Anda di halaman 1dari 5

Vacuum dewatering

experts answer questions


he questions answered here continue for 5 or 6 hours depending foot on the suction mat and feel

T were collected by the editors


and submitted to Ha ra l d
Wenander, Technical Di re c-
tor, Tremix AB, Skarholmen, Swe-
den. Mr. Wenander has answe re d
on working conditions. This gives a
total area of 7,000 to 8,400 square
feet per day,(3) achieved with one
vacuum pump running two suction
mats and using two men for the en-
whether the concrete gives way to
your weight. If it feels somewhat
soggy, continue dewatering for
some additional time; if it feels hard
the vacuum can be shut off.
most of them himself but re p o rt s tire vacuum treatment. These two
that some replies were written in men are not occupied full time and Q. What is the maximum thickness
cooperation with Professor Roman can also be used for other jobs such of floors to which vacuum dewater -
Malinowski, of Chalmers University as floating and troweling while each ing can be applied?
of Technology, Gothenburg, Swe- vacuum cycle proceeds. In Scandi-
den. navia the whole job of placing, vi- A. The generally accepted maxi-
brating, screeding, vacuum treat- mum penetration depth is about 12
OPERATION OF EQUIPMENT ment, floating and troweling of the inches.(5) Processing time for this
slab is done by a crew of 4 to 5 men. depth is about 45 minutes. Experi-
Q. How many men are there to a
crew for vacuum dewatering of con - ments made at the Lund Technical
crete? Q. Who operates the pump? University in Sweden have shown
that it is possible to remove some
A. The system requires two men to A. If this question means “Is a spe-
water from concrete to a depth of
place the suction mats or pads; but cial mechanic required to run the
about 31 inches(6) but the vacuum
once this is done and the vacuum pump?” the answer is no. The
time was 11⁄2 hours and this is too
valve to the pump is opened, the pumps sold in the United States
long to be practical except for very
vacuum treatment continues on its generally are driven by internal
special circumstances. A very thick
own for the 15 to 20 minutes of op- combustion engines with electric
slab can be treated successfully,
eration. The pump needs no super- starters. Once the engine is started it
howe ve r, because generally the
vision. Should the tank become can be left on its own during the
overfilled with water the pump main objective is to remove excess
whole vacuum dewatering opera-
stops automatically. In fact, in Scan- water near the surface so the slab
tion. When the vacuum mat is to be
dinavia the work cycle is planned to can be walked upon and finished
moved to the next location the
start up a new vacuum treatment within a short time. The top part of
pump is stopped and the water dis-
cycle just before a work break and the slab is usually the more impor-
charge valve is opened so that the
the vacuum is left on during the tant portion and dewatering here
water collecting tank is emptied.
break so that the treated part of the provides increased compressive
The pump is again started and
slab is ready for finishing immedi- strength and wear resistance, great-
nothing else need be done. Should
ately afterward. ly reduced water permeability, low-
the water collecting tank for any
reason become full, the pump stops er shrinkage and higher modulus of
Q. What is the productivity of such a elasticity.
automatically. Some models have
crew in square feet per day?
two collecting tanks which can be
A. With the type of equipment in emptied independently while the Q. When concrete slabs are to be
most general use in Europe at pre- pump is running. treated by vacuum is it necessary to
sent, about 700 square feet(1) * can be screed a little bit high in order to
vacuum treated at a time. If the vac- Q. How do you decide when it is time compensate for the loss in thickness
uum is left on for 20 minutes and to shut off the vacuum dewatering due to water removal?
another 10 minutes are required to equipment?
move the suction mats to the next A. Since water is removed, some
location (while the water collecting A. The vacuum is left on for about 2 concrete volume is lost. The result-
tank of the pump is being emptied), 1
⁄2 to 4 minutes per inch(4) of slab ing compaction is about 2 percent,
the resulting cycle is 1⁄2 hour. This thickness. Different types of con- which means that a slab of 6-inch(7)
means 1,400 square feet are treated crete vary in the rate at which they thickness will settle by .02 x 6 or
per hour.(2) Without ove rt i m e, con- release their water. For this reason a about 1⁄8 inch.(8)
crete placing and dewatering can simple test is required: Place one
Manager”; and “Part 2—For the
Floorlayer,” by G. Barnbrook. These
can be obtained from the Cement &
Concrete Association, 52 Grosvenor
Gardens, London SW1W OAQ, Eng-
land. A two-page summary of these
booklets is given in “Vacuum Dewa-
tering Procedures,” Concrete Con-
struction, July 1975, page 280

