town Extension
(approx. 3.1 m2/person) 15 and Yuen Long South development (approx. 3.2
m2/person)16.
the Phase 1 development of West and East NTN will yield a population of 95,000
and 119,000 jobs.
Phase 2 (Figure 3.8.4 refers)
3.8.10 In Phase 2, possible railway line covering HYW, TKL, PC, QH and connecting to
the nearby new town is proposed to be developed, which triggers further
development of East NTN. The entire QH and HYW PDAs are to be developed in
this phase; and majority of the TKL PDA, which includes low to high density
residential uses, G/IC facilities, commercial uses (e.g. the cross-boundary retail in
HYW, retail area in QH, and Mixed Uses in PC and HYW) are to be developed in
this phase. During Phase 2, about 88 ha of land at HLH area, which is considered
far away from major development nodes will not be developed at this phase.
About 16 ha of land at HLH east of the proposed ring road is developed for
medium-rise residential in this phase as it can be supported by the proposed road
network.
3.8.11 In general, Phase 2 development of the East NTN will generate an additional
population of 160,000 and an employment of 89,000. The total (Phase 1 + Phase
2) population and employment will be 255,000 and 209,000 respectively, of
which the transport network performance would not be worsened by the
development as compared with the Base Case.
Phase 3 – Ultimate (Figure 3.8.5 refers)
3.8.12 In Phase 3, population beyond 255,000 is to be triggered and supported by a
possible railway extension from the nearby new town to other new towns and/or
urban area.
3.8.13 With the support of new rail connection to HLH and additional passenger
capacity actuated by the possible railway extension to further southward to other
new towns and/or urban area, further development at the remaining 88 ha of land
at HLH area is triggered for a high-density residential community with associated
commercial and G/IC use. This yields an additional of about 95,000 population
and about 6,000 jobs at high density residential uses.
3.8.14 Inevitably, the additional population intake would also induce additional road
traffic demand that would need more stringent traffic demand management
measures and/or new transport initiatives (e.g. possible new highway) to be in
place for attenuating such impact.
3.8.15 This Scenario in total (Phase 1+2+3) can generate a population of about 350,000
and provide about 215,000 jobs, with jobs/population ratio equals to about 61%.
3.8.16 The population and employment estimates for the CP under Scenario II are
presented in Table 3.8.1.
57
provide an employment node for the locality, serving as nodes for retail, office,
hotel and other commercial activities.
3.8.20 Within the QH PDA, sites locating along Sha Tau Kok Road are designated with
a PR of 6.5. Similar to Scenario I, the strip of land is intended for commercial use
to serve as a buffer from the traffic noise and air pollution along the Sha Tau Kok
Road for residential areas to the south. The designated “C” sites are intended to
form a commercial activity centre which serves local retail, dinning and other
activities of the PDAs.
Mixed Use (“MU”) – 14 ha
3.8.21 “Mixed Use” sites are proposed within the LMC PDA, HYW PDA and TKL
PDA. All sites are located near the proposed NOL or possible stations in the East
NTN to maximise development potential for development of the core centre for
each PDA, similar to Scenario I. The planning intention of “MU” is for a mixed
residential and commercial uses. A combination of various types of compatible
uses including commercial, residential, educational, cultural, recreational and
entertainment uses, either vertically within a building or horizontally over a
spatial area is allowed. People movement are spanned both under and above the
possible stations creating the necessary pedestrian connection across the at-grade
or underground railway line.
3.8.22 “MU” sites in LMC PDA is designated with domestic PR of 5 and non-domestic
PR of 1 are the same as Scenario I.
3.8.23 “MU” sites with domestic PR6 and non-domestic PR1.5 are proposed at TKL
and HYW PDAs near possible railway stations in PC and HYW. The sites will
comprise both retail and residential uses and be reaching a total of PR7.5 to
optimize the benefits of TOD. At TKL PDA, the “MU” site will form the new
urban core near the possible stations in PC and will be located south to the high
density commercial areas up to PR6.5. At the HYW PDA, a “MU” site is
designated immediately south to the cross boundary retail facilities up to PR7.5.
The intention of this “MU” zone is to serve as capture the development potential
bought by the TOD arrangement and integrating with the cross boundary retail
activities in connection to the BCP.
Residential (“R”) - 248 ha
3.8.24 In general there are about 248 ha of land designated for residential uses. These “R”
zone clusters are mainly located around the possible railway stations and density
gradually reduces away from the station, with PR ranging from PR7.5 to PR1.5,
which is higher than Scenario I.
3.8.25 While residential zones at LMC PDA are the same as Scenario I, the TKL PDA
in general provides residential uses ranging from PR1.5 to PR7.5. They are
generally located around the two possible stations, i.e. PC and HLH and nearby
the proposed road network. For instance, residential developments of PR6 to
PR7.5 are located near the central area of HLH, where possible station in HLH
and various district G/IC facilities are located. The residential developments
generally decrease westward to PR 5 and further decrease towards the east which
is delineated by the proposed district road to PR3.5. Around the possible station
in PC, at the periphery of the commercial core, high-density residential area of
PR 7.5 are designated, and gradually reduced to PR5 and then transform to
medium-density residential uses with PR 3.5 to the southwest. Low-rise rural type
60
3.8.33 The location and arrangement of the “G/IC” zone in the LMC PDA is the same as
Scenario I.
3.8.34 New G/IC facilities are proposed in the HYW PDA, which includes a primary
school, a secondary school and a fire station cum ambulance depot.
3.8.35 In the TKL PDA, existing G/IC uses are the same as Scenario I. A range of new
G/IC facilities are proposed in the TKL PDA, which includes 16 primary schools
and 12 secondary school, a swimming pool complex, 4 sports centres, a sports
ground, a fire station cum ambulance depot, a clinic, a hospital and a vehicle
depot for FEHD. Most of the G/IC facilities are located at the edge of
development hub, the only difference is at the HLH area, and it is located at the
centre of the population as this location provides the largest amount of population
among the PDA. Same as Scenario I, a hospital as a regional facility is proposed
at the eastern edge of the TKL PDA. Moreover, similar to the LMC PDA, a site
of about 0.86 ha locating along main road has been reserved for a vehicle depot
which is requested by FEHD. The scale and location of these regional facilities
are to be further discussed with the relevant Government departments.
3.8.36 The QH PDA, existing G/IC facilities include the Kwan Ti Public School,
Agricultural Station, existing church and a planned fire station cum ambulance
depot located along the Sha Tau Kok Road. New G/IC facilities include 5
primary schools, a secondary school, a clinic, a sports centre and a police station.
It should be noted the planned QH Development will also include an additional
primary school and an international school. The “G/IC” zones are located at area
where they can serve the population at the core of the hub and also the population
at villages/ existing settlements.
Open Space (“O”) – 83 ha
3.8.37 About 83 ha of land is designated as “Open Space” within the PDAs, which the
area and distribution is largely the same as Scenario I.
Logistics Industry – 24 ha
3.8.38 The arrangement and intention of the zones are the same as Scenario I.
Agri-Logistics – 33ha
3.8.39 The arrangement and intention of the zones are the same as Scenario I.
Tourism/ Leisure (“T/L”) – 12 ha
3.8.40 Tourism/ Leisure with a PR of 0.8 occupies about 12 ha of land at HYW PDA.
The arrangement and intention of the zone is the same as Scenario I.
Industrial Estate (“IE”) – 39 ha
3.8.41 Land at TKL PDA and HYW PDA are designated as “IE”, with a total area of 39
ha, with a PR of 4. The IE sites are located on the two sides of the planned
LT/HYW BCP Link Road. The arrangement and intention of the zone is the same
as Scenario I.
Science Park (“SP”) - 22 ha
3.8.42 About 22 ha of land at TKL PDA is designed for “SP” with a PR of 3. It is
envisaged that the SP will be arranged as a walkable community with shared
62
conference and recreational spaces as well as dining areas. The arrangement and
intention of the zone is the same as Scenario I.
Enterprise Park (“EP”) - 13 ha
3.8.43 About 13 ha of land with PR of 3 is reserved for “EP” at the LMC PDA along the
San Tin Highway. The arrangement and intention of the zone is the same as
Scenario I.
Planned Queen’s Hill Development – 20 ha
3.8.44 About 20 ha of land is for the planned QH Development. This includes a planned
public housing development (13.77 ha site) which will be developed with a PR6,
a private housing site (3.97 ha), assuming a PR3.6, and a “G/IC” site (2.34 ha)
planned for international school use. It is estimated that the planned QH
Development will provide a total population of about 40,000 18 . Within the
planned public housing site, two primary schools, a public transport terminus and
a community hall will also be provided.
Other Specified Use (“OU”) and Others – 151 ha
3.8.45 About 25 ha and 8 ha of land are planned as “OU” in the HYW PDA, for a
railway depot planned for accommodating the railway-related facilities for
possible north-south railway.
3.8.46 Besides, about 118 ha of land in the CP are designated for other uses such as
roads, which include about 64 ha for existing/planned roads and 54 ha new roads.
18
Source: North District Council Paper No. 49/2014 discussed on 9 Oct 2014 and RNTPC Paper No. 7/15, on 8.5.2015 on
the proposed amendments to the Draft Lung Yeuk Tau and Kwan Tei South Outline Zoning Plan No. S/NE-LYT/15.
63
locations and urban fringe areas on the CP. This is intended to also provide
recreational outlet to serve wider needs of territorial population and tourists. It is
also shown in our CP that the proposed open space is located near proposed
population centre, easily accessible by both new and existing population, as well
as serving as linkage of future activity centres throughout NTN.
3.8.53 Thus, a total of about 83 ha of open space will be provided in the CP under
Scenario II 19 . As compared to Scenario I, with a much higher population of
350,000 in the NTN, a more or less similar amount of open space is provided to
serve the future population. This is due to the competing land uses in Scenario II
to accommodate the additional 95,000 population with the same amount of
employment to be generated.
3.8.54 For comparison purpose, the overall provision of open space per new population
is approx. 2.4 m2 per person, which is slightly lower than the open space
provision proposed in recent planning studies such as Tung Chung New Town
Extension (approx. 3.1 m2/ person)20 and Yuen Long South development (approx.
3.2 m2/ person)21. Nevertheless, the provision of open space under Scenario II is
able to meet the requirement under the HKPSG.
19
The total amount of Open Space provision shown on the CP include RO, DO and LO (required for
employment only). Required LO for residential population is assumed to be provided within individual
residential development lots in detailed design stage and therefore not shown on the CP at this stage..
20
According to the latest RODP for Tung Chung New Town Extension in June 2016.
21
According to the Stage 3 Public Engagement Digest for the Yuen Long South Study.
65
Link Road to be completed by 2018 and the highway network in Tai Po. It is
large enough to accommodate a SP cum IE development to achieve
agglomeration of innovation, research and development, and production allowing
vertical integration of industries within the I&T ecosystem.
3.9.4 In view of the 56-ha site identified for SP/IE development near LT/HYW BCP,
the land uses of the sites originally planned for SP and IE in the east of the NTN
New Town27 (total land area of about 61 ha) under the NTN Study have been
reviewed to avoid a situation where the NTN New Town is dominated by a single
industry and to achieve an integrated community of new industrial productions
and urban living28.
3.9.5 After the review, sites of about 34 ha could be retained for SP/IE development
and other supporting industries whilst the remaining sites could be considered for
other competing uses such as modern logistics. It is considered that the SP and
IE sites in the NTN New Town with a total area of about 90 ha are appropriate as
far as sustained I&T development and the balanced composition of the New
Town are concerned.
3.9.6 The aforesaid changes in broad land uses would lead to an increase in SP, IE and
modern logistics uses and a reduction in “Mixed Use”, “C”, “GB”, “O” and
“G/IC”. Nevertheless, the overall population and employment levels of the NTN
development under the two scenarios remain unchanged.
27
HYW, TKL and QH PDAs are presented as the NTN New Town in the public engagement for "Hong Kong
2030+" (please refer to paragraph 7.1.2 for details).
28
Residential and community facilities would be provided to support new anchor uses of the Eastern
Knowledge and Technology Corridor.
67
4 Technical Assessments
4.1 Introduction
4.1.1 “Smart Green Resilient” (“S-G-R”) has been proposed as the overarching
approach to the NTN development. This concept of this approach has embedded a
number of future city development concepts including eco-city, low carbon city,
walkable city and wise city concepts. The diagram below illustrates the overall
process and key components of the S-G-R framework for development of NTN.
This framework serves the following purposes:
identifying not only technical, but also institutional and management
components to steer the future S-G-R development;
demonstrating individual technical assessments and institutional
components to be seen as part of an integrated strategic approach; and
Diagram 4.1.1 S-G-R Governance Framework
4.1.2 In this Study, recommendations are made for way forward of infrastructure
provisions to shape the vision of NTN development. Measures and technologies
68
are also proposed for smart, green and resilient city for key infrastructure areas.
The recommendations and measures proposed are based on evaluation of existing
conditions and also extensive desktop research and review. Some of them are
supplemented by overseas examples showing that current applications of the
technologies in overseas are available.
4.1.3 Both Scenario I and Scenario II are recommended for further study in the next
stage. As compared to Scenario I, Scenario II has a higher population level and
higher development intensity and is expected to have greater impacts. Scenario II
has therefore been adopted as the worst-case scenario for the technical
assessments under the Study.
4.1.4 Detailed technical assessments integrally ascertain the feasibility of the proposed
measures taking into account the characteristics of the Study Area including
topography, land use, population and existing infrastructure. A number of
technical aspects have been assessed:
Geotechnical
Traffic and Transport
Drainage, Sewerage, Water Supply and Utility
Air Ventilation
Socio-economics
Sustainability
Green Initiative and Carbon Appraisal Study and “Wise City” Concept
Environment (Strategic)
Landscape and Visual
Broad Cost
4.1.5 The following summary of technical assessments is based on an earlier version of
the CP and illustrative BLCPs for PDAs. Changes to the CP have been made
subsequently, including the expansion of the possible SP and IE development
discussed in Section 3.9. As such, some of the quoted figures/data contained in
this section for Technical Assessment may not entirely tally with the CP
presented in Section 3 which has already incorporated those changes. As the
overall population and employment levels of the NTN development under the two
scenarios remain unchanged, it is considered that those changes to the CP do not
have material impact on the broad technical feasibility of the CP.
4.2.2 The solid geology of the Study Area generally comprises metamorphosed lapilli
ash or coarse ash crystal tuff, locally schistose, of the Tai Mo Shan formation of
Upper Jurassic age. The MKT PDA comprises meta-siltstone, meta-sandstone
and phyllite with metasandstone of the MC formation of early Carboniferous age.
4.2.3 The Study Area is within part of the NE-SW orientated Lo Wu-Tuen Mun fault
zone. This fault zone includes the San Tin fault, which is located to the south of
all PDAs. The San Tin fault is a south west to north east trending thrust fault
which dips at a low to moderate angle towards the northwest, forming the
unconformity between the Upper Jurassic volcanics and the older Carboniferous
meta-sediments. The older metasediments are thought to have been thrust over
the volcanic deposits during the Late Cretaceous (Figures 4.2.1 to 4.2.2).
4.2.4 The locations of Enhanced Natural Terrain Landslide Inventory (ENTLI)
landslides within the Study Area are presented on Figures 4.2.3 to 4.2.7. There
are 138 nos. of landslides recorded in the natural hillside.
4.2.5 For the existing registered feature, a preliminary review of the Geotechnical
Engineering Office (GEO) Slope Information System (SIS) records has identified
the presence of over 615 nos. of manmade slope or retaining wall features within
the Study Area (Figures 4.2.8 to 4.2.12).
4.2.6 A search of the records held within the Geotechnical Information Unit of GEO
and previous publications identified over 500 nos. of drillhole records within and
in close vicinity to the Study Area (Figures 4.2.13 to 4.2.17).
Constraints
4.2.7 The initial review of the anticipated final landform of the Study Site has
identified some areas which require cautions for developments and infrastructures.
4.2.8 Areas with anticipated deep weathering - according to the latest 1:100,000
geological map (Sewell et al., 2000), the Study Area is generally traversed by the
San Tin fault and NE to NEE trending faults at central and south portion (Figure
4.2.19). The presence of faults or fault zone may result in deep weathering and
sharp contrast in engineering and hydrogeological properties of the bedrock,
which could be a major concern to engineering projects. A steeply inclined and
irregular rockhead profile makes the construction of end-bearing piles very
difficult. It is also problematic for driven pile construction as piles have to
penetrate very deep to pass through the weak material and may be prone to
deflection along the rockhead surface.
