Client: MITSUI ENGINEERING AND SHIPBULIDING CO.

LTD
Project : TANJUNG JATI B 5&6 COAL UNLOADING JETTY
HANDRAIL CHECKLIST
Record No. Date:
STRUCTURE: Handrail GL no:
LOCATION: Wharf Transfer tower MDO
DRAWING No: REFERENCE DOCUMENT:

NO. ACTIVITY ACCEPTANCE


BAM MES
1 PRELIMINARIES Y/N/NA
- Verify handrail type in accordance with shop drawing.

- No Visual Damage (coating and structural)

2 INSTALLATION Y/N/NA
- M16 thread bar (on concrete curb) minimum torsion 70 Nm

- M12 nut fixed properly to pipe socket (only for TTW


handrail)

- M16 bolt (between bracket plate and handrail post)


minimum torsion 70 Nm

- Gap between handrail max. 100 mm (±10 mm tolerance)

- Handrail alignment within ±5 mm tolerance with nearest


handrail section.

- Handrail verticality within ±5 mm tolerance with nearest


handrail section.

REMARKS

For BAM DECORIENT For MES

NAME: NAME:

SIGNATURE: SIGNATURE:

DATE: DATE: