BRIDGE AT CH : 122+420

Typical Calculations of Voulme of RCC Girder - 20m c/c span

TYPICAL SECTION

AT END AT MID SPAN

Area at End Section = 0.855 Sqm


Area at Mid Span = 0.484 Sqm

Total Length of Girder form Expansion joint to Expansion Joint = 15.00 m


Length of End Section = 1.40 m
Length of Varying Section = 1.80 m
Length of Mid Section = 11.80 m
Length C/s Area
Area of End Section = 1.40 X 0.855 = 1.197 Cum
Area of Varying Section = 1.80 X 0.670 = 1.205 Cum
Area of Mid Section = 11.80 X 0.484 = 5.710 Cum
Total volume of Each Girder = 8.112 Cum

Length of Girder Width Avg. Thickness


Total volume of Deck slab = 15.000 X 16.000 X 0.240 = 60.480 Cum

Total volume of Each Diaphgram =


Length of Diaphgram Width Avg. Thickness
9.000 X 0.300 X 1.000 = 2.835 Cum

Total Concrete and Steel for One Span :

Concrete Quantity No's qty/no Total qty.


in RC Deck Slab - 1 60.48 60.48
in RC Girder - 6 8.11 48.67
in Diaphgram - 3 2.84 8.51
117.66 Cum / Span

Steel Quantity kg / cum Total steel


in RC Deck Slab - 105.00 6350.40
in RC Girder - 325.00 15819.08
in Diaphgram - 325.00 2764.13
24933.61 Kgs / Span
24.93 T / Span

FOR WIDENED PORTION

Length of Girder Width Avg. Thickness


Total volume of Deck slab = 4.000 X 12.000 X 0.240 = 12.096 Cum

Total volume of Each Diaphgram =


Length of Diaphgram Width Avg. Thickness
4.000 X 0.300 X 1.000 = 1.260 Cum

Total Concrete and Steel for One Span :

Concrete Quantity No's qty/no Total qty.


in RC Deck Slab - 1 12.10 12.10
in RC Girder - 2 8.11 16.22
in Diaphgram - 3 1.26 3.78
32.10 Cum / Span

Steel Quantity kg / cum Total steel


in RC Deck Slab - 105.00 1270.08
in RC Girder - 325.00 5273.03
in Diaphgram - 325.00 1228.50
7771.61 Kgs / Span
7.77 T / Span

CALCULATION DETAILS FOR ABUTMENT (FOR NEW CONSTRUCTION)

B9 B6 B5

600

D1
600
B2

B9 B6 B5

H
h
600

D1

D2
600 600
B2 B1 B3 B4
B

H
h
B9 B1 B3 B4

B7

B8
2
300

D
B6

B1 B3 B4
B

B9 B1 B3 B4
B7

B8

B6

Len of abut : 19500 mm Skew of 0 deg 1.0000


Total Depth of Abutment (H) : 12000 mm B/H Ratio 0.57
B 6800 mm
B1 4500 mm Nos L B D Area Volume
B2 900 mm Dirtwall 1 0.30 2.04 0.75 0.135
B3 1100 mm Abut cap 1 1.10 0.60 0.66
B4 1200 mm Stem 1 1.00 8.26 8.26
B5 300 mm Minolithic return 2 4.6 0.5 11.30 51.98
B6 500 mm End Counterfort 2 1.9 0.5 11.70 22.23
B7 500 mm Flywingwall 2 4.00 0.5 1.63 6.53
B8 3500 mm 9.67 80.74
B9 4000 mm
D1 2040 mm Foundation 1 6.80 0.70 4.76
D2 1100 mm 4.76
Conc Steel
Total Quantity for One Abutment (Substr): 269.25 24.23 @ 90 kgs / cum
Total Quantity for One Abutment (Footing): 92.82 8.35 @ 90 kgs / cum

FOR WIDENING

Len of abut : 4000 mm Skew of 0 deg 1.0000


Total Depth of Abutment (H) : 9000 mm B/H Ratio 0.76
B 6800 mm
B1 4500 mm Nos L B D Area Volume
B2 900 mm Dirtwall 1 0.30 2.04 0.75 0.135
B3 1100 mm Abut cap 1 1.10 0.60 0.66
B4 1200 mm Stem 1 1.00 5.26 5.26
B5 300 mm Minolithic return 2 4.6 0.5 8.30 38.18
B6 500 mm End Counterfort 2 1.9 0.5 8.70 16.53
B7 500 mm Flywingwall 2 4.00 0.5 1.63 6.53
B8 3500 mm 6.67 61.24
B9 4000 mm
D1 2040 mm Foundation 1 6.80 0.70 4.76
D2 1100 mm 4.76
Conc Steel
Total Quantity for One Abutment (Substr): 87.91 7.91 @ 90 kgs / cum
Total Quantity for One Abutment (Footing): 19.04 1.71 @ 90 kgs / cum

CALCULATION DETAILS FOR PIER :

Overall Height of Substructure H = 9960 mm


Width of Pier in the Trans Dirn. B4 = 7000 mm L B D steel
Width of Pier in the Long Dirn. B1 = 900 mm Pier Wall : 7.00 0.90 7.96 50.15 5.01 @ 100 kgs / cum
Pier Cap Width in Long Dirn. B5 = 1600 mm Pier ft (st): 11.00 4.80 0.50 26.40
Pier Cap Length in Trans Dirn. B6 = 14500 mm Pier ft (Vary): 11.00 2.85 0.50 15.68
Straight Depth of Pier Cap D1 = 500 mm Pier Footing : 42.08 3.79 @ 90 kgs / cum
Varying Depth of Pier Cap D2 = 500 mm Pier Cap(st): 14.50 1.60 0.50 11.60
Length of Footing B3 = 11000 mm Pier Cap (Vary): 10.75 1.60 0.50 8.60
Width of Footing B2 = 4800 mm Pier Cap : 20.20 2.42 @ 120 kgs / cum
Total Depth of Footing D3 = 1000 mm

B5 B6
D 2D 1

D 2D 1

100
B5 B6

D 2D 1

D 2D 1
100

H
B1 B4

100 100

500

D3
B2 B3

CALCULATION DETAILS FOR PIER (FOR WIDENED PORTION) :

Overall Height of Substructure H = 9960 mm


Width of Pier in the Trans Dirn. B4 = 3500 mm Conc steel
Width of Pier in the Long Dirn. B1 = 800 mm Pier : 23.97 2.40 @ 100 kgs / cum
Pier Cap Width in Long Dirn. B5 = 1000 mm Pier footing : 15.12 1.36 @ 90 kgs / cum
Pier Cap Length in Trans Dirn. B6 = 4000 mm Pier Cap : 2.40 0.24 @ 100 kgs / cum
Straight Depth of Pier Cap D1 = 600 mm
Varying Depth of Pier Cap D2 = 0 mm
Length of Footing B3 = 4500 mm
Width of Footing B2 = 4200 mm
Straight Depth of Footing D3 = 800 mm
Varying Depth of Footing D4 = 0 mm

B5 B6
D1

D1

B1 B4
D3

B2 B3
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)

Clearing and grubbing at site which


includes cleaning and removal of
vegetation growth from structures,
1.01 ha. 1 160.00 26.00 0.42
channel and protective works as per
direction of Engineer as per Tech.Spec. Cl.
201