4.2.9 Areas with extensive coverage of soft compressible deposits - highly
compressible and soft sediments are commonly present in the areas of flat-lying
terrain, including organic pond deposits and marine mud in the north-western
portion near the coastal areas, such as LMC PDA (Figure 4.2.18). In addition,
alluvium of high clay/ silt content is generally presented in other Study Area as
indicated by the existing Ground Investigation (GI) information. These materials
may pose settlement problems for shallow founding of the proposed structures. In
addition, excavations in such materials may be problematic due to the low batter
angles generally required and the highly anticipated water inflows.
Comprehensive ground investigations would be required to determine suitable
founding conditions in such areas.
4.2.10 Marble-bearing strata - The 100,000 scale geological map indicates an inferred
subcrop area of Carboniferous metasedimentary rocks including marble present in
70
the northern portion of the Study Area (Figure 4.2.18). An area of complex
geology due to the presence of marble or marble-bearing strata and karst features
is also known to occur at depth (-200 mPD) based on the 1:20,000 scale
geological cross section. Considerable care will be required during investigation,
design and construction of any facilities within the marble areas. According to
Geotechnical Area Studies Programme (GASP) Report IV (GCO, 1988a), bearing
capacities are reasonable only for low to moderate loads on meta-sediments and
marble without large cavities. Rapid fluctuation of the groundwater table can lead
to the formation of either collapse, sinkholes or gradual settlement in the
overlying superficial deposits if hydraulic continuity exists, as soil is washed into
the void system.
4.2.11 The presence of marble provides engineering challenges for the design and
construction of pile foundation. There are practical difficulties in installing long
piles through difficult ground conditions. Locally steeply dipping rockhead
leading to foundations are time-consuming and costly. Additional ground
investigation works is required to ensure adequate information for the foundation
design. ETWB TC(W) No. 4/2004 should be followed where marble was
identified.
4.2.12 Areas with substantial natural terrain hazards - natural terrain areas are present
generally in the Study Area (Figure 4.2.18). These natural terrain areas may be
subject to landslide and rock/boulder fall hazards, which may present adverse
impact on the proposed development adjacent to the natural hillside. Where
possible, it is preferable to avoid construction of new occupied facilities and
infrastructure in these hillsides, instead opting for the placement of Group 4 or 5
facilities within the 50 m buffer zone adjacent to any high risk natural terrain
areas. According to GEO Report 138, Table 1, Group 4 facility corresponds to
lightly-used open-air recreation area (e.g. district open space, lightly-used
playground, cemetery, and columbarium), non-dangerous goods storage site and
road with low vehicular or pedestrian traffic density. Group 5 facility corresponds
to remote area (e.g. country park, undeveloped green belt, abandoned quarry) and
road with very low vehicular or pedestrian traffic density.
Opportunities – Rock Cavern
4.2.13 Rock cavern suitability maps have been developed to present territory-wide
potential area to utilise rock caverns. The map was developed in order to aid the
selection of potential areas for cavern development during the planning stage.
The map shows areas of high, medium and low cavern suitability depending on a
range of factors including whether the relevant areas have poor geology, are
scheduled or landfill areas and whether it is in close proximity to tunnels and
other underground structures. High suitability areas are those areas that are
considered to be more easily developed with reduced overall construction cost.
Areas which are considered not suitable for cavern development are also shown
on the cavern suitability map. Taking account of the terrain, the cavern suitability
map will be used to identify those locations with the opportunity for cavern
development. Areas of medium to high suitability will be considered suitable for
further consideration in the study. Cavern Suitability Map of the Study Area is
given in Figure 4.2.20.
4.2.14 There are many potential uses for rock cavern and the future development should
consider what facilities are suitable for locating underground. The functional
requirements of cavern shall decide the required size and number of caverns
71
P&E Studies as the development and infrastructure plans and designs further
developed. The contents of ETWB TCW No. 15/2005, which outlines the policy
and procedures for geotechnical control of planning, design and construction for
tunnel works will be followed.
Natural Terrain Hazard Assessment
4.2.21 In accordance with GEO Report No. 138, the natural hillside catchment within
the Study Area and overlooking respective PDAs would fall under “Alert
Criteria”, and a Natural Terrain Hazard Study (NTHS) will be required to study
the hazards and identify any mitigation. The extent of natural hillside potentially
requiring NTHS is indicated in Figures 4.2.21 to 4.2.25.
Central Link (SCL) (under construction), while observing the capacity constraints
on the existing ER Line (future North South Corridor) and WR Line (future East
West Corridor). The initial concepts of the transport infrastructure described in
the ensuing paragraphs are assumptions adopted in this traffic and transport
impact assessment.
4.3.5 In the west, to take advantage of the proposed NOL, provision of intermediate
stations along the proposed NOL (subject to further study and land planning) is
proposed to serve the LMC PDA (Figure 4.3.1 refers).
4.3.6 In the east, to enhance the connectivity and capacity of the railway network
serving the eastern PDAs, a possible north-south railway is proposed. (Figure
4.3.1 refers). The possible north-south railway is proposed connecting the eastern
PDAs from HYW with possible intermediate stations at QH, PC, HYW and HLH
to (i) a nearby new town, and (ii) further extension to other new towns and/or
urban area.
4.3.7 Subject to further study, the possible north-south railway is proposed to be
entirely underground. This is to minimise surface disruption to land use for
railway construction and for operation and to eliminate major environmental
issues such as noise, vibration, ecology, trees and heritage loss for the operational
stage.
4.3.8 With the possible railway scheme in place, the loading condition at the most
critical section of West Rail Line would remain generally the same as the Base
Case. The possible north-south railway connecting to other new towns and/or
urban area is recommended for supporting the CP under Scenario II.
4.3.9 The scheme can be implemented in phases to suit the progressive phasing of the
NTN development. Subject to further study of railway planning, the main line
section from HYW to the nearby new town will first be provided in Phase 2 that
will then be extended further southwards connecting to other new towns and/or
urban area in Phase 3 to serve the new developments in HLH area of the TKL
PDA.
Strategic Road Network Review
4.3.10 The strategic highway performance based on the more critical Scenario II has
been assessed. Unlike the employment-focused development under Scenario I,
which is envisaged to provide marginal improvements to the performance of
some of the major existing highways such as Tolo Highway, Tai Lam Tunnel and
Tuen Mun Road (Siu Lam section) serving strategic traffic in the north-south
direction over and would not be worse than the base case without NTN
development, Scenario II would inevitably increase traffic loading on these
highways worsening their operational performance.
4.3.11 Subject to the Government’s holistic review of traffic growth and development
potential from the territory-wide perspective, more stringent traffic demand
management measures (e.g. car free zone or vehicle restrictions, traffic adaptive
control system, integrated intelligent public transport system etc) and/or new
transport initiatives/proposals would need to be further investigated in the future.
Local and District Road Network Review
4.3.12 The proposed local and district road network will provide connectivity both
internally and externally to the PDAs via a combination of upgraded existing
74
roads, and new single and dual carriageways. All upgraded and new roads will
incorporate the appropriate pedestrian and cycling facilities. The proposed road
network (as shown in Figure 4.3.2) together with necessary improvements at key
local junctions would be capable of handling the traffic generated by the NTN
development without causing insurmountable traffic impact.
4.3.13 The possibility of access connection between the planned QH public housing
development and Po Kak Tsai Road to enhance its connectivity with QH PDA
would be investigated in the stage of P&E Studies.
4.3.14 To provide a continuous and connected cycle network, the upgraded and new
roads are proposed to include a standard cycle track (4.0m wide) running in
parallel with the road. The proposed cycle network is shown in Figure 4.3.3
which will provide cycle linkage within and between PDAs, as well as
connections to the strategic cycle network in the region.
Other Transport and Mobility Strategies
4.3.15 The overarching transport and mobility vision for the NTN is to serve internal
and external trips efficiently and effectively through a comprehensive, multi-
modal transport system, which will be complemented by high-density, mixed use
development around station areas, and policies and infrastructure that are
conducive and favourable to green transport modes including walking, cycling,
public transport, and alternative mobility schemes. Apart from the traffic and
transport schemes proposed in the preceding sections to facilitate efficient traffic
and passenger movements, different transport and mobility strategies have also
been explored under the purview of six key guiding principles (in order of
priority):
Principle A: Appropriate Land Use and Transit-Oriented Development
(TOD) – Develop mixed use, higher density developments around rail
stations (i.e., Transit-Oriented Development) to reduce auto ownership and
use, shorten average trip lengths, and to encourage reverse commuting trips
to utilize spare system capacity.
Principle B: Pedestrians First – Prioritise pedestrians in the planning,
design and urban fabric of streets, green areas, and transport infrastructure to
provide a safe, continuous, and convenient walking environment that
facilitates greater public transport use and reduces private vehicle use, and
complements the car free zone concept.
Principle C: Cycling as a Primary Mode of Transport for Short and
Medium Distance Trips – Provide direct, continuous, and segregated
cycling paths and dedicated parking facilities to encourage cycling (and
greater public transport use), facilitate the car free zone concept, and link to
the existing/planned Strategic Regional Cycling Network.
Principle D: Convenient, Efficient and Environmentally-Friendly
Transport Options – Provide multiple transport options that are convenient,
efficient, and environmentally-friendly to discourage car ownership and use,
and thereby encourage use of more sustainable and green transport modes.
Rail will continue to serve as the backbone of the network, with walking,
75
cycling, rubber-tire public transport etc. providing the first- and last-
kilometre connection.
Principle E: Transportation Demand Management (TDM) – Employ a
variety of TDM strategies and measures to encourage alternatives to driving
and private vehicle use, and for better management of parking demand and
supply. This may include financial incentives/disincentives and other policy-
driven measures.
Principle F: Smart Technologies and Strategies – Deploy emerging smart
technologies and strategies to improve the transport user experience,
enhance operations and efficiency of the multi-modal transport system, and
reduce environmental impacts.
4.3.16 A summary of the strategies explored and their applicability to individual NTN
PDAs is given in Table 4.3.1.
Table 4.3.1 List of Transport and Mobility Strategies and Their Applicability
to the NTN PDAs
Applicability of Strategy to NTN PDAs
No. Strategy LMC MKT HYW TKL QH
Principle A: Appropriate Land Use and Transit-Oriented Development (TOD)
A1 TOD X X X X
A2 Mixed Use X (ST) X X X
A3 Jobs-Housing Balance X (ST) X X X
Principle B: Pedestrians First
B1 Walkable City R R R R
B2 Car Free Zone R
(ST R R R
Only)
B3 Comprehensive Pedestrian
X X X X X
Network
B4 Universal Accessibility X X X X X
Principle C: Cycling as a Primary Mode of Transport for Short and Medium Distance Trips
C1 Comprehensive Cycle Network
X X X X X
and Facilities
C2 Cycle “Shortcuts” X X
C3 Cycle “Superhighways” R R X R
C4 Cycle Parking System X X X X X
C5 Cycle Rental / Sharing X X X X
Principle D: Convenient, Efficient and Environmentally-Friendly Transport (EFT) Options
Comprehensive Public
D1 X X X XX X
Transport Network
Electric and Environmentally
D2 X
Friendly Buses
Enhanced Bus and Bus Priority
D3 X X X X X
Treatments
D4 Bus Rapid Transit (BRT) X
D5 Modern Tram X
D6 Urban Light Transit (ULTra) X
D7 Optimised San Tin PTI X
Bus-Bus Interchange (BBI)
D8 (Note: BBIs located south of X X
noted PDAs)
Principle E: Transportation Demand Management (TDM)
E1a Car Sharing XXX X X XXX XXX
76
4.3.17 While some of the above identified strategies (such as those related to land use
and TOD, comprehensive public transport network (with railway as backbone),
etc.) have been incorporated in the CP, others are largely conceptual at this
preliminary stage of study. Specific schemes to support the relevant strategies
will need to be further developed and examined in the stage of P&E Studies. In
particular, the implementation of certain strategies will have to be examined on a
wider regional or territorial basis rather than in the local context of NTN
development areas only.
4.3.18 For the purpose of TTIA, the travel behaviour and transport demands were
assessed based on the “business as usual” model. This provides more
77
4.4.3 To mitigate the potential drainage impacts arise, it is recommended in the DIA to
provide retention ponds and lakes to attenuate peak surface runoff within the
PDAs. Multiple formation levels and stormwater treatment are proposed to be
considered in these retention tanks / lakes. Preliminary size and location of the
proposed retention tanks / lakes is summarized in Table 4.4.2 and on Figures
4.4.1a to 4.4.1f.
Table 4.4.2 Summary Details of Proposed Retention Ponds and Lakes
Proposed Land use for
Retention Ponds /
the Ponds / Lakes
Name of PDA Lakes Storage Volume (m3)
Locations
Designations
Green Belt
MKT PDA MKT-1 5,925
Agriculture
HYW PDA TKL-1 34,035
Open Space
TKL PDA TKL-2 12,605
*Implementation of these proposed retention ponds and lakes should be carried in the stage of
P&E Studies.
4.4.4 The following existing main drainage systems potentially conflict with the PDAs
have been identified in the DIA and Table 4.4.3 below summarized the proposed
treatment to these existing drainage systems.
Table 4.4.3 Proposed Treatment of Existing Drainage System Potentially in Conflict with
the Development in Various PDAs
Existing Drainage System
Name of PDA Potentially in Conflict with the Proposed Treatment
Development
(a) Upstream section of San Tin
Channel proposed to be retained
Eastern Channel
4.4.5 A broad review of the existing engineered drainage channels and nullahs within
the Study Area has also been conducted under the DIA. Table 4.4.4 below
summarized the proposed revitalization and rehabilitation works to these existing
drainage channels / nullahs.
Table 4.4.4 Existing Drainage Channels and Nullahs to be Revitalised and
Rehabilitated
Existing Drainage System Potentially in Conflict with the
Name of PDA
Development
- San Tin Eastern Channel (feasibility of revitalising the
LMC PDA channel is currently being studied by the Drainage Services
Department (DSD))
- Ping Yuen River (feasibility of revitalising the channel is
currently being studied by DSD)
- Channel (l)
TKL PDA - Channel (m)
- Ng Tung River
- Tan Shan River
- Kwan Tei River
81
4.4.8 To deal with the additional sewage generated within the LMC PDA, two options
have been recommended in the SIA for consideration at later stage of the Project.
Under Option 1, 16,000m3/day sewage is recommended to be handled by the
Yuen Long Sewage Treatment Works (STW) and the remaining some
22,100m3/day sewage would be treated in the new proposed STW (designated as
“LMC STW”) on Figure 4.4.3. Under Option 2, a new STW of design capacity
of 38,100m3/day is proposed to handle all additional sewage generated within the
LMC PDA.
4.4.9 For HYW PDA, TKL PDA and QH PDA, since there is no space in the current /
expanded Shek Wu Hui STW for further expansion, it is recommended to
construct a new STW (designated as “PC/TKL STW”) on Figure 4.4.3 to handle
the additional sewage generated within the 3 PDAs.
4.4.10 In the SIA, it is also recommended that the MKT PDA would be handled by
existing Shek Wu Hui STW. Diversion of flow from existing NENT sewerage
system, which collects sewage flows from the existing village areas in PC and
TKL as well as the leachate flows from the existing and planned expansion of the
NENT Landfill, and from Shek Wu Hui STW to the new PC/TKL STW is
proposed to free up spare capacity at Shek Wu Hui STW for the development at
MKT PDA.
82
4.4.11 In order to comply with the “No Net Increase in Pollution Loading” Requirement
of the Deep Bay Water Control Zone, three options have been considered:-
i. Option 1 – Reuse of treated sewage effluent (TSE) within the PDAs and
other existing urban areas / proposed developments;
ii. Option 2 – Export of the TSE outside of the Deep Bay Water Control
Zone; and,
iii. Option 3 – Hybrid solution of Option 1 and Option 2.
Water Supply Impact Assessment
4.4.12 A Water Supply Impact Assessment (WIA) was carried out for the CP under
Scenario II to confirm the acceptability of the proposed developments under this
Study in water supply aspect and to recommend water supply systems.
4.4.13 The Table 4.4.6 below and summarized the development details and fresh and
flushing water demand within the proposed PDAs.
