ANÁLISIS DE PRECIOS UNITARIOS

PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA


PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 1.1 Replanteo de Línea M.T. Hasta 34.5 KV. ML
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 250.00 $10,000.00 40.00
E7 Equipo(s) de topografía Día 250.00 $50,000.00 200.00

SUBTOTAL EQUIPOS/HERRAMIENTAS $240.00


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $240.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.004 $10,000.00 5% $42.00
$0.00
$0.00
$0.00

SUBTOTAL DE MATERIALES $42.00


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $42.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O6 Comisión topoDía 1.00 $180,000.00 0.00% $180,000.00 250.00
O8 Ing. ElectricisDía 1.00 $80,000.00 60.00% $128,000.00 250.00

SUBTOTAL M $1,232.00
VALOR RED $1,232.00
TOTAL COST $1,514.00

ANÁLISIS DE PRECIOS UNITARIOS


PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 1.2 Suministro, transporte e instalación de poste de concreto 12 m * 10 UND
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 2.00 $10,000.00 5,000.00
E11 Grúa Día 2.00 $380,000.00 190,000.00
SUBTOTAL EQUIPOS/HERRAMIENTAS $195,000.00
VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $195,000.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.500 $10,000.00 5% $5,250.00
M158 Postes de conUn 1.000 $1,102,000.00 0% $1,102,000.00
$0.00
$0.00

SUBTOTAL DE MATERIALES $1,107,250.00


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS ###
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL
T1 Carga vía pa TON 1.05 3 $800.00 $2,520.00
T2 Carga vía sin TON 1.05 0.7 $900.00 $661.50

$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O8 Ing. ElectricisDía 0.50 $80,000.00 60.00% $128,000.00 2.00
O7 Maestro ElectrDía 0.50 $55,000.00 60.00% $88,000.00 2.00
O4 Oficial Eléctri Día 1.00 $45,000.00 60.00% $72,000.00 2.00
O3 Ayudante Día 3.00 $28,000.00 60.00% $44,800.00 2.00
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO ###
ANÁLISIS DE PRECIOS UNITARIOS
PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 1.3 Suministro, transporte e instalación de un conductor ACSR No 2/0 A ML
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 300.00 $10,000.00 33.33

SUBTOTAL EQUIPOS/HERRAMIENTAS $33.33


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $33.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.003 $10,000.00 5% $35.00
M179 Conductor ACml 1.000 $2,227.20 0% $2,227.20
0% $0.00
0% $0.00

SUBTOTAL DE MATERIALES $2,262.20


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $2,262.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL
T1 Carga vía pa M3 0.001 3 $800.00 $2.40
T2 Carga vía sin M3 0.001 0.7 $900.00 $0.63

$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O8 Ing. ElectricisDía 0.25 $80,000.00 60.00% $128,000.00 300.00
O7 Maestro ElectrDía 0.50 $55,000.00 60.00% $88,000.00 300.00
O4 Oficial Eléctri Día 1.00 $45,000.00 60.00% $72,000.00 300.00
O3 Ayudante Día 2.00 $28,000.00 60.00% $44,800.00 300.00
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO $3,090.00

ANÁLISIS DE PRECIOS UNITARIOS


PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 1.4 Preparacion concreto 2500 PSI M3
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 1.00 $10,000.00 10,000.00
E1 Mezcladora Día 3.50 $50,000.00 14,285.71
SUBTOTAL EQUIPOS/HERRAMIENTAS $24,285.71
VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $24,286.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M1 Cemento gris Kg 300.000 $480.00 5% $151,200.00
M2 Arena M3 0.480 $28,000.00 5% $14,112.00
M3 Triturado M3 0.950 $60,000.00 5% $59,850.00
M113 Agua Lt 170.000 $90.00 5% $16,065.00

SUBTOTAL DE MATERIALES
VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS
III. TRANSPORTE
No. ART. DESCRIPCIÓN UNID. CANT. KM. PRECIO/KM
T1 Carga vía pavimentada - cemento Ton 0.315 3 $800.00
T2 Carga vía sin pavimentar - cemento Ton 0.315 0.7 $900.00
T1 Carga vía pavimentada - arena M3 0.504 5.4 $800.00
T2 Carga vía sin pavimentar - arena M3 0.504 0.7 $900.00
T1 Carga vía pavimentada - triturado M3 0.9975 50 $800.00
T2 Carga vía sin pavimentar - triturado M3 0.9975 30.7 $900.00
SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O1 Maestro GeneDía 1.00 $55,000.00 60.00% $88,000.00 3.50
O2 Oficial Día 1.00 $45,000.00 60.00% $72,000.00 3.50
O3 Ayudante Día 4.00 $28,000.00 60.00% $44,800.00 3.50
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO $433,337.00
ANÁLISIS DE PRECIOS UNITARIOS
PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 1.5 Suministro, transporte e instalación de una caja corta circuito de 1 UND
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 10.00 $10,000.00 1,000.00