Dismantle existing cross drainage


structure Including disposal of resulting
1.02 Cu.m.
material and salvage reusable materials
complete as per Tech.Spec.Cl. 202
a) Brick / Stone/RCC structure 0.00
RCC Abutment 0 7.50 5.50 1.20 0.00
RCC Pier 0 7.50 5.50 1.20 0.00
Returnwall 0 11.14 5.50 0.60 0.00
Returnwall (in between spans) 0 7.00 1.70 4.00 0.00
Parapet 0 129.80 0.60 0.60 0.00

b) PCC in Substructure Cu.m. 0.00


Abutment 0 7.80 5.80 0.15 0.00
Pier 0 7.80 5.80 0.15 0.00
Returnwall 0 11.44 5.80 0.15 0.00
Arch 0 7.50 12.00 0.70 0.00
Parapet 0 125.80 0.60 0.60 0.00

c) RCC in Superstructure Cu.m. 0.00


Girders 0 8.20 7.70 1.10 0.00
Slab 0 7.50 7.40 0.80 0.00
Approach slab 0 7.50 3.50 0.30 0.00
Railings 0 63.14 0.50 1.20 0.00

d) Stone Slabs in super structure Sq.m 0 7.50 2.00 0.00


e) Steel I beams MT 0 7.00 0.04 0.50 0.00
f) HP ( > 300 dia) m 0 10.00 0.00
g) Wearing coat sqm 0 63.14 6.50 0.00

Earthwork in excavation of foundation for


structures in all types of soil including
1.03 Cu.m. 3592.81
lead and lifts complete as per Tech. Spec.
Cl. 304
a) ordinary soil
Abutment AL 1 16.60 9.60 3.15 501.98
Abutment AR 1 16.60 9.60 3.65 581.66
Pier - 1 1 13.10 7.80 3.65 372.96
Pier - 2 1 13.10 7.80 3.00 306.54
Pier - 3 1 13.10 7.80 3.65 372.96
Pier - 4 1 13.10 7.80 3.15 321.87
Pier - 5 1 13.10 7.80 1.50 153.27
Pier - 6 1 13.10 7.80 2.50 255.45
Pier - 7 0 13.10 7.80 3.65 0.00
Independent Returnwall on AL side 2 10.60 5.05 2.65 283.96

4
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
Independent Returnwall on AR side 2 10.60 3.84 3.15 256.19
Toe wall on side slopes AL 2 15.45 2.10 1.65 107.05
AR 2 11.39 2.10 1.65 78.92

b) in soft/weathered rock 301.43


AL 1 16.60 9.60 0.00 0.00
AR 1 16.60 9.60 0.00 0.00
Pier - 1 1 13.10 7.80 0.00 0.00
Pier - 2 1 13.10 7.80 0.65 66.42
Pier - 3 1 13.10 7.80 0.00 0.00
Pier - 4 1 13.10 7.80 0.00 0.00
Pier - 5 1 13.10 7.80 1.65 168.60
Pier - 6 1 13.10 7.80 0.65 66.42
Pier - 7 0 13.10 7.80 0.00 0.00
Independent Returnwall on AL side 2 10.60 5.05 0.00 0.00
Independent Returnwall on AR side 2 10.60 3.84 0.00 0.00

c) in Hard Rock 0.00


Abutment - A1 1 16.60 9.60 0.00 0.00
Abutment - A2 1 16.60 9.60 0.00 0.00
Pier - 1 1 13.10 7.80 0.00 0.00
Pier - 2 1 13.10 7.80 0.00 0.00
Pier - 3 1 13.10 7.80 0.00 0.00
Pier - 4 1 13.10 7.80 0.00 0.00
Pier - 5 1 13.10 7.80 0.00 0.00
Pier - 6 1 13.10 7.80 0.00 0.00
Pier - 7 0 13.10 7.80 0.00 0.00
Back filling behind abutments, wing walls,
return walls and foundation trenches with
selected granular material of approved
1.04 Cu.m. 2343.64
quality complete with all leads as per
Tech. Spec. Cl.710.1.4 of IRC:78and lifts
complete
Abutment - AL 1 16.60 0.60 1.20 11.95
Abutment - AR 1 16.60 0.60 1.20 11.95
Pier - 1 1 13.10 0.60 1.20 9.43
Pier - 2 1 13.10 0.60 1.20 9.43
Pier - 3 1 13.10 0.60 1.20 9.43
Pier - 4 1 13.10 0.60 1.20 9.43
Pier - 5 1 13.10 0.60 1.20 9.43
Pier - 6 1 13.10 0.60 1.20 9.43
Pier - 7 0 13.10 0.60 1.20 0.00
Independent Returnwall on AL side 2 10.60 0.60 0.80 10.18
Independent Returnwall on AR side 2 10.60 0.60 0.80 10.18
Abutment - AL 1 16.60 8.10 1.95 262.20
Abutment - AR 1 16.60 8.10 2.45 329.43
Pier - 1 1 13.10 6.60 2.45 211.83
Pier - 2 1 13.10 6.60 2.45 211.83
Pier - 3 1 13.10 6.60 2.45 211.83
Pier - 4 1 13.10 6.60 1.95 168.60
Pier - 5 1 13.10 6.60 1.95 168.60
Pier - 6 1 13.10 6.60 1.95 168.60
Pier - 7 0 13.10 6.60 2.45 0.00

5
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
Pier - 1 1 2.00 1.20 2.45 5.88
Pier - 2 1 2.00 1.20 2.45 5.88
Pier - 3 1 2.00 1.20 2.45 5.88
Pier - 4 1 2.00 1.20 1.95 4.68
Pier - 5 1 2.00 1.20 1.95 4.68
Pier - 6 1 2.00 1.20 1.95 4.68
Pier - 7 0 2.00 1.20 2.45 0.00
Independent Returnwall on AL side 2 10.60 4.45 1.85 174.70
Independent Returnwall on AR side 2 10.60 4.45 1.85 174.70
Toe wall AL 2 15.45 0.60 0.30 5.56
2 15.45 1.85 1.20 68.59
AR side 2 11.39 0.60 0.30 4.10
2 11.39 1.85 1.20 50.56

Cement Concrete/Reinforced Cement


Concrete in open foundation / leveling
1.05 course including centering and shuttering Cu.m.
but excluding reinforcement all complete
as per Tech. Spec.Cl. 1500, 1700 & 2100

a) M15 Grade - Levelling Course 171.66

Abutment - AL 1 16.30 9.30 0.15 22.74


Abutment - AR 1 16.30 9.30 0.15 22.74
Pier - 1 1 12.80 7.50 0.15 14.40
Pier - 2 1 12.80 7.50 0.15 14.40
Pier - 3 1 12.80 7.50 0.15 14.40
Pier - 4 1 12.80 7.50 0.15 14.40
Pier - 5 1 12.80 7.50 0.15 14.40
Pier - 6 1 12.80 7.50 0.15 14.40
Pier - 7 0 12.80 7.50 0.15 0.00
Independent Returnwall on A1 side 2 10.30 4.75 0.15 14.69
Independent Returnwall on A2 side 2 10.30 3.54 0.15 10.93
Toe wall 2 15.15 1.80 0.15 8.18
2 11.09 1.80 0.15 5.99

c) M15 Grade - Below Approach Slab


Below Approach slab 2 16.00 3.65 0.15 17.52

Cement concrete grade M20 in sub-


1.06 structures and Foundation as per Tech. 46.14
Spec. Cl. 1700.
Toe wall
AL
Base Slab 2 14.85 1.50 0.30 13.36
Stem wall 2 14.85 0.25 1.80 13.36
AR
Base Slab 2 10.79 1.50 0.30 9.71
Stem wall 2 10.79 0.25 1.80 9.71

Cement concrete grade M30 in sub-


1.07 structures and Foundation as per Tech. Cu.m. 33.60
Spec. Cl. 1700.

