MEMORANDUM
This has reference to the status of the one (1) project in the Municipality of Lubao
marked as “Not yet started” in the submitted Locally-Funded Projects Signed Monthly
Report as of February 25, 2019.
With this, please enjoin the LGU to submit a justification letter highlighting the
specific cause of delays and/or problems encountered on the implementation of the project
together with a catch-up plan.
In this regard, you are directed to submit the needed reports regarding the above-
mentioned concern and shall receive to this level not later than March 08, 2019