-1-
40 Door Shutters CL – 40 52
41 Internal Painting for Walls & Ceiling CL – 41 55
42 External Painting CL – 42 56
43 Fabrication Work CL – 43 57
44 Handing over of flat – Check List CL – 44 59
45 Passenger Lift CL – 45 64
46 Fire Fighting System CL – 46 66
47 Road Work CL – 47 67
48 Landscape Works CL – 48 69
49 Cleaning of Water Tank CL – 49 70
50 Cleaning of Drain Line CL – 50 71
51 Collection and Disposal of Dry Garbage / CL – 51 72
Wet Garbage
52 Lift Maintenance CL – 52 73
53 Working and Maintenance of Fire CL – 53 74
Fighting Equipments
54 Cleaning of Swimming Pool CL – 54 75
55 Safety Measures at Site CL – 55 76
56 Rain Water Harvesting CL – 56 77
INDEX
CHECK LISTS FOR FIELD TEST
SR. FIELD TEST FOR FIELD PAGE
NO. TEST NO. NO.
1 Receiving, Inspection & Testing : Cement FT – 01 86
2 Receiving, Inspection & Testing : Steel FT – 02 87
3 Receiving, Inspection & Testing : Binding Wire FT – 03 88
4 Receiving, Inspection & Testing : Sand FT – 04 89
(Fine Aggregate)
5 Receiving, Inspection & Testing : Stone Metal FT – 05 90
(Coarse Aggregate)
6 Receiving, Inspection & Testing : Murum FT – 06 91
7 Receiving, Inspection & Testing : Flush Door FT – 07 92
8 Receiving, Inspection & Testing : Bricks FT – 08 93
9 Receiving, Inspection & Testing : Instant Sunla FT - 09 94
10 Receiving, Inspection & Testing : M.S. Windows FT – 10 95
11 Receiving, Inspection & Testing : Glass Fixing FT – 11 96
12 Receiving, Inspection & Testing : Rolling Shutter FT – 12 97
13 Receiving, Inspection & Testing : Aluminum FT – 13 98
Windows
14 Receiving, Inspection & Testing : Plumbing G.I. FT – 14 99
Pipes and Fittings
15 Receiving, Inspection & Testing : Plumbing C.I. FT – 15 100
Pipes and Fittings
16 Receiving, Inspection & Testing : Plumbing PVC FT – 16 101
Pipes and Fittings
17 Receiving, Inspection & Testing : Hume Pipes FT – 17 102
18 Receiving, Inspection & Testing : Mosaic Tiles FT – 18 103
19 Receiving, Inspection & Testing : Ceramic / FT – 19 104
Glazed Tiles
-2-
20 Receiving, Inspection & Testing : Granite / FT – 20 105
Marble / Kotah / Tandoor Stones
21 Receiving, Inspection & Testing : Wood / Timber FT – 21 106
/ Plywood / Block Board / Laminates
22 Receiving, Inspection & Testing : Shingle FT – 22 107
23 Receiving, Inspection & Testing : Stone Dust FT – 23 108
24 Receiving, Inspection & Testing : Crushed Sand FT – 24 109
25 Receiving, Inspection & Testing : Fly Ash FT – 25 110
26 Receiving, Inspection & Testing : Fly Ash Bricks FT – 26 111
SR. FIELD TEST FOR FIELD PAGE
NO. TEST NO. NO.
27 Receiving, Inspection & Testing : Citadel Blocks FT – 27 112
28 Receiving, Inspection & Testing : CPVC Pipes FT – 28 113
and Fittings
29 Receiving, Inspection & Testing : RCC Door FT – 29 114
Frames
INDEX
OTHER ENGINEERING INFORMATION
SR. SUBJECT PAGE
NO. NO.
1 Handling, Storage and Preservation 82
2 Sampling Plan 84
3 Durocrete Mix Design Manual and Mix Deign for M15 to 115-131
M35 Grade of concrete
4 Tables of Engineering Information 132-155
5 List of I.S. Codes 156
6 List of Architects and Consultants with Telephone Numbers 158
7 List of Important Telephone Numbers 163
-3-
CHECKS WHILE RECEIVING DRAWINGS CL - 01
Check List
c) Working Drawings :
1. North direction and name plate as per specified form.
2. Project name, Drawing Title, Sub-Title and Scale.
3. Whether sizes are as per printed broachers.
4. Flat number as per printed broachers.
5. Brick / Block walling convention.
6. Chajja at terrace level shown in dotted on all plan.
7. Level with respect to T.B.M. for all plan on Plinth, Parking, Landing
and Mid-Landing etc.
8. All room door opening sides with Bath W.C.
9. Duct dimension and open area dimension.
10. Column reduction arrows.
11. Centre line checking such as size of column at footing level, all open ducts, space and
staircase details direction, room sizes as per broachers & wall thickness.
12. Dotted lines for Chajja, Rolling Shutter’s pardi, drop etc.
13. Kitchen Otta position with sink size
14. Lift position and size.
15. Balcony, W.C. and Bath drop.
16. All windows, door frames opening rolling shutters, R.C.C. grill sizes, Schedule, exhaust for
opening and balcony grill opening.
17. Specification in brief.
18. W.C. / Bath / Toilet / Terrace sunk line shown shaded.
19. Terrace drain, shopping patterns and rain water pipe opening locations
20. Lift shaft sizes, O.H.W.T. / Lift room positions.
21. Staircase pardi thickness, riser thread details.
-4-
22. Parking drawing.
23. Extract details for plinth side flats.
24. Meter cabinet locations.
Check List :
-5-
Records :
1. Demarcation Plan.
2. Plane table survey plan
3. Contour Map.
4. Verification Certificate of Architect and Technical Cell.
Check List :
Records :
1. Developed plan showing all above amenities and their respective levels.
2. Verification Certificate by Architect / RCC consultant and Technical Cell.
-6-
LAYOUT OF THE BUILDINGS ON SITE CL – 04
Check List :
1. As per CL – 02 approved layout showing North direction, Plot Boundaries of all building,
Amenities Area, Open Parking, Compound Wall, Gates, Roads, U.G.W.T., Electrical
Substation, etc.
2. Marking the Buildings and Structures, Roads on ground with lime powder and check for
fouling if any.
3. Check set-backs required for all structure as per rules and regulations
4. Clearance from Architect, Technical Cell for individual building lineout.
Check List :
1. Latest approved centre line plan of the building showing North Direction, adjoining
structures, expansion joint if any & reference point with distances.
`2. Verify the center line with respect to RCC foundation plan, Architectural Floor plans and
service drawings.
3. Establish T.B.M. near each building.
4. Fixing four corners of building and check diagonals.
5. Fixing side rails & all center lines, including lift pit position on rails, diagonals checking part
wise.
6. Making pits for footings & lift on ground with lime powder and check for fouling of footings
etc.
7. Consent from architect, RCC designer and Technical Cell for proceeding ahead with concrete
works.
PLUM CONCRETE CL - 06
Check List :
-7-
5. Percentage of plums with respect to concrete – maximum 40 %
6. PCC below footing is to be done above plum concrete as per specified thickness.
7. Curing for 07 days (minimum)
Check List :
1. Refer To :
a) Architect drawing.
b) RCC drawing and revision.
c) Strata for foundation approved by RCC consultant.
d) Any service lines passing below PCC or above PCC.
2. Check whether rubble soling below PCC preferred / anti termite treatment below PCC is
necessary.
3. PCC top level as per RCC drawing and also with reference to developed ground level or road
level.
4. Size, depth and diagonals of the pit size is more than required PCC size; provide side
shuttering to get required size.
5. Grade of concrete and thickness of concrete.
6. Placement of concrete and compaction.
7. Top of PCC must in level.
8. Curing for 7 days (minimum)
Check List :
-8-
a) Weigh batcher installed in level.
b) Calibration – Once in six months.
c) Adjust weigh scale for error.
d) Weights should be washed and cleaned.
e) The design mix of concrete should be displayed prominently near the
weigh batcher.
f) Weights of a particular weigh batcher should not be used for any other
weigh batcher.
4. During Concreting :
a) Type of cement, grade of cement, approved mix design.
b) Exact weight of each type of material i.e. cement, coarse aggregate, and fine aggregate and
– fly ash, shingle, crushed sand if to be used.
c) Check workability of concrete by relating to the slump.
d) Casting of cubes and identification marks – min. 6 cubes.
e) Check weight in pan and marker of weight on scale as these get disturbed due to vibration.
5. After Concreting :
a) Record actual consumption of material.
b) Compare actual consumption with theoretical consumption.
c) Cube test results with related slump for 7 days and 28 days strengths
d) Curing for 10 days.
e) De-shuttering period with respect to type of cement used and consultant’s notes on
drawings.
2) Consumption statement.
A) SLUMP TEST :
This test is conducted for determining consistency of concrete where nominal size of
aggregate does not exceed 38 mm.
Apparatus Used :
i. Slump Cone : Top Diameter 100 mm
Bottom Diameter 200 mm
Height 300 mm
ii. Tamping Rod : Diameter 16 mm
Length 600 mm
Rod rounded at one end.
Procedure :
The internal surface of the slump cone shall be thoroughly cleaned before commencing the
test. Slump cone shall be placed on a carefully leveled metal plate, the slump cone being
firmly held in place while it is being filled. The slump cone shall be filled in four layers, each
approximately one- quarter of the height of the cone. Each layer shall be tamped with twenty-
five strokes of the rounded end of the tamping rod. The strokes shall be distributed in a
uniform manner over the cross-section of the cone and for the second and subsequent layers
shall penetrate into the underlying layer. The bottom layer shall be tamped throughout its
depth. After the top layer has been rodded, the concrete shall be struck off level with a trowel
or the tamping rod, so that the mould is exactly filled. Any mortar which may have leaked out
between the mould and the base plate shall be cleaned away. The mould shall be removed
from the concrete immediately by raising it slowly and carefully in a vertical direction. This
allows the concrete to subside and the slump be measured immediately by determining the
-9-
difference between the height of the mould & that of the highest point of the specimen being
tested. The above operation shall be carried out at a place free from vibration or shock, and
within a period of two minutes after sampling.