6
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
Approach Slab
2 16.00 3.50 0.30 33.60

Cement concrete grade M35 in


1.08 Cu.m. 1116.65
Foundations as per Tech. Spec. Cl. 1700.
Independent Returnwall on AL side (Foundation) 2 10.00 4.45 0.80 71.27
Independent Returnwall on AR side (Foundation) 2 10.00 3.24 0.80 51.78
Abutment base - AL 1 16.00 9.00 1.20 172.80
Abutment base - AR 1 16.00 9.00 1.20 172.80
P1 Foundation 1 12.50 7.20 1.20 108.00
P2 Foundation 1 12.50 7.20 1.20 108.00
P3 Foundation 1 12.50 7.20 1.20 108.00
P4 Foundation 1 12.50 7.20 1.20 108.00
P5 Foundation 1 12.50 7.20 1.20 108.00
P6 Foundation 1 12.50 7.20 1.20 108.00
P7 Foundation 0 12.50 7.20 1.20 0.00

Cement concrete grade M35 in sub-


1.09 Cu.m. 1015.08
structures as per Tech. Spec. Cl. 1700.
Return wall
Independent Returnwall on AL side wall 2 10.00 0.50 6.12 61.24
2 10.00 0.20 6.12 12.25
Independent Returnwall on AR side 2 10.00 0.50 4.09 40.94
2 10.00 0.20 4.09 8.19
Abutments
Abutment - AL (Shaft) 1 16.00 0.80 3.86 49.40
1 16.00 0.70 3.86 21.61
Monolithic Return Wall AL 2 5.00 0.80 3.86 30.87
Abutment Cap AL 1 16.00 0.80 0.60 7.68
Triangle portion 2 16.00 0.45 0.60 4.32
1 16.00 1.70 0.90 24.48
Dirt wall 1 16.00 0.30 2.30 11.04
Projection 1 16.00 0.30 0.30 1.44
Triangle portion 1 16.00 0.30 0.30 0.72
Abutment - AR (Shaft) 1 16.00 0.80 2.33 29.81
1 16.00 0.70 2.33 13.04
Monolithic Return Wall AR 2 5.00 0.80 2.33 18.63
Abutment Cap AR 1 16.00 0.80 0.60 7.68
Triangle portion 2 16.00 0.45 0.60 4.32
1 16.00 1.70 0.90 24.48
Dirt wall 1 16.00 0.30 2.30 11.04
Projection 1 16.00 0.30 0.30 1.44
Triangle portion 1 16.00 0.30 0.30 0.72
Piers
Pier-1
1 10.50 1.20 5.18 65.23
Top cap 1 10.50 2.80 0.50 14.70
1 14.50 2.80 0.70 28.42
1 4.00 2.80 0.50 2.80
Pier-2
1 10.50 1.20 4.99 62.87
Top cap 1 10.50 2.80 0.50 14.70
1 14.50 2.80 0.70 28.42

7
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
1 4.00 2.80 0.50 1.12
Pier-3
1 10.50 1.20 4.93 62.14
Top cap 1 10.50 2.80 0.50 14.70
1 14.50 2.80 0.70 28.42
1 4.00 2.80 0.50 5.60
Pier-4
1 10.50 1.20 4.52 56.89
Top cap 1 10.50 2.80 0.50 14.70
1 14.50 2.80 0.70 28.42
1 4.00 2.80 0.50 2.80
Pier-5
1 10.50 1.20 4.23 53.32
Top cap 1 10.50 2.80 0.50 14.70
1 14.50 2.80 0.70 28.42
1 4.00 2.80 0.50 2.80
Pier-6
1 10.50 1.20 4.18 52.64
Top cap 1 10.50 2.80 0.50 14.70
1 14.50 2.80 0.70 28.42
1 4.00 2.80 0.50 2.80
Pier-7
0 10.50 1.20 -3.57 0.00
Top cap 0 10.50 2.80 0.50 0.00
0 14.50 2.80 0.70 0.00
0 4.00 2.80 0.50 0.00

Cement concrete grade M40 in super


1.10 Cu.m. 1431.88
structures as per Tech. Spec. Cl. 1700.
Pedestrals
98 0.80 0.80 0.25 15.68

Diaphgram 14 16.00 0.40 1.30 116.48


RC Deck slab 7 16.00 20.00 0.20 448.00

b) in RC Girder
End Block 49 4.00 Area = 1.08 211.68
Tapering 49 2.40 Area = 0.94 110.25
Mid Section 49 13.60 Area = 0.80 529.79

Providing, cutting, bending and fixing in


position of TMT bar reinforcement in
1.11 T 539.50
reinforced cement concrete structures
complete as per Tech. Spec. Cl 1600
Toe wall 1 wt = 3.23 3.23
Abutment & Dirt wall 1 wt = 39.41 39.41
Piers 1 wt = 94.46 94.46
Return Wall 1 wt = 11.04 11.04
RC Girder 1 wt = 170.34 170.34
RC slab 1 wt = 67.20 67.20
pedestals 1 wt = 2.35 2.35
Diapharam 1 wt = 17.47 17.47

8
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
Foundations 1 wt = 134.00 134.00
Filter media with stone crushed
aggregates abutments/return walls as per
1.12 Cu.m. 137.33
clause 2504.2.2 and Tech. Spec.
Cl.710.1.4 of IRC:78
Behind Abutment - AL 1 16.00 0.60 4.06 38.97
Behind Abutment - AR 1 16.00 0.60 1.53 14.68
Independent Returnwall on AL side 2 10.00 0.60 4.06 48.71
Independent Returnwall on AR side 2 10.00 0.60 1.53 18.35
below pitching 4 55.42 0.15 16.63

Providing weep holes in abutments,


returnwalls, with 100mm dia AC pipes
1.13 no's 203.00
complete as per drawing and Tech. Spec.
Cl. 2706
Abutment - A1 1 16.00 4.06 1.00 65.00
Abutment - A2 1 16.00 1.53 1.00 25.00
Independent Returnwall on A1 side 2 10.00 4.06 1.00 82.00
Independent Returnwall on A2 side 2 10.00 1.53 1.00 31.00

1.14 Providing and fixing Expansion joint


Bitumin Plug joint Rmtr 2 16.00 32.00
strip expansion joint Rmtr 8 16.00 128.00

Providing and fixing Tar paper bearing


1.15 complete as per drawing and IRC:SP:13- 9.60
1973.
in Approach slab Sq.m 2 16.00 0.30 9.60

Supply, fitting and fixing in position true


1.16 to line and level POT-PTFE Bearings 98
complete as per Tech. Spec. Cl. 2000

Pot-PTFE Bearing - 200 MT No's 7 7


Guided Pot-PTFE Bearing - 200 MT No's 84 84
Free Pot-PTFE Bearing - 200 MT No's 7 7