Table 4.4.6 Water Demand within PDAs
Total Demand
Population
Name of PDA (m3/day)
Residential Employment Fresh Water Flushing Water
4.4.14 To provide fresh water supply for the NTN Development, it is recommended to
consider the additional fresh water demand from the NTN development for future
expansion of Tai Po Water Treatment Works (WTW). In addition, uprating of
existing pumping station or new pumping station will also be required to feed the
treated water to the proposed service reservoirs. Two new fresh water service
reservoirs (FWSRs), one in PC (designated as “PC/TKL FWSR”) and another in
Ngau Tam Mei (designated as “NTM FWSR”) are recommended in the WIA to
feed the proposed PDAs (as shown in Figure 4.4.2). The PC/TKL FWSR would
feed QH PDA, TKL PDA and HYW PDA, and also make provision of storage for
supply to MKT PDA through adjustment of supply zone with Table Hill and
Tong Hang FWSR. Its proposed fresh water demand from the above PDAs is
104,608 m3 and thus requires a storage capacity of 104,700 m3. Another NTM
FWSR is proposed to provide fresh water supply for the proposed LMC PDA.
The fresh water demand from LMC PDA is 32,349 m3 which will require a
storage capacity of 32,400 m3 to serve primary and secondary function.
83
4.4.15 Apart from FWSRs, two sites are also identified for new flushing water storage
reservoirs (FLWSR) in PC (designated as “PC FLWSR”) and in NTM
(designated as “NTM FLWSR”) which are indicated in Figure 4.4.4. In this stage,
it was proposed to supply the FLWSRs with TSE generated from the existing and
/ or proposed STWs. Apart from the new FWSRs and FLWSRs, associated trunk
and distribution mains will also be required. Since the additional water demand is
recommended to be taken up by the expansion of Tai Po WTW, a link should be
provided for linking up the trunk mains of Tai Po WTW, Sheung Shui WTW and
NTM WTW so that the additional water demand arising from LMC PDA could
be provided by Tai Po/Sheung Shui WTW.
Utility Impact Assessment
Existing and Planned Power Transmission and Distribution System
4.4.16 In the Study Area, there is only one electricity power service provider, the CLP
Power Hong Kong Limited (CLPP). In general, most of the existing distribution
cables are laid underground along public roads within the NTN. Overhead high
voltage transmission powerline supported on pylons can also be found in hilly
terrain and rural areas.
4.4.17 The clearance requirements for the 400kV and 132kV overhead power cables
within the Study Area are considered to be constraints to the boundary of
proposed land use developments. CLPP, Fire Services Department (FSD) and
Electrical and Mechanical Services Department (EMSD) should be consulted if
there are any proposed structures encroaching onto this preferred working
corridor or any reduction of existing ground clearance of the overhead lines.
4.4.18 New 132kV sub-station to the network may be required if the loading
requirement on these land use development exceeded the planned system capacity.
4.4.19 The existing and planned power transmission and distribution cable system are
properties of the CLPP. System capacity and its potential for expansion would
require the CLPP to review. It is necessary to present the land use plan and
associated infrastructure proposal to CLPP for discussions of future power supply
network strategies and planning.
Gas Supply Network
4.4.20 At the moment there is only one town gas supply company, the Hong Kong and
China Gas Company Limited (HKCG) is supplying gas via pipeline system.
4.4.21 The need of town gas supply by pipeline would be up to the nature and density of
land use. For PDAs with sufficient number of gas users, it would become a good
justification for HKCG to lay mains and pipeline to a new area. For extension of
gas supply system, pipes can be branched off from the existing mains and be laid
along existing or future distributor roads in the PDAs.
Telecommunication Network
4.4.22 Telecommunication services are essential for the developments in PDAs. The
mobile network operators will need to reserve land space within the development
and along public road for their future installation of base stations of mobile
services in the areas that are outside the existing coverage.
Street Lighting
84
4.4.23 Street lightings are required along all public roads including highways, distributor
roads, local roads, cycle tracks and pedestrian walkways. These lights shall be
powered by low voltage cable from the CLPP network. The demand of street
lighting provision and associated facilities will be considered in the technical
assessment in the stage of P&E Studies when necessary.
4.5.8 The NE-SW running road network of MKT PDA would be the major breezeway
that would facilitate wind penetration towards the adjacent NDAs (i.e. KTN and
FLN NDA) and across the PDA under ENE/E and SW/WSW winds.
4.5.9 However, with presence of Agri-Logistics/ Light Industry with plot ratio of 3 in
MKT PDA, it would slightly affect the wind environment of the most northern
area of FLN NDA and villages at the leeward side under N/NNE and S/SSW
wind directions, respectively. Hence, localized air paths align with N-S direction
at the southern side of the PDA is recommended for better wind penetration
towards leeward side.
HYW PDA (Refer to Figure 4.5.3)
4.5.10 With presence of open spaces at the northern side, the land lots for Tourism/
Leisure with PR of 0.8 and villages zone at the northern part would enjoy good
wind availability under N/NNE and ENE/E prevailing winds.
4.5.11 The green belt and agriculture of HWY PDA would facilitate wind penetration,
especially for wind coming from N-E quadrant.
4.5.12 The Commercial (Cross Boundary Retail) and Mixed Use with plot ratio of 7.5 in
the western part of PDA would potentially cast wind shadow over the villages
and existing settlements under N/NNE wind directions. The major road network
in between the commercial land lots would act as secondary breezeways, which
extend the breezeway to its eastern side. The secondary breezeway would slightly
alleviate the wind impact at the leeward side.
4.5.13 The Commercial (Cross Boundary Retail) and Mixed Use with plot ratio of 7.5 at
the western part of HYW PDA would potentially shield the adjacent villages
under all studied wind direction. To minimize the impact, localized air paths and
street alignment in prevailing wind directions are suggested in the commercial
area for better wind penetration. It is also recommended the Mixed Use and
Commercial Cross Boundary Retail areas to adopt Sustainable Building Designs
(PNAP APP-152) to enhance the wind permeability.
TKL PDA (Refer to Figure 4.5.4)
4.5.14 In the presence of extensive green belt, agriculture and open space at the northern
part of TKL PDA would allow incoming wind to ventilate the PDA easily. The
high-rise residential and commercial area at the most western part would be
easily ventilated under annual wind condition in the absence of infrastructures at
its windward side. The village clusters and low-rise residential area at the central
area of the PDA would freely enjoy both annual and summer winds.
4.5.15 The green belt and road network at the eastern part of the PDA would act as wind
entrance that would allow ENE/E wind to ventilate the PDA. Considering the
extensive area of the Science Park, a wind corridor running in NE-SW direction
within Science Park, in form of green belt, open space and road network, would
be suggested to enhance wind environment of existing villages at the leeward side.
4.5.16 At the most southern area of the PDA, the green belt and agriculture running in
NE-SW direction would serve as a major breezeway to ventilate the southern
developments under ENE/E and SW/WSW directions.
86
4.5.17 At the most western area of the PDA, the open space would form the breezeways
to allow ENE/E and SW/WSW winds to penetrate across the western area of
PDA.
4.5.18 The stepping building height arrangement would also favour local wind
ventilation under N/NNE and S/SSW winds. These would slightly alleviate the
potential shielding effect caused by the high-rise residential and commercial area
in that part of PDA.
4.5.19 The Logistic Industries at the most northern part of TKL PDA would potentially
shield the SW/WSW approaching wind towards villages to its east. To enhance
the wind permeability of Logistic Industries, localized air paths align with
SW/WSW wind direction are recommended.
4.5.20 The G/IC area at central of the far western part of TKL PDA would be potentially
suffered from relatively calm wind as it is surrounded by land lots with higher
plot ratio. Although the presence of green space areas may help to facilitate wind
penetration into the inner area and improve the wind environment, breezeways or
localized air paths in form of open space, road network or Non Building Area
(NBA) connecting to green area (indicated by black dotted arrow) are
recommended to facilitate wind penetration.
4.5.21 The high-rise Residential areas with plot ratio ranged from 5 to 7.5 at far western
part of TKL PDA would also shield the approaching wind under all studied area.
Street alignment and building separation in parallel with major breezeways or
localized air paths are also suggested for the far western part of TKL PDA to
enhance the wind permeability. The Residential areas with plot ratio of 7.5 at the
central part are also recommended to adopt Sustainable Building Designs (PNAP
APP-152) to enhance the wind performance.
4.5.22 The open space adjacent to high-rise commercial area at the lower middle part of
the PDA would facilitate wind penetration and slightly improve the wind
environment of the village clusters at the leeward side under S/SSW wind.
4.5.23 The high-rise Commercial, Mixed Use and Residential areas at lower middle part
of TKL PDA would potentially cast a wind shadow over the adjacent village,
existing settlement upgraded and G/IC areas at leeward side including in its own
site under all studied winds. In order to minimize the impact, setback from the
road and open space of the future development together with adoption of
localized air paths are recommended during detailed building layout design stage
to enhance wind penetration across middle part of this PDA area.
4.5.24 In addition, the Mixed Use area with plot ratio of 7.5 and Residential area with
plot ratio of 7.5 at this lower middle part of TKL PDA are recommended to adopt
Sustainable Building Designs (PNAP APP-152) to enhance the wind permeability
under all studied winds.
QH PDA (Refer to Figure 4.5.5)
4.5.25 The major road (i.e. Sha Tau Kok Road (Lung Yeuk Tau)) at the co-boundary of
TKL PDA and QH PDA would serve as a major breezeway to ventilate across the
PDAs and its surrounding areas under ENE/E and SW/WSW winds.
4.5.26 In addition, although the presence of existing villages, the villages are low-rise in
natural that the open space and agriculture at the middle part of the QH PDA
87
would facilitate wind penetration to serve the adjacent village clusters to the east
and west of QH PDA and within the PDA under ENE/E and SW/WSW winds.
4.5.27 At the northern part of QH PDA, the land areas proposed for residential use with
plot ratio of 7.5 and Commercial use with plot ratio of 6.5 would likely cast wind
shadow towards planned development at QH at its leeward side under N/NNE
and ENE/E wind, respectively. Localized air paths and adoption of Sustainable
Building Designs (PNAP APP-152) are recommended during detailed building
layout design stage to enhance wind penetration.
4.5.28 Moreover, the residential use with plot ratio of 7.5 would also likely shield the
incoming wind across the QH PDA towards villages to its west and east under
ENE/E direction and SW/WSW direction, respectively. Although the District
Open Space at the middle of this residential area would improve ENE/E and
SW/WSW wind penetration, street alignment align with ENE-WSW directions is
also recommended for this residential land lot to enhance wind permeability.
4.5.29 The residential areas with plot ratio of 5.5 and 6 at the most southern part would
potentially shield the planned development at QH, localized air paths in
alignment with S/SSW direction are recommended to serve the planned
development at QH.
4.5.30 The residential area with plot ratio of 6 located at the southeastern part of the
PDA would potentially shield the approaching wind towards planned housing
sites at QH under ENE/E wind direction. Localized air path in form of open space
or road network to serve planned housing sites at QH is suggested to encourage
wind penetration.
4.6.9 With estimated logistics employees of 900 based on assumed worker density of
200 m2 per worker, the total employment generated at LMC would be
approximately 80,000.
East NTN (MKT, HYW, TKL and QH PDAs)
4.6.10 Similar to the LMC cross-boundary retail hub, the 664,000 m2 facility could
support about 33,000 jobs if staffing ratios are line with typical retail
establishments in Hong Kong.
4.6.11 Other office-based commercial developments in PC hub (including QH PDA) has
been planned a combined GFA of 860,000 m2. Based on similar working density
of 20 m2 per employee, employment estimated for these commercial areas would
be approximately 43,000.
4.6.12 The Science Park at 396,000 m2 could accommodate some the innovation jobs
and the environmental and testing/certification jobs. The HKPSG guidelines state
15m2 per employee in Science Parks, estimating some 26,000 jobs could be
created at the science park area.
4.6.13 With Industrial Estates space of 948,000m2 planned and assuming 150m2 per
employee for space intensive jobs, it is estimated to accommodate around 6,300
employees.
4.6.14 The 590,000m2 of agri-logistics spaced allocated in MKT can be supported up to
4,000 jobs, and potentially 1,300 jobs for logistics, based on worker density of
150-200m2 per worker. A further 258,000 m2 of space has been allocated for
logistics industry to meet the industry demand, generating about 1,300 jobs.
There are also 1,200 jobs created for tourism and leisure.
4.6.15 Together with 383,000m2 of space for local retail, it is estimated to create 19,000
population-supporting employments. Thus, the total employment generated at
East NTN would be approximately 135,000.
4.6.16 The employment distribution in NTN under Scenario II is included below:
Table 4.6.2: Employment distribution in NTN under Scenario II
4.6.17 CP under Scenario II has designated a total of about 280 ha for developing new
residential units and about 180 ha for villages and “Existing Settlements”. With
planned residential units to cater for additional population of 350,000, it is
expected to help mitigate the part of the shortage in housing supply. There would
be also potential upgrades in terms of the productivity of business activities given
the existing brownfield operation does not represent an efficient utilization of
land.
4.6.18 The five PDAs involve about 720 ha development area, it is estimated that more
than 50% is under private ownership. Given that the CP only shows broad land
use concepts and detailed survey of existing land uses is yet to be conducted, the
impacts on land uses will be subject to further investigation in the stage of P&E
Studies.
Scenario 1 Scenario 2
Indicators (Without the NTN (With the NTN
Development) Development)
Scenario 1 Scenario 2
Indicators (Without the NTN (With the NTN
Development) Development)
Income differential
Innovation
Job Creation/ Loss
Landfill capacity
Local freshwater
Managed terrestrial habitat
Marine water quality
Municipal solid waste
Open space shortfall
River water quality
Significant landscape features
(area)
Scenario 1 Scenario 2
Social Checklist Questions
(Without Project) (With Project)
Safety Net
Living Space
Adequate Housing
92
Scenario 1 Scenario 2
Social Checklist Questions
(Without Project) (With Project)
Legends
Annotates no change to the current baseline situation
Very Moderate
Small Moderate Large Very Large
Small to Large
4.7.5 On the negative side, there will be a small to very small deterioration of condition
with respect to construction waste, criteria air pollutants, excessive noise, landfill
capacity, marine water quality, river water quality, significant landscape features
(area), significant landscape features (point), terrestrial eco-value, and
archaeological and historical site due to the proposed development. These
changes are considered to be extremely small as compared with the Hong Kong
territory-wide values. Moderate deterioration is anticipated for carbon dioxide
emitted per year.
4.7.6 On the positive side, the proposed development is expected to extend NTN into a
district which can meet housing, social, economic, environmental and local needs.
The development will bring about value-added contribution to GDP and
employment creation to the economy. The development will also improve fixed
capital, freight costs, provision of open space, travel speed and renewable energy
generation.
4.8.1 The sustainability framework for NTN aims to highlight the opportunities in
different areas in achieving the sustainable principles. These areas cover a
number of technical areas where measures can be implemented to achieve S-G-R
development of NTN and relevant sustainable principles.
4.8.2 The sustainablility framework for NTN comprises the following areas in which
strategies are formulated: Energy & Building, Transport, Water, Drainage, Waste
and City Systems Integration. For each aspect, a number of measures are
proposed for achieving the overall vision of NTN. Some examples of the
proposed measures under each specific area are illustrated below. The details are
further elaborated in subsequent sections.
4.8.3 The process in arriving different specific practices within the above areas started
in the beginning of the study when the infrastructure provisions are recommended
to achieve the vision of NTN development. More specific measures and
technologies are proposed for smart, green and resilient city for key infrastructure
areas, where baseline infrastructure assessment and feasibility of these proposed
measures in the PDAs are investigated and summarized below.
Energy & Building Transport Water
Renewables (e.g. solar, Transport vehicles (e.g. Water supply
wind, etc.) EV, biodiesel vehicles) technologies
Tri-generation Traffic Demand Measures Rainwater harvesting
District Cooling (e.g. Car sharing, taxi Grey water recycling
Smart grid pooling)
Building technologies , ICT management for
automation and energy transport management
systems
Energy storage systems
Drainage Waste City Systems Integration
Sustainable urban Automatic waste collection Real-time infrastructure
drainage system (SuDS) system management
Storm water treatment Organic waste treatment Co-treatment and co-
system Waste-to-energy plant location of infrastructure
Co-treatment of sewage provisions
sludge and Municipal Solid Optimization between
Waste (MSW) centralized and
decentralized systems
4.8.4 Various green initiatives under the different themes outlined in the previous
section are proposed for the NTN development. For Municipal Solid Waste and
sludge arising forecast within NTN, please refer to Appendix C.
Site Planning & Urban Design
Creating Harmony between Development and the Surrounding Context
4.8.5 View corridors and breezeways are proposed to improve air circulation as well as
to provide major view corridors that formalize the relationship between the
vegetated mountain backdrop of the NTN and the new urban cores. They mostly
replicate the visual corridors already identified in the NTN that mark the
relationship with the surrounding natural environment.
