Anda di halaman 1dari 2

Birla Institute of Technology & Science, Pilani

Work-Integrated Learning Programmes Division


First Semester 2018-2019
Comprehensive Examination
(EC-3 Regular)

Course No. : ET ZC413


Course Title : ENGINEERING DESIGN
Nature of Exam : Open Book
Weightage : 40% No. of Pages =2
Duration : 3 Hours No. of Questions = 8
Date of Exam : 24/11/2018 (FN)
Note:
1. Please follow all the Instructions to Candidates given on the cover page of the answer book.
2. All parts of a question should be answered consecutively. Each answer should start from a fresh page.
3. Assumptions made if any, should be stated clearly at the beginning of your answer.

Q.1. Sketch a simple hand mixer with parts. Develop a function structure for the same.
[2 + 4 = 6]

Q.2. Take a simple metal foldable chair and improve with the help of industrial design [5]

Q.3. Identify the reliabilities of A, B and the overall system for the following combination of
components, In B, minimum 3 components need to work for the subsystem to work. [4]

Q.4. Design a potable water bottle life cycle with the help of life cycle design [5]

Q.5. List any five daily used products and select one critical component in each of those.
Analyze how DFM guidelines can influence the manufacturing of the selected critical
components of those products. Use five different DFM guidelines [5]

Q.6. A firm sells two products. Product G sells for INR20; its variable cost is INR6. Product K
sells for INR50; its variable cost is INR30. Product G accounts for 65 percent of the firm's
sales, while K accounts for 35 percent. The firm's fixed costs are INR300000 annually.
Calculate the firm's break-even point (in quantities and in INR). [5]

ET ZC413 (EC-3 Regular) First Semester 2018-2019 Page 1 of 2


ET ZC413 (EC-3 Regular) First Semester 2018-2019 Page 2

Q.7. A project has the following activities which needs to be completed based on the
precedence relationship given below. a) develop a network diagram, b) Determine critical
path (s) and project completion time, c) Determine slack time for each activity
[2 + 2 + 1 = 5]

Activity Immediate Predecessor Time (days)


A -- 2
B A 8
C A 6
D B 4
E C, D 10
F D 4
G F 4
H E, G 6

Q.8. Ram bought a mixer and while trying to use that blade came off and caused injuries,
analyze this mishap using the concepts of legal and ethical issues and suggest the future
course of action of Ram [5]

********