18 Jan '19 1 Feb '19 15 Feb '19 1 Mar '19 15 Mar '19 29 Mar '19 12 Apr '19
22/1 27/1 1/2 6/2 11/2 16/2 21/2 26/2 3/3 8/3 13/3 18/3 23/3 28/3 2/4 7/4 12/4 17/4
1 Group 8 Project 56 days Fri 25/1/19 Fri 12/4/19
2 Preliminary Gantt Chart 0 days Fri 25/1/19 Fri 25/1/19 25/1
3 Feasibility Study on Process Plant 15 days Fri 25/1/19 Thu 14/2/19
4 Background of process design 2 days Fri 25/1/19 Mon 28/1/19 LWS,TJZ,TKH,TZZ,YKH
5 Market and business study 3 days Tue 29/1/19 Thu 31/1/19 TKH,TZZ,YKH
6 Literature survey on most feasible 10 days Fri 1/2/19 Thu 14/2/19 LWS,TJZ,TKH,TZZ,YKH
reaction pathway
7 Chemical properties analysis and 10 days Fri 1/2/19 Thu 14/2/19 LWS,TJZ
hazard identification of aniline
8 Determination on plant capacity and 10 days Fri 1/2/19 Thu 14/2/19 TKH,TZZ,YKH
plant location
9 Preliminary Process Synthesis and 20 days Fri 8/2/19 Thu 7/3/19
Heuristics
10 Preliminary flowsheet 3 days Fri 8/2/19 Tue 12/2/19 TJZ,LWS
11 Identification of major equipment 12 days Wed 13/2/19 Thu 28/2/19 LWS,TJZ,TKH,TZZ,YKH
and process conditions
12 Identification and labeling of 5 core 12 days Wed 13/2/19 Thu 28/2/19 LWS,TJZ,TKH,TZZ,YKH
system
13 Progress Report 1 0 days Fri 1/3/19 Fri 1/3/19 1/3
14 Block Flow Diagram 4 days Mon 4/3/19 Thu 7/3/19 TZZ,TKH,YKH
15 Simulation and Manual Calculation 20 days Fri 1/3/19 Thu 28/3/19
on Material and Energy Balances
16 Aspen HYSYS Simulation 7 days Fri 1/3/19 Mon 11/3/19 LWS,TJZ
17 Reaction system 1 material and 9 days Tue 12/3/19 Fri 22/3/19 TJZ
energy balances
18 Reaction system 2 material and 9 days Tue 12/3/19 Fri 22/3/19 TKH
energy balances
19 Distillation system 1 material and 9 days Tue 12/3/19 Fri 22/3/19 TZZ
energy balances
20 Distillation system 2 material and 9 days Tue 12/3/19 Fri 22/3/19 LWS
energy balances
21 Separator system material and 9 days Tue 12/3/19 Fri 22/3/19 YKH
energy balances
22 Simulation results and manual 4 days Mon 25/3/19 Thu 28/3/19 LWS,TJZ,TKH,TZZ,YKH
calculation comparison
23 Process Flow Diagram (PFD) 11 days Fri 29/3/19 Fri 12/4/19
24 Create Process Flow Diagram 10 days Fri 29/3/19 Thu 11/4/19 TJZ,TZZ,TKH
25 Stream Tables with process data 10 days Fri 29/3/19 Thu 11/4/19 LWS,YKH
preparation
26 Progress Report 2 0 days Fri 12/4/19 Fri 12/4/19 12/4
Page 1