94
4.8.6 Visual relationships are preserved by configuring greenways and major roads
within developments to create a series of visual relationships that frame
significant landscape markers in the vicinity of the new urban cores. These
mostly include mountain peaks and ridgelines towards which the routes are
axially arranged, enhancing their monumental significance and lending a clear
identity to the neighbourhoods they traverse.
Protecting Established Wildlife Habitats
4.8.7 Existing streams are a valuable landscape resource which could be preserved and
integrated with the adjoining urban development and the existing village
settlements. The concept of ecological stream is proposed in NTN, which
involves creation of riparian buffer zones along the banks of the preserved
streams. Apart from streams, the existing watercourse will be preserved to
provide natural habitat for the wildlife. Boulders, riparian vegetation and niches
with varied water depths are to be introduced to promote biodiversity and to
achieve a naturalistic look.
Preservation of Significant Landscape Features
4.8.8 Continuous landscape systems that envelop various natural features are all
grouped into linear spatial ribbons that are intended to maintain the existing open
space continuity throughout the region. These systems are coordinated with the
streetscapes and open space system in NTN with linkages which take the form of
green corridors and establish a continuous and robust landscape framework in
which ecological values are preserved.
4.8.9 In particular, Fung Shui woodlands will be preserved and incorporated with the
network of open spaces. Eco-farming will be encouraged in the agricultural plots
to promote biodiversity.
Transport
Green Transport Analysis
4.8.10 Provision of a comprehensive environmentally-friendly transport (EFT) system is
proposed for NTN which serves as a layered network, integrated at the local level,
as well as the regional level, aiming to reduce the desire to drive for both internal
circulation (i.e., short trips) and external access (i.e., long trips).
4.8.11 Various types of public transport modes and services will provide the mobility
backbone to/from NTN and within the PDAs, which are classified as individual-
based, road-based as well as rail-based systems.
EFT Systems Mode/ service
Individual-based Comprehensive Pedestrian Network
Travellator
Cycle Tracks
Cycle Parking Facilities
Electric Cars
Road-based Electric and Environ-mentally Friendly Buses (for
Local and Express Buses)
Enhanced Bus and Bus Priority Treatments A
Bus Rapid Transit (BRT) A
Rail-based Heavy Rail (MTR)
95
4.8.17 There are certain fixed costs associated with such systems. Initial outlay costs
may be moderate especially to equip an entire fleet with such sensors, although
the benefits would be clearly reflected in reduction of lost time due to
maintenance or delay.
97
Table 4.8.1 High Level Assessment of EFT Options
Speed / Carbon Reduction Ease of
Mode/ Service Capacity Flexibility Accessibility Cost Footprint Applicability for NTN Role in NTN
Reliability Potential Implementation
Individual-based EFT Options (Mode/Service Evaluated Against Other Individual EFT Options Only)
Applicability: A
comprehensive
pedestrian network is
All trips begin or end
essential to cater for
with a walking trip,
Comprehensive The most Easiest and short-trips and Serves as principal local
therefore a
Pedestrian - - accessible mode Relatively low cost - cheapest to minimize driving. It is connection system within
comprehensive
Network of all expand important to have such NTN
network encourages
networks around
greater walking
railway stations, as well
as at major residential
and employment hubs.
Applicability:
Travellators should not
be implemented
everywhere. They may
Expansion be warranted at specific
Travellators Minimal Minimal as Provide on selected corridor
requires Access is limited Higher capital and locations where the
can reduce the footprint, travellators are meant Requires right-of- for local connections where
Travellators - adequate right- to locations with O&M costs than a walking distance is
effective although 2.0m for short-distance way and funding walking distance exceeds
of-way and travellators sidewalk longer than normal.
walking time width required walk trips typical distance
funding They are most
applicable in the local
context, for instance
linking a railway station
to a nearby mall.
Applicability: Cycle
tracks should be
provided to/from rail
stations and
Provide for local access
Expansion Depends on type Minimal as it residential/employment
Depending on level between rail stations and
requires Access is limited of cycle track depends on the More difficult to nodes for localized
Allows for the of segregation residential / employment
Cycle Track - adequate right- to locations with and level of volume of new implement due to access. In rural
fastest journey required, costs can nodes; also provide for
of-way and cycle tracks segregation cyclists using the land availability contexts, cycle tracks
be quite substantial secondary access to other
funding required facility may also be used to
PDAs, mainly for recreation
connect PDAs. High
degree of segregation
will be more costly and
difficult to implement.
98
4.8.24 Three possible sources of recycled water that could be used as non-potable water
to reduce fresh water consumption are (1) Rainwater harvesting, (2) Greywater
harvesting; and (3) Treated Sewage Effluent (TSE).
Rainwater Harvesting
4.8.25 For building level, it is estimated that 70% of the rooftop area in NTN
development can be accounted for the feasibility calculation for high-rise
development in Hong Kong.
4.8.26 If 100% buildings in NTN development are of concrete roof with efficiency
factor for rainwater collection is 0.8 and all of them would install rainwater
harvesting system on their rooftop, it is anticipated that the rainwater collected is
able to provide around 10% of the total water demand for flushing.
Greywater Recycling
4.8.27 It is assumed that the greywater which can be recovered is equivalent to around
30% of the freshwater being used, the greywater collected daily equals to 85% of
the flushing water use in NTN.
4.8.28 As far as initial and operational cost is concerned, it should be noted that it will
be more expensive comparing to rain water harvesting. Also, it is likely that the
supply of rain water collection and TSE is sufficient to cater for the non-potable
water demand of the NTN development. Therefore, it is recommended that
greywater recycling should be adopted as a supplement to rainwater and TSE
supply as appropriate.
Recycling of Treated Sewage Effluent
4.8.29 To treat and disposal the sewage generated from the various PDAs, two sewage
treatment works (STWs) are currently proposed. This includes:
• A proposed STW to serve HYW / TKL / QH PDAs.
• A proposed STW to serve LMC PDA.
4.8.30 To achieve the requirement of “No net increase in pollutant loading” requirement
of the Deep Bay Water Control Zone and to provide flushing water supply for the
various PDAs, sewage collected from the two proposed STWs will be treated to a
standard suitable for recycling for toilet flushing use.
4.8.31 As there is a credit limit of pollution load to Deep Bay, TSE should be used as a
primary source for flushing and non-potable water use for NTN.
4.8.32 As far as the whole Deep Bay catchment area is concern, by assuming 90%
recovery of TSE from sewage, a total of 244,500 m3/day effluent has to be reused
within NTN, and within and outside the Deep Bay Catchment. The details of the
preliminary effluent reuse strategy are summarized as below.
105 Final Report – on Concept Plan for NTN
`
4.8.40 Waste measures proposed with their technical and planning feasibility are listed
in the Table below.
108
Table 4.8.4 Summary of Feasibility of Waste Measures in PDA
Related Strategies /
Category Main Advantages Main Constraints Stage of Application Technical Feasibility Planning Feasibility
Waste Measures
Waste S2 Automatic Refuse - No need for waste - High cost for initial Commercialized - Proven Technology & - Environmentally
Collection Collection System storage or packer traffic installation Well Commercialized friendly and with
& Sorting (ARCS) due to automated - High operation and - Many cases have positive contribution to
collection maintenance cost already been in Hong the environment
- More hygienic for users - Potential misuse of the Kong29
and waste management system - Subject to further
workers investigation on whether
current limitations can be
overcome and the cost-
effectiveness on its
design and maintenance
S1 Iceberg & Eco- - Reduce the frequency - Higher cost than Commercialized - Trucks and the whole - Need underground
Island collection for waste collection conventional waste system of waste space to accommodate
- Larger waste storage collection system collection system needs the system
capacity to be planned together
S1 Automatic waste - Improve the efficiency - High cost Early Commercialized - Limited range of the - Key role and functions
sorting and for the sorting - Currently still limited sorting material & to be defined in addition
Material Recovery - Increase the possibility to a small range of limited accuracy & not to the existing Eco-Park
Facility (MRF) for reuse and recycling, materials widely applied - Not In My Back Yard
thus reduce the reliance - Insufficient accuracy of - Some expected (NIMBY) Problem
for incineration and the automatic sorting solvable technical
landfill process barriers
Waste S4 Waste-to-energy Incineration - May cause airborne Demonstrated/ Early - Proven Technology & - NIMBY Problem
Treatment via thermal - Relatively less contamination Commercialized Well Commercialized - Need to deal with the
treatment expensive for initial - May produce - The technology has pollutant produced from
(incineration / construction compared incineration by-products, been applied in Hong the incineration
pyrolysis / with pyrolysis and which would typically be Kong
gasification) gasification stabilized prior to
- Mature technology with disposal
many applications
around the world
29
ARCS implemented in Hong Kong has been refrained from public housing estates.
109 Final Report – on Concept Plan for NTN
`
Related Strategies /
Category Main Advantages Main Constraints Stage of Application Technical Feasibility Planning Feasibility
Waste Measures
Pyrolysis - The pyrolysis Commercialized - Technologies are - NIMBY problem
- Convert trash into performance is related to currently unproven on a
valuable new products the quality of feedstock commercial scale, and
- Higher performance input overseas experience is
than traditional - Requires pre-treatment patchy
incineration at any scale of the waste feedstock
Gasification - Large initial investment Technology R&D / Early - Some projects are not - NIMBY problem
- Organic waste costs relative to landfill Commercialized proven on a commercial
conversion rate exceeds - May release and form scale
99% toxicants during the - Many new technologies
- Produce synthetic gas process under research such as
for fuel production - Requires pre-treatment plasma
- The process is of the waste feedstock
ecologically clean
S3 Organic waste to - Low lost with simple - Loss of ammonia Commercialized - Proven Technology & - Impact on odour
quality agricultural equipment - Long time involved Well Commercialized
grade fertiliser via - Reduce the volume of - Footprint requirement
composting the waste, thus reduce - Odour control
landfill space - Limited demand
requirement.
- Compost, when added
to soil, provides organic
matter, reduces potential
for soil erosion, and
reduces fertilizer
requirements.
S3 Organic waste to - Convert waste to - Safety issue Commercialized - Proven Technology - NIMBY problem
biogas (methane) energy (biogas), thus - Plant area and
via biological reduces the need for complexity
treatment landfill and cut the use of
(anaerobic fossil fuel
digestion) - Large scale application
110
Related Strategies /
Category Main Advantages Main Constraints Stage of Application Technical Feasibility Planning Feasibility
Waste Measures
S3 Waste / used oil to - Less carbon intensive - High cost Early Commercialized - Proven Technology - NIMBY problem
biodiesel for than fossil fuels - Need facilities for fuel Commercial project in
transport vehicle - Rapidly biodegradable mixing and dispensing Hong Kong TKO
via chemical and completely non-toxic - Regulatory limitations
treatment - Higher flash point than
(transesterification) fossil diesel and so is
safer in the event of a
crash.
- Capacity for local
biodiesel production
exists
S5 Co-Treatment of - Save plant space by - Large capital cost Technology R&D / Early - Need to optimize the - NIMBY problem
Sewage Sludge and integrating NIMBY - Design complexity Commercialized combustion performance
MSW facilities of various types of
- Optimize resources use wastes with different
energy and moisture
content
S5 Co-Treatment of - Save plant space by - Optimized mixed of Technology R&D / Early - Need to optimize the - NIMBY problem
Sewage Sludge and integrating NIMBY sewage sludge and food Commercialized combustion performance
food waste facilities waste in HK’s context of with different energy
- Optimize resources use - Integrative design of and moisture content
STW
separately serve the separately serve the separately serve separately serve the the dense commercial
enterprise park, agri-logistics, or light commercial, tourism science park, and residential areas
commercial area & industry area area, and industrial commercial area,
mixed use areas at the estate industrial estate and
station area, and northern public high density
commercial area residential clusters
Iceberg & Eco-Island collection - Provide to remote - Provide for each land - Provide to remote - Provide to remote - Provide to remote
village settlement areas, lot, and collected to village settlement village settlement village settlement
or open space ARCS areas, or open space areas, or open space areas, or open space
Automatic waste sorting - Mixed waste from LMC and MKT PDAs to be sent to the Integrated RTS, Sorting & MRF Facilities at southern LMC PDA for
through RTS & MRF further sorting
- Mixed waste from TKL, HYW and QH PDAs to be sent to the Sorting & MRF in PC for further sorting
Waste-to-energy (WtE) via - WtE plant to be recommended in the cavern of PC area to serve both NTN and MSW of future New Territories
thermal treatment - Non-recyclables are sent from the Integrated RTS, Sorting & MRF Facilities to the Waste-to-Energy Plant (or Combined
Cooling, Heating and Power (CCHP) plants) for treatment
Organic Waste to Quality - Organic Waste (Commercial and Industrial (C&I) and domestic Food waste) of urban areas to be sent to planned Organic Waste
Agricultural Grade Fertiliser Treatment Facilities (OWTF) II (300 tpd) in Sha Ling or to be co-digested with sewage sludge by using anaerobic digestion in
via Composting STWs
Organic waste to biogas - In-vessel composting serves remote village settlement areas
(methane) via biological - Production of biogas for onsite or external use
treatment (anaerobic digestion)
Waste / used oil to biodiesel for - Convert waste oil to biofuel locally (e.g. industrial estate)or external site (Tseung Kwan O)
transport vehicle via chemical - Provide biofuel for transport and tri-generation
Waste Treatment
treatment (transesterification)
Smart waste management - Installation of metering infrastructure, IT facilities and cablings from plants, trucks and related waste facilities
system
Co-Treatment - Co-incineration of sewage sludge and MSW is not likely but plant co-location by sharing facilities (e.g. chimney) and some
process (e.g. air filtration, heat recovery) are more feasible
- Co-treatment / Co-digestion of sewage sludge and food waste is feasible to be incorporated into future STW
112
Energy
Renewable Energy (Building Level)
4.8.41 Various renewable energy applications have been discussed. It is estimated the
proposed renewable energy applications in NTN including photovoltaics (PV),
building-integrated photovoltaics (BIPV), solar thermal, wind turbine, PV
integration, fuel cell and bio fuel. While the renewable application for all
developments are listed in the table below:
Table 4.8.6 Summary for renewable application for all developments
Development RE Option
Area
PV Area
LMC PDA Solar Thermal Area
Nos. of Combined wind & solar street lamp
PV
Solar Thermal
MKT PDA Combined wind & solar street lamp
Fuel Cell
TKL PDA PV
Solar Thermal
HYW PDA Combined wind & solar street lamp
Bio-Facade
PV
QH PDA Solar Thermal
Combined wind & solar street lamp
District Energy
4.8.42 District cooling system will be appropriate for a mix of commercial building
operation, such as commercial development, industry area, educational and
healthcare facilities. From the land use design, LMC, MKT and HYW/TKL are of
centralised commercial / industrial area and are commercially dominant
development. Broad financial analysis was performed to evaluate the financial
feasibility of the implementation of the DCS in LMC, MKT in HYW, and
DCS/tri-generation system in TKL, and to derive the best institutional
arrangement.
4.8.43 Based on the discount rate assumed to be the 6%, which is the rate used in
estimating the financial performance of the DCS system in West Kowloon
Cultural District, the financial analysis of the DCS are shown in the table below.
Table 4.8.7 Financial Analysis of DCS
LMC MKT HYW & TKL
Discounted payback (yrs.) 15 24 16
Capital costs (HKD million) 2,179 1,088 4,634
4.8.44 Procurement options that could be considered include inviting the private sector
to implement the projects under models such as Design and Build, Operate and
Maintain, and Design Build Operate and Maintain contracts.
113 Final Report – on Concept Plan for NTN
Building Energy;
Fresh and Sea Water;
Sewage; and
Transport.
Carbon Reduction Scenarios
4.8.52 Two carbon saving scenarios for NTN developments are assessed: Prevailing
Best Practice Scenario and Low-Carbon Scenario. Under these two scenarios, one
or more of the following carbon reduction strategies would be applied. Energy
efficient measures adopted by these two cases are summarized in Appendix B.
Prevailing Best Low-Carbon
Practice Scenario Scenario
Energy efficient measures in
building level
Renewable energy application
District Cooling System
4.8.53 Four DCS are proposed to be installed in LMC(N), LMC(S), MKT and
HYW+TKL to provide a more energy-efficient cooling system. It has a potential
saving of around 20% and 35% energy consumption when compared to water-
cooled and air-cooled air-conditioning systems respectively.