Fixed Pot Bearing - 250 MT No's 0 0


Guided Pot-PTFE Bearing - 250 MT No's 0 0
Free Pot-PTFE Bearing - 250 MT No's 0 0

Fixed Pot Bearing - 300 MT No's 0 0


Guided Pot-PTFE Bearing - 300 MT No's 0 0
Free Pot-PTFE Bearing - 300 MT No's 0 0

Fixed Pot Bearing - 350 MT No's 0 0


Guided Pot-PTFE Bearing - 350 MT No's 0 0
Free Pot-PTFE Bearing - 350 MT No's 0 0

Proving and fixing Drainage spouts


1.17 Each 58 58.00
complete as per Tech. Spec. Cl. 2705

9
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)

Providing and filling joint sealing


compound as per drawings with coarse
sand and 6 percent bitumen by weight
1.18 (0.083 kg/m bitumen) including cost and Rmtr 8 16.00 128.00
conveyance of all materials, labour, fixing
in position, etc., complete as per drawing
and Tech. Spec. Cl

Providing and laying wearing course on


top of deck complete as per
1.19 Sq.m 1 147.00 11.00 1617.00
Tech.Spec.Cl.515 & 2702 65mm Thick
(40BC+ 25 Asphaltic)

Construction of Crash Barrier M40 grade


1.20 incl. cost of all materials, labour, lead, Rmtr 298.00
lifts, loading, unloading etc., complete

Inner 0 149.00 0.00


Outer 2 149.00 298.00

1.21 PVC Utility pipes (150 dia) Rmtr 2 149.00 298.00

Providing and applying 2 coats of Enamel


paint to plastered concrete surface
1.22 Sq.m 1 298.00 2.30 685.40
complete as per Tech.Spec Cl. 800 for RC
Crash barrier

Painting details of Structure and span


1.23 No's 4 4.00
arrangements as Tech.Spec.Cl. 800

Provide and lay stone pitching as per


1.24 Cu.m. 66.51
Tech. Spec. Cl. 2504.
for quandrantal pitching 4 Area= 55.42 0.30 66.51

1.25 metallic crash barrier m15 garde Cum 40.00

2 10.00 20.00
2 10.00 20.00

1.26 Railing Rmtr


2 149.00 298.00

Providing and painting of flood gauge


on substructure in full height and 500
1.27 Nos 2.00
mm width as per IRC: 67-2001 and
the directions of the Engineer.

2.00 2.00

10
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
Painting of concrete hand rails/
parapets/ crash barriers with two coats
1.28 of enamel paint as per Technical Sq.m 804.60
Specification and the directions of the
Engineer

1.00 298.00 2.70 804.60


Paininting of sub structures & super
structures with two coats of enamel
1.29 Sq.m 7525.31
paint as per Technical Specification
and the directions of the Engineer

Pedstrals 2.00 32.90 0.60 39.48


Girders
End section 49.00 4.00 4.14 811.44
Mid section 49.00 13.60 4.60 3065.44
Trapered section 49.00 2.40 4.37 513.91
Slab 1.00 140.00 16.40 2296.00
Pier shaft
Pier-1 1.00 23.40 3.00 70.20
Pier-2 1.00 23.40 3.00 70.20
Pier-3 1.00 23.40 3.00 70.20
Pier-4 1.00 23.40 3.00 70.20
Pier-5 1.00 23.40 3.00 70.20
Pier-6 1.00 23.40 3.00 70.20

Abutment shaft
AL 1.00 19.00 1.00 19.00
AR 1.00 19.00 1.00 19.00
Pier Cap
Pier 6.00 34.60 0.70 145.32
6.00 26.60 0.50 79.80
12.00 9.60 0.50 57.60
Abutment cap
2.00 19.40 0.90 34.92
2.00 18.50 0.60 22.20

11
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)

Clearing and grubbing at site which


includes cleaning and removal of
vegetation growth from structures,
1.01 ha. 1 65.00 26.00 0.17
channel and protective works as per
direction of Engineer as per Tech.Spec.
Cl. 201

Dismantle existing cross drainage


structure Including disposal of resulting
1.02 Cu.m.
material and salvage reusable materials
complete as per Tech.Spec.Cl. 202

a) Brick / Stone/RCC structure 241.41


RCC Abutment 2 8.00 3.00 1.20 57.60
RCC Pier 3 8.00 3.00 1.20 86.40
Returnwall 4 11.01 3.00 0.60 79.26
Returnwall (in between spans) 0 7.00 1.70 4.00 0.00
Parapet 2 25.20 0.60 0.60 18.14

b) PCC in Substructure Cu.m. 58.20


Abutment 2 8.30 3.30 0.15 8.22
Pier 3 8.30 3.30 0.15 12.33
Returnwall 4 11.31 3.30 0.15 22.39
Arch 0 7.50 12.00 0.70 0.00
Parapet 2 21.20 0.60 0.60 15.26

c) RCC in Superstructure Cu.m. 152.48


Girders 0 8.20 7.70 1.10 0.00
Slab 4 8.00 5.30 0.80 135.68
Approach slab 2 8.00 3.50 0.30 16.80
Railings 0 63.14 0.50 1.20 0.00

d) Stone Slabs in super structure Sq.m 0 7.50 2.00 0.00


e) Steel I beams MT 0 7.00 0.04 0.50 0.00
f) HP ( > 300 dia) m 0 10.00 0.00
g) Wearing coat sqm 1 63.14 7.00 441.98

Earthwork in excavation of foundation for


structures in all types of soil including
1.03 Cu.m. 2203.45
lead and lifts complete as per Tech. Spec.
Cl. 304
a) ordinary soil
Abutment AL 1 16.60 8.10 3.15 423.55
Abutment AR 1 16.60 8.10 3.15 423.55
Pier - 1 1 13.10 7.20 3.15 297.11
Pier - 2 1 13.10 7.20 3.15 297.11
Pier - 3 0 13.10 7.20 0.00 0.00
Independent Returnwall on AL side 2 10.60 5.00 2.65 281.09
Independent Returnwall on AR side 2 10.60 4.85 2.65 272.73
Toe wall on side slopes AL 2 15.28 2.10 1.65 105.88
AR Side 2 14.78 2.10 1.65 102.44

b) in soft/weathered rock 0.00

12
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
AL 1 16.60 8.10 0.00 0.00
AR 1 16.60 8.10 0.00 0.00
Pier - 1 1 13.10 7.20 0.00 0.00
Pier - 2 1 13.10 7.20 0.00 0.00
Pier - 3 0 13.10 7.20 0.00 0.00
Independent Returnwall on AL side 2 10.60 5.00 0.00 0.00
Independent Returnwall on AR side 2 10.60 4.85 0.00 0.00

c) in Hard Rock 0.00


Abutment - A1 1 16.60 8.10 0.00 0.00
Abutment - A2 1 16.60 8.10 0.00 0.00
Pier - 1 1 13.10 7.20 0.00 0.00
Pier - 2 1 13.10 7.20 0.00 0.00
Pier - 3 0 13.10 7.20 0.00 0.00