.
EQUIPMENT
Five pumps used on this large job assured that there was always a pump
available and maintained rapid progress. Q. What is the largest size mat in
use?
A. Our company’s largest standard
Q. What can be done if there is a Q. Is there ever any trouble with plas - mat is about 400 square feet(9) (17 by
power failure during the vacuum de - tic shrinkage cracking when vacuum 23 feet(10)), though larger sizes have
watering cycle and the slab is only dewatering is used? If so, is it any been used successfully for special
partially dewatered when it is time more difficult to beat the cracks jobs. The largest one we know of is
to finish the surface? closed than it would be with ordi - about 550 square feet.(11)
nary concrete ? (This is sometimes
A. If there is a failure in the prime Q. Has the vacuum process been
done by hammering the surface with
mover of the vacuum pump, you used with 45-foot(12) screeds such as
wood floats.)
would be no worse off than if you are in commercial use in the States?
had placed concrete without vacu- A. There is no trouble with plastic
um treatment in the first place. If for shrinkage cracking during vacuum A. The longest standard screed we
strength, wear qualities or other rea- dewatering. The cracks which may use is 40 feet(13) For special applica-
sons it is imperative to use vacuum appear along the perimeter of the tions 45-foot(12) screeds have been
treatment, then the use of a standby mat because of the reduction of used and are entirely practical. A
vacuum pump or a standby electric concrete volume due to the vacuum gasoline engine or electric motor
generator must be considered. The process are closed efficiently and distributes the vibrations evenly
vacuum pump today is a very well completely during use of the plan- along the entire length of the screed.
developed piece of equipment and ing disc immediately after vacuum
chances of failures are very small. treatment. Because of the reduced Q. How much pressure per square
water-cement ratio, subsequent foot can be created in vacuum dewa -
Q. What can be done if it rains while plastic shrinkage and likelihood of tering?
the vacuum is being applied and it plastic shrinkage cracking are less
continues to rain afterward? Is there A. At full vacuum the pressure is
than with non-vacuumed concrete. about 2,000 pounds per square
any way to finish the slab without
working water into the surface? foot.(14) In practice the vacuum devel-
Q. Are there any specifications avail - oped is 80 to 90 percent of the theo-
A. Obviously dewatering can take able on recommended practices for retical maximum: 1,600 to 1,800
place while it rains because the sur- vacuum dewatering? pounds per square foot.(15)
face being treated is covered by a
vacuum mat during the process. If a A. Handbooks and instructions are Q. How often must vacuum mats be
heavy downpour occurs when the available for recommended prac- replaced?
process is finished there is no way of tices based on experience from
finishing the concrete but if the rain thousands of work sites in Eu ro p e. A. When using soft vacuum mats
is only a light drizzle the concrete The best recommended practices which come in two parts (filter pads
can be floated immediately, using yet published are from the Cement and top covers) the filter pads which
the troweling machine with planing & Concrete Association in England, are placed directly on the concrete
disc. If the surface is to be troweled, which has published three booklets are the more vulnerable parts. If
plastic covers can be used immedi- on concrete floor placing: “Concrete properly cared for they will last for
ately after disc planing and, when Ground Floors, Their Design, Con- 100,000 square feet or more of use; if
the surface has set to a certain de- struction and Finish,” by R. Colin not cleaned after each day’s work,
g re e, it can again be exposed and Deacon; “Concrete Ground Floor they may become clogged with hy-
troweled. Immediately after this op- Construction for the Man on Site, drated concrete and will then have a
eration it should be covered again. Part 1—For the Site Supervisor and much shorter life.
thus a very small fraction of 1 per-
cent of the cement content of the
mix and is of no practical impor-
tance whatsoever.
Q. If you must avoid dumping water
in the immediate vicinity, what is the
Two men are usual procedure for disposing of wa -
needed to place ter from the vacuum tanks? Also,
suction mats. The how much water does one unit pro -
same men start and duce in a day?
stop the pump.
A. In all our experience there always
seems to be some place fairly close
to the pump where water can be