4.8.54 With different combination of these three carbon reduction strategies, it is
estimated that Prevailing Best Practice Scenario would save around 20%, while
Low-carbon Scenario would save around 46% of the carbon emission when
comparing to the carbon emission for NTN (Scenario II).
Infrastructure proposed in Caverns
4.8.55 Various key infrastructure and facilities have been proposed in previous sections
in this Chapter (e.g. waste-to-energy plant, etc.). These infrastructures are
proposed to be located within caverns out of the Study Area. Their proposed
location and estimated footprint are shown in Figure 4.8.2 and Table 4.8.8. In
this table, the percentage of the site area to be allocated within caverns is
preliminary estimates which should be subject to future feasibility study and
design stage. Issues need to be resolved for co-locating infrastructures includes
structural, safety and hazard considerations.
Table 4.8.8 Estimated footprint of various infrastructure within caverns
Assumed Percentage
Proposed Total Estimated
No. Infrastructure Provisions of Site Area within
Location Site Area
Cavern (Note 1)
2
100% (6700 m2)
8 Flushing Water Reservoir Ngau Tam 2300m , 5 meters
Mei (note 3) (depth) 100% (2300 m2)
50% (0.75ha)
RTS & Local Sorting & Recycling [In Cavern]
3 Centre 1.5ha (Note 4) 50% (2ha)
11 STW 4ha
Plan under
4 OWTF (II) Sha Ling EPD’s project NA
LMC PDA
12-1 District Cooling Plant (South) 1ha NA
LMC PDA
12-2 District Cooling Plant (North) 1ha NA
Note 1. Only non-explosive facilities are suggested locating within cavern. All potential explosive facilities
such as anaerobic digester, chimney, stack, combustion chamber etc. are suggested locating right outside cavern.
The exact allocation between cavern and outside cavern site areas would be subject to subsequent feasibility
study and design.
Note 2. The footprints of all plants are preliminary estimation based on other existing projects with similar size
and capacity. For instance, the estimation of the WtE plant site area (18ha) is slightly larger than the size of
IWMF size area in Shek Kwu Chau (15.9ha) as it needs to deal with both MSW (in similar order of magnitude
of Shek Kwu Chau) and sludge in the plant planning. Nevertheless, site area of each plant would be subject to
adjustment in detailed design & engineering stage.
Note 3. RTS & Local Sorting & Recycling Centre and STW should be located in separate caverns to avoid
contamination of the fresh water and flushing water reservoirs in Ngau Tam Mei.
Note 4. 1.5ha is only for conventional RTS, if MRF is to be incorporated, a larger footprint will be required, of
which the exact amount of land required will depend on the capacity of the facility which will be determined in
the detailed design stage.
these agricultural lands have been heavily managed for farming, the remaining
inactive or wet agricultural land is of some ecological value in supporting
amphibians. Only a few floral and faunal species of conservation concern were
present within the PDA, and these were recorded in low numbers.
4.9.2 Certain areas near to the PDA are considered to be of potential ecological concern;
these include agricultural land at Chau Tau, LMC and Ma Tso Lung,
watercourses at Ping Hang and Ma Tso Lung, grassland and secondary woodland
near Ngau Tam Mei, as well as the fishpond habitats in the Wetland Conservation
Area (WCA). Nevertheless, it is anticipated that the proposed development
footprint will not affect these areas as they are located far away from the LMC
PDA. The habitat map of LMC PDA is shown in Figure 4.9.1.
4.9.3 Significant direct ecological impacts are not expected as most of the ecologically
sensitive habitats within the PDA will be avoided through zoning as agricultural
land and Green Belt, as well as through provision of buffer areas in riparian zones
in the CP. Indirect impacts would be mitigated via building design and set-back
(in the vicinity of the WCA and STEMDC) such that building height close to the
WCA will be adhere to the current 3-storey norm in the area, enhancement of
screen planting, careful design of road/footpaths and cycle tracks (including
lighting) and careful design of development layout.
MKT PDA
4.9.4 MKT PDA is comparatively small, and mainly comprises developed areas
(including villages, open storage and road infrastructure). Semi-natural habitats of
potential ecological importance include, to the southwest of Sandy Ridge, a
mosaic of agricultural land, ponds and watercourses that provide suitable habitat
for amphibians and wetland birds. A mixture of active and inactive agricultural
fields is present, with other low-lying inactive agricultural land elsewhere in the
PDA. Ponds in this area are mostly overgrown by grassy vegetation. No floral
species of conservation importance and few faunal species of conservation
importance are present in the agricultural land and watercourses within the PDA.
4.9.5 Away from MKT PDA, the relatively less disturbed grassland and secondary
woodland in the Sandy Ridge area are considered to be of higher ecological value
and support a number of species of conservation importance. Some adjacent
habitats outside the PDA, such as agricultural land, ponds, watercourses and
shrubland, also support rare species or species of conservation importance.
Indirect impacts to these habitats or species may arise but are anticipated to be
minor in magnitude and significance. The habitat map of MKT PDA is shown in
Figure 4.9.2.
4.9.6 Direct ecological impacts in terms of habitat loss in the MKT PDA are mostly
insignificant due to their low ecological value, with the exception of certain
watercourses. Mitigation measures, including provision of buffer areas, should be
proposed at the stage of P&E Studies. In terms of indirect impacts, loss of wet
agriculture and ponds south of Sandy Ridge would impose an impact of Low to
Moderate ecological significance on wetland bird species. Approximately 18.6%
of flight lines from Ho Sheung Heung egretry entered the PDA boundary, and
would potentially be impacted directly via loss of airspace or indirectly via
disturbance. The preferred option is to provide wetland compensation in a unified
area of enhanced wetland habitat with a view to providing an environmental
benefit of the project. This should be situated closest to Ng Tung River. This
117 Final Report – on Concept Plan for NTN
would also provide some mitigation for flight line impacts by providing
alternative foraging areas. In order to minimize potential impacts on flight lines,
building height in critical areas should be restricted to 3 storeys, as currently
dominates the area. Defining critical areas requires to be done at detailed design/
Environmental Impact Assessment (EIA) stage in order to use the most up-to-date
data.
TKL PDA
4.9.7 Quite extensive developed areas are present in TKL PDA, comprising villages,
industrial areas, open storage, road infrastructure and public facilities. Natural
habitats of potential ecological concern include agricultural land, lowland and
hillside grassland, and secondary woodlands scattered within the PDA. A mixture
of active and inactive agricultural land was located in Shui Hau, Tai Po Tin,
Chow Tin Tsuen, Lei Uk, Sing Ping and Sheung Shan Kai Wat. Grassland in
village environs belong to lowland grassland that has developed from abandoned
agricultural land; some of these could be seasonally flooded. Hillside grasslands
under natural succession and human disturbance were also present. A number of
semi-natural or channelised watercourses are also considered to be of ecological
concern; these include Tan Shan River, the middle section of Ng Tung River, the
central and western tributaries of Ping Yuen River, and Sheung Shan Kai Wat
watercourse.
4.9.8 Certain important habitats, such as the Man Uk Pin Ecologically Important
Stream (EIS), the middle and upper sections of Tan Shan River, as well as Loi
Tung fung shui woodland, are located to the east of TKL PDA along the existing
Sha Tau Kok Road. Significant indirect impacts to these areas from the current
development footprint are not expected given the distances between them and the
TKL PDA. The habitat map of TKL PDA is shown in Figure 4.9.3.
4.9.9 Direct impacts on important habitats within TKL PDA, including pond,
watercourses, secondary woodland and the Ping Che Egretry are mostly avoided
by zoning as Green Belt, Agriculture and District Open Space. Where avoidance
is impractical, minimisation or compensation via compensatory planting/
transplantation scheme and wetland enhancement plan should be proposed at later
EIA design stage.
HYW PDA
4.9.10 Extensive areas in the PDA are occupied by grassland, shrubland and
grassland/shrubland, which are typical hillside habitats under natural succession.
Natural habitats of ecological concern mostly comprise secondary woodland and
two fung shui woodlands preserved in the village environs. Kan Tau Wai fung
shui woodland is rather small and disturbed. Diversity in this woodland is low
and vegetation development in the understorey limited. Tsung Yuen Ha fung shui
woodland is larger in size and located to the south of the village. Though signs of
human disturbance are present in the understorey or along the woodland edge, it
generally supports higher plant diversity, and the overstorey is occupied by more
mature trees. Floral species of conservation importance were recorded in both
fung shui woodlands. The HYW watercourse, the east tributary of Ping Yuen
River, and Tsung Yuen Ha watercourse are also considered to be of ecological
concern.
4.9.11 The HYW PDA is located at the edge of the Study Area, between TKL PDA and
the boundary formed by Shenzhen River. Thus, adjacent areas of potential
118
sewerage catchments of SWH STW and Yuen Long (YL) STW beyond 2041 and
the full development will be increased. Sewage could first be explored to divert to
SWH STW, the YL STW, and the new STW at Kam Tin South etc., depending
on the sewage catchment area in which the PDA is situated in detailed design
stage. It is however evident that these existing sewage treatment facilities, even
after the major expansion and upgrading works, are still inadequate to serve the
sewage flows generated from the NTN development. Thus, new sewage treatment
facilities strategically at LMC and TKL/HYW are therefore necessary. “No Net
Increase in Pollution Loads Requirement in Deep Bay” will be incorporated into
the design by considering cumulative sewage catchment in the vicinity.
4.9.23 Broad water quality planning and mitigation measures, including reuse of treated
effluent, possible sewage treatment and disposal measures and application of
SuDS, have also been proposed to alleviate the impacts arising from construction
and operational phases. With above measures, adverse water quality impact is not
anticipated.
Noise
Representative Noise Sensitive Receivers
4.9.24 Representative existing noise sensitive receivers (NSRs) within the PDAs have
been identified with reference to the HKPSG. Besides, representative planned
noise sensitive land uses within each PDA have also been identified based on
proposed land use (e.g. Commercial, Residential, G/IC and Mixed Uses). The
identified existing NSRs and planned noise sensitive land uses include mainly
Residential / G/IC, and their locations are shown in Figures 4.9.16 and 4.9.17.
Construction Noise Impacts
4.9.25 During the construction phase, construction noise will be generated by the use of
Powered Mechanical Equipment (PME) in various construction activities such as
excavation, concreting, compaction works, material handling activities, etc.
4.9.26 The construction methodology, work site area and detailed implementation
programme are currently not yet available. Hence, quantitative construction noise
assessment will be conducted in the stage of P&E Studies.
4.9.27 The extent and significance of construction noise impacts would depend on the
scale of construction activities, number of PME in operation, duration of
construction activities, number of construction vehicle movements, etc.
Appropriate mitigation measures, such as adoption of noise barriers, use of quiet
plants, scheduling of the construction works, etc., are proposed to minimize the
impacts.
Operational Noise Impacts
Road Traffic Noise Impacts
4.9.28 The major existing roads in the vicinity of the Study Area include the San Tin
Highway, Fanling Highway, Sha Tau Kok Road, Man Kam To Road and Fan
Kam Road. With the PDAs developed, the traffic flow will be increased to cater
for the increasing population. Identified representative existing and planned
NSRs are shown in Figures 4.9.16 and 4.9.17.
121 Final Report – on Concept Plan for NTN
4.9.29 Road traffic noise assessment results indicate that the overall noise levels with the
project scenario at some existing NSRs within LMC PDA, TKL PDA, HYW
PDA and QH PDA would exceed the respective noise criteria.
4.9.30 For planned NSRs, the overall noise levels at some planned NSRs within LMC
PDA, TKL PDA, HYW PDA and QH PDA would also exceed the respective
noise criteria.
4.9.31 No noise sensitive use is planned within the MKT PDA. Hence, no adverse road
traffic noise impact is anticipated in the area.
4.9.32 For the planned noise sensitive land use within PDAs, it is recommended that
noise tolerant building should be placed in the buffer zones or closer to the roads
which act as shielding/screening for sensitive uses locate behind. Other
environmental & innovation planning measures such as the use of sunken roads,
tunnels, designated truck routes and peripheral highways will be explored in the
stage of P&E Studies.
4.9.33 Direct noise mitigation measures are proposed such that the overall noise levels
would comply with the relevant standards. Apart from the application of vertical
barriers, noise mitigation measures in form of cantilever barriers, and full
enclosure and low noise road surfacing are also practicable mitigation that could
alleviate the noise level and reduce excessive road traffic noise impacts on the
existing and planned NSRs. Direct noise mitigation measures should be provided
on the proposed road project in order to alleviate the adverse noise impacts on
those affected NSRs.
4.9.34 As major at-receiver mitigation measures, such as single aspect design and use of
air conditioning, are undesirable for future developments, especially for public
housing developments, direct mitigation measures such as roadside noise barrier,
low noise surfacing material would be deployed. As a last resort, minor at-
receiver mitigation measures, such as acoustic fins and acoustic windows, could
be considered to alleviate the road traffic noise level in the detail design stage,
where the building layout is available.
4.9.35 Besides, retrofitting of existing roadside noise barrier or low noise surfacing
material in some heavily trafficked roads such as San Tin Highway, Fanling
Highway, Sha Tau Kok Road and Lian Tong Road would be explored as the
possible at-source mitigation measures.
Railway Noise Impacts
4.9.36 The existing and proposed, and possible rails in the vicinity of the Study Area
include the followings:
The ER Line
The possible viaduct section of LMCS
The proposed NOL; and
The possible north-south railway.
4.9.37 For LMC PDA, the horizontal separation distances of 105m and 255m from the
proposed NOL are required subject to area sensitive rating. A GIC area is planned
to be located along the proposed NOL and some planned noise sensitive uses are
located within 255m of the proposed NOL. Adverse rail noise impacts from the
122
proposed NOL on these planned noise sensitive uses may be anticipated. Besides,
a possible section of LMCS are running on viaduct through the northern end of
the LMC PDA. Since it is located at more than 400m from the nearest noise
sensitive uses within the PDA, adverse rail noise impacts arising from LMCS is
not anticipated.
4.9.38 ER is running at approximately 110m to the southwest of MKT PDA. Proposed
land use adjacent to the ER includes the logistics industries. Offices are
anticipated in connection with the logistics industries within the PDA. These
offices are generally provided with mechanical ventilation and not relying on
window ventilation. Hence, no adverse rail noise impact is anticipated in the area.
4.9.39 In addition, the possible north-south railway, which will be running through TKL
PDA, HYW PDA and QH PDA, is proposed. The possible railway is planned to
be running underground except for the aboveground section near the possible
station in HYW PDA. Since no noise sensitive uses area is planned in the vicinity
of the viaduct section of the possible north-south railway, no rail noise impacts
arising from it is anticipated.
4.9.40 Mitigation measures for the planned G/IC area in LMC PDA are proposed. Since
it is located adjacent to the proposed NOL, it is recommended placing non-
sensitive land uses, such as a multi-storey car park building facing NOL, central
air conditioned buildings which do not rely on natural ventilation, etc., to provide
noise screening to the residential zone or other noise sensitive buildings behind.
For future railway development, at-source noise mitigation measures shall be
provided. As a last resort, minor at-receiver mitigation measures, such as acoustic
fins and acoustic windows, could be considered to alleviate the rail traffic noise
level. Other major at receiver mitigation measures, such as single aspect design
and use of air conditioning, are undesirable for future developments, especially
for public housing developments.
Fixed Noise Impacts
4.9.41 Major industrial noise sources identified within the Study Area include LMC
BCP, Sheung Shui Water Treatment Works (SSWTW), Animal Waste
Composting Plant, NTMWTW, and NENT Landfill, etc. Some rural industries
with different industrial activities were identified outside the industrial zones,
such as container storage, workshop, recycling yard etc.
4.9.42 Potential fixed noise impacts would also include industries, ventilation shafts,
pump houses, electricity sub-stations, wholesale markets, bus depots/termini,
open car/lorry parks, refuse handling areas, etc. which will be planned within
PDA.
4.9.43 In addition, there are numbers of firing ranges located within the Study Area,
including Table Hill Firing Range, San Wai/ Tai Ling Firing Range, Lo Wu
Classification Range and planned shooting range within the Police Facilities in
Kong Nga Po. For fixed noise impact associated with the operation of shooting
ranges, reference has been made to the approved EIA studies within the vicinity.
According to the approved EIA Study of North East New Territories New
Development Areas (EIA-213/2013), the average sound power level
(SWL(30mins)) for Lo Wu Classification Range was established to be 88.7dB(A).