Back filling behind abutments, wing


walls, return walls and foundation
trenches with selected granular material
1.04 Cu.m. 1354.22
of approved quality complete with all
leads as per Tech. Spec. Cl.710.1.4 of
IRC:78and lifts complete
Abutment - AL 1 16.60 0.60 1.20 11.95
Abutment - AR 1 16.60 0.60 1.20 11.95
Pier - 1 1 13.10 0.60 1.00 7.86
Pier - 2 1 13.10 0.60 1.00 7.86
Pier - 3 0 13.10 0.60 1.00 0.00
Independent Returnwall on AL side 2 10.60 0.60 0.80 10.18
Independent Returnwall on AR side 2 10.60 0.60 0.80 10.18
Abutment - AL 1 16.60 6.90 1.95 223.35
Abutment - AR 1 16.60 6.90 1.95 223.35
Pier - 1 1 13.10 6.20 2.15 174.62
Pier - 2 1 13.10 6.20 2.15 174.62
Pier - 3 0 13.10 6.20 -1.00 0.00
Pier - 1 1 2.00 1.00 2.15 4.30
Pier - 2 1 2.00 1.00 2.15 4.30
Pier - 3 0 2.00 1.00 -1.00 0.00
Independent Returnwall on AL side 2 10.60 4.40 1.85 172.70
Independent Returnwall on AR side 2 10.60 4.40 1.85 172.70
Toe wall AL side 2 15.28 0.60 0.30 5.50
2 15.28 1.85 1.20 67.83
AR side 2 14.78 0.60 0.30 5.32
2 14.78 1.85 1.20 65.63

Cement Concrete/Reinforced Cement


Concrete in open foundation / leveling
1.05 course including centering and shuttering Cu.m.
but excluding reinforcement all complete
as per Tech. Spec.Cl. 1500, 1700 & 2100

a) M15 Grade - Levelling Course 109.15

Abutment - AL 1 16.30 7.80 0.15 19.07


Abutment - AR 1 16.30 7.80 0.15 19.07
Pier - 1 1 12.80 6.90 0.15 13.25

13
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
Pier - 2 1 12.80 6.90 0.15 13.25
Pier - 3 0 12.80 6.90 0.15 0.00
Independent Returnwall on A1 side 2 10.30 4.70 0.15 14.53
Independent Returnwall on A2 side 2 10.30 4.55 0.15 14.07
Toe wall 2 14.98 1.80 0.15 8.09
2 14.48 1.80 0.15 7.82

c) M15 Grade - Below Approach Slab


Below Approach slab 2 16.00 3.65 0.15 17.52

Cement concrete grade M20 in sub-


1.06 structures and Foundation as per Tech. 52.49
Spec. Cl. 1700.
Toe wall
AL
Base Slab 2 14.68 1.50 0.30 13.21
Stem wall 2 14.68 0.25 1.80 13.21
AR
Base Slab 2 14.48 1.50 0.30 13.03
Stem wall 2 14.48 0.25 1.80 13.03

Cement concrete grade M30 in sub-


1.07 structures and Foundation as per Tech. Cu.m. 33.60
Spec. Cl. 1700.
Approach Slab
2 16.00 3.50 0.30 33.60

Cement concrete grade M35 in


1.08 Cu.m. 591.53
Foundations as per Tech. Spec. Cl. 1700.

Independent Returnwall on AL side (Foundation) 2 10.00 4.40 0.80 70.45


Independent Returnwall on AR side (Foundation) 2 10.00 4.25 0.80 68.07
Abutment base - AL 1 16.00 7.50 1.20 144.00
Abutment base - AR 1 16.00 7.5 1.20 144.00
Foundation 1 12.50 6.60 1.00 82.50
Foundation 1 12.50 6.60 1.00 82.50
Foundation 0 12.50 6.60 1.00 0.00

Cement concrete grade M35 in sub-


1.09 Cu.m. 579.26
structures as per Tech. Spec. Cl. 1700.
Return wall
Independent Returnwall on AL side wall 2 10.00 0.50 6.04 60.39
2 10.00 0.20 6.04 12.08
Independent Returnwall on AR side 2 10.00 0.50 5.79 57.91
2 10.00 0.20 5.79 11.58
Abutments

Abutment - AL (Shaft) 1 16.00 0.75 3.12 37.49


1 16.00 0.45 3.12 11.25
Monolithic Return Wall AL 2 3.80 0.80 3.12 18.99
Abutment Cap AL 1 16.00 0.75 0.60 7.20
Triangle portion 2 16.00 0.45 0.60 4.32
1 16.00 1.70 0.90 24.48
Dirt wall 1 16.00 0.30 1.95 9.36

14
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
Projection 1 16.00 0.30 0.30 1.44
Triangle portion 1 16.00 0.30 0.30 0.72
Abutment - AR (Shaft) 1 16.00 0.75 2.88 34.51
1 16.00 0.45 2.88 10.35
Monolithic Return Wall AR 2 3.80 0.80 2.88 17.49
Abutment Cap AR 1 16.00 0.75 0.60 7.20
Triangle portion 2 16.00 0.45 0.60 4.32
1 16.00 1.70 0.90 24.48
Dirt wall 1 16.00 0.30 1.95 9.36
Projection 1 16.00 0.30 0.30 1.44
Triangle portion 1 16.00 0.30 0.30 0.72
Piers
Pier-1
1 10.50 1.00 5.76 60.52
Top cap 1 10.50 2.80 0.50 14.70
1 14.50 2.80 0.70 28.42
1 4.00 2.80 0.50 2.80
Pier-2
1 10.50 1.00 5.16 54.22
Top cap 1 14.50 2.80 0.50 20.30
1 14.50 2.80 0.70 28.42
1 4.00 2.80 0.50 2.80
Pier-3
0 10.50 1.00 -3.02 0.00
Top cap 0 14.50 2.80 0.50 0.00
0 14.50 2.80 0.70 0.00

Cement concrete grade M40 in super


1.10 Cu.m. 424.21
structures as per Tech. Spec. Cl. 1700.
Pedestrals
42 0.80 0.80 0.25 6.72

Diaphgram 6 16.00 0.40 0.95 36.48


RC Deck slab 3 16.00 15.00 0.20 144.00

b) in RC Girder
End Block 21 4.00 Area = 0.87 73.08
Tapering 21 2.40 Area = 0.78 39.31
Mid Section 21 8.60 Area = 0.69 124.61

Providing, cutting, bending and fixing in


position of TMT bar reinforcement in
1.11 T 228.51
reinforced cement concrete structures
complete as per Tech. Spec. Cl 1600
Toe wall 1 wt = 3.67 3.67
Abutment & Dirt wall 1 wt = 33.77 33.77
Piers 1 wt = 31.83 31.83
Return Wall 1 wt = 12.78 12.78
RC Girder 1 wt = 47.40 47.40
RC slab 1 wt = 21.60 21.60
pedestals 1 wt = 1.01 1.01
Diapharam 1 wt = 5.47 5.47
Foundations 1 wt = 70.98 70.98

15
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
Filter media with stone crushed
aggregates abutments/return walls as per
1.12 Cu.m. 190.54
clause 2504.2.2 and Tech. Spec.
Cl.710.1.4 of IRC:78
Behind Abutment - AL 1 16.00 0.60 3.82 36.71
Behind Abutment - AR 1 16.00 0.60 3.58 34.33
Independent Returnwall on AL side 2 10.00 0.60 3.82 45.89
Independent Returnwall on AR side 2 9.70 0.60 3.58 41.62
below pitching 4 53.31 0.15 31.99