B) CASTING OF CUBES :
Cubes of concrete should be cast regularly to estimate the strength of concrete. Concrete for
filling the cubes should be taken from the middle discharge of concrete mixer. Concrete from
beginning or at the end of discharge should be avoided. Cubes should be filled in 3 equal
layers. Each layer should be uniformly tampered at least 35 times with a 16 mm blunt rod.
Cubes should be properly leveled and finished using hand trowel. Cubes should be de-molded
after 24 hours and immersed in water for curing. It is important to keep the cubes away from
the shocks or vibrations especially for initial 3 days of casting.
We recommend that minimum 6 cubes should be taken every day and the batch of 3 cubes be
tested for 7 days and 28 days respectively.
Calculation :
The measured compressive strength of the specimen shall be calculated by dividing the
maximum load applied to the specimen during the test by the cross-sectional area, calculated
from the mean dimensions of the section and shall be expressed to the nearest kg per sq.cm.
Average of three values shall be taken as the representative of the batch provided the
individual variation is not more than +/- 15 percent of the average. Otherwise repeat test shall
be made.
- 10 -
Grade of Concrete 28 day’s 03 day’s 07 day’s 14 day’s
Required Strength Indicative Indicative Indicative
Strength Strength Strength
M 10 13.5 N / mm2 05.4 N/mm2 09.05 N/mm2 11.47 N/mm2
M 15 18.5 N / mm2 07.4 N/mm2 12.40 N/mm2 15.73 N/mm2
M 20 24.0 N / mm2 09.6 N/mm2 16.08 N/mm2 20.40 N/mm2
M 25 29.0 N / mm2 11.6 N/mm2 19.43 N/mm2 24.65 N/mm2
M 30 35.0 N / mm2 14.0 N/mm2 23.45 N/mm2 29.75 N/mm2
M 35 40.0 N / mm2 16.0 N/mm2 26.80 N/mm2 34.00 N/mm2
M 40 45.0 N / mm2 18.0 N/mm2 30.15 N/mm2 38.25 N/mm2
CONCRETING OF FOOTINGS CL – 10
Check List :
1. Latest approved center line drawing
2. Latest approved RCC drawings.
3. Footing size and respective column number.
4. Placement of steel with reference to drawings.
5. Orientation of footings and column.
6. Cover blocks for reinforcement.
7. Grade of concrete and mix design.
8. Concrete placement and mechanical vibration.
9. Surface finishing.
10. Cubes with identification marks and related slump – min. 6 cubes.
11. Testing of cubes for 7 days and 28 days strength.
12. Consumption records.
13. Curing ( minimum 10 days )
Consumption statement
CONCRETING OF COLUMN CL – 11
Check List :
1. Marking of centers for columns to be done before starting any work for above floor.
2. Starters to be casted with minimum height 6” & with vibrated concrete.
3. Starters to be casted at least 2 days in advance before erecting the column shuttering.
4. Check for orientation as per RCC and Architectural drawings.
5. Column reinforcement, links, and their arrangement as per drawings
6. Fixing cover blocks to reinforcement.
7. Checking of shuttering materials.
a) Quality of shuttering material.
b) Apply shuttering oil to plywood and planks.
c) To close the gaps / gabdies with mud paste to prevent cement slurry flowing out.
8. Column to cast up to bottom of beams.
- 11 -
9. Concrete with mixer should be insisted, if mixer is not used 10% extra cement is to be used.
10. Checking of column while concreting, for plumb.
11. Type of cement, grade of cement, grade of concrete and design mix.
12. Six cube mould are kept ready to cast cubes from different batches and slump test for each.
13. Compaction by needle vibrator and poking / tamping.
14. Check for lap length above top of concreting of columns.
15. Checking of columns after concreting
a) De-shuttering of column after 24 hours.
b) Finishing of honeycombing immediately after de-shuttering.
c) Hacking of columns within 3 days from de-shuttering.
16. Cube testing
a) Remove cubes next day and keep for curing.
b) Cover the column by gunny bags.
c) Testing of cubes on due dates ( 7th day and 28th day )
Check List :
Check List :
1. Architectural drawing showing lift shaft size and orientation of shaft with reference to
manufacturers requirements and required depth of pits.
2. Latest approved RCC drawings.
3. Check whether base water proofing is done.
4. Check size, diagonal, plumb, support and depth below level required by lift manufacturers.
- 12 -
5. Check grade of concrete and reinforcement.
6. Centers of raft, pardi, covering for raft and pardi.
7. Check for lift door opening to be provided in lift pardi wall.
8. Water proofing on sides of lift pardi up to plinth level.
9. Hacking to concrete surface.
10. Cubes with identification marks.
11. Curing for minimum 10 days.
12. Cube tests on 7 and 28 days with related slump.
CONCRETING OF STAIRCASE CL - 14
Check List :
1. Scrutiny of RCC Drawing with respect to latest revised Architectural Drawing and details of
staircase such as riser, trade and thickness of waist slab.
2. Ensure height of riser is within specified limit (not to exceed 175 mm)
3. Before erecting formwork for staircase check by marking on plain ground, whether
arrangement given in drawing is suitable or not.
4. Check whether slab / floor level landing top is provided with sunk slab (50 mm) or not ?
5. The sunken (50 mm) provided should be distributed among all risers at parking floor.
6. Check quality of shuttering and staging material.
7. Shuttering plates should be well supported by chavi’s for full length.
8. All props supporting chavi’s must in plumb. Top of mundha to cut at an required angle.
9. Check reinforcement is laid as per RCC drawing or not.
10. Mark top of mid-landing / slab level on shuttering sides.
11. Check shuttering provided to steps is of plywood finish or not ?
12. Check size of risers and trades is as per drawing.
13. Check verticality of risers.
14. Check thickness of waist slab as per drawing.
15. Check dowel provided for upper flight or not ?
16. Concreting as per design mix and proper grade of concrete.
17. Proper compaction of concrete with vibrator and hand pocking.
18. Casting of cubes with related slumps.
19. Curing for minimum 10 days.
Records :
Consumption Statement
Cube Test Results and related slumps.
Check List :
1. Scrutiny of structural drawing with respect to latest revised architectural drawing and details
of staircase such as riser, thread, thickness of waist slab, sunk for landing flooring, lift size
and opening.
2. Level of each bay of the slab and internal panel measurement beam to beam & diagonals.
3. Location and depth of sunken slab.
4. Proper laps for reinforcement of columns, beams and slab and Lift pardi.
- 13 -
5. Check reduction of columns and reinforcement is done as per above floor requirements as per
RCC drawings.
6. Check for expansion joint details and the same should be provided as per RCC details.
7. Chairs for reinforcement with 8 mm.
8. Dowels for future columns if any in slab and beams.
9. Quality of Centring and Shuttering and staging materials.
10. Shuttering plates should be well supported by chavis at 3-0” c/c for the full length.
11. Provide camber for cantilever beams as specified by structural consultant.
12. Cross bracing should be provided for vertical supports (wooden & M.S. both) for slab and
beams at maximum 4’00” interval.
13. Make the top of concrete on sides of beam / slab shuttering around
14. Making of required GHODI of various thickness of slab.
15. Concealed conduit / junction boxes / fan hooks as per electrical drawings.
16. Require number of sleeves opening for RWP, drainage pipe etc.
17. Inform well in advance to Architect, RCC designer, Technical Cell for checking of slabs.
18. Provide sufficient cover blocks for beams, columns and slabs.
19. Keep six numbers of cubes and one slump cone ready.
20. Type of cement, grade of cement and grade of concrete / design mix.
21. Proper compaction of concrete with vibrator hand pocking
22. Control of W/C ratio in the concrete to be checked frequently as per the slump desired.
23. Add water proofing compound for sunken slab and terrace slab.
24. Finishing of slab to the required line and level without honeycombing.
25. For curing ensure water ponding minimum 2” depth with maximum size of 6-0” X 6-0”
between bunds for minimum 7 days.
26. Cross-Bracing should not be removed before 03 days after casting.
27. De-shuttering of slabs after 7, 10 or 15 days and beams 14 or 21 days depending upon span
and type of cement used, also refer notes on consultant’s drawing and instructions of
Technical Cell.
28. Cube tests with related slump for 7 days and 28 days strength.
STAGE VERIFICATION BY
1. Centring / Shuttering but before
laying reinforcement Project In-Charge
2. After Laying reinforcement
but before concreting RCC Consultant,
Tech. Cell, Architect
3. During Concreting Project In-Charge
4. After concrete for curing
& before de-shuttering Project In-Charge
- 14 -
RCC OF LIFT MACHINE ROOM AND O.H.W.T. CL – 16
Check List :
a) Check for latest approved drawings from lift manufacturer / and architect.
b) Check the size of machine room, height, access, ventilation etc.
c) Check for the sleeves in the bottom slab as per drawings.
d) Check for lifting hook in the top slab as per designed capacity
e) Grade of concrete and thickness of concrete.
f) Cube test results related with slump.
g) Curing for minimum 10 days.
2. For O.H.W.T. :
a) Check the capacity as per Architect or Consultants drawings for domestic, potable water
and fire fighting water and treated water for flushing.
b) Check for Sleeves for washout, inlet, outlet overflow, fire fighting and treated water for
flushing etc.
c) Check for chamfer in concrete for bottom slab
d) Check for chamber cover openings.
e) Grade of concrete and design mix.
f) Water proofing compound.
g) Cube test results with related slumps.
h) Curing for minimum 10 days.
Check List :
Stages :
- 15 -
Emulsion Spray :
Mix chemical with water ( 1 part of chemical, 30 parts of water ), make the holes by crowbar
at two feet center and two feet deep and spray the emulsion with pressure pump, consumption
5 liters per Sq. meter.
Records :
RUBBLE SOLING CL – 18
Check List :
Check List :
1. Architectural drawings.
2. Stage wise / thickness wise bottom and top levels of masonry.
3. Proportion of cement mortar (not more than 1:6) and raking of joints for specific type of
pointing (proportion of mortar not more than 1:2)
4. Provision of one header for every 5 Sq.Ft., staggered horizontally and vertically.
5. Check whether weep holes required in case of retaining walls.
6. Curing ( for 10 days minimum )
7. Ensure there should not be voids in UCR masonry wall.
8. Ensure that only 3 ft height of wall is constructed in one day.
9. Provide pins for boundary of upper level masonry work for every 5 rft.
- 16 -
BRICK MASONARY CL – 20
Check List :
1. Latest approved architectural drawings showing thickness of walls, door windows and other
openings.