Horizontal separation distances of 190 m and 340 m for ASR “C” and ASR “B”
are required respectively (subject to site specific data) as appropriate setback for
123 Final Report – on Concept Plan for NTN
noise sensitive uses from Lo Wu Classification Range. For the 2 firing ranges
within San Wai/ Tai Ling Firing Range, according to the approved EIA of Police
Facilities in Kong Nga Po (AEIAR-201/2016), horizontal separation distances of
270m and 480m are required subject to the area sensitive rating. Since the
shortest separation between the planned residential areas at the western area of
TKL PDA and the San Wai/ Tai Ling Firing Range is about 480m which satisfies
the distance setback from the shooting ranges, it is anticipated the San Wai/ Tai
Ling Firing Range will not impose any planning constraint on NTN development.
4.9.44 For LMC PDA, some existing rural industries are scattered just beyond the
boundary of LMC PDA and NTM area which may affect the planned residential
and G/IC areas nearby. Besides, some logistics industries are planned along San
Tin Highway within the LMC PDA. However, no noise sensitive uses area is
planned to locate nearby. Potential noise sources planned within the PDA could
be controlled to acceptable levels through proper design or specification of
maximum allowable noise level.
4.9.45 No noise sensitive uses area is planned within the MKT PDA and hence fixed
noise impacts on MKT PDA is unlikely. However, some logistics/light industrial
areas are to be located within MKT PDA which may affect the existing village
areas nearby.
4.9.46 The NENT Landfill is located adjacent to the northeast of HYW PDA. Since no
noise sensitive uses area is planned in the vicinity of HYW PDA, the noise
impacts arise from the operation of NENT Landfill is not anticipated. Some
existing rural industries located just outside the TKL PDA and QH PDA may
affect the planned residential areas in these PDAs.
4.9.47 Logistics industries are planned at the northwestern area of TKL PDA and HYW
PDA which may affect the planned low density residential area as well as the
existing village areas and GIC area in the vicinity. Industrial estates planned
within HYW PDA may also pose potential impact on the nearby existing village
areas.
4.9.48 In addition, there are two firing ranges identified within the San Wai/ Tai Ling
Firing Range. Horizontal separation distances of 270m and 480m are required
subject to the area sensitive rating. The shortest separation between the planned
residential areas at the western area of TKL PDA and the San Wai/ Tai Ling
Firing Range is about 480m which satisfies the distance setback from the
shooting ranges. However, it is considered that the operation of San Wai/Tai
Ling Firing Range may be different from Lo Wu Classification Range. Hence,
more information on the operation of San Wai/Tai Ling Firing Range shall be
collected during the stage of P&E Studies and the noise impact shall be
reassessed.
4.9.49 As stated in the approved EIA of Police Facilities in Kong Nga Po (AEIAR-
201/2016), by installing at least 2.5m height perimeter wall / boundary wall at the
project site of police facilities and extra 5m height 4-side walls at Ma Tso Lung
firing range, adverse fixed noise impact from the planned shooting range to its
nearby NSRs (approximately 50m away from the Project boundary) is not
anticipated. Since the shortest separation from the planned residential areas at the
western area of TKL PDA is about 190m, which is far away from its concerned
NSR, it is anticipated the operation of police facilities in Kong Nga Po will not
pose insurmountable constraints on NTN development.
124
4.9.50 Nevertheless, mitigation measures including suitable passive building design (e.g.
self-protected building design, noise tolerant building, etc.) for the planned high
and medium density residential areas should be considered to avoid direct line of
sight to the existing industrial noise sources and shooting ranges. For the planned
low density residential area potentially affected by the planned logistic industries
nearby, site boundary wall / barrier would be able to provide screening to the low
rise developments. It is also recommended to work with the operators for the
provision of at-source mitigation measures including noise barrier, enclosure,
acoustic treatment, etc. to mitigate the noise impact.
4.9.51 Working with Hong Kong Police Force will be required for the provision of at-
source mitigation measures including noise barrier, enclosure, etc. to reduce the
noise level at the affected area. Single aspect building design should be adopted
to avoid direct line of sight to the shooting range. At-receiver mitigation
measures including noise screening balcony, acoustic window, etc. should also be
considered to alleviate the noise impacts in the detail design stage, where the
building layout is available.
4.9.52 Potential noise sources planned within the PDA could be controlled to acceptable
levels through proper design or specification of maximum allowable noise level.
Hence, adverse fixed noise impact from the proposed development is unlikely,
subject to the stage of P&E Studies.
Helicopter Noise Impacts
4.9.53 A number of helipads is located within the Study Area, which would generate
noise from manoeuvring over the helipad and during the lateral flight. It was
advised by Government Flying Service (GFS) that the helipads would be used for
both emergency and pre-planned tasks by the government departments. There are
no fixed flight paths and routes. Currently, two types of helicopter are used,
namely aircraft type Super Puma AS 332 L2 and EC 155 B1.
4.9.54 For helicopter noise impact assessment, reference has been made to the approved
EIA Study “Helipad at Yung Shue Wan, Lamma Island” (EIA-114/2005). With
reference to the EIA Study, the helipad and its associated taking off path would
have to be located ≥ 386m from the nearest NSR within direct line of sight to
eliminate the manoeuvring noise. As a first thumb planning principle, a buffer
distance of 386m is adopted for planning purpose.
4.9.55 According to the approved EIA Study “North East New Territories New
Development Area”, the helipad within Lo Wu Firing Range is also used for fire-
fighting and police training with the use of two helicopters. Hence, a horizontal
separation distance of 542m from the Lo Wu Firing Range Helipad and its
associated taking off path is required to mitigate the noise impact on noise
sensitive uses.
4.9.56 Based on the Civil Aviation Ordinance, CAP 448C, a helicopter should maintain
a separation of 1,500 feet, over a congested area of a city, town or settlement
during the lateral flight. On considering the large separation of 1,500 feet,
adverse helicopter noise impacts are not anticipated during flyover mode.
4.9.57 MKT PDA is located at 386m from the “taking-off” paths of Lo Wu Firing Range
Helipad, MKT Helipad and Sandy Ridge Helipad. Offices are expected in
connection with the logistics industries within the PDA. However, offices are
generally provided with mechanical ventilation and not relying on window
125 Final Report – on Concept Plan for NTN
4.9.65 The proposed development in the Hyw PDA is located within the Consultation
Zone of the NENT Landfill and its extension. Qualitative LFG hazard assessment
indicates that the overall risk levels of LFG hazards are Medium (Category C)
and Low (Category D)/ High (Category B) during construction and operational
phases. It is recommended that below ground rooms/voids should be avoided as
far as practicable in the developments within the CZ. Besides, as the proposed
development of “Tourism/Leisure” zones and “Industrial Estate” zone is about
5m from the boundary of NENT Landfill and its extension, a setback of 20m
from the boundary of the existing landfill and its extension is recommended to be
adopted in detailed design stage. Suitable building management and appropriate
broad engineering and precautionary measures have been proposed making
reference to the “Landfill Gas Hazard Assessment Guidance Note”.
4.9.66 Moreover, monitoring should be undertaken when construction works are carried
out in confined space within the Consultation Zone. Routine gas monitoring
should be undertaken during groundwork construction and in all excavations.
Monthly gas monitoring should also be conducted at the basement. Nevertheless,
the requirements of operational monitoring by future site developers should be
determined during the detailed design stage when the site layout details are
confirmed.
Waste
4.9.67 The construction activities of the proposed development would generate a variety
of wastes including construction and demolition (C&D) materials from site
clearance, site formation and during the construction of buildings and structures
as well as chemical waste. Mitigation measures recommended in ETWB(W) No.
19/2005 Environmental Management on Construction Sites and other relevant
guidelines, shall be included in the Particular Specification for the Contractor as
appropriate.
4.9.68 The waste management hierarchy could be categorized as avoidance and
minimization; reuse of materials; recovery and recycling; and treatment and
disposal. The hierarchy shall be adopted to allow maximum waste reduction.
Records of quantities of waste generated, recycled and disposal (locations) shall
be properly kept. In particular excavation waste generation would be minimized
as the blasting/excavated material from the quarry could be sold as quarry
products according to the quarry rehabilitation contract.
4.9.69 During the operational phase, residential buildings, public areas and other
facilities such as refuse collection point will generate food waste, chemical waste
and municipal solid waste (MSW) will be disposed of. A Waste-to-Energy Plant
is proposed to be constructed, with the aim of reducing the quantities of non-
recyclable MSW to be disposed of at NENT landfill. In addition, the sewage
treatment works will generate sewage sludge. It is proposed to incorporate sludge
incineration facility into the WtE plant in NTN to cope with the future
requirement.
4.9.70 The waste management hierarchy of ‘Reduce, Replace, Reuse and Recycle’ shall
be used to evaluate the waste management options to allow maximum waste
reduction. Mitigation measures such as hiring a reputable waste collector to
remove general refuse and industrial waste from the stations on a daily basis,
handling chemical wastes in accordance with the Code of Practice on Packaging,
Handling and Storage of Chemical Wastes, and implementation of a trip-ticket
127 Final Report – on Concept Plan for NTN
mitigation, including but not limited to further field surveys, rescue excavations
and/or archaeological watching brief programmes for Mai Po SAI, in prior
agreement with the Antiquities and Monuments Office. In general, there is the
potential for further archaeology within the PDA and archaeological impact
assessments should be considered at the detailed design stage.
QH PDA
4.9.76 The impact to QH SAI (see Figure 4.9.18b), within QH PDA from proposed
commercial, residential and G/IC development will be direct and adverse. The
SAI is already compromised by the QH development under a different project
and detailed archaeological impact assessments including archaeological surveys,
followed by possible rescue excavation and/or watching brief programmes to be
envisioned for the stage of P&E Studies. Desk-based identified areas of
archaeological potential and historical village with archaeological potential and
historical villages, including Fu Tei Pai, Kwan Tei, and San Tong Po are located
within existing village zones or outside of development parameters and will thus
not require any action. In general, there is the potential for further archaeology
within the PDA and archaeological impact assessments should be considered at
the detailed design stage.
4.9.77 There are only five graded historic buildings identified within within QH
proposed development (see Figure 4.9.18b). Yi Kung Lok Mansion, Kwan Tei,
Fanling (Grade 3) is located within existing village zone and thus will not be
impacted by the PDA. Hung Leng Station and Fanling- Sha Tau Kok Branchline
(Grade 3) are situated within proposed residential development and may be
impacted during construction or operational phases. Detailed built heritage
impact assessment is recommended. Finally, Hindu Temple, Fanling (Grade 3)
falls within proposed agricultural development area or open space. Built heritage
impact assessment is recommended at the detailed design stage.
TKL PDA
4.9.78 The TKL PDA will have direct impact on Hung Leng SAI and Ping Che SAI (see
Figure 4.9.18b) and on the area of archaeological potential at Ping Che Kat Tin
where residential development is proposed. Impacts on archaeology occurring
from site formation and construction are adverse and irreversible. Detailed
archaeological impact assessments are recommended to establish acceptable
mitigation, including further field surveys, rescue excavations and/or
archaeological watching brief programmes for these areas. The desk-based
review identified further areas and historical villages with archaeological
potential at Ping Yeung, Tong Fong, Fung Wong Wu, Ha Shan Kai Wat, Tai Po
Tin, Shui Hau, Lo Shue Ling, and Lei Uk. These are located within village zones
and proposed agricultural zone or green belt zones. In general, there is the
potential for further archaeology within the PDA and archaeological impact
assessments should be considered at the detailed design stage.
4.9.79 Nine historic buildings of which eight graded and one under consideration for
grading (New Item) are identified in desk-based review within the TKL PDA (see
Figure 4.9.18b). The majority are located within existing village zone or
proposed green belt. These are Nos. 138-139 Ping Yeung (Grade 2), Sit Kin
Ancestral Hall, Ping Yeung, Ta Kwu Ling (Grade 3), Chan Ancestral Hall, Sit
Wan Tso, Ping Yeung (Grade 3), Tin Hau Temple, No. 72 Ping Che, Ta Kwu
Ling (Grade 3), Village Houses Nos. 35-37, Fung Wong Wu (Grade 3), Yeung
129 Final Report – on Concept Plan for NTN
Ancestral Hall, Fung Wong Wu (Grade 3), Ng Ancestral Hall, Fung Wong Wu
(Grade 3), Village Houses Nos. 24-27, Fung Wong Wu (New Item). Identified
historic villages with the potential for built heritage within the proposed
development include Ping Yeung (some 300 years ago), Tai Po Tin (over 100
years old), Ping Che (a few hundred years ago), Fung Wong Wu (more than 300
years old), Lei Uk (some 150 years old), Lo Shue Ling (17th century) all however,
fall within existing village zones and will not be impacted by the proposed
development.
4.9.80 Of the remaining graded historic buildings, Wing Kit Study Hall, nos. 12-13
Tong Fong (Grade 3) is located within an existing village zone which will not be
changed. Hung Shing Temple, Hung Leng (Grade 3) and Sam Tung Uk, Kwan
Tei North Tsuen, Fanling (Grade 2) fall within proposed agricultural development
area or open space.. Built heritage impact assessments are recommended for
developments around both graded historic buildings and Tong Fong village in
general as it has the potential to contain further heritage structures.
HYW PDA
4.9.81 There are no sites of archaeological interest within Hyw PDA. However, impacts
from transport corridor, cross boundary retail use, agriculture and residential
development to areas of archaeological potential at Nga Yiu Ha and Chuk Yuen
may be expected. Archaeological impact assessments are recommended at
investigation stage. Two other areas of archaeological potential identified during
desk-based review namely Tsung Yuen Ha and Wo Keng Shan are located within
existing village zones. In general, there is the potential for further archaeology
within the PDA and archaeological impact assessments should be considered at
the detailed design stage.
4.9.82 The two graded historic buildings, Kiu Fong Ancestral Hall, Tsung Yuen Ha
(Grade 3) and Nos.57-59, Tsung Yuen Ha (Grade 3) and the historical villages
with archaeological potential, including Wo Keng Shan and Tsung Yuen Ha
identified within the Hyw PDA (see Figure 4.9.18c) are located within existing
village zones and will not be impacted by the proposed development. For Ta Kwu
Ling Police Station, Ping Che Road (Grade 3) which falls within proposed cross
boundary retail development, impacts may be direct or indirect. Nga Yiu Ha on
the other hand may include historic structures and lies within proposed cross
boundary retail and transport network development. A built heritage impact
assessment is recommended at the detailed design stage.
MKT PDA
4.9.83 There are no known archaeological or built heritage resources and no historical
villages within MKT PDA (see Figure 4.9.18d). In general, there is the potential
for archaeology within the PDA and archaeological impact assessments should be
considered at the detailed design stage.
4.10.8 Due to the irreversible changes of LCA4a, the landscape impact cannot be fully
addressed with the implementation of recommended measures. However, after
applied the planning principle of ‘Urban-Rural-Nature Integration’ in the CP, the
impacts can be generally alleviated in local scale. Considered the possibility of
landscape enhancement on those newly proposed land-use, the landscape impact
for LCA4a will be reduced from substantial to moderate level by operation year
10. LCA7a and LCA10a are all expected to experience slightly adverse impact in
both construction and operation stages after mitigation.
Conclusion
132
4.10.9 Moderate adverse impact or lower from the proposed development is anticipated.
It is inevitable that landscape impacts caused by such major development cannot
be fully reduced and would remain at some locations even after implementation
of all possible mitigation measures. On review of the likely residual impacts on
the LRs/ LCAs within LMC, most of them are possibly reduced to slight/ or
insignificant level by operation year 10 when the mitigation measures have been
matured and taken effect. As a result, the overall residual landscape impacts from
the proposed scheme of LMC PDA are possibly acceptable with mitigation
measures if required mitigation measures are feasible and implemented prior to
impact commencement, and are able to fully account for all impacts.
MKT PDA
4.10.10 The assessment area of this PDA (Figure 4.10.1b) is from Ng Tung River and Lo
Wu Station in the west to Kong Nga Po in the east, and from MKT BCP in the
northeast to Fu Tei Au Tsuen in the south, major road access to the area is Man
Kam To Road.
Landscape Resources
4.10.11 A total of 16 LRs were identified within this PDA (refer to Figure 4.10.2b). No
registered OVT and floral species of conservation importance were recorded
within the PDA. 4 out of 16 LRs are subject to adverse impact before mitigation
and detailed description of these LRs are included from Table 4.10.3.
Table 4.10.3 Identification of LRs in MKT PDA
Code Landscape Quality & Rarity Ability to Sensitivity Degree of
Resources Maturity accommodate Impact
change
LR1b Agricultural Medium Medium Medium Medium Substantial
Land in MKT
LR2b Pond in MKT Medium Medium Medium Medium Moderate
LR4b Natural Medium Medium Low High Moderate
Stream in
MKT
LR14b Open Storage Low Low High Low Moderate
in MKT
4.10.14 A total of 6 LCAs were identified within 500m assessment area in MKT PDA
(refer to Figure 4.10.3b). 2 out of 6 LCAs are subject to adverse impact before
mitigation and detailed description of these LCAs are included in Table 4.10.4.