Providing weep holes in abutments,


returnwalls, with 100mm dia AC pipes
1.13 no's 336.00
complete as per drawing and Tech. Spec.
Cl. 2706
Abutment - AL 1 16.00 4.82 1.00 77.18
Abutment - AR 1 16.00 4.58 1.00 73.22
Independent Returnwall on AL side 2 10.00 4.82 1.00 96.48
Independent Returnwall on AR side 2 9.70 4.58 1.00 88.77

1.14 Providing and fixing Expansion joint


Asphaltic Plug joint Rmtr 2 16.00 32.00
Strip seal expansion joint Rmtr 4 16.00 64.00

Providing and fixing Tar paper bearing


1.15 complete as per drawing and IRC:SP:13- 9.60
1973.
in Approach slab Sq.m 2 16.00 0.30 9.60

Supply, fitting and fixing in position true


1.16 to line and level POT-PTFE Bearings 42
complete as per Tech. Spec. Cl. 2000

Pot-PTFE Bearing - 200 MT No's 3 3


Guided Pot-PTFE Bearing - 200 MT No's 36 36
Free Pot-PTFE Bearing - 200 MT No's 3 3

Fixed Pot Bearing - 250 MT No's 0 0


Guided Pot-PTFE Bearing - 250 MT No's 0 0
Free Pot-PTFE Bearing - 250 MT No's 0 0

Fixed Pot Bearing - 300 MT No's 0 0


Guided Pot-PTFE Bearing - 300 MT No's 0 0
Free Pot-PTFE Bearing - 300 MT No's 0 0

Fixed Pot Bearing - 350 MT No's 0 0


Guided Pot-PTFE Bearing - 350 MT No's 0 0
Free Pot-PTFE Bearing - 350 MT No's 0 0

Proving and fixing Drainage spouts


1.17 Each 20 20.00
complete as per Tech. Spec. Cl. 2705

16
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
Providing and filling joint sealing
compound as per drawings with coarse
sand and 6 percent bitumen by weight
1.18 (0.083 kg/m bitumen) including cost and Rmtr 4 16.00 64.00
conveyance of all materials, labour, fixing
in position, etc., complete as per drawing
and Tech. Spec. Cl

Providing and laying wearing course on


top of deck complete as per
1.19 Sq.m 1 52.00 11.00 572.00
Tech.Spec.Cl.515 & 2702 65mm Thick
(40BC+ 25 Asphaltic)

Construction of Crash Barrier M40 grade


1.20 incl. cost of all materials, labour, lead, Rmtr 108.00
lifts, loading, unloading etc., complete

Inner 0 54.00 0.00


Outer 2 54.00 108.00

1.21 PVC Utility pipes (150 dia) Rmtr 2 54.00 108.00

Providing and applying 2 coats of Enamel


paint to plastered concrete surface
1.22 Sq.m 1 108.00 2.30 248.40
complete as per Tech.Spec Cl. 800 for RC
Crash barrier

Painting details of Structure and span


1.23 No's 4 4.00
arrangements as Tech.Spec.Cl. 800

Provide and lay stone pitching as per


1.24 Cu.m. 63.98
Tech. Spec. Cl. 2504.
for quandrantal pitching 4 Area= 53.31 0.30 63.98

1.25 metallic crash barrier m15 garde Rmtr 40.00

2 10.00 20.00
2 10.00 20.00

1.26 Railing Rmtr


2 54.00 108.00

Painting of concrete hand rails/


parapets/ crash barriers with two
1.27 coats of enamel paint as per Technical Sq.m 291.60
Specification and the directions of the
Engineer

1.00 108.00 2.70 291.60


Painting of sub structures & super
structures with two coats of enamel
1.28 Sq.m 2181.52
paint as per Technical Specification
and the directions of the Engineer

17
Sl. Length Breadt
Description Unit No. Depth (m) Quantity
No. (m) h (m)
Pedstrals 42.00 3.20 0.25 33.60
Girders
End section 21.00 4.00 3.40 285.60
Mid section 21.00 8.60 3.70 668.22
Trapered section 21.00 2.40 3.55 178.92
Slab 1.00 45.00 16.40 738.00
Pier shaft
Pier-1 1.00 23.00 3.00 69.00
Pier-2 1.00 23.00 3.00 69.00
Pier-3 0.00 23.00 3.00 0.00
Abutment shaft
AL 1.00 18.40 1.00 18.40
AR 1.00 18.40 1.00 18.40
Pier Cap
Pier 1.00 34.60 0.70 24.22
1.00 23.00 0.50 11.50
2.00 9.60 0.50 9.60
Abutment cap
2.00 19.40 0.90 34.92
2.00 18.45 0.60 22.14

18
Highway/Drain Cost Estimate VUP Hazira
Sr No Item Description Unit Qty Rate Total
Construction of Subgrade with approved material statisfying the
1 requirements all leads and lifts complete as per Technical Specifications Cu.m 34450.00
Minimum CBR 8% -
Filling of median/island as per drawings and Technical specifications clause
2 Cu.m 3382.34
407 with selected earth -
Constructing granular sub-base (GSB) complete as per drawing and
3 Cu.m 13260.00
Technical specifications clause 401 -
Constructing Wet Mix Macadam (WMM) base complete as per drawing
4 Cum 16250.00
and Technical Specifications Clause 406 -

Providing and laying bituminous primer coat over granular surface as per
5
drawing and Technical Specifications Clause 502. (Slow Setting Emulsion)

a) 6.0 kg to 9.0 kg/10 sqm (Slow Setting) Sqm 65000.00


-
Providing and applying hot bituminous (Rapid Setting) tack coat over
6 prepared surface all complete as per Technical specifications Clause 503.
(Rapid setting)

a) @ 2.5 kg /10 sqm over Granular surface Sqm 65000.00


-

b) @ 2.0 kg /10 sqm over bituminous surface Sqm 53300.00


-
Providing and laying Dense Bituminous Macadam (DBM) course using
7 bitumen of 60/70 grade(VG 40), complete as per drawing and Technical Cum 4693.00
Specifications clause 507 -

Providing and laying Bituminous Concrete (BC) using 60/70 (VG 30) Grade
8 Bitumen with Modified Bitumen as per drawing and Technical Cum 2470.00
Specifications Clause 509
-
9 RCC Cover Drain (1.500m Width Section) -
i) Excavation Cum 6440.00 -
ii) PCC M15 Concrete Cum 470.00 -
iii) Base Slab (M-30) Cum 780.00 -
iv) Drain Wall (M-30) Cum 780.00 -
V) Top Slab (M-30) Cum 390.00 -
Vi) Steel Grate No. 170.00 -
vii) HYSD Steel Reinforcement 500D MT 87.86 -
Pavement markings with hot applied thermoplastic material complete as
10
per drawing and Technical Specifications clause 803
a) Lane/Centre line/Edge marking/ Traverse marking and any other marking Sqm 1733.33
-
S&F in position cut stone neatly dressed including earth work, C.C. 1:4:8 painting
11 with enamel paint engraving letters and numerals as per IRC standard design
complete.
i) 5th Km. Stone No.
ii) 200 M. Stone. No. 7.00
iii) Boundary Pillars No. 7.00

Supplying and fixing sign boards complete as per Technical Specifications


clause 801 and as directed by engineer, including the cost of posts,
12
fixtures, foundation, fitting & fixing. Sheeting will be retro-reflective tyupe of
high intensity grade and messages/borders will be screen printed
-
a) Informatory signs size: -
i) Advance Direction 1500 mm x 900 mm No. 1.00 -
ii) Destination 1500 mm x 950 mm No. 1.00 -
iii) Reassurance 600 mm x 800 mm No. -
iv) Facility (standard) 800 mm x 600 mm No. -
v) Facility (Special) 600 mm x 400 mm with definition plate 600 mm x 300 No. -
mm.
vi) Route marker NH/SH signs with definition plate of size 300 x 250 mm No. -
vii) General information 800 mm x 600 mm No. 1.00 -
b) Cautionary signs size No. -
i) triangular 900 mm side No. 1.00 -
ii) Circular 900 mm side No. -
c) Mandatory signs, size No. -
i) Octagon 900 mm height No. -
ii) Triangular 900mm No. -
iii) Triangular 600mm No. -
Providing cement concrete (M-20) median kerb ('L' Type Kerb) including
13 painting of kerbs as per Drawing and MORT&H Specifications Clause 408
and Technical Specifications. -
(a) For kerb ('I' Type) Rm 5200.00 -
Providing and applying two coats of synthetic enamel paint including primer
14 to concrete kerb surfaces etc. complete as per MORT&H Specifications Sqm 1629.00
clause 803. -
Total -
Sl. Length Breadth
Description Unit No. Depth (m) Quantity Rate Amount
No. (m) (m)

Clearing and grubbing at site which includes cleaning and


removal of vegetation growth from structures, channel and
1.00 ha. 3.58 0.00
protective works as per direction of Engineer as per
Tech.Spec. Cl. 201

1 1300.00 27.50 3.58

Earthwork in excavation of foundation for structures in all


2.00 types of soil including lead and lifts complete as per Tech. Cu.m. 2834.48 0.00
Spec. Cl. 304
a) ordinary soil
Abutment AL 1 28.50 6.10 2.40 417.24
Abutment AR 1 28.50 6.10 2.40 417.24
REWALL 4 500.00 1.00 1.00 2000.00

Back filling behind abutments, wing walls, return walls and


foundation trenches with selected granular material of
3.00 approved quality complete with all leads as per Tech. Cu.m. 913.00 0.00
Spec. Cl.710.1.4 of IRC:78 and lifts complete (Behind
Abutment)
Behind Abutment - AL 1 27.50 2.00 8.30 456.50
Behind Abutment - AR 1 27.50 2.00 8.30 456.50

Cement Concrete/Reinforced Cement Concrete in open


foundation / leveling course including centering and
4.00 Cu.m.
shuttering but excluding reinforcement all complete as per
Tech. Spec.Cl. 1500, 1700 & 2100
a) M15 Grade - Levelling Course Below Pilecap 315.04 0.00
Abutment AL 1 27.80 5.40 0.15 22.52
Abutment AR 1 27.80 5.40 0.15 22.52
Below RE WALL 4 500.00 0.90 0.15 270.00

c) M15 Grade - Below Approach Slab 30.11 0.00


Below Approach slab 2 27.50 3.65 0.15 30.11

Cement concrete grade M30 in sub-structures and


5.00 Cu.m. 57.75 0.00
Foundation as per Tech. Spec. Cl. 1700.
Approach Slab (Concrete + Reinforcment ) 2 27.50 3.50 0.30 57.75

Provinding Bored cast-in-situ M35 grade R.C.C. Pile in all


types of soil including soft rock (1200 dia) incl cost of all
materials, labour, loading, unloading, lead upto 5 km,
6.00 m 880.00 0.00
curing, hire charges tech spec: 1100,1600,1700 excluding
Reinforcement
(Pile Boring)
a) in Abutment
Abutment - A1 16 27.50 440.00
Abutment - A2 16 27.50 440.00

Provinding Bored cast-in-situ M35 grade R.C.C. Pile in all


types of soil including soft rock (1200 dia) incl cost of all
materials, labour, loading, unloading, lead upto 5 km,
6.00 Cu.m 995.26 0.00
curing, hire charges tech spec: 1100,1600,1700 excluding
Reinforcement
(Pile Concreteing)
a) in Abutment
Abutment - A1 16 27.50 Area = 1.13 497.63
Abutment - A2 16 27.50 Area = 1.13 497.63

7.00 Conducting Load Tests on Piles


a) Initial Load Test on Pile
Vertical load test MT 1.00 750.00 750.00 0.00

b) Routine Load Test on Pile


Vertical load test MT 1 450.00 450.00 0.00
Horizontal load test MT 1 15.00 15.00 0.00

8.00 MS Steel Liner for Piles (6mm thick) MT 28.41 0.00


in Abutment 32 5.00 Wt / m = 0.18 28.41

21
Sl. Length Breadth
Description Unit No. Depth (m) Quantity Rate Amount
No. (m) (m)

Cement concrete grade M35 in Foundations as per Tech.


9.00 Cu.m. 954.90 0.00
Spec. Cl. 1700. (Pile Cap Concrete)
Abutment - AL 1 27.50 5.10 1.80 252.45
Abutment - AR 1 27.50 5.10 1.80 252.45
REWALL 4 500.00 0.75 0.30 450.00

Cement concrete grade M35 in sub-structures as per


10.00 Cu.m. 378.68 0.00
Tech. Spec. Cl. 1700.
Abutments Concrete
Abutment & Cap - AL 1 Area= 6.00 27.50 165.00
Abutment & Cap - AR 1 Area= 6.00 27.50 165.00
Dirt wall 2 27.50 0.30 2.50 41.25
Corbel 2 27.50 0.30 0.30 4.95
Triangle portion 0.5 2 27.50 0.30 0.30 2.48

Cement concrete grade M45 in super structures as per


11.00 Cu.m. 387.29 0.00
Tech. Spec. Cl. 1700. ( Concrete )
Pedestrals 16 0.93 0.70 0.350 3.65
Diaphgram 6 10.80 0.30 1.500 29.16
RC Deck slab 1 27.50 25.00 0.225 154.69

PSC I Girder (25m)


End Portion 8 3.00 Area = 1.45 34.80
Varing Portion 8 3.00 Area = 1.18 28.20
Mid Portion 8 19.00 Area = 0.90 136.80

Providing, cutting, bending and fixing in position of TMT


12.00 500D bar reinforcement in reinforced cement concrete T 291.02 0.00
structures complete as per Tech. Spec. Cl 1600
Pile 1 995.26 wt = 0.110 109.48
Abutment,Piers & Dirt wall 1 378.68 wt = 0.150 56.80
PSC I Girder 1 199.80 wt = 0.125 24.98
RC slab 1 154.69 wt = 0.120 18.56
pedestals 1 3.65 wt = 0.100 0.36
Diapharam 1 29.16 wt = 0.175 5.10
Foundations 1 504.90 wt = 0.150 75.74

Providing High Tensile Steel strands including all


accessories for stressing and jacking operations and
13.00 T 12.99 0.00
grouting etc. complete as per Technical Specifications
Section - 1800
PSC I Girder - for 25m span 1 199.80 Qty = 0.065 12.99

Filter media with stone crushed aggregates


14.00 abutments/return walls as per clause 2504.2.2 and Tech. Cu.m. 321.30 0.00
Spec. Cl.710.1.4 of IRC:78
Behind Abutment - AL 1 27.50 0.60 8.50 140.25
Behind Abutment - AR 1 27.50 0.60 8.50 140.25
Monolithic Return Wall- AL 2 2.00 0.60 8.50 20.40
Monolithic Return Wall- AR 2 2.00 0.60 8.50 20.40