dumped. If there is none, perhaps
the only solution is to move it away
in tank trucks.
One pump unit can treat up to
about 8,000 square feet in a day.(17) If
the slab has a thickness of 6 inch-
es,(18) this means about 150 cubic
yards(19) of concrete and if 5 to 7 gal-
lons of water are extracted from
Vacuum mats protect the slab during each cubic yard (20) there would be
a sudden rain and permit dewatering about 750 to 1,050 gallons(21) of water
to be done during a storm; finishing
per day.
operations require a period virtually
free of precipitation.
Q. Are vapor barriers needed when
building a floor with vacuum dewa -
tered concrete?
A. If you are thinking of a vapor bar-
rier as a means of sealing the vacu-
The top cover, made of a durable Q. What kind of servicing of parts um system, there is no need for it.
reinforced plastic, has a very long and repairs can be expected on The concrete itself seals around the
life, perhaps as much as seve ra l equipment made in Sweden? vacuum mat edges and no air is
years. A. I can answer only for our own sucked in through the bottom of the
Where vacuum plates are used the company, which never sells any- slab until the vacuum has penetrat-
filter cloths of the plates have to be where without also providing ser- ed all the way from surface to bot-
cared for in the same way as the fil- vice. We now have dealers in Indi- tom. By that time the vacuum treat-
ter pads of soft mats. The filter ana, Minnesota, Ohio and ment is finished anyway. Only for
cloths must be replaced at regular Connecticut; each provides service very thin slabs may a vapor barrier
intervals but as a rule this is a fairly facilities. Our dealer network is be required.
simple operation. gradually expanding. If a certain If a vapor barrier is needed for the
spare part is not on hand with a more common purpose of blocking
Q. Is there any problem with ripping dealer, it will be flown in at once. moisture from entering the building
or tearing of mats through ordinary through the slab, then a vapor bar-
job handling? If so, what measures Q. What happens to the minus-50 rier may be needed although the
are taken to prevent it? mesh(16) material that accompanies permeability of vacuum treated
the water removed by vacuum? concrete is ordinarily lower than
A. Mats may of course be torn on that of untreated concrete.
A. A very small amount of fines in
sharp ends of rebars or other projec-
the concrete, mostly cement and
tions but this does not occur very of- ECONOMICS OF USE
filler, accompanies the extracted
ten. A small rip in a filter pad does
water to the water collecting tank of Q. What is the smallest size job on
not make it useless. Rips in the top
the vacuum pump. The actual which vacuum dewatering is practi -
cover can very easily be repaired by
amount is very small—less than 1 cal?
gluing on a patch.
percent by volume of the collected
A. There really is no lower limit; al-
water. The amount of cement lost is
most any size job can be tackled.
A. Yes, but they are often unneces- the aggregate, some of which is ex-
sary. The only admixtures with tracted. When the vacuum is shut
which special care must be taken off, atmospheric pressure presses
are air entraining agents. The fine some of the water back into the ag-
air bubbles they produce tend to gregate as its air content again con-
slow the rate at which water can be tracts. This means that the concrete
extracted. No more air entraining after vacuum treatment gets fairly
agent should be used than the hard and dry and can quickly be fin-
amount needed for a total air con- ished. The short waiting time before
Lightweight aggregate such as this
highly porous 34⁄ -inch particle (shown tent of about 4 percent in the origi- finishing can be completed reduces
enlarged) retains some water for nal mix. Slump should not be more the risk of plastic shrinkage.
curing after vacuum is released. than 3 inches(22) and preferably only
2 inches(23) since higher slump may Q. Lightweight aggregate is said to
lead to segregation. The suction hold water which is available for
time should be lengthened by about curing the cement paste. Is there any
Q. What is the cost per square foot of 50 percent. likelihood that this so-called curing
vacuum dewatering? Air content in concrete after vacu- water will be removed by vacuum -
um treatment is slightly more than ing, thus losing the advantage?
A. There is no ready answer to this
before treatment. In view of the
question since the total time taken
greatly reduced water permeability A. When some of the water re t u rn s
to place and finish a slab when vac-
of the surface of vacuum treated to the aggregate after the vacuum is
uum dewatering is used is generally
concrete—especially if it has been shut off the surface gets fairly hard,
less than that required to place and
thoroughly machine floated and and floating as well as troweling can
finish one by usual methods. This is
troweled —the use of air entraining take place immediately. If properly
because vacuum dewatering per-
agents for prevention of frost dam- done, there is no danger of too little
mits the concrete to be stepped on
age is sometimes reduced in water being left for hydration of the
immediately after treatment; ma-
amount or completely omitted. concrete.
chine floating also can be started In ordinary circumstances there is
immediately. There may have to be no risk that too much water will be
a certain waiting time before final Q. Is shrinkage compensating ce -
extracted from the concrete. The
troweling can be started but gener- ment ever used in combination with
water is extracted through capillar-
ally the time before the slab can be vacuum dewatering?
ies of the concrete. The diameter of
completely finished is greatly re- A. There has been no experience yet these capillaries is proportional to
duced. This time gain is very pro- with the use of shrinkage compen- the water-cement ratio of the con-
nounced, especially in cold and sating cement in combination with crete and by the time the water-ce-
damp weather. So in actual fact, the vacuum dewatering. There is proba- ment ratio gets down to 0.35 the
total cost per slab is less when using bly no reason why this type of ce- capillary diameters are so small that
vacuum dewatering than when not. ment could not be used. no more water can be extracted.
There is no possibility of extracting
Q. Does anyone rent vacuum dewa -
Q. Is a vacuum dewatered slab equal so much water that there will not be
tering equipment?
in wear resistance to a concrete slab enough left in the concrete to hy-
A. Not to our knowledge but dealers treated with a dry shake hardener? drate the cement.
will certainly do so when they get
properly started. A. Se ve ral recent official tests have Q. How long does it take to vacuum
shown that a vacuum dewatered dewater structural lightweight ag -
Q. Has anyone gone into the special - slab which has been properly ma- gregate concrete?
ized contracting business of vacuum chine floated and troweled has a
dewatering as a service to floor con - wear resistance 2 to 3 times that of A. For this type of concrete it is ad-
tractors? ordinary or treated concrete. vantageous to use a slightly lower
vacuum than normal—60 to 70 per-
A. We do not know of any such firms cent of maximum vacuum—and ex-
yet in the United States but it is like- Q. Can vacuum dewatering be used
tend the timing by 30 to 50 percent.
ly there will be such specialists in with lightweight aggregate concrete?
This is to ensure that the top part of
the future. A. Yes, and to great advantage. Since the slab is not dewatered more
the water and fluid phase of the rapidly than deeper portions. Be-
MIX DESIGNS AND TESTING concrete is subject to vacuum, air in cause of the porous nature of the ag-
Q. Can admixtures be used in con - the pores of lightweight aggregate gregate, rapid dewatering of the top
crete to be vacuum dewatered? expands and presses water out of might lead to too dry a surface.
Q. Is there any difference in the han -
dling of test cylinders for vacuum de -
watered concrete? If not, how does
one estimate the actual strength of
the concrete at any given age?
A. As yet there is no proper way to
make vacuum treated test cylinders
correspond exactly to conditions on
the actual slab. The only way to find
out precisely the strength of the
vacuum treated slab is to drill out
test cores. The Schmidt rebound
hammer will give fair readings if
calibrated against the actual con-
crete. Our company is developing a
method to vacuum-treat test cylin-
ders but the equipment needed is
not yet on the market.
Metric equivalents
1. 65 square metres
2. 130 square metres per hour
3. 650 to 780 square metres per day
4. 1 to 1.6 minutes per 10 millimetres
5. 300 millimetres
6. 800 millimetres
7. 150-millimetre
8. 3-millimetre
9. 35 square metres
10. 5 by 7 metres
11. 50 square metres
12. 14 metres
13. 12 metres
14. 9750 kilograms per square metre
15. 7,800 to 8,800 kilograms per square
metre
16. minus 0.300-millimetre
17. 740 square metres per day
18. 150 millimetres
19. 115 cubic metres
20. 24.8 to 34.7 litres per cubic metre
21. 2,840 to 3,975 litres
22. 75 millimetres
23. 50 millimetres

PUBLICATION#C760301
Copyright © 1976, The Aberdeen Group
All rights reserved

Anda mungkin juga menyukai