The business will be registered under the name "MENA private milk-processing plant" as a group
proprietorship and owned by 4 friends: Fasika, Million, Mathios and ebessa. It will have its
business address located at Akaki sub city.
The business will be managed by the owners but all of them have their own management tasks.
Fasika melse will act as a general manager, Million demie as a personnel manager, mathios
kassahun as a production manager and ebessa as a marketing manager. A supervisor will be
hired to manage the production process when the owners are not around.
The entrepreneurs are graduates of civil engineering in 2018. No other prior experience after
graduation.
Organizational Chart
MENA private milk-processing plant
General Manager
(Fasika)
(Endale) Secretary
(to be hired)
supervisor
(to be hired)
Daily Laborer
(to be hired)
We have listed down the following activities to be undertaken before we can operate our
business:
we aim to start our operation approximately three months after our loan application, or six
weeks after release of our loan.
These pre-operating activities with their corresponding timetable appear in Table in a Gantt
chart.
1 2 3 4 5 6 7 8 9 10 11 12 13
3. Applying/Approval of Loan
6. Hiring Labour
8. Trial Production