Table 4.10.4 Identification of LCAs in MKT PDA
Code Landscape Quality & Rarity Ability to Sensitivity Degree of
Character Maturity accommodate Impact
Area change
LCA2b Rural Inland Medium Medium Medium Medium Moderate
Plain
Landscape
LCA3b Miscellaneous Medium Medium Medium Medium Moderate
Rural Fringe
Landscape
4.10.15 Due to the irreversible changes of LCA2b and LCA3b, the landscape impact
cannot be fully addressed with the implementation of recommended measures.
However, after applied the planning principle of ‘Landscape Integration’ and
‘Urban-Rural-Nature Integration’ in the CP, the impacts can be generally
alleviated in local scale. Considered the possibility of landscape enhancement on
those newly proposed land-use, the landscape impact for those LCAs will be
reduced from slight to insignificant level by operation year 10.
Conclusion
4.10.16 Moderate adverse impact or lower from the proposed development is anticipated.
It is inevitable that landscape impacts caused by such major development cannot
be fully reduced and would remain at some locations even after implementation
of all possible mitigation measures. On review of the likely residual impacts on
the LRs/ LCAs within MKT, most of them are possibly reduced to slight or
insignificant level by operation year 10 when the mitigation measures have been
matured and taken effect. As a result, the overall residual landscape impacts from
the proposed scheme of MKT PDA are considered acceptable with mitigation
measures.
HYW PDA
4.10.17 The assessment area (Figure 4.10.1c) is from Lo Fong in the west to Ngong Tong
in the east, and from Hyw in the north to TKL in the south, major road access to
the area is Wo Keng Shan Road.
Landscape Resources
4.10.18 A number of sites of recognized conservation importance have been identified in
or near the HYW PDA and adjoining areas, including the following (refer to
Figure 4.10.1):
Lin Ma Hang Stream SSSI
Lin Ma Hang Lead Mines SSSI
4.10.19 A total of 17 LRs were identified within this PDA (refer to Figure 4.10.2c). Two
flora species (Aquilaria sinensis 土沉香 and Pavetta hongkongensis 香港大沙葉)
of conservation importance were identified. In addition, one (1) OVTs
(Cinnamomum camphora 樟樹, registered. no. LANDSD/ N3) was also found at
Wo Keng Shan within the PDA. 15 out of 17 LRs are subject to adverse impact
before mitigation and detailed description of these LRs are included in Table
4.10.5.
134
grassland in Tung Lo Hang, Tung Fung Au, Nga Yiu Ha and Lung Mei Teng)
will also be preserved as Green Belt in the future land-use.
4.10.21 After the implementation of recommended mitigation measures, the LRs will all
experience slight adverse to moderate adverse impacts during construction and at
the early stage of operational phase. When the compensatory measures are
applied, and further landscape enhancement is well established to enhance the
degraded landscape, it is considered that the landscape impacts for the LRs would
be reduced to insignificant/ or slight level by operation year 10.
Landscape Character Areas
4.10.22 A total of 5 LCAs were identified within 500m assessment area in HYW PDA
(refer to Figure 4.10.3c). 2 out of 5 LCAs are subject to adverse impact before
mitigation and detailed description of each LCAs are included from Table 4.10.6.
Table 4.10.6 Identification of LCAs in HYW PDA
Code Landscape Quality & Rarity Ability to Sensitivity Degree of
Character Area Maturity accommodate Impact
change
LCA2c Rural Inland Medium High Low Medium Substantial
Plain Landscape
LCA3c Urban Peripheral Medium High Low Medium Substantial
Village
Landscape
4.10.23 Due to the irreversible changes of LCA2c and LCA3c, the landscape impact
cannot be fully addressed with the implementation of recommended measures.
With the consideration of landscape enhancement on those newly proposed land-
use, the landscape impact for these LCAs will be reduced from substantial to
slight level by operation year 10.
Conclusion
4.10.24 Moderate adverse impact or lower from the proposed development is anticipated.
It is inevitable that landscape impacts caused by such major development cannot
be fully reduced and would remain at some locations even after implementation
of all possible mitigation measures. On review of the likely residual impacts on
the LRs/ LCAs within HYW, most of them are possibly reduced to slight/ or
insignificant level by operation year 10 when the mitigation measures have been
matured and taken effect. As a result, the overall residual landscape impacts from
the proposed scheme of MKT PDA are possibly acceptable with mitigation
measures if required mitigation measures are feasible and implemented prior to
impact commencement, and are able to fully account for all impacts.
TKL PDA
4.10.25 The assessment area (Figure 4.10.1d) is from Wo Keng Shan, Cat Hill and Ma
Tau Leng to Sha Tau Kok Road. Major roads, such as the Sha Tau Kok Road,
are also taken into consideration in forming the PDA boundary.
Landscape Resources
4.10.26 A total of 17 LRs were identified within this PDA (refer to Figure 4.10.2d).
Three floral species (Aquilaria sinensis 土沉香, Pavetta hongkongensis 香港大
沙葉 and Camellia crapnelliana 紅皮糙果荼) of conservation importance were
recorded within the PDA. In addition, two (2) OVTs (Ficus elastic 印度榕,
registered. no. LCSD/ N2 and Ficus microcarpa 細葉榕 registered. no. LCSD/
136
N4) were also found at Ping Che Road within the PDA. 15 out of 17 LRs are
subject to adverse impact before mitigation and detailed description of these LRs
are included from Table 4.10.7:
Table 4.10.7 Identification of LRs in TKL PDA
Code Landscape Quality & Rarity Ability to Sensitivity Degree of
Resources Maturity accommodate Impact
change
LR1d Agricultural High Medium Low High Substantial
Land in TKL
LR2d Pond in TKL High Medium Low High Substantial
LR3d Marsh/ Reedbed Medium High Low High Substantial
in TKL
LR4d Natural Stream Medium High Low High Moderate
in TKL
LR5d Channelised Medium Medium Medium Medium Moderate
Watercourse in
TKL
LR6d Grassland in Medium Low High Low Moderate
TKL
LR7d Shrubland in High Medium Low High Substantial
TKL
LR8d Mixed Shrubland Medium Medium Medium Medium Moderate
and Grassland in
TKL
LR10d Secondary High High Low High Substantial
Woodland in
TKL
LR11d Plantation in High Medium Low High Substantial
TKL
LR12d Orchard in TKL High Medium Low High Substantial
LR13d Village Type Medium Low Medium Medium Moderate
Development in
TKL
LR14d Urbanised/ Medium Low High Low Moderate
Ongoing Major
Development in
TKL
LR15d Open Storage in Low Low High Low Moderate
TKL
LR16d Waste Ground/ Low Low High Low Moderate
Temporary Used
Area in TKL
would be zoned as Agriculture, Green Belt and Open Space, which would be
beneficial for the local landscape quality. These planned land use types can help
to alleviate the adverse impacts caused by the development effectively.
4.10.29 After the implementation of recommended mitigation measures, the LRs will all
experience Slight adverse to Moderate adverse impacts during construction and at
the early stage of operational phase. When the compensatory measures are
applied, and further landscape enhancement is well established to enhance the
degraded landscape, it is considered that the landscape impacts for the LRs would
be reduced to insignificant/ or slight level by operation year 10.
Landscape Character Areas
4.10.30 A total of 7 LCAs were identified within 500m assessment area in TKL PDA
(refer to Figure 4.10.3d). 4 out of 7 LCAs are subject to adverse impact before
mitigation and detailed description of these LCAs are included in Table 4.10.8.
Table 4.10.8 Identification of LCAs in TKL PDA
Code Landscape Quality & Rarity Ability to Sensitivity Degree of
Character Area Maturity accommodate Impact
change
LCA1d Upland and High High Low High Moderate
Hillside
Landscape
LCA2d Rural Inland Plain Medium High Low Medium Moderate
Landscape
LCA3d Urban Peripheral Medium High Low Medium Moderate
Village Landscape
LCA4d Miscellaneous Medium High Low Medium Moderate
Rural Fringe
Landscape
4.10.31 With the consideration of those proposed land-use, such as Agriculture, Green
Belt and Open Space, together with the Village Type Development in Sing Ping,
Lei Uk and Ping Yeung, the changes of the local landscape character can be
alleviated gradually during the operational stage. With the implementation of
recommendation mitigation measures, the adverse impacts for LCA1d, LCA2d
and LCA3d would be reduced to slight by day 1 of operation. And the residual
impacts of these LCAs would be reduced to insignificant by year 10 of operation.
4.10.32 Given the proposed development are located within such a large scale area, the
fundamental change in LCA4d would not be able to alleviate completely. Thus,
the proposed development will generate moderate landscape impacts on that LCA
during both construction and operational phases before mitigation.
4.10.33 Due to the irreversible change of landscape character for LCA4d, the landscape
impact cannot be fully addressed with the implementation of recommended
measures. With the consideration of landscape enhancement on those newly
proposed land-use, the landscape character would be more compatible with the
surroundings and the landscape impacts can be alleviated gradually. By year 10
of operation, the residual impacts would be reduced to slight level eventually.
Conclusion
4.10.34 Moderate adverse impact or lower from the proposed development is anticipated.
It is inevitable that landscape impacts caused by such major development cannot
be fully reduced and would remain at some locations even after implementation
138
development in Burma Lines and near Lau Shui Heung Road would be planned
as District Open Space, which would be beneficial for the local landscape quality.
In addition, some of the landscape resources (such as the secondary woodland,
plantation, urbanised and village type development areas near Lau Shui Heung
Road and Sa Tong Po) will also be preserved as Green Belt in the future land-use.
These newly proposed District Open Space and Green Belt could provide
adequate space for the compensatory planting.
4.10.39 After the implementation of recommended mitigation measures, the LRs will all
experience slight adverse to moderate adverse impacts during construction and at
the early stage of operational phase. When the compensatory measures are
applied, and further landscape enhancement is well established to enhance the
degraded landscape, it is considered that the landscape impacts for the LRs would
be reduced to slight level by operation year 10.
Landscape Character Areas
4.10.40 A total of 7 LCAs were identified within 500m assessment area in QH PDA
(refer to Figure 4.10.3e). 4 out of 7 LCAs are subject to adverse impact before
mitigation and detailed description of these LCAs are included in Table 4.10.10.
Table 4.10.10 Identification of LCAs in QH PDA
Code Landscape Quality & Rarity Ability to Sensitivity Degree of
Character Area Maturity accommodate Impact
change
LCA2e Upland and High High Low High Moderate
Hillside
Landscape
LCA3e Rural Inland Plain Medium High Low Medium Substantial
Landscape
LCA4e Urban Peripheral Medium High Medium Medium Moderate
Village Landscape
LCA6e Institutional Medium Medium Medium Medium Moderate
Landscape
4.10.41 Given the proposed development are located within such a large scale area, the
fundamental change in LCA3e would not be able to alleviate completely. Thus,
the proposed development will generate substantial landscape impacts on this
LCA during both construction and operational phases before mitigation.
4.10.42 Due to the irreversible changes of LCA3e, the landscape impact cannot be fully
addressed with the implementation of recommended measures. With the
consideration of landscape enhancement on those newly proposed land-use, the
landscape impact for this LCA will be reduced from substantial to slight level by
operation year 10.
Conclusion
4.10.43 Moderate adverse impact or lower from the proposed development is anticipated.
It is inevitable that landscape impacts caused by such major development cannot
be fully reduced and would remain at some locations even after implementation
of all possible mitigation measures. On review of the likely residual impacts on
the LRs/ LCAs within QH, most of them are possibly reduced to slight/ or
insignificant level by operation year 10 when the mitigation measures have been
matured and taken effect. As a result, the overall residual landscape impacts from
the proposed scheme of QH PDA are possibly acceptable with mitigation
140
VSR Location Type of Users Quality of Alternative Degree of Duration Frequency Sensitivity
ID (Residential, Existing View Views (Yes, Visibility of View of View (Low,
Recreational, (Good, Fair, No) (Full, (Long, (Frequent, Medium,
Occupational, Poor) Partial, Medium, Occasional, High)
Transportation) Glimpse, Short) Rare)
No view)
Views from the top of hillside near Robin’s Nest (Hung Fa Leng) which is mostly visited by hikers. From this
elevated location viewing towards Peng Che with a panoramic background of the ridgeline of Wutong Shan,
Shenzhen. The trial on the hillside of this area does not appear to be well used, suggesting a few visitors to pass daily,
which would be moderately sensitive to any visual changes. Therefore the overall sensitivity is considered to be
‘Medium’.
The VSR is located on the pedestrian trail of Cheung Shan, looking in a north direction towards PC, HYW. It partially
contained with NENT landfill to the left and Sheung Wo Hang Tsuen (Sha Tau Kok) to the right with natural
mountains (Pak Fu Shan, Wo Keng Shan and Robin’s Nest) as the visual background. Regarding the characteristic of
the site, the VSR will be low usage during daily operation, which would be moderately sensitive to any visual changes
and the overall sensitivity is considered to be ‘Medium’.
VSR3 Sheung Shui Recreational Good Yes Full Medium Occasional Medium
Wa Shan
It is the view from Sheung Shui Wa Shan, facing to north towards TKL. From this elevated VSR, it given a
panoramic view for mountains of Wong Mau Hang Shan with an electricity pylons situated in the middle of the
foreground, and HLH is partially be visible at the right. This VSR represents visitors and hikers, which would be
moderately sensitive to any visual changes. Therefore the overall sensitivity is considered to be ‘Medium’.
VSR4 Lung Shan Recreational/ Fair Yes Full Long Frequent High
Residential/
Occupational
The VSR is located from Lung Shan Temple facing at north east direction, which is visited by visitors and villagers
frequently, workers from the Lung Shan Temple will also be occupied from this location. The VSR is offering a
distance view of natural mountains (Wutong Shan, Wo Keng Shan and QH). Due to the recreational or residential and
frequent usage of the view point, it would be highly sensitive to any visual changes. Therefore the overall sensitivity
is considered to be ‘High’.
Views on the pedestrian trial looking north east towards Liantong Shan and Wutong Shan from Shenzhen in the far
distance. An electricity pylons is situated in a close distance with small coverage of natural vegetation at the
foreground. Apart from hikers, villagers will be used frequently during daily operation and would be highly sensitive
to any visual changes. Therefore the overall sensitivity is considered to be ‘High’.
VSR Location Type of Users Quality of Alternative Degree of Duration Frequency Sensitivity
ID (Residential, Existing View Views (Yes, Visibility of View of View (Low,
Recreational, (Good, Fair, No) (Full, (Long, (Frequent, Medium,
Occupational, Poor) Partial, Medium, Occasional, High)
Transportation) Glimpse, Short) Rare)
No view)
The VSR is located on the hillside of Ki Lun Shan, facing east towards Tai Shek Mo and Sheung Shui. It is situated
within the woodland area and a group of vegetation is covered from the hillside from both sides of this location. This
area does not appear to be well used, suggesting a few visitors pass daily, which would be moderately sensitive to any
visual changes. Therefore the overall sensitivity is considered to be ‘Medium’.
VSR7 Cheung Lek Recreational/ Fair Yes Full Medium Frequent High
Residential
The VSR is located at the pedestrian walkway from Cheung Lek, facing east towards MKT. It is situated within the
natural vegetated area with panoramic view of Pak Tai To Yan ridgeline as the background, the Fanling golf course
can be visible at the left and some low rise development is located in the middle with far distance. Same as above, due
to the characteristic of the site, the usage of this VSR would be highly sensitive to any visual changes. Therefore the
overall sensitivity is considered to be ‘High’.
VSR8 Kai Kung Recreational Fair Yes Part Medium Occasional Medium
Leng
Views from the top of hillside Kai Kung Leng which is mostly visited by hikers. From this elevated location facing
north east towards LMC, with a far distance view of Fanling and Shenzhen City development. Natural view of
mountains such as Nam Shan and Wo Keng Shan are visible from the right from this VSR. The trial on the hillside of
this area does not appear to be well used, suggesting a few visitors to pass daily, which would be moderately sensitive
to any visual changes. Therefore the overall sensitivity is considered to be ‘Medium’.
4.10.47 In summary, for VSRs, it is considered the most sensitive views are those which
currently experience a direct and broad connection with the wider undeveloped
landscape setting. The proposed development’s visual impact on the existing
development has been preliminary reviewed in this VIA and will be detailed
assessed in the future detailed P&E Studies.
4.10.48 Prior to mitigation, substantial adverse impacts are predicted in relation to VSR3
‘Sheung Shui Wa Shan’ and VSR5 ‘Cheung Po Tau’. This impact is generated
due to the substantial loss of visual elements and large magnitude of visual
change. While, moderate adverse impacts are predicted in relation to VSR1
‘Robin’s Nest’, VSR2 ‘Cheung Shan’, VSR4 ‘Lung Shan’, VSR6 ‘Ki Lun Shan’,
VSR7 ‘Cheung Lei’ and VSR8 ‘Kai Kung Leng’.
4.10.49 Mitigation works in development area during the construction stage rely heavily
on the optimisation of the footprint of the works area, avoidance of significant
topographical changes together with the retention, protection and compensatory
planting of trees/ vegetation. Following the implementation of mitigation
measures, adverse visual impact would be reduced to lower level compared with
before mitigation, both at construction stage and operation early stage in general
case. These measures have the capacity to reduce the level of residual impact
experienced by the VSRs during construction stage. Greening measures such as
use of climbing plants and verge planting help to break up the uniformity of new
143 Final Report – on Concept Plan for NTN
road formation and associated structures, when used in combination with wider
screening measures e.g. sensitive design of infrastructure, facade treatment,
colour scheme etc. which help to reduce the visual impacts in the early
operational stage. The suggested mitigation measures are illustrated in Figures
4.10.5 to 4.10.10 and summarised in Table 4.10.12 and Table 4.10.13.
Table 4.10.12 Summary of Proposed Mitigation Measures in Construction Stage
ID No. Visual Mitigation Measures
CM7 Site Hoarding
To reduce negative visual impact, construction site hoarding should be erected around
the site to screen pedestrian level views into the construction area from visual sensitive
receivers. Hoarding design should consider greening measures such as colour variations
or plantation, and should be adopted to improve its visual appearance.
CM8 Management of Facilities on Work Sites
To provide proper site management of the facilities on the sites, give control on the
height and disposition/ arrangement of all welfare facilities and construction plant on
site to minimise landscape and visual impacts to adjacent VSRs and existing/ retained
site features.
CM9 Construction Programme
Employ construction techniques which assist in streamlining construction programme,
minimise the duration of plant operations. Consider prefabrication of building elements
offsite to minimise on site works and construction period.
CM10 Light Control
Day and night time lighting should be controlled to minimise glare and light spill from
the construction sites. Shrouded or directional lighting should be considered where
appropriate as a general good practice construction measure.
CM11 Optimisation of Construction Areas & Providing Temporary Landscape on Temporary
Construction
Construction areas’ control shall be enforced, where possible, to ensure that the
landscape and visual impacts arising from the construction activities are minimised. It
includes reduction of the extent of working areas and temporary works areas,
management on storing and using the construction equipment and materials, and
consideration of detailed schedules to shorten the construction period. Temporary
landscape treatments are considered to be adopted such as applying hydro-seeding on
temporary stockpiles and reclamation areas to alleviate the potential impacts.
CM12 Advanced Tree Planting
Advanced tree planting works would help to mitigate for loss of existing resources and
also to mitigate the effects of construction, such as tall screen/buffer trees and shrubs
should be planted to screen proposed buildings and other structures where appropriate.
The planting should also be free from utility and noise barrier structures. This measure
will form part of the compensatory planting and will improve compatibility with the
surrounding environment and create a pleasant pedestrian environment.
CM13 Minimum Topographical Change
The footprint of construction elements and temporary works areas should be optimised
to reduce topographical/ landform changes, as well as reduce land take and interference
with natural terrain. Where there is a need to significantly cut into the existing landform,
retaining walls and cut slopes should be considered as appropriate. To minimize
landform changes and land resumption, earthworks and engineered slopes should be
designed to be a visually interesting, compatible with the surrounding landscape and to
mimic the natural contouring and terrain as appropriate e.g. introduction and
continuation of natural features such as spurs and ridges where appropriate, to support
assimilation with the hillside setting. Landscape reinstatement of disturbed existing
topography should match adjacent area and condition.
144
4.10.50 The overall visual character in NTN would be completely changed by the
proposed development after the construction, all the recommended mitigation
measures might not be able to alleviate the fundamental change in character, and
therefore, the residual adverse impacts are still predicted in the operational stage.
In terms of effectiveness of mitigation measures such as landscape planting or
screening measures, and lighting control, they would help to alleviate the adverse
visual impacts from the new urban development and enhance the compatibility
145 Final Report – on Concept Plan for NTN
with the existing development. It is considered that the cumulative impacts would
be reduced to slight/ moderate by year 10 of operation when the mitigation
measures have been matured and taken effect.
4.10.51 As a result, with the possible alleviation of adverse visual impacts by means of
effective mitigation measures proposed above, the overall residual visual impacts
from the proposed scheme of NTN development are considered surmountable
given the mitigation measures are feasible and implemented prior to impact
commencement, and are able to fully account for all impacts. A comprehensive
VIA shall be conducted at detailed design stage to demonstrate the effectiveness
of proposed mitigation measures, and to verify the conclusion at this preliminary
feasibility stage.
5.2.4 The entire QH and HYW PDAs and majority of the TKL PDA, which includes
low to high density residential uses, G/IC facilities, commercial uses will be
developed in this phase.
5.2.5 For HLH, only about 16 ha of land located to east of the proposed ring road has
been included for high-rise residential development in this phase as it can be
supported by the proposed road network. About 88 ha of land at HLH area, which
is considered far away from major development nodes has not been included in
this development phase.
5.2.6 In general, the Phase 2 development will generate an additional population of
160,000 and employment of 89,000. The total (Phase 1 + 2) population and
employment will be 255,000 and 209,000 respectively.
Ultimate Phase 3 Development
5.2.7 In Phase 3 development, population beyond 255,000 will trigger the support of
the possible north-south railway extension to further southward connecting other
new towns and/or urban area.
5.2.8 With the support of new railway extension and additional passenger capacity
actuated by connecting to further south of NT connecting other new towns and/or
urban area , further development of the remaining 88ha of land at HLH area can
be enabled for high-density residential development with associated commercial
and G/IC use. The Phase 3 development will yield an additional of 95,000
population and 6,000 jobs. The total (Phase 1 + 2 + 3) population and
employment will be 350,000 and 215,000 respectively.
5.2.9 Inevitably, the additional population intake would also induce additional road
traffic demand that would need more stringent traffic demand management
measures and/or new transport initiatives (e.g. possible new highway) to be in
place for attenuating such impact.
30
There are about 80 potentially registrable Old and Valuable Trees; and at least another 84 tress of protected
species (e.g. Aquilariasinensis, Artocarpus hypargyreus, Keteleeria fortune) found within the FGC
(according to a tree survey conducted by the Hong Kong Golf Club).
31
Tree clusters and secondary woodland are linearly arranged on both sides of fairways.
32
A total of 69 graves and 80 urns are scattered throughout the FGC.
33
There are three graded historic buildings (Fanling Lodge – Grade 1; Club House – Grade 2 and Half-way
House – Grade 3) within the FGC.
34
Fan Kam Road is currently a substandard single two-way rural road running through the FGC. Widening of
Fan Kam Road is constrained by mature trees on both sides of the road and the 48-inch diameter Dongjiang
water mains.
149 Final Report – on Concept Plan for NTN
7 Conclusion
7.1.1 The purpose of this FR is to document the study flow and methodology, key
findings, recommendations, conclusion of the Study, the land use proposals of the
CP and the summary of the aforementioned broad technical assessments. To
conclude, this Study has:
Formulated a “Smart Green Resilient” Study Approach - This was
undertaken at the beginning to set the overall approach for the Study;
Conducted a Baseline Review and Identified Key Issues and
Opportunities & Formulated Key Planning and Design Principles - A
baseline review and land use review of the 5,300ha Study Area informed
the six over-arching opportunities and four key planning and design
principles which guided the study process;
Delineated PDA Boundaries and Provided Population &
Employment Estimates for NTN - Given the vast area of land in NTN, a
GIS-based MCD Analysis has been carried out to provide a basis for
delineation of the boundaries of the PDAs. The exercise also involved the
estimation of the appropriate level of population and employment to be
planned in the future NTN;
Formulated Concept Plan for NTN – A set of planning approaches
guided the distribution of land uses and led to the formulation of three
development scenarios, together with the considerations of development
phasing for progressive implementation of the CP triggered by different
infrastructure provision. Two development scenarios, namely Scenario I
(Balanced Population and Employment) and Scenario II (High Population
and Employment) are recommended for further study; and
Conducted Broad Technical Assessments in Support of the Concept
Plan for NTN -Throughout the Study, three rounds of broad technical
assessments were carried out iteratively to support the planning and
development of the CP. The broad technical feasibility for the CP under
both Scenarios I and II has been ascertained.
7.1.2 Way Forward –
Being one of the two strategic growth areas under the conceptual spatial
framework in the “Hong Kong 2030+”, the two development scenarios of NTN
and broad land use concepts which were simplified from the CP in Section 3,
have been presented in public engagement for “Hong Kong 2030+” conducted by
PlanD in October 201635(Figure 7.1.1). While LMC and MKT PDAs are named
ST/LMC Development Node and MKT Logistics Corridor respectively, HYW,
TKL and QH PDAs are presented as the NTN New Town in the public
engagement. Subject to the outcome of “Hong Kong 2030+”, the preliminary
findings and recommendations of this Study together with the public views on the
NTN development, will provide the basis for detailed P&E Studies to be
conducted, if the NTN development is taken forward.
35
The public engagement exercise of the “Hong Kong 2030+” is conducted from 27 October 2016 to end April
2017.
Figures
Appendices
Appendix A
Working Assumptions (Domestic Uses)
Large Site Reduction Factor: 40%
A LSRF is deployed within all site areas that are intended for domestic uses. The purpose of
keeping this Factor is to estimate the net maximum area that can be employed for domestic
uses, given that domestic land plots require internal roads for access.
Flat Sizes, Persons/Flat and Floor-to-Floor Height
Assumptions for average flat size and persons/ flat for each plot ratio have employed by
making reference to the HKPSG, where appropriate. Certain floor-to-floor height has also
been assumed for deriving the broad number of storeys and building height. The CP for NTN
have thus made use of the following assumptions:
Domestic Plot Ratio Average Flat Persons/ Flat Floor-to-Floor Height
Size (m2) (ppf) (about)
Mixed Use
5+1 60 2.8 3m
6+2.5 60 2.8 3m
Residential Use
7.5 60 2.8 3m
6 60 2.8 3m
5.5 60 2.8 3m
5 65 2.8 3m
4.5 65 2.8 3m
4 80 2.8 3m
3.5 80 2.8 3m
3 80 2.8 3m
1.5 95 2.8 3m
Appendix A
Working Assumptions (Non-domestic Uses)
Large Site Reduction Factor: 40%
A LSRF is deployed within all site areas that are intended for non-domestic uses. The
purpose of keeping this Factor is to estimate the net maximum area that can be employed for
non-domestic uses, given that non-domestic land plots require internal roads for access.
No. of Jobs / GFA (m2)
Assumptions have been adopted for the average number of jobs per GFA per industry,
which are detailed as follows:
Non-domestic Use Average Job / GFA (m2)
Resident
55,081 0 190,075 8,887 72,620 326,663
Population
Disposal MSW
(Domestic) 30.2 0.0 104.3 4.9 52.8 192
(tonnes / day)
Disposal MSW
(C&I) 113.8 35.9 103.6 77.3 22.7 353
(tonnes / day)
Total Disposal
MSW 144.0 35.9 207.8 82.2 75.5 545
(tonnes / day)
Recovery MSW
176.0 43.9 254.0 100.5 92.3 667
(tonnes / day)
Domestic Food
Waste (tonnes / 11.7 0.00 40.3 1.9 15.4 69
day)
C & I Food
Waste (tonnes / 39.5 12.5 356.0 26.9 7.9 123
day)
Total Food
51.2 12.5 76.3 28.7 23.3 192
Waste
Note: (1) Assume typical sludge generation per head per day: 75g; (2) Dry sludge content 30%; (3) allowance %
= 20%
Appendix D
Broad Assessment of the Development Potential of the Fanling Golf Course Site
1.1 The closest point of Fanling Golf Course (FGC) is about 800m to the west of
Sheung Shui Railway Station. It is composed of three distinct 18-hole courses set
within 172 ha of land. The Old, New and Eden Courses (Figure 1) were built in
1911, 1931 and 1970 respectively.
Old Course
Fanling Lodge
Eden Course (Grade 1)
New Course
Clubhouse (Grade 2)
Figure 1
Trees
2.3 According to the broad brush tree/vegetation survey conducted by the Hong Kong
Golf Club (HKGC), there are about 30,000 trees in the golf course (with a diameter
at breast height (DBH) over 150mm). Registration of Old and Valuable Trees (OVTs)
within FGC has yet to be carried out. There are about 80 trees potentially meeting
the criteria for OVTs (with a DBH over 1,000mm, the majority of which are
estimated to be over 100 years old and scattered across the golf course), and at least
another 84 trees protected species (such as Aquilariasinensis (土沉香), Artocarpus
hypargyreus (白桂木), Keteleeria fortune (油杉)) found within the FGC. In addition,
there are large tree clusters and secondary woodland of considerable sizes with
mature trees with ecological value within the FGC (Figures 2 and 3).
2
Figure 2
Figure 3
3
Graves and Road Widening
2.4 Apart from the built heritage and tree clusters, the scattered ancestral graves 1 and the
difficulty of widening Fan Kam Road 2 involving substantial tree felling and
relocation of the Dongjiang water mains also pose significant constraints to the
development of the FGC.
2.6 In general, the HK Open is mainly played on part of the New Course and the Eden
Course, while the remaining portion of the FGC including the Old Course would
provide supporting services to a total of 40,000 spectators and volunteers, as well as
practising areas for the golfers of the tournament and grounds for a junior event over
four days of the event. The supporting functions during HK Open include providing
car parking and space for hospitability tents, media center, etc. The Old Course is
also important in ensuring continuous provision of golfing venue within the FGC
when the course for HK Open is closed for maintenance or inclement weather during
summer months leading to HK Open.
3.1 Besides the above site-specific factors, the Study has taken into account the
surrounding environment, overall infrastructure capacity, the potential impacts of the
development as well as urban design considerations in examining the two
development options of FGC, including (a) partial development; and (b) full
development.
3.3 Under this option, residential developments of higher density are concentrated in the
northern part of the site closest to the Fanling/Sheung Shui New Town which has
better access to the major road network and public transport, as well as existing
government, institution or community (GIC) and commercial facilities. Residential
developments of lower density are proposed in the southern portion of the site due to
limited capacity of Fan Kam Road and low-rise character of neighbouring uses.
3.4 The proposed development area within Old Course is shown in Figure 4. A
conservative estimate of the flat production in this option is 4,600 accommodating a
population of about 13,000.
Figure 4
5
Full Development Option
3.5 Under this option, the entire FGC is proposed for housing, commercial, GIC, open
space, and tourism/leisure uses, with woodland covers and major tree clusters
conserved as green belt. Similar to the considerations under the Partial
Development Option, residential developments of higher density are located in the
northern portion of the site. GIC and open space uses are proposed in accordance
with the requirements set out under the Hong Kong Planning Standards and
Guidelines and advice of relevant bureaux/departments.
3.6 The proposed development area is shown in Figure 5. The flat production from this
option is 13,200 accommodating a population of about 37,000.
Figure 5
6
3.7 A comparison of the key development parameters of the two options is shown in the
table below:
3.8 The Study confirms that both options are technically feasible. The Full Development
Option is assumed to be pursued together with the NTN development proposed
under the Study, where a possible north-south railway connecting Heung Yuen Wai
to a nearby new town and/or the main urban areas will have to be implemented.
The Partial Development Option alone may be implemented independent of the
NTN development subject to infrastructural improvements in terms of road
interchange, road, sewerage, drainage and water supply 3.
3
Infrastructure enhancements in support of the Partial Development Option include (i) improvement of Po Shek Wu Road
Interchange by another project; (ii) widening of a short section of Fan Kam Road between Po Kin Road and the proposed
site access; (iii) new on-site self-contained sewage treatment works (STW) or sewerage requirements incorporated in the
new STWs in the North District South; (iv) necessary drainage mitigation measures; and (v) expansion/upgrading of
existing water treatment works/pumping stations in Ngau Tam Mei and Tai Po.
7