2. Customer changes / NOC
3. Cleaning the entire floor, stacking of bricks on either side of beam.
4. Cleaning of slab conduits and passing GI wire through conduits before brickwork starts.
5. Soaking of bricks.
6. Preparation of mortar in proper proportion in M.S. Tray, check whether cement mortar or any
other ready mixed mortar is to be used. Prefer for design mix and use of mixer for BBM
mortar.
7. Confirm diagonals and dimensions of room after first layer.
8. Check right angle, plumb lines, levels, joints ( max ¾” ) at sill and lintel level.
9. Plumb for external wall to be taken from outside and for internal walls from side flush with
beam / column.
10. Not more than 4’-00” masonry in day’s time.
11. In case of long walls (exceeding 4.5 m length), provision of horizontal / vertical RCC bands
should be considered
12. Provide ¾” metal chip at the junction of RCC and BBM (insert by thumb pressure)
13. Provide RCC band, if 4” thick brick wall above 3.0 m and if 6” brick wall above 4.0 m with
nominal reinforcement and M15 grade of concrete.
14. Racking of Joints.
15. Provide sufficient number of hold fast embedded in concrete for all frames property covered.
16. Cleaning the working area.
17 Curing for minimum 10 days.
18. Check the line and plumb of door frame.
EXTERNAL PLASTER CL – 21
Check List :
- 17 -
13. Check proportion of mortar for base coat and finishing coat mixing to be done in M.S. trays.
Also whether cement mortar or ready mortar to be used. Prefer for design mix and use of
mixer for plaster mortar.
14. For single coat plaster with rubdi coat for sponge finish – thk. 12 + 6 = 18 mm. both coats to
be done simultaneously. For double coat plaster – thk. 19 + 6 = 25 mm. Second coat is to be
done 03 days after first coat is completed.
15. Check for line, level and plumb of plaster, check right angles for all openings.
16. Cleaning of working area to be done on the same day, especially railings, RCC grills, door
and window frames etc.
17. Curing for 10 days minimum.
INTERNAL PLASTER CL – 22
Check List :
1. Soaking of brick-wall surface well in advance for minimum 03 days before plastering.
2. Ensure horizontal and vertical electrical conduits laid chiseling with cutter.
3. Patching up of chiseling area with rich mortar and ¾” metal 2 days before.
4. Sufficient hacking to all RCC work.
5. Making thiyyas of minimum thickness 2 days before plater.
6. Conduiting of plumbing, electrical and other service lines.
7. Customer changes / NOC
8. Check electrical conduiting with reference to electrical points, switch boxes with DB box.
9. Chicken mesh at joints of RCC and BBM, Excess conduiting locations etc.
10. Verticality and alignment of all doors and windows frames.
11. Proportion of mortar and mixing in tray, check whether prefer cement mortar or ready mix
mortar to be used with type of finishing coat. Prefer for design mix and use of mixer for
plaster.
12. Ensure plumb, right angle, dhar corners, window jam levels, position of electrical boxes etc.
13. Ensure finishing of loft top.
14. Ensure application of neeru in proper proportion and finish except dado position.
15. Check for finishing of joints between internal and external plaster.
16. Smooth trowelling of neeru finish on next day.
17. Cleaning of all working area.
18. Check all electrical points and switch boxes are open and cleaned.
19. Curing for minimum 10 days.
20. Donga (white wash) to be applied after 03 weeks.
- 18 -
PROVIDING EXPANSION / CONSTRUCTION JOINTS CL – 23
Expansion Joint :
These joints are provided to accommodate the expansion of adjacent building parts and to relieve
compressive stresses that may otherwise develop.
The joints formed by providing an initial gap between the adjacent building parts which gets widened
or shortened while accommodating the contraction or expansion of the building. The width of the gap
should be sufficient to accommodate the maximum thermal-induced moment likely to be encountered.
Normally it varies between 10 mm to 40 mm. There should be complete discontinuity of masonry,
reinforcement or concrete at the joint and the gap should permit unobstructed movement of the
adjacent parts. Expansion joint should start from the top of footing (in case of combined footing for
adjacent columns) tip topmost point of structure.
Construction Joints :
Joints installed at location where construction stops for any reason is known as construction joint. If it
is possible to plan construction in such a way that the days work ends at expansion or contraction
joint, then there is no necessity of construction joint. But many times it is not possible to complete the
concreting work in one operation. Therefore special measures are necessary to be taken to achieve
perfect continuity in old and new concrete. For structural stability, it is necessary to ensure that
construction joints are provided at pre-determined locations.
- 19 -
4. R.C.C. Walls : At suitable location where erection of formwork, compaction of concrete and
supervision is convenient.
CURING CL – 24
Curing is the process of preventing the loss of moisture from the concrete / mortar.
Curing should be done for minimum 07 days for 43 / 53 Grade cement.
Curing should be done for minimum 10 days for blended cement, but recommended to continue for 14
days.
- 20 -
CONCEALED PLUMBING CL – 25
Check List :
Check List :
1. Consultant’s approved drawings / specifications for materials and pumps / work order.
2. Ensure the provision of valve and NRV, PRV
3. Position of delivery pipes, air vent pipes, over flow pipes, wash out drain pipes.
4. Joining and alignment of pipes near overhead tank.
5. Installation of water pumps of required capacity its Earthing and Electrical connection.
6. If auto control system is provided, then ensure
a) Quality of the sensors of the system.
b) Display panel for water tank.
c) Cabling used for system.
d) Protection for dry run.
7. Proper clamping for pipes.
8. Adopt telescopic arrangement in down take pipe lines and check the plumb and alignment.
9. Pressure of water to each floor.
10. Identification marks on pipes PMC / wash water supply.
- 21 -
BUILDING DRAINAGE SYSTEM UPTO
THE VERTICAL STACK CL – 27
Check List :
Check List :
1. Refer to specification and schedule of fittings, fixtures and sanitary ware and type of outlet
trap of W.C.
2. Customer changes and NOC
3. Free flow of water at least 15 minutes by removing plugs and then fixing fittings / sanitary
wares.
4. C.P. fixtures should be fixed with cloth packing while using the spanners.
5. Check all the fittings for free flow of water, leakages if any ( to be rectified )
6. Fix the identification mark on domestic and PMC water connection.
7. Ensure the sanitary fitting before fixing for colour code, defects if any.
8. Ensure proper grouting of EWC / WB brackets.
9. Ensure the proper functioning of flush tank / half turn valve / PVC connection for colour
code, defects if any.
10. Seat cover of correct size and matching colour.
11. Check for cleaning of tiles and sanitary ware, C.P. fiitings
12. Ensure that the plugs for boiler connections are easy to remove but at the same time the plug
is non-leaking.
- 22 -
7 Bottle Trap Outlet 18”
8 Low level Cistern height 36”
9 Urinal 24”
10 Soap Dish 36”
11 Kitchen Sink Cock 39”
12 Kitchen Platform 31”
13 Flush Valve 41”
14 Fourway Divertor / Single Lever Divertor 39”
Check List :
SEPTIC TANK CL – 30
Check List :
1. Approved drawing
2. Invert level of incoming sewer.
3. Record initial ground level.
4. Record final excavated ground level.
5. PCC / RCC, BBM, Water-proofing to be done as per respective check list.
6. Inlet – Outlet levels of tank.
7. Free board.
8. All the documents, Size of the compartments and the baffle walls.
9. Filler media materials and filling procedure.
10. Water tightness of septic tank.
11. Vents are provided.
12. Connected effluent to sock pit or nearest drain or STP
- 23 -
EXTERNAL WATER SUPPLY – RISING MAIN CL – 31
Check List :
Records :
Consumption Statement
Check List :
COLOUR PURPOSE
Red, Yellow, Blue Phase Wires
Black Neutral
Green Earthing
- 24 -
EXTERNAL ELECTRICAL M.S.E.D.C.L. SUPPLY CL – 33
Check List :
1. Civil instrument work of LT room and transformer yard based on approved layout of
M.S.E.D.C.L. and electrical inspector and detailing by Architects and RCC consultants.
2. M.S.E.D.C.L. approved layout of transformer, four pole structure, LT / HT panels, earthing
provision switchgear, feeder pillars, cable layout from transformer to meter board including
sizing.
3. Work order for transformer, LT / HT panels, switchgear, cables, steel structure, feeder pillar
and all accessories required.
4. Electrical contractors scope of work, his work order, installation schedule.
5. Approvals from M.S.E.D.C.L. and electrical inspector after erection.
6. M.S.E.D.C.L. supply from outside mains for charging transformer, testing and commissioning
of the total system.
Material Consumption
Check List :
1. Civil construction work as per manufacturer’s requirement, detailing by architect and RCC
consultant.
2. Approved layout of generator foundation, AMF and switching panels, diesel stock provision,
ducting and ventilation, chimney for smoke disposal, earthing, canopy etc by the approved
suppliers and erection contractor.
3. Schedule for erection, testing and commissioning.
4. Approval from electrical inspector concerned.
5. Maintenance Manual.
6. Maintenance contract.
Check List :
Records :
- 25 -
WATERPROOFING OF TOILETS,
DRY BALCONY, TERRACE, LIFT PIT AND BASEMENT CL – 36
Check List :
A) TOILETS :
1. Fixing of machine cut rough shahabad below raft slab with waterproof plaster.
2. Fixing of machine cut rough shahabad for RCC pardi from outside with waterproof plaster up
to plinth level.
3. In case of basement encasing column and footings with machine cut rough shahabad is
necessary.