22
Sl. Length Breadth
Description Unit No. Depth (m) Quantity Rate Amount
No. (m) (m)
Providing weep holes in abutments, returnwalls, with
15.00 100mm dia AC pipes complete as per drawing and Tech. no's 536.00 0.00
Spec. Cl. 2706
Abutment - AL 1 27.50 8.50 1.00 234.00
Abutment - AR 1 27.50 8.50 1.00 234.00
Monolithic Return Wall- AL 2 2.00 8.50 1.00 34.00
Monolithic Return Wall- AR 2 2.00 8.50 1.00 34.00

16.00 Providing and fixing Expansion joint


a)Asphatic Plug joint Rmtr 2 27.50 55.00 0.00

b)Strip seal jt. in PSC Girder catering to maximum


Rmtr 2 27.50 55.00 0.00
horizontal movement upto 70 mm

Providing and fixing Tar paper bearing complete as per


17.00 0.00 0.00
drawing and IRC:SP:13-1973.
in Approach slab Sq.m 0 27.50 0.30 0.00

providing and laying elastromeric bearing as per engineer


18.00 CCC
in charge .
16 60.00 40.00 9.60 368640.00 0.00

Proving and fixing Drainage spouts complete as per Tech.


19.00 Each 12.00 0.00
Spec. Cl. 2705
12 12

Providing and laying wearing course on top of deck


20.00 complete as per Tech.Spec.Cl.515 & 2702 65mm Thick Sq.m 550.00 0.00
(40BC+ 25 Asphaltic)
2 25.00 11.00 550.00

Construction of Crash Barrier M40 grade incl. cost of all


materials, labour, lead, lifts, loading, unloading etc.,
21.00 Rmtr 64.00 0.00
complete
(Concrete + Reinforcment + Steel Pipe)
Inner 2 32.00 64.00

Construction of RCC Kerb M30 grade incl. cost of all


22.00 materials, labour, lead, lifts, loading, unloading etc., Cu.m. 12.24 0.00
complete (Concrete + Reinforcment )
2 34.00 0.30 0.60 12.24

23.00 PVC Utility pipes (150 dia) Rmtr 64.00 0.00


2 32.00 64.00

Providing and applying 2 coats of Enamel paint to


24.00 plastered concrete surface complete as per Tech.Spec Cl. Sq.m 178.36 0.00
800 for RC Crash barrier
1 64.00 Perimeter= 2.50 160.00
1 12.24 Perimeter= 1.50 18.36

Painting details of Structure and span arrangements as


25.00 No's 2 2.00 0.00
Tech.Spec.Cl. 800

Construction of Reinforced Earth Retaining Structures

Construction of earthwork in layers, assembling and


erection of reinforcing elements and placing of facia
26.00 panels and all associated components as per Additional
Technical Specification A-16, approved design and
drawing of specialised firm
a) Providing and laying M-35 grade RCC facia panels
includingreinforcement and reinforcing elements with all
sqm 9800.00 0.00
fixtures and accesories complete
(Including Geo Grid)

Approach sides 4 500.00 4.90 9800.00

b) Providing Filter Media Behind Reinforced Earth Panel


with well packed material to specified thickness with
smaller size towards the soil and bigger size towards the cum 5880.00 0.00
wall complete with all leads and lifts as per approved
design, drawings and Technical S
Approach sides 4 500.00 4.90 0.60 5880.00

23
Sl. Length Breadth
Description Unit No. Depth (m) Quantity Rate Amount
No. (m) (m)
c) Providing, Filling, grading and compaction with selected
soil meeting approved design parameters in layers in soil cum 123750.00 0.00
reinforced zone complete.
Approach sides
behing Abutment 2 500.00 27.5 4.50 123750.00

d) Providing and laying in position RCC Crash Barrier with


Friction Slab complete as per the approveddrawing and
Technical Specifications Clause 809 and Sections 1000 m 2000.00 0.00
and 1600.
(Concrete + Reinforcment + Steel Pipe)
4 500.00 2000.00
Construction of RCC Kerb M30 grade incl. cost of all
materials, labour, lead, lifts, loading, unloading etc.,
27.00 Cu.m. 369.00 0.00
complete, Protection Kerb Parellal to Bridge (Concrete +
Reinforcment )
2 1025.00 0.30 0.60 369.00

Providing and fixing 150 mm dia. GI pipe of approved


quality for drainage purposes including clamping
28.00 arrangement with the structure as per Tech. Spec. Cl m 2410.00 0.00
2705, 2708 and 2709 and as directed by Engineer all
complete.
Parellal to bridge 4 512.50 2050.00
Down take Pipe 80 4.50 360.00

Painting of sub structures & super structures with two


29.00 coats of enamel paint as per Technical Specification and Sq.m 2358.96 0.00
the directions of the Engineer
Pedestals 16.00 3.26 0.35 18.26
Girders
End section 8.00 3.00 5.00 120.00
Trapered section 8.00 3.00 5.25 126.00
Mid section 8.00 19.00 5.50 836.00
Deck 1.00 25.00 27.50 687.50
Abutment + Dirtwall - AL 1.00 8.50 33.60 285.60
Abutment + Dirtwall - AR 1.00 8.50 33.60 285.60

30.00 Geotechnical Investigation for Foundation Rmt 80.00 0.00


Abutment Foundation 2.00 30.00 60.00
Re Wall 2.00 10.00 20.00
Total = 0.00

24
SUMMARY OF COST ESTIMATE FOR MAIN CORRIDOR

CONSTRUCTION COST FOR FLEXIBLE PAVEMENT


Amount as per
Amount
Sl. No Bill. No. Description Derived Rates % cost
(Crores)
(Rs.)

1 Bill No.1 SITE CLEARANCE AND DISMANTLING #REF! #REF! #REF!

2 Bill No.2 EARTH WORK #REF! #REF! #REF!

3 Bill No.3 GRANULAR SUB-BASE AND BASE COURSES #REF! #REF! #REF!

4 Bill No.4 BITUMINOUS COURSES #REF! #REF! #REF!

5 Bill No.5 SLAB, BOX AND PIPE CULVERTS #REF! #REF! #REF!

6 Bill No.6 MAJOR AND MINOR BRIDGES #REF! #REF! #REF!

7 Bill No.7 DRAINAGE AND PROTECTION WORKS #REF! #REF! #REF!

TRAFFIC SIGNS, MARKING AND OTHER


8 Bill No.8 #REF! #REF! #REF!
APPURTENANCES

9 Bill No.9 BUS BAY_TRUCK LAY BAY #REF! #REF! #REF!

MISCELLANEOUS (Highway Patrol,


10 Bill No.10 Operation and Maintenance Centre #REF! #REF! #REF!
Excluding the Cost of Maintenance)
HIGHWAY TRAFFIC MANAGEMENT SYSTEMS
11 Bill No.11 #REF! #REF! #REF!
(HTMS)

12 Bill No.12 TOLL PLAZA #REF! #REF! #REF!

Grand Total #REF! #REF!


Total Package Length, Km 61.24
Total Length, Km 61.240
Per Km cost of Construction, Rs. Crores #REF!