SUBTOTAL EQUIPOS/HERRAMIENTAS $1,000.00


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $1,000.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.100 $10,000.00 5% $1,050.00
M177 caja corta ci Un 1.000 $112,199.84 0% $112,199.84
0% $0.00
0% $0.00

SUBTOTAL DE MATERIALES $113,249.84


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $113,250.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL
T1 Carga vía pa M3 0.15 3 $800.00 $360.00
T2 Carga vía sin M3 0.15 0.7 $900.00 $94.50

$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O8 Ing. ElectricisDía 0.25 $80,000.00 60.00% $128,000.00 10.00
O7 Maestro ElectrDía 0.50 $55,000.00 60.00% $88,000.00 10.00
O4 Oficial Eléctri Día 1.00 $45,000.00 60.00% $72,000.00 10.00
O3 Ayudante Día 2.00 $28,000.00 60.00% $44,800.00 10.00
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO $138,465.00

ANÁLISIS DE PRECIOS UNITARIOS


PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 1.6 Suministro, transporte e instalación de un pararrayo de 10 o 12 KV UND
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 10.00 $10,000.00 1,000.00

SUBTOTAL EQUIPOS/HERRAMIENTAS $1,000.00


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $1,000.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.100 $10,000.00 5% $1,050.00
M178 pararrayo de Un 1.000 $105,199.24 0% $105,199.24
0% $0.00
0% $0.00

SUBTOTAL DE MATERIALES $106,249.24


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $106,249.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL
T1 Carga vía pa M3 0.15 3 $800.00 $360.00
T2 Carga vía sin M3 0.15 0.7 $900.00 $94.50

$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O8 Ing. ElectricisDía 0.25 $80,000.00 60.00% $128,000.00 10.00
O7 Maestro ElectrDía 0.50 $55,000.00 60.00% $88,000.00 10.00
O4 Oficial Eléctri Día 1.00 $45,000.00 60.00% $72,000.00 10.00
O3 Ayudante Día 2.00 $28,000.00 60.00% $44,800.00 10.00
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO $131,464.00
ANÁLISIS DE PRECIOS UNITARIOS
PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 1.7 Certificación RETIE de la obra - Redes GL
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL

SUBTOTAL EQUIPOS/HERRAMIENTAS $0.00


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $0.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M94 Certificación Un 1.000 $5,000,000.00 0% $5,000,000.00
$0.00

SUBTOTAL DE MATERIALES $5,000,000.00


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS ###
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.

SUBTOTAL M $0.00
VALOR RED $0.00
TOTAL COST ###

ANÁLISIS DE PRECIOS UNITARIOS


PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 1.8 Certificación RETIE de la obra - viviendas GL
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL

SUBTOTAL EQUIPOS/HERRAMIENTAS $0.00


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $0.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M95 Certificación Un 1.000 $90,000.00 0% $90,000.00
$0.00

SUBTOTAL DE MATERIALES $90,000.00


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $90,000.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
SUBTOTAL M $0.00
VALOR RED $0.00
TOTAL COST$90,000.00

ANÁLISIS DE PRECIOS UNITARIOS


PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 2.1 Replanteo red de Baja Tensión ML
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 250.00 $10,000.00 40.00
E7 Equipo(s) de topografía Día 250.00 $50,000.00 200.00

SUBTOTAL EQUIPOS/HERRAMIENTAS $240.00


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $240.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.004 $10,000.00 5% $42.00
$0.00
$0.00
$0.00

SUBTOTAL DE MATERIALES $42.00


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $42.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O6 Comisión topoDía 1.00 $180,000.00 0.00% $180,000.00 250.00
O8 Ing. ElectricisDía 1.00 $80,000.00 60.00% $128,000.00 250.00

SUBTOTAL M $1,232.00
VALOR RED $1,232.00
TOTAL COST $1,514.00
ANÁLISIS DE PRECIOS UNITARIOS
PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 2.2 Suministro, transporte e instalación de poste de concreto 8 m * 750 UND
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 3.00 $10,000.00 3,333.33
E11 Grúa Día 3.00 $380,000.00 126,666.67

SUBTOTAL EQUIPOS/HERRAMIENTAS $130,000.00


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $130,000.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.333 $10,000.00 5% $3,500.00
M158-1 Postes de conUn 1.000 $458,200.00 0% $458,200.00
$0.00
$0.00

SUBTOTAL DE MATERIALES $461,700.00


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $461,700.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL
T1 Carga vía pa TON 0.75 3 $800.00 $1,800.00
T2 Carga vía sin TON 0.75 0.7 $900.00 $472.50

$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O8 Ing. ElectricisDía 0.50 $80,000.00 60.00% $128,000.00 3.00
O7 Maestro ElectrDía 0.50 $55,000.00 60.00% $88,000.00 3.00
O4 Oficial Eléctri Día 1.00 $45,000.00 60.00% $72,000.00 3.00
O3 Ayudante Día 3.00 $28,000.00 60.00% $44,800.00 3.00
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO $698,773.00

ANÁLISIS DE PRECIOS UNITARIOS


PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 2.3 Suministro, transporte e instalación de herrajes y elementos para baj
UND
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 10.00 $10,000.00 1,000.00

SUBTOTAL EQUIPOS/HERRAMIENTAS $1,000.00


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $1,000.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.100 $10,000.00 5% $1,050.00
M184 CABLE DE COML 7.000 $9,081.64 5% $66,750.05
M185 CINTA ACEROML 2.000 $3,200.00 5% $6,720.00
M186 VARILLA COBUN 1.000 $98,506.00 0% $98,506.00
M187 HEBILLA PARAUN 3.000 $896.00 0% $2,688.00
M116 CONECTOR UN 2.000 $2,613.00 0% $5,226.00
SUBTOTAL DE MATERIALES $180,940.05
VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $180,940.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL
T1 Carga vía pa M3 0.05 3 $800.00 $120.00
T2 Carga vía sin M3 0.05 0.7 $900.00 $31.50

$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O8 Ing. ElectricisDía 0.25 $80,000.00 60.00% $128,000.00 10.00
O7 Maestro ElectrDía 0.25 $55,000.00 60.00% $88,000.00 10.00
O4 Oficial Eléctri Día 1.00 $45,000.00 60.00% $72,000.00 10.00
O3 Ayudante Día 1.00 $28,000.00 60.00% $44,800.00 10.00
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO $199,172.00
ANÁLISIS DE PRECIOS UNITARIOS
PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 2.4 Preparacion concreto 2500 PSI M3
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 1.00 $10,000.00 10,000.00
E1 Mezcladora Día 3.50 $50,000.00 14,285.71

SUBTOTAL EQUIPOS/HERRAMIENTAS $24,285.71


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $24,286.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M1 Cemento gris Kg 300.000 $480.00 5% $151,200.00
M2 Arena M3 0.480 $28,000.00 5% $14,112.00
M3 Triturado M3 0.950 $60,000.00 5% $59,850.00
0 Agua Lt 170.000 $90.00 5% $16,065.00

SUBTOTAL DE MATERIALES
VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS
III. TRANSPORTE
No. ART. DESCRIPCIÓN UNID. CANT. KM. PRECIO/KM
T1 Carga vía pavimentada - cemento Ton 0.315 3 $800.00
T2 Carga vía sin pavimentar - cemento Ton 0.315 0.7 $900.00
T1 Carga vía pavimentada - arena M3 0.504 5.4 $800.00
T2 Carga vía sin pavimentar - arena M3 0.504 0.7 $900.00
T1 Carga vía pavimentada - triturado M3 0.9975 50 $800.00
T2 Carga vía sin pavimentar - triturado M3 0.9975 30.7 $900.00
SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O1 Maestro GeneDía 1.00 $55,000.00 60.00% $88,000.00 3.50
O2 Oficial Día 1.00 $45,000.00 60.00% $72,000.00 3.50
O3 Ayudante Día 4.00 $28,000.00 60.00% $44,800.00 3.50
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO $433,337.00

ANÁLISIS DE PRECIOS UNITARIOS


PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 2.5 Suministro, transporte e Instalacion de cable trenzado Tripex 600 ML
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 100.00 $10,000.00 100.00

