1
9/14/2018
Acknowledgement
With the completion of the internship I would like to thank some notable person
who have unforgettable contribution:
Precap
Road Over
Loading and
Objective Bridge at
Unloading test
Iradatganj
Chronological
Background order of activities
setting of Project during
Internship
2
9/14/2018
Objective
Indian Railway
3
9/14/2018
4
9/14/2018
5
9/14/2018
6
9/14/2018
7
9/14/2018
8
9/14/2018
9
9/14/2018
▪ Foundation :
Pile foundation is provided.
Eight in total, each of diameter 1.2 m.
Grade of concrete use M35 & Grade of Steel Fe 500
R/F – 20 Φ ; 16 in total.
Length of pile – 20 m
Capacity – 508 tonnes for normal condition.
10
9/14/2018
▪ This test in accordance with IRC SP 51 for testing the deflection of the
bridge.
▪ Two instruments mainly use one for official reporting and other for
check.
▪ For the official record Total Station was use.
▪ For temporary purpose Dial gauge was use.
▪ For loading purpose sand bags were used.
▪ Each sand bag weighed 44 kg.
11
9/14/2018
▪ The application of load on the Girder was carried out in 5 stages i.e.
(0%, 50%, 75%, 90%, 100%).
▪ The maximum load was maintained for 24 Hours on the deck of the
girder.
▪ The loading on the Girder commenced at 11:00 hrs. on 8 June 2018
and was completed at 15:00 hrs on the same day.
▪ Further the Girder was subjected to test load for 24 hr.
▪ Unloading was done in the decremental basis in the same sequence.
▪ After recording the final defelections, unloading process commenced
at 15:oo hrs. on 9 June 2018 and was completed at 19:00 hrs on 9
June 2018.
▪ Further the final deflection was observed after 24 hrs of unloading at
19:00 hrs. on 10 June.
12
9/14/2018
Result
▪ Calculation: -
▪ R3 - R5 = 19 mm
▪ R3 - R1 = 21 mm
▪ Percentage of recovery = × 100 = 90.47%
13
9/14/2018
Launching of Girder
14
9/14/2018
15
9/14/2018
Staircase
16
9/14/2018
▪ Foundation
Raft Foundation;(Raft of 500 mm thick of M30 Grade of concrete, with pedestals to erect column
on it )
▪ Column
Steel column are fabricated using two ISMC 400 separated apart by 400mm and connected
using Batten plate of 350mm x 8mm, columns are 8 in total at one side.
Bolts of Grade M20 HSFG used to erect it over pedestals.
17
9/14/2018
▪ Girders
Total in 3 girders are erected of I section Fabricated with Plates (Flange of 500mm x 40mm, web
of 928mm x 16mm)
▪ Beam in staircase
Two in total running at ends of ISMB 125.
▪ Waist Slab
RCC deck slab should be casted of M30 Grade(WSM) with thickness of 150 mm steel of tor
10mm @ 150mm c/c.
▪ Deck Slab
RCC deck slab should be casted of M30 Grade(WSM) with thickness of 150 mm steel of tor
10mm @ 150mm c/c.
Introduction to Design
18
9/14/2018
Results of Staging
19
9/14/2018
20
9/14/2018
Conclusion
References
21
9/14/2018
▪ ANY
QUESTIONS?
22