4. Curing for 10 days minimum.
- 26 -
TILING WORK CL – 37
Check List :
Records :
Consumption Statement
KITCHEN PLATFORM CL – 38
Check List :
Records :
Consumption Statement
- 27 -
ALUMINUM WINDOWS AND DOORS CL – 39
Check List :
DOOR SHUTTERS CL – 40
Check List :
- 28 -
d) Door Stopper As per requirement 5 cm (2”) 7.5 cm (3”)
at opening edge
- 29 -
d) Handle ‘D’ type bottom 120 cm (48”) 6.5 cm (2 ½”) from opening
of shutter edge
e) Night Latch 100 cm (40”) Opening edge of shutter
f) Tadi Patti 85 cm (34”) At the opening of edge
g) Rubber Gattu 7.5 cm (3”) 7.5 cm (3”) from opening edge
of shutter
2 Outside
a) Unit number place 175 cm (70”) Center to shutter
b) Name Plate 167.5 cm (67”) Center to shutter
c) Decorative handle 110 cm (44”) 7.5 cm (3”) from opening edge
(bottom) of shutter
d) Al-drop 90 cm (36”) 5 cm (3”) from opening edge
of shutter
e) Door Stopper As per requirement At the opening edge
Check List :
1. Approved colour scheme and check customer’s changes, if any, regarding paint.
2. Wall has been scraped for all unwanted material like excess cement, mortar nails, dust etc.
3. Donga has been removed completely and the wall surface is rubbed by the fine sand paper,
wide cracks completely opened and filled with crack seal compound.
4. Mix, preparation and application of primer.
5. Primer has been allowed to dry for at least 24 hours before application of putty.
6. All the undulations of minor nature, dents and cracks in proper way are filled up with putty
and surface is smooth to receive paint.
7. Surface has been rubbed with fine paper to get smooth finish after 24 hours of application of
putty.
8. Check any brush marks bristles from the brush stick to the wall.
9. Mix, preparation and application of second coat shall be done only after drying 1st coat.
10. Check for floor, door, windows fittings cleaned properly.
11. Check all cement mortar, unwanted welding burr etc. are removed before application of
primer polishing properly.
12. Check for free movement of hinges, fittings and fixtures of door and windows before
application of primer.
13. Application of zinc cromite metal primer before application of first coat of oil paint to the
steel works.
14. Application of first coat of oil paint and proper finish, fill up putty whenever necessary,
application for second coat of oil paint after 24 hours drying of first coats.
- 30 -
EXTERNAL PAINTING CL – 42
Check List :
FABRICATION WORK CL – 43
Check List :
Records :
Consumption Statement
- 31 -
CUSTOMER CHANGES
B) TILING :
1. Is the floor in proper level ?
2. Is the floor and skirting properly polished and cleaned ?
3. Is the skirting in one line and at right angles ?
4. Are the floor tiles of one type ?
5. Is the mosaic / ceramic tiles in the room continued up to outer edge of main door frame ?
6. Is the butt joint properly finished ?
7. Is the skirting and butt properly inline level and right angle around the column ?
8. Are cracked tiles replaced and finished properly ?
9. Are glazed tiles cleaned and finished properly ?
10. Are all glazed tiles cleaned and finished properly ?
11. Are the glazed tile dado in right angle and level ?
12. Is the gap between glazed tile dado and room ceiling / flooring filled properly ?
13. Are jams of windows properly finished with glazed tiles ?
14. Are you sure that there is not a single cracked tile in dado ?
15. Are the glazed tile around W.C. pan properly fixed ?
16. Are you sure that no water accumulates on flooring of W.C. ?
17. Have you confirmed by knocking each tile that there are no loose patches left in the dado ?
18. Is there proper slope towards nahani trap and no water accumulates in between ?
19. Is there proper slope given to bathroom ?
- 32 -
20. Is there bath and W.C. floor down than room floor ? Is boundary edge finished properly ?
21. Is the slope properly given to the balcony towards water spout ?
22. Is the terrace or balcony floor level minimum 1” down than floor ? If not check whether
threshold ( Umbra Patti ) has been provided ?
23. Is the gap between terrace, toilet, dry balcony floor and room floor filled properly with white
cement.
24. Are water spouts in balcony fitted properly and cleaned properly ?
25. Is there any necessity to provide threshold fixed to bath and W.C. ?
26. Is the kitchen platform finished properly ?
27. Is the kitchen platform leak proof ?
28. Are the edges of granite around kitchen sink and fascia patti polished properly and edges soft
chamfered ?
29. Is there proper slope given to kitchen platform top ?
30. Are the glazed tiles near water taps properly cut and fixed ?
31. Is the hole for gas provided with pvc bend above the kitchen otta ?
32. Is polishing of kitchen otta cuddappa verticals and shelves done ?
33. Is edge polishing and rounding done ?
34. Flooring below kitchen platform to be in level with the room floor ?
35. Check whether skirting below kitchen platform provided ?
36. Is the space for gas cylinder ok to put cylinder freely /
37. Are you sure that hole for gas pipe is not chocked with cement / debris ?
38. Is the finishing and painting of walls below kitchen platform done properly ?
E) LOFTS :
1. Are the lofts finished by I.P.S. from top ?
2. Are the ceilings and walls around loft properly painted and finished ?
3. Is the loft properly cleaned and no rabit / debris left out ?
4. Is the finished thickness of loft maintained all over ?
- 33 -
F) PLUMBING AND SANITATION :
1. Are all fixtures like bibtaps, mixers etc fixed properly and at proper height from floor level.
2. Is there any leakage from taps / other c.p. fixtures /
3. Is there proper pressure to all the taps ?
4. Is there half turn cock or flush tank operating properly ?
5. Is there continuous flow of water through w.c. when half turn cycle or flush tank is kept open.
6. Is ‘P’ – trap of w.c. properly cleaned to be without any lump.
7. Is there continuous flow of water without any chock-up through nahani trap when tested for at
least 5 minutes. A check for finishing of watta below nahani trap cover.
8. Is the hot / cold operation proper.
9. Are boiler connections properly plugged, non leaking & easy to remove ?
10. Is the low level flushing water tank operation of commode proper ?
11. Is the seat cover of commode fixed properly and cleaned ?
12. Check whether provision for soap dish mode ?
13. Are the mirror over w.h.b. and tile dado filled with sealant ?
14. Is height of mirror (Bottom) 1.25 m from toilet floor ?
15. Is proper cleaning done for all sanitary fixtures ?
16. Are the brackets of basin painted with oil paint ?
17. Are open GI pipe connected to w.c. painted ?
18. Is basin and counter if any fitted properly ? is the sturdy ?
19. Are all the sanitary fittings in proper condition without any leakage or crack ?
20. Are the CI or PVC lines (7.5 cm / 10 cm) found leak proof when tested for at least 15 min.
with continue water flow ?
21. Is the fixing of GI / CI / a.c. or PVC lines inline and proper clamping ?
22. Are you sure there is no chock-up in the drainage chamber ?
23. Are the main inlet and outlet GI lines of water tanks leak proof ?
24. Is the white cement filled between w.h.p. and wall smooth, without ay crack.
25. Is PVC outlet pipe for w.h.b and kitchen sink fixed properly ?
26. Is there any convention marked for municipal water tap and wash water tap and also
respectively GI pipes with colour bads.
G) ELECTRIFICATION :
1. Is the individual meter allotted to flat ?
2. Is the main switch fixed in meter cabinet ?
3. Is there any testing report of electrical points given by electrical contractor ?
4. Are all the kitkat / fuses fitted properly ?
5. Are all electrical switches working properly ?
6. Is the earthing connection tested for working condition ?
7. Are all the fan hooks in fan boxes ?
8. Are all the switch boards fitted in line and level ?
9. Is the position and quality of electrical points as per working drawings ?
10. Are all extra amenities provided as per customer changes ?
11. Is the colour of switches and accessories same as provided initially ?
12. Are the battens / casing capping in perfect line and right angles ?
13. Are the wires on batten fixed with proper clipping ?
14. Are you sure there is no gap between wall and batten ?
15. Are you sure that no screw is left from boards / switches / plugs etc ?
16. Is the type of bell same as approved initially ?
17. All the fittings fixed on board are inline and level or not ?
H) PAINTING :
1. Is the painting properly done for walls and ceiling ?
2. Is the oil painting done properly for doors and windows ?
- 34 -
3. Are all the windows glasses cleaned by painter /
4. Are all the door / windows fixtures cleaned by painter ?
5. Is the painting done on lofts ?
6. Are all the paint stains cleaned properly ?
7. Are all painting of battens / wires done properly throughout ?
I) MISCELLANEOUS :
1. Is the letter box with owners name provided ?
2. Are the keys for all doors and letter box tagged and their numbers recorded ?
3. Is the flat number displayed on electrical meter ?
4. Is the electrical meter number and initial reading recorded ?
CERTIFICATE
TO,
THE DIRECTOR
__________________
PASSENGER LIFT CL – 45
Check List :
1. Lift pit and lift shaft size as per lift manufacturers specifications and the work order.
2. Waterproofing to the lift pit and top of the machine room slab.
3. Size of the shaft, size of the all door openings, floor levels and height of machine room as per
manufacturers requirements.
4. Cleaning of lift pit, ducts and shafts.
5. All material produced is as per the specifications. (Refer work order)
6. Angels and channels in the lift shaft / duct.
7. Fixing of template.
8. Scaffolding is made in the lift shaft is steardy and approved by the lift erector.
9. Electrical cabling and light points in shaft as per manufacturer’s requirement.
10. All the door frames (except ground floor) are fixed in the plumb line fixed by the erector.
11. Rope hole in the bottom slab of machine room and pockets are made in the side walls for
clamping of angles.
12. Grouting of brackets and check rigidity.
13. Whitewash in the lift shaft.
- 35 -
14. For the machine room
a) I.P.S. flooring
b) Ventilation and Exhaust fan.
c) Shutter fixing
d) Painting of machine room.
e) Provide electrical points as per manufacturers requirement.
15. Angles (rails) fixing and roping.
16. Machine of the lift is fixed with proper bolting, grouting, and anti vibration pads are fixed
below it.
17. Flooring in the landing is done as per levels fixed previously and slope of the flooring is away
from the lift.
18. Button box holes are marked and made properly.
19. Ensure three phase meter exclusively for lift.
20. Ensure the safety arrangement as
a) Ladder for pit.
b) Weld mesh guard to the motor.
c) Weld mesh guard to the window to avoid entry of the birds.
d) All safety indicators working properly.
e) Effectiveness of electrical switches.
f) Emergency key operations.
g) Instruction plates for the usefulness of the passengers guidance.
h) Earthing done properly.