SUBTOTAL EQUIPOS/HERRAMIENTAS $100.00


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $100.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.010 $10,000.00 5% $105.00
M182 Conductor ACml 1.000 $8,584.00 0% $8,584.00
0% $0.00
0% $0.00

SUBTOTAL DE MATERIALES $8,689.00


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $8,689.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL
T1 Carga vía pa M3 0.001 3 $800.00 $2.40
T2 Carga vía sin M3 0.001 0.7 $900.00 $0.63

$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O8 Ing. ElectricisDía 0.25 $80,000.00 60.00% $128,000.00 100.00
O7 Maestro ElectrDía 0.50 $55,000.00 60.00% $88,000.00 100.00
O4 Oficial Eléctri Día 1.00 $45,000.00 60.00% $72,000.00 100.00
O3 Ayudante Día 2.00 $28,000.00 60.00% $44,800.00 100.00
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO $11,168.00
ANÁLISIS DE PRECIOS UNITARIOS
PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
Suministro, transporte e instalación de sistema de contrapeso para mejoramiento de resistividad de puestas a
ÍTEM: 3.1 UND
tierras para transformadores de distribución. (en cable de cobre)
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 5.00 $10,000.00 2,000.00

SUBTOTAL EQUIPOS/HERRAMIENTAS $2,000.00


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $2,000.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.200 $10,000.00 5% $2,100.00
M184 CABLE DE COML 12.000 $9,081.64 5% $114,428.66
M185 CINTA ACEROML 6.000 $3,200.00 5% $20,160.00
M186 VARILLA COBUN 2.000 $98,506.00 0% $197,012.00
M187 HEBILLA PARAUN 6.000 $896.00 0% $5,376.00
M116 CONECTOR UN 4.000 $2,613.00 0% $10,452.00
SUBTOTAL DE MATERIALES $349,528.66
VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $349,529.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL
T1 Carga vía pa M3 0.05 3 $800.00 $120.00
T2 Carga vía sin M3 0.05 0.7 $900.00 $31.50

$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O8 Ing. ElectricisDía 0.25 $80,000.00 60.00% $128,000.00 5.00
O7 Maestro ElectrDía 0.25 $55,000.00 60.00% $88,000.00 5.00
O4 Oficial Eléctri Día 1.00 $45,000.00 60.00% $72,000.00 5.00
O3 Ayudante Día 1.00 $28,000.00 60.00% $44,800.00 5.00
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO $385,841.00

ANÁLISIS DE PRECIOS UNITARIOS


PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 3.2 Suministro trasnporte e intalacion de trasnformador 75 KVA 13200 UND
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 0.20 $10,000.00 50,000.00
SUBTOTAL EQUIPOS/HERRAMIENTAS $50,000.00
VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $50,000.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 2.000 $10,000.00 5% $21,000.00
M165 Transformad.Un 1.000 $7,000,000.00 0% $7,000,000.00
$0.00
$0.00

SUBTOTAL DE MATERIALES $7,021,000.00


VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS ###
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL
T1 Carga vía pa M3 1 3 $800.00 $2,400.00
T2 Carga vía sin M3 1 0.7 $900.00 $630.00

$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O8 Ing. ElectricisDía 1.00 $80,000.00 60.00% $128,000.00 0.50
O7 Maestro ElectrDía 1.00 $55,000.00 60.00% $88,000.00 0.50
O4 Oficial Eléctri Día 1.00 $45,000.00 60.00% $72,000.00 0.50
O3 Ayudante Día 3.00 $28,000.00 60.00% $44,800.00 0.50
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO
ANÁLISIS DE PRECIOS UNITARIOS
PROPONENTE UNIÓN TEMPORAL MIRANDA ASOCIADOS FECHA
PROYECTO: PLAN INTERVENCIÓN SAN PABLO - EL PALMAR I Oct-15
CAPITULO: PRESUPUESTO GENERAL REDES ELÉCTRICAS UNIDAD
ÍTEM: 4.1 Suministro, transporte e instalación de Luminarias de sodio 70 w y UND
I. EQUIPOS/HERRAMIENTAS
No. ART. DESCRIPCIÓUNID. REND. VR. UNIT. VR. PARCIAL
H1 Herramienta menor Gl 6.00 $10,000.00 1,666.67

SUBTOTAL EQUIPOS/HERRAMIENTAS $1,666.67


VALOR REDONDEADO SUBTOTAL DE EQUIPOS/HERRAMIENTAS $1,667.00
II. MATERIALES E INSUMOS
No. ART. DESCRIPCIÓUNID. CANT. VR. UNIT. DESPERDICIO % VR. PARCIAL
M11 Accesorios (vaGl 0.167 $10,000.00 5% $1,750.00
M172 LAMPARA CON
UN 1.000 $187,399.16 0% $187,399.16
M173 FOTOCELDA UN 1.000 $35,000.00 0% $35,000.00
M174 BRAZO METÁLUN 1.000 $25,000.00 0% $25,000.00
M175 BOMBILLA DEUN 1.000 $25,000.00 0% $25,000.00
M176 COLLARÍN DEUN 2.000 $12,000.00 0% $24,000.00
SUBTOTAL DE MATERIALES $298,149.16
VALOR REDONDEADO SUBTOTAL DE MATERIALES E INSUMOS $298,149.00
III. TRANSPORTE
No. ART. DESCRIPCIÓUNID. CANT. KM. PRECIO/KM VR. PARCIAL
T1 Carga vía pa M3 0.05 3 $800.00 $120.00
T2 Carga vía sin M3 0.05 0.7 $900.00 $31.50

$0.00
$0.00
$0.00
$0.00

SUBTOTAL TRANSPORTE
VALOR REDONDEADO SUBTOTAL TRANSPORTE
IV. MANO DE OBRA
No. ART. DESCRIPCIÓUNID. CANT. JORNAL %. PREST. P.UNIT RDTO.
O8 Ing. ElectricisDía 0.25 $80,000.00 60.00% $128,000.00 6.00
O7 Maestro ElectrDía 0.50 $55,000.00 60.00% $88,000.00 6.00
O4 Oficial Eléctri Día 1.00 $45,000.00 60.00% $72,000.00 6.00
O3 Ayudante Día 2.00 $28,000.00 60.00% $44,800.00 6.00
SUBTOTAL MANO DE OBRA
VALOR REDONDEADO SUBTOTAL DE MANO DE OBRA
TOTAL COSTO DIRECTO $339,568.00
$0.00
$0.00

VR. PARCIAL
$720.00
$512.00
$3,181.50
$3,182.00

VR. PARCIAL
$32,000.00
$22,000.00
$36,000.00
$67,200.00
$157,200.00
$157,200.00
$3.03
$3.00

VR. PARCIAL
$106.67
$146.67
$240.00
$298.67
$792.00
$792.00
$241,227.00
$241,227.00

VR. PARCIAL
$756.00
$198.45
$2,177.28
$317.52
$39,900.00
$27,560.93
$70,910.18
$70,910.00

VR. PARCIAL
$25,142.86
$20,571.43
$51,200.00
$96,914.29
$96,914.00
$454.50
$455.00

VR. PARCIAL
$3,200.00
$4,400.00
$7,200.00
$8,960.00
$23,760.00
$23,760.00
$454.50
$455.00

VR. PARCIAL
$3,200.00
$4,400.00
$7,200.00
$8,960.00
$23,760.00
$23,760.00
$0.00
$0.00

VR. PARCIAL

$0.00
$0.00

VR. PARCIAL
$0.00
$0.00

VR. PARCIAL
$720.00
$512.00
$2,272.50
$2,273.00

VR. PARCIAL
$21,333.33
$14,666.67
$24,000.00
$44,800.00
$104,800.00
$104,800.00
$151.50
$152.00

VR. PARCIAL
$3,200.00
$2,200.00
$7,200.00
$4,480.00
$17,080.00
$17,080.00
$241,227.00
$241,227.00

VR. PARCIAL
$756.00
$198.45
$2,177.28
$317.52
$39,900.00
$27,560.93
$70,910.18
$70,910.00

VR. PARCIAL
$25,142.86
$20,571.43
$51,200.00
$96,914.29
$96,914.00
$3.03
$3.00

VR. PARCIAL
$320.00
$440.00
$720.00
$896.00
$2,376.00
$2,376.00
e resistividad de puestas a

$151.50
$152.00

VR. PARCIAL
$6,400.00
$4,400.00
$14,400.00
$8,960.00
$34,160.00
$34,160.00
$3,030.00
$3,030.00

VR. PARCIAL
$256,000.00
$176,000.00
$144,000.00
$268,800.00
$844,800.00
$844,800.00
###
$151.50
$152.00

VR. PARCIAL
$5,333.33
$7,333.33
$12,000.00
$14,933.33
$39,600.00
$39,600.00