21. Ensure while the trial run of the lift that there are no jerks and sudden stops, floor levels
matching to lift level at all floors.
22. Ensure about the guarantee period and certification from P.W.D.
23. Instructions for users from manufacturer should be displayed inside lift cabin.
24. Maintenances :
a) Ensure local agency for A.M.C. with full address, telephone numbers of contractor and
engineer.
b) Frequency of Maintenance.
c) Lubrication of wire ropes and guide rails.
d) Levels of machine oil.
e) Greasing to the motor.
f) Cleaning of all the equipment.
g) Adjustment in electrical circuits, leading gate locks, lift car switches etc.
h) Inspection of hoist way switches.
- 36 -
FIRE FIGHTING SYSTEM CL – 46
Check List :
1. The capacity of U.G.W.T. and O.H.W.T. with provision in that for fire fighting storage.
2. Other requirement as per municipal authorities in provisional N.O.C.
3. Authorized agency for fire fighting installation work.
4. Quality of material supplied by the contractor refers work order.
5. Civil work like excavation, making holes to the bricks, wall, concrete and refinishing of the
same is done properly as per the requirements of working agency.
6. Scaffolding fixed in such a way that no work in fire fighting is disturbed.
7. Testing done before inspection by Municipal authorities.
8. All G.I. / M.S. pipe line for straightness, level plumb, etc for perfect ness.
9. G.I. / M.S. line painted in red colour.
10. Check all required electrical connections are provided and are in working condition.
11. Check that all fire extinguishers are working and installed at proper location.
12. Fire hydrant located is easily accessible.
ROAD WORK CL – 47
Check List :
A) GENERAL :
1. Approved cross-section for road work.
2. Demarcation of road on the layout plan and type of road to be provided. Distinguish roads,
ramps, open parking areas, paving etc.
3. Preparation of longitudinal and cross-section of the existing ground level with respect to TBM
4. Decide the layers in foundation (subgrade) and base course and wearing surface thickness (
for bituminous road 2” and for concrete road min 4” )
5. Decide the formation level with respect to plinth of buildings and approach road.
6. Balancing of cutting and filling area.
7. Decide the longitudinal slope, camber, super elevation etc.
B) SUB GRADE :
1. Initial ground level.
2. Excavated final ground level.
3. Murrum filling in layers and rolling by 8 to 10 ton roller.
4. Record final sub grade levels.
C) BASE COURSE : By Soling
1. Record initial levels laid.
2. Ensure the pipes are laid for cross-drain, electrical, drainage, water line and any other service
line.
3. Soling with stone laid on their edges and chips filled in voids properly of minimum 9”
thickness.
4. Width of soling 1’00” more than the width of road.
5. Rolling of the road by 8 to 10 ton roller.
6. Record final formation levels.
7. Soling and WBM should be completed minimum 2 months before for concrete roads.
- 37 -
D) BITUMINOUS ROAD (ON BASE COURSE) :
1. Record initial levels.
2. Spreading the grit as per specification.
3. Proper slope, gradient, camber.
4. Decide grouting pattern (semi grout, full grout) and weight of bitumen per square meter area.
5. Ensure spreading of grit when bitumen is hot. Ensure the compaction by roling.
6. Final levels.
E) TACK COAT, CARPET AND SEAL COAT (ON BASE COURSE) :
1. Record initial levels.
2. Decide weight of bitumen / sq.m. to be used.
3. Mixing of 20 mm & 12 mm metal with bitumen.
4. Spreading the mixture in uniform thickness.
5. Rolling when mix is hot.
6. Same procedure is to be adopted for seal coat (metal size smaller ¼”)
7. Record final level.
F) CONCRETE ROAD (ON BASE COURSE) :
1. Initial level about base course.
2. Drawings showing layout of slabs panels, expansion joints, construction joints.
3. Proper cleaning.
4. Channel thickness to match concrete thickness.
5. Grade of concrete / mix design.
6. Concreting in alternate bays. Area of each bay not to exceed 36 sq.meter.
7. Filler for expansion joints.
8. Needle vibrator and screed vibrator.
9. Mechanical trovelling and vacuum dewatering.
10. Broom finish.
11. Curing by ponding for minimum 10 days.
12. Filling bitumen 25 mm thick and deep in joints
13. Provision for speed breakers.
G) PAVING BLOCKS :
1. Approved drawings.
2. Levels to be decided.
3. Pattern of fixing to be decided.
4. Block fixed in proper line, level and pattern.
H) STORM WATER SYSTEM :
1. Approved drawings.
2. Ensure that the storm water drain is not connected to sewage line in any case.
3. Ensure that no turbulence is created at junctions.
4. Periodic cleaning / Pre monsoon precautions.
- 38 -
LANDSCAPE WORKS CL – 48
Check List :
1. Latest approved layout of total landscape works from landscape consultant and parent
architect.
2. For location and size of building and structures as Club House, Swimming Pool, Tennis
Court, Garden, Library Hall, Gymnasium, Other Games, Children’s Park, Entrance Gate,
Open Parking Place, Plantation refer to approved detail drawings of landscape of landscape
consultants and RCC
3. Civil construction works to be completed with reference to other check list of construction
activities.
4. Work order for specialized equipment along with, manufacturer’s specification, catalogues.
5. Work order for horticulture contractor, his scope of work, schedule of completion.
6. Arrangement for cutting, developing, manufacturing and watering of plants, lawns, and
shrubs area.
7. Maintainace contracts for swimming pools water purification plants play game equipment,
gymnasium equipment etc.
Check List :
Check List :
1. Ensure that the person who is cleaning the drainage line uses the rubber gloss, mask &
helmet.
2. Chamber to chamber cleaning by using steel rod.
3. Ensure that the chamber should be cleaned by wire brush & hand broom.
4. Clean the entire tank surface by using water twice and then ensure there is no wash water
inside.
5. Ensure that this procedure follows quarterly every year.
6. A.M.C. may be given to approved agency.
- 39 -
COLLECTION AND DISPOSAL OF
DRY GARBAGE / WET GARBAGE CL - 51
Check List :
1. For 100 kg wet garbage per day (approximately half kg / family / day), construct 7 bins of
size 8’ x 4’ x 2’6” (plastering is optional) over ground level along suitable part of the
compound wall.
2. Bins should be marked “Monday, Tuesday,…..” for efficient disposal.
3. Spread broken piece of bricks evenly at bottom of bins.
4. On the layer of bricks spread coconut fiber, dry leaves.
5. Instruct every flat owner to collect wet and dry garbage in separate bags or buckets.
6. Ensure that the person is appointed for collecting wastage from every house.
7. Ensure that the person collects wet and dry garbage separately.
8. Spread wet garbage inside bin (of respective day)
9. Sprinkle rock-dust on it.
10. On these layers sprinkle vermi ++ Biosanitizer (Biosanitizer is an enzyme used to process
biodegradable waste in simple and efficient manner).
11. Cover it with thin layer of garden waste.
12. Sprinkle ‘Sujala Biosanitizer’ water with a watering can evenly over entire bins. (Packet of
‘Sujala Biosanitizer’ to be left in watering can permanently)
13. Repeat the process in the next bin for next day.
14. Spread the waste wet in every day in the respective bin only, but every day sprinkle ‘Sujala
Biosanitizer’ water in all bins.
15. Ensure that the dry wastage is separate like paper and plastic for recycling and remaining
garbage dump into the PMC separate dust bin for dry garbage.
16. Ensure that the PMC container comes and collects all the wastage and dump into the depot
everyday.
17. A.M.C. may be given to approved agency.
LIFT MAINTENANCE CL – 52
Check List :
- 40 -
WORKING AND MAINTENANCE
OF FIRE FIGHTING EQUIPMENTS CL –53
Check List :
1. Ensure that OHWT capacity 10,000 liters serve for fire fighting.
2. Ensure that UGWT capacity 50,000 liters serve for fire fighting if applicable.
3. Ensure that 4” dia pipeline for each building in each one main valve & NRV at OHWT & 3
HP with back up pump is connected to the line. Hydrant valve with lugs for every floor to
attach delivery hose & branch pipe fire alarm system with control panel pill box & siren at
ground floor.
4. Ensure that the oiling to lungs assembly, Female coupling hydrant Spindles, Gate Valves
Spindle & pump checking for inner gaskets of hydrant valve & coupling.
5. Ensure that the Portable extinguisher for each building servicing fire extinguisher quarterly
done and yearly refilling and demonstration before refilling.
6. Ensure that Fire Drill System is done quarterly.
Check List :
1. Ensure display of instructions for use to maintain hygienic condition of swimming pool.
2. Ensure that the water sample is tested by test kit from pool for Ph & Chlorine content. Ph =
7.6 > 7.2 & Chlorine = 2.00 > 1.5
3. Ensure that the materials for cleaning swimming pool are
Chlorine = TCC Granules, Alum = Normal – Powder or Cub’s,
Hypo (liquid chlorine) = 12 %, Cooper Sulphate = Granules.
4. Ensure that the brushing is done to bottom of pool and all impurities are collected to deep end
of pool.
5. Ensure that the trolley pump section is done & outlet is connected to overflow trap which
goes to filtration plant & all impurities are collected in filtration plant & clean water goes to
pool.
6. Ensure that the back wash is done to filtration plant & filter is cleaned.
7. Ensure that the Risen of filter is done.
Dose for cleaning : Chlorine = 250 gm per day, Alum = 1.5 to 2.0 kg per four day, Hypo = 7
lit. Per day, C.S. = 1 kg per 15 days.
- 41 -
SAFETY MEASURES AT SITE CL – 55
C) First Aid
i. First Aid kit should be readily available.
ii. Administration of First-Aid.
iii. Information to ambulance.
iv. Shifting to nearby hospital.
v. Information to corporate office.
vi. Information to other concerned agency.
vii. Police, Fire Brigade etc
Due to unlimited use, sub-soil water level decreased. Due to building, roads, footpaths and concreting
deposition of rain water to subsoil water is reduced. To reinstate this water bank rain water harvesting
is absolutely necessary. This can be done by
- 42 -
b) Bore Well Method :
Roof top rain. Water may also be diverted to a bore well.
A settlement / filter tank of required size to be provided.
Overflow water may be diverted to a percolation pit nearby.
Recharge through bore well is less effective than open wells.
Defunct bore wells may also be used.
- 43 -
d) Recharge Well Method (Shallow / Small) :
Meant for large areas with heavy run-off
Size : 3’00” diameter with 5’0” – 10’0” depth.
Constructed with Brick / Concrete rings.
Side walls must be perforated.
Bottom (1’0”) is filled with brickbats.
Covered with RCC slab / manhole.
Suitable for sandy sub-soil area.
Note :
1. For area with clay / hard formations recharge wells with
diameter (5’0”) / depth (10’0” – 15’0”) has to be constructed.
2. Run-off water diverted through a filter media preferably.
3. One wall is sufficient for areas with one ground extent.
4. Rainwater from the open spaces may be diverted through mall
trenches.
- 44 -
e) Recharge trench with bore method :
Along the recharge trench boreholes has to be drilled.
Borehole interval, 10’0” – 15’0”
Suitable for clay area.
Notes :
1. Above structures are meant for area with large catchments like
Apartments / Big Complexes.
2. RCC slab cover is optional.
3. Top (1’00”) portion may be filled with sand.
- 45 -
g) Percolation Pit with Bore Method :
A borehole is to be drilled at the bottom of the percolation pit.
Bore hole size 150 – 300 mm diameter with 10’0” -15’0” depth. (approx.)
Filled with broken bricks / pebbles.
Suitable for clay area.
Note :
1. Above structures are meant for area with
small catchments like individual houses.
2. RCC slab cover is optional.
3. Top (1’00”) portion may be filled with
sand.
B) For Steel :
1. To be stacked on concrete block in different diameter stacks, diameter wise stock and labels.
2. Steel yard should have proper Access / Space for Vehicles, Fitters movement.
C) For Sand, Metal, Dust, Grit, Bricks, Concrete Blocks :
1. All above material should be stacked separately with avoiding direct contact with soil.
2. Should be stacked systematically for easy use and minimizes wastage.
- 46 -
G) For Flooring Material :
1. Should be stacked on leveled floor with locking arrangement and free from dampness.
2. Store separately, Quality Wise, Colour wise, Size wise
3. Store position and labels.
Note : All rejected materials should be kept separately with identification tags.
Records :
SAMPLING PLAN
Sr. Material Frequency Sampling Reference / Remarks
No. Plan Criteria
1 Cement Every truck 01 bag for For all Instructions for use
load every 100 criteria’s given of specific brand of
bags. in field test. cement to be
Random Format MT-01 obtained from
selection purchase dept..
2 Tor-steel For each 03 nos of 1 For all If fields test results
delivery & m length cut criteria’s given are not satisfactory
every dia of piece for in field test. send the samples for
steel, if wt each dia of Format MT-02 Laboratory test with
of each dia steel the approval of
is 500 kg received. purchase department
3 Binding Every 01 bundle For all ----
Wire Delivery criteria’s given
in field test.
Format MT-03
4 Bricks Every truck 03 bricks for For all If supplier and
load every 1000 criteria’s given source is same for
nos random in field test. more than one truck
selection Format MT–8 load in a single day,
then sampling from
one truck load is
enough.
5 Sand Every truck Sample from For all If supplier and
load central part criteria’s given source is same for
of the truck. in field test. more than one truck
Random Format MT-04 load in a single day,
selection then sampling from
one truck load is
enough.
6 Stone Every truck Sample from For all If supplier & source
Metal load central part criteria’s given is same for more
of truck in field test. than one truck load
Format MT-05 in a single day, then
sampling from one
truck load is enough.
7 Sanla Every 01 bag for For all If supplier & source
delivery every 50 criteria’s given is same for more
bags. in field test. than one truck load
Random Format MT-09 in a single day, then
selection
- 47 -
sampling from one
truck load is enough.
Sr. Material Frequency Sampling Reference / Remarks
No Plan Criteria
.
8 Ceramic / Every 05 tiles from For all As per sample
Glazed delivery / 2 each criteria’s given approved by
Tiles boxes for Random in field test Purchase
each 150 selection. Format MT-19 Department
boxes for
each brand
& for each
size.
9 Kota / Every Each Piece For all As per sample
Kadappa/ Delivery criteria’s given approved by
Tandur/ in field test. Purchase
Granite/ Format MT-20 Department
Marble
10 Mosaic Every 05 tiles from For all As per sample
Tiles & Delivery every 100 criteria’s given approved by
Chequered numbers. in field test. Purchase
Tiles Random Format MT-18 Department
selection.
11 M.S. Door Every Each Frame As specified in ----
Frame Delivery work order &
criteria’s given
in field test.
12 Timber / Every Each For all ----
Wood Delivery member criteria’s given
in field test.
Format MT-21
13 Flush Every Each Shutter For each ----
Doors Delivery criteria given
in field test
Format MT-07
14 Rolling Every Each Shutter As specified in ----
Shutter Delivery work order&
criteria’s in
field test
Format MT-12
15 Aluminum Every flat One piece of As specified in As per sample
windows and each section work order & approval by
& doors common used, criteria’s given purchase
area including in field test. department.
glass & Format MT-13
gasket
RECEIVING, INSPECTION AND TESTING :
CEMENT FT - 01
- 48 -
3 FINENESS TEST
a) Feeling the fineness after rubbing in Should feel silky
the fingures.
b) When hand immersed in the bag Should feel hot / warm.
4 FLOATING TEST Should float on water before sinking
5 TYPE OF BAG Jute / Polythene / Paper Bag
6 HANDLING & STORAGE a) Should be stacked / stored on raised
platform
b) Flooring should be damp proof
c) First in first out should be followed.
d) Max 10 bags should be stored in each stack
e) Receipt date of cement should be displayed.
f) Period of storage : Ensure use within 3
months avoid storage more than 2 months.
- 49 -
RECEIVING, INSPECTION AND TESTING :
SAND (FINE AGRREGATE) FT – 04
- 50 -
RECEIVING, INSPECTION & TESTING :
FLUSH DOOR FT – 07
- 51 -
RECEIVING, INSPECTION & TESTING :
INSTANT SANLA FT – 09
- 52 -
RECEIVING, INSPECTION & TESTING :
GLASS FIXING FT - 11
- 53 -
RECEIVING, INSPECTION & TESTING :
ALUMINUM WINDOWS FT – 13
- 54 -
(PIGEON HOLE TYPE DIAMETERWISE,
PROPERLY CLASSIFIED LIKE ELBOW, TEE,
ETC)
RECEIVING, INSPECTION & TESTING :
PLUMBING C.I PIPES & FITTINGS FT – 15
- 55 -
5 STORAGE & HANDLING DIAWISE SEPERATELY ON
WOODEN SLEEPERS
HORIZONTALLY.
AVOID ENDS ABUTTING EACH
OTHER.
- 56 -
8 THICKNESS NOT LESS THAN 5 MM
9 TOP FINISHING & GLAZE UNIFORM & GOOD
10 STORAGE / HANDLING 1) STACKING DONE LOTWISE,
COLOURWISE & SIZE WISE
2) FLOOR TO BE IN LEVEL
3) 1ST / PREMIUM & 2ND / COMMERCIAL
QUALITY SHALL BE STACKED
SEPERATELY.
4) STORED WITH LOCKING
ARRANGEMENTS
5) FLOOR SHALL BE FREE FROM
DAMPNESS
- 57 -
RECEIVING, INSPECTION & TESTING :
SHINGLE FT – 22
- 58 -
2 IMPURITIES SHOULD NOT CONTAIN FLACKY
PARTICLES
3 STORAGE SEPARATE CLEAN AREA.
AVOID DIRECT CONTACT WITH SOIL
- 59 -
FROM THE BUILDING DOES NOT FALL ON
THE STACK.
- 60 -
RECEIVING, INSPECTION AND TESTING :
R.C.C. DOOR FRAMES MT – 29
- 61 -
Design Variables in Mix Design :
A. Water Cement Ratio
B. Cement Content
C. Proportion of Fine & Coarse aggregate.
D. Use of Admixtures.
Cement Content
Cement is the core material in concrete which acts as a binding agent and imparts strength to the
concrete. From durability considerations cement content should not be reduced below 290 kgs / m3
considering moderate conditions of exposure. IS 456 recommends higher cement contents for more
severe conditions of exposure of weathering agents to the concrete. It is not necessary that higher
cement content would result in higher strength. Higher cement content helps us in getting the desired
workability at a lower water cement ratio.
Proportion of fine aggregate to coarse aggregate is decided with the help of the gradation curves.
The coarse aggregate of 20 mm & 10 mm are generally used for concreting. 20 mm coarse aggregate
is defined as the one, which passes through 20 mm sieve and is retained on 10 mm sieve. While 10
mm metal should pass the 10 mm IS sieve and should be retained on 4.75 mm sieve. Some common
problems to metal available in Pune are as follows :
1. The metal has considerable proportion of over-size aggregates varying from 20 mm to 40 mm
size.
Generally when the sand is fine, smaller proportion of it is enough to get a cohesive mix, while
coarser the sand, greater has to be its proportion in the concrete.
Excess sand increases the water requirement of concrete & reduces the strength, while under – sandy
mix results in segregation and honey combed concrete.
Generally sand available in Pune is very coarse (FM > 3.2) and needs to be blended with fine particles
(like stone dust) to get a cohesive mix.
Use of Admixtures
Now a day’s admixtures are rightly considered as a fourth ingredient of concrete. Use of plasticizers is
essential to control the water cement ratio on site. Plasticizers help us in increasing the workability of
concrete at lower water cement ratio. Hence we can achieve much higher strength at the same cement
content. Use of plasticizers is economical as the cost incurred on them is less than the cost of cement
saved. This is made possible by mix design.
- 62 -
6. 250 ml measuring cylinder.
7. Forms of various sizes.
Note : If any of the above conditions are not satisfied a trial mix should be conducted at laboratory to
determine fresh proportions.
Water cement ratio = (water added per batch + Surface moisture in sand – absorption of
coarse aggregate) / 50
- 63 -
To get a rough estimate of surface moisture following thumb rule may be used when sand is
not extremely wet.
Water to be added per batch = (water cement ratio * 50) – Surface moisture * wt. of sand per
batch
If moisture content = 4 %
Wt of sand = 135 kgs
Water-cement ratio = 0.55
Water to be added per batch = 0.55 * 50 – 4 % * 135
= 27.5 – 5.4
= 22.11 liters
Weight of sand per batch should be increased correspondingly by wt. of surface moisture in
sand e.g. 5.4 kgs
Moisture content in sand will vary from day to day and also with different lots of sand. It is
therefore very important to make corrections for moisture in sand to maintain w/c ratio. If
slump on site is kept under control, the water cement ratio is automatically controlled.
FINDING AGGREGATE ABSORPTION :
For any mix design, the coarse aggregate is considered to be in saturated surface dry
condition. Whereas the metal on sites is often in bone dry condition (especially in summers).
This dry aggregate often absorbs the water added in concrete & reduces the workability of
concrete. Correction for surface absorption is necessary to maintain the water cement ratio. A
correction of 1 % to 2 % of coarse aggregate may be made in case of bone dry condition of
aggregate. For example if the aggregate absorption is 2 % and water and total weight of
aggregates is 180 kgs then
Aggregate absorption = 0.02 * 180
= 3.6 liters.
Hence quantity of water added (from previous example) = 22.1 + 3.6
= 25.7
- 64 -
Bulk density = 58 / 35 = 1.66 kgs / liters.
Volume of sand per batch = wt. of aggregate per batch
------------------------------
Bulk density
VOLUME BATCHING
For example, if weight of sand per batch = 135 kgs.
Volume of sand = 135 / 1.66 = 81.3 liters, say 80 liters.
Hence use 2 forms of 25 liters & one form of 30 liters. Bulk density of sand changes with
bulkage. Hence correction for bulk density of sand should be made every day.
Bulk density of metal is between 1.4 kg / lit to 1.5 kg / lit whereas bulk density of sand varies
with bulkage and usually lies between 1.6 to 1.8 kg / lit.
A. WEIGHT BATCHING
i. Increase in the weight of sand up to 15 kgs and reduce the weight of
metal by equal quantity. Total weight of aggregate going per batch
should remain constant.
ii. If the mix does not improve with above correction, replace up to 15
kgs of sand by dust in the weights mentioned in the design.
- 65 -
B. VOLUME BATCHING
i. Increase the volume of sand by 10 liters and reduce volume of metal
by 10 lit.
ii. If the mix does not improve with above correction replace 10 liters of
sand in mix design proportion by 10 lits of dust.
Stone dust should not be too fine or powdery ( FM should be between 2.0 to 2.5 )
It should be used used in limited quantity as mentioned above unless, higher quantity
is recommended by the laboratory.
Strict control on water cement ratio should be kept. Stone dust reduces the
workability; hence the water cement ratio is likely to increase. The slump may be
maintained 2 cms below the value given in the mix design.
Note : If above corrections in the proportion do not yield satisfactory mix, fresh trial should
be conducted at the laboratory for a revised mix design.
DUROCRETE
Engineering Services Pvt. Ltd.
1160 / 5, Shivaji Nagar, Gharpure Colony, Pune – 411 005
Telefax - 25520456, 25534335
Date : 29 Jan. 2005
MIX DESIGN SHEET
Name :
Purpose of Experiment : Mix design for M15 grade of concrete
Site :
Brand of Cement : Ultratech 43 Grade.
* Corrections for moisture content in sand & aggregate absorption in metal should be
made on water / cement ratio (Refer our mix design manual)
* Any change in material like cement, plasticizer, sand or aggregate would require re-
validation of design.
- 66 -
* The volumetric proportion are rounded of to nearest 5 liters, however, in case of
volume batching, weight to volume conversion should be done on the basis of Dry Loose
Bulk Density of ingredients actually found out at site.
* The above mix design requires certain control practices on site to ensure results.
DUROCRETE
Engineering Services Pvt. Ltd.
1160 / 5, Shivaji Nagar, Gharpure Colony, Pune – 411 005
Telefax - 25520456, 25534335
Date : 22 Oct. 2004
MIX DESIGN SHEET
Name :
Purpose of Experiment : Mix design for M20 grade of concrete
Site :
Brand of Cement : Vasavadatta 43 Grade
- 67 -
K = Himsworth Constant which is 1.65 for 5 % results to fall below the characteristic
strength.
Standard Deviation Assumed = 4 N / mm2 (As per IS 456 – 2000 )
Table 8, Clause 9.2.4.2
Target Mean Strength = 20.00 + 1.65 x 4 = 26.60 N/mm2
DUROCRETE
Engineering Services Pvt. Ltd.
1160 / 5, Shivaji Nagar, Gharpure Colony, Pune – 411 005
Telefax - 25520456, 25534335
Date : 22 Oct. 2004
MIX DESIGN SHEET
Name :
Purpose of Experiment : Mix design for M25 grade of concrete
Site :
Brand of Cement : Vasavadatta 43 Grade
* Corrections for moisture content in sand & aggregate absorption in metal should be
made on water / cement ratio (Refer our mix design manual)
* Any change in material like cement, plasticizer, sand or aggregate would require re-
validation of design.
* The volumetric proportion are rounded of to nearest 5 liters, however, in case of
volume batching, weight to volume conversion should be done on the basis of Dry Loose
Bulk Density of ingredients actually found out at site.
* The above mix design requires certain control practices on site to ensure results.
- 68 -
DUROCRETE
Engineering Services Pvt. Ltd.
1160 / 5, Shivaji Nagar, Gharpure Colony, Pune – 411 005
Telefax - 25520456, 25534335
Date : 15 Sept. 2006
MIX DESIGN SHEET
Name :
Purpose of Experiment : Mix design for M30 grade of concrete
Site :
Brand of Cement : Coromandal 43 Grade
- 69 -
DUROCRETE
Engineering Services Pvt. Ltd.
1160 / 5, Shivaji Nagar, Gharpure Colony, Pune – 411 005
Telefax - 25520456, 25534335
- 70 -
10 mm 3 0.30 0.30 99.70
4.75 mm 19 1.90 2.20 97.80
2.36 mm 233 23.30 25.50 74.50
1.18 mm 200 20.00 45.50 54.50
600 micron 191 19.10 64.60 35.40
300 micron 100 10.00 74.60 25.40
150 micron 85 8.50 83.10 16.90
75 micron 100 10.00 93.10 6.90
Pan 69 6.90 100.00 0.00
Total 1000
F.M. = 2.958
20 mm Metal
Specific Gravity = 2.872
Water Absorption = 1.21 %
Flakiness Index = 21.05 %
Loose Bulk Density = 1.44 kg / lit (for conversion to volumetric)
Sieve Size Wt. (gm) Wt. Cumu. Wt. Cumu. IS Passing
Retained Retained % Retain % Passing % % Limits
40 mm 0 0.00 0.00 100.00 100
25 mm 0 0.00 0.00 100.00 ----
20 mm 290 14.50 14.50 85.00 85 to 100
16 mm 806 40.30 54.80 45.20 ----
12.5 mm 689 34.45 89.25 10.75 ----
10 mm 191 9.55 98.80 1.20 0 to 20
Pan 24 1.20 100.00 0.00 ----
Total 2000
- 71 -
- 72 -
- 73 -
- 74 -
EQUIVALENT UNITS / CONVERSION TABLES
A) LINEAR MEASUREMENTS :
Sr. No. Unit Equivalent Unit
1 1 Kilometer 1000 Meter
2 1 Kilometer 0.62 Miles
3 1 Meter 100 Centimeters
4 1 Meter 3.28 Feet
5 1 Meter 1.093 Yards
6 1 Centimeter 10 Millimeter
7 1 Centimeter 0.393 Inch
8 1 Mile 8.00 Furlong
9 1 Furlong 220 Yards
10 1 Yard 3 Feet
11 1Mile 5280 Feet
- 75 -
B) WEIGHT MEASUREMENTS :
Sr. No. Unit Equivalent Unit
1 1 Tonne 1000 Kilogram
2 1 Kilogram 1000 Grams
3 1 Kilogram 2.205 Pounds
4 1 Quintal 100 Kilogram
5 1 Gram 0.086 Tola
6 1 Ounce 28.35 Grams
C) AREA MEASUREMENTS :
Sr. No. Unit Equivalent Unit
1 1 Sq. Kilometer 106 Sq. Meter
2 1 Sq. Kilometer 0.386 Sq. Miles
3 1 Sq. Meter 10000 Sq. Centimeter
4 1 Sq. Meter 10.76 Sq. Ft.
5 1 Acre 40 Guntha
6 1 Guntha 1089 Sq.Ft.
7 1 Acre 43560 Sq.Ft.
8 1 Acre 4047 Sq. Meter
9 1 Hector 100 Are
10 1 Are 100 Sq. Meters
11 1 Hector 10000 sq. Meters
12 1 Hector 2047 Acre
13 1 Brass 100 Sq.Ft.
14 1 Brass 9.29 Sq. Meter
15 1 Acre 4840 Sq. Yards
D) VOLUME MEASUREMENTS :
WEIGHT’S OF MATERIALS
- 76 -
12 Cement Mortar 2080
13 Lime Mortar 1760
14 Lime 640
15 Glass 2530
16 Teak Wood 670 to 830
17 Sal Wood 990
18 Marble Stone 2620
19 Granite Stone 2460 to 2800
20 Cuddappah 2720
21 A.C. Sheet (Corrugated) 16 kg / sqm
22 Bitumen 1040
USEFUL NOTES ON CEMENT
1 cu.ft. of 1 loose Portland Cement with 1 part of sand will cover 16.8 sq.ft. 1” thick
1 cu.ft. of 1 loose Portland Cement with 2 part of sand will cover 29 sq.ft. 1” thk.
1 cu.ft. of 1 loose Portland Cement with 3 part of sand will cover 35.7 sq.ft. 1” thick
1 cu.ft. of loose Portland Cement with 6 parts of sand will lay about 410 bricks with 3/8” joints and
527 bricks with 1/4” joints
- 77 -
For External Plaster 0.15 cum 0.50 cft
For Tiling 0.04 cum 0.13 cft
For Water-Proofing 0.03 cum 0.09 cft
For Others 0.01 cum 0.02 cft
Total 0.72 cum 2.35 cft
4 Metal For RCC work 0.27 cum 0.90 cft
5 Rubble For Plinth Soling 0.06 cum 0.20 cft
6 Murrum For Plinth Filling 0.23 cum 0.75 cft
7 Bricks 6” For Ext. Wall (6” thk.) 43 nos 04 nos
(Thokla) For Int. Wall (6” thk.) 32 nos 03 nos
Total 75 nos 07 nos
8 Sunla For Internal Plastering 0.27 bag 0.025 bag
9 Flooring For all rooms and 0.75 sqm 0.75 sq.ft
Tiles balcony/terrace flooring
10 Skirting For all rooms and 0.25 rm 0.25 rft
balcony/terrace flooring
11 Bath/Toilet For Flooring 0.05 sqm 0.05 sq.ft.
Dado 0.20 sqm 0.20 sq.ft.
12 Kitchen ---- 0.04 rm 0.012 rft
Platform
13 Parking Parking Area 0.15 sqm 0.15 sq.ft.
Flooring
14 Staircase For Risers 0.014 sqm 0.014 sq.ft.
stone For Trades 0.028 sqm 0.028 sq.ft.
flooring For Landings 0.022 sqm 0.022 sq.ft.
Total 0.084 sqm 0.084 sq.ft.
Sr. Material Item of Work Quantity / Quantity /
No. Sq.M. Sq.Ft.
15 Brick bats For Water-Proofing 0.03 cum 0.10 cft
16 Door ---- 0.09 nos 0.0085 nos
Frames
17 Door ---- 0.14 sqm 0.14 sq.ft
Shutters
18 Concrete For Staircase 0.03 sqm 0.03 sq.ft
Grills
- 78 -
15 Sheet Roofing 2%
16 Tile Roofing 5%
17 Floor Tiling 2 to 5 %
18 Wall Tiling 3%
19 Pigments 5%
20 Paints 5%
- 79 -
Activity Percentage Cost Break-Up (Labour)
RCC 37 %
Brick work and Plaster 21 %
POP 7%
Tiling 12 %
Plumbing and Sanitation 3%
Doors 1%
Water Proofing 3%
Painting 8%
Electrical 8%
TOTAL 100 %
Material cost = 76 %
Labour Cost = 24 %
- 80 -
(B) MASONARY ITEMS :
S. Description Unit Cement Sand Rubble Bricks Bricks
N. Per 23x10x7 23x15x9
cm cm
1 U.C.R. 100 4.5 bags 40 cft 125 cft -- --
Masonry cft
In C.M. 1:6 1 1.6 bags 0.4 cum 1.25 cum
cum
2 23 cm (9”) 100 2.5 bags 20 cft -- 1000 nos --
B.B. sft
Masonry 1 0.27 bag 0.06 cum -- 110 nos --
In C.M. 1:5 sqm
3 15 cm (6”) 100 1.5 bags 15 cft -- -- 400 Nos
B.B. sft
Masonry 1 0.16 bag 0.05 cum -- -- 45 Nos
In C.M. 1:5 sqm
4 10 cm (4”) 100 1 bags 8 cft -- 475 nos --
B.B. sft
Masonry 1 0.11 cum 0.025 -- 50 nos --
In C.M. 1:4 sqm cum
- 81 -
4 SAND FACED PLASTER
DOUBLE COAT 20 TO 25 MM THK
a) in C.M. 1:4 100 sft 3.75 bags 28 cft ---
1 sqm 0.41 bags 0.09 cum ---
b) in C.M. 1:5 100 sft 3.00 bags 28 cft ---
1 sqm 0.32 bags 0.09 cum ---
c) in C.M. 1:6 100 sft 2.50 bags 28 cft ---
1 sqm 0.27 bags 0.09 cum ---
- 82 -
(E) WATER PROOFING :
Sr. Description Unit Per Cement Sand Brickbat
No.
1 Brickbat Coba 100 sft 6.00 bags 30 cft 30 cft
Water Proofing in 1 sqm 0.65 bags 0.09 cum 0.09 cum
W.C. / Bath / Toilet
2 Etc 100 sft 4.00 bags 30 cft 30 cft
Brickbat Coba 1 sqm 0.43 bags 0.09 cum 0.09 cum
Water Proofing to
Terrace
Notes : 1) Crushed Sand and Natural sand should confirm to RCC acceptance
criteria
2) Mortar to be used within 45 minutes of addition of water.
- 83 -
2. Density of Steel = 7850 kg / meter3
3. Weight of Steel = Density x cross-sectional area of bar (in mm2)
e.g. For 20 mm square bar : Wt. = (7850 x 10-6) x 400 = 3.140 kg / meter
- 84 -
ISMB 550 103.7 132.11 550 190 19.3 11.2
ISMB 600 122.6 156.21 600 210 20.8 12.0
INDIAN STANDARD ROLLED STEEL CHANNELS
- 85 -
ISA 6565 65 x 65 5.5 4.9
6.0 5.8
8.0 7.7
10.0 9.4
DESIGNATION SIZE THICKNESS WEIGHT /
hXb OF FLANGE METER
mm X mm ‘t’ mm ‘w’ (Kg)
ISA 7070 70 x 70 5.0 5.3
6.0 6.3
8.0 8.3
10.0 10.2
ISA 7575 75 x 75 5.0 5.7
6.0 6.8
8.0 8.9
10.0 11.0
ISA 8080 80 x 80 6.0 7.3
8.0 9.6
10.0 11.8
12.0 14.0
ISA 9090 90 x 90 6.0 8.2
8.0 10.8
10.0 13.4
12.0 15.8
ISA 100100 100 x 100 6.0 9.2
8.0 12.1
10.0 14.9
12.0 17.7
ISA 110110 110 x 110 8.0 13.4
10.0 16.5
12.0 19.6
15.0 24.2
ISA 130130 130 x 130 8.0 15.9
10.0 19.7
12.0 23.4
15.0 28.9
ISA 150150 150 x 150 10.0 22.8
12.0 27.2
15.0 33.6
18.0 39.9
ISA 200200 200 x 200 12.0 36.6
15.0 45.5
- 86 -
20.0 3.0 0.471
4.0 0.628
5.0 0.785
6.0 0.942
25.0 3.0 0.589
4.0 0.785
5.0 0.981
6.0 1.18
30.0 3.0 0.707
4.0 0.942
5.0 1.18
6.0 1.41
35.0 3.0 0.824
4.0 1.10
5.0 1.37
6.0 1.65
40.0 3.0 0.942
4.0 1.26
5.0 1.57
6.0 1.88
MS PLATES (PLAIN)
THICKNESS WEIGHT
mm KG / SQ.M.
5.0 39.25
6.0 47.10
8.0 62.8
10.0 78.5
12.0 94.2
14.0 109.9
16.0 125.6
18.0 141.3
20.0 157.00
22.0 172.70
25.0 196.25
- 87 -
1.40 11.00
1.60 12.60
1.80 14.10
1.90 14.90
2.0 15.70
2.24 17.60
2.50 19.60
2.80 22.00
3.15 24.70
3.55 27.86
4.0 31.40
4.30 33.75
4.65 36.50
STEEL TUBES FOR STRUCTURAL PURPOSE
- 88 -
Gauge of Ply Gauge of Gap between Approx. Wt. Approx.
Barbs two Barbs Kg. / meter Length in
25 Kg.
bundle (m)
12 12 75 mm (3”) 0.166 151
14 14 75 mm (3”) 0.083 300
12 14 100 mm (4”) 0.119 210
12.5 12 75 mm (3”) 0.135 185
12.5 14 75 mm (3”) 0.119 210
GAUGE CONVERSION TO MM
- 89 -
2470-1985 (Part I & II) Code of Practice for Septic Tanks
2502-1963 Code of Practice for Bending and Fixing of bars for
Concrete Reinforcement
2751-1979 Code of Practice for Welding of Mild Steel bars used
for Reinforcement Cement Concrete Construction
2911 (Part I to IV) Code of Practice for Design and Construction of Pile
and Pile Foundations
3370 (Part I to IV) Liquid Retaining Structures
3414-1968 Expansion Joints
3696 (Part I & II) Safety Code for Scaffolds and Ladders
3764-1992 Safety Code for Excavation work
I.S. CODE TITLE
3812-1981 Fly Ash for use as Pozzolana and Admixture
4082-1996 Storage of Materials
4326-1993 Ductile Design for Earthquake Structures
4925-1968 Battening of Concrete
4926-2003 Ready Mixture Concrete
6313 (Part I to III) Anti-termite Measure in Building
7969-1975 Safety Code for Storage and Handling of Building
Materials
8041-1990 Rapid Hardening Portland Cement
8112-1989 43 Grade Ordinary Portland Cement
9103-1999 Admixtures
11817-1986 Construction Joints
12089-1987 Ground Granulated Blast Furnace Slag
12269-1987 53 Grade Ordinary Portland Cement
13311-1992 (Part I & II) Non-Destructive Testing
13920-1993 Ductile Design for Earthquake Structures
14687-1999 Formwork Design and Detailing
- 90 -
LIST OF ARCHITECT’S & CONSULTANT’S WITH PHONE NUMBERS
LIST OF ARCHITECTS :
- 91 -
Design Systems 25658851 --- 25630851 design_systems407@
Ar. Pankaj yahoo.com
Sanghavi, Pune
Ar. Dilip Kale, 24478869 --- 24478869 archdgk@yahoo.co.in
Pune
Savli Architects 24321908 9822035973 24336964 savliarchitects@gmai
Ar. Hingmere, l.com
Pune
Dandekar & 25468923 --- 64001002 dandekar.associates
Associates @gmail.com
Ar. Sapre- rsapre@vsnl.com
Dandekar, Pune
Atul 27033137 9822268190 27033137` ---
Dharwadkar &
Associates
Ar. Atul
Dharwatkar,
Pune
Infinity 24209110 9890122511 24209110 id_infinity11@rediff
Ar. Ajinkya mail.com
Dhumal, Pune Idajinky11@rediffma
il.com
Skyline 30404010 / 9820198904 24944868 lakshmigovekar@yah
Architects 11 oo.com
Ar. L. Govekar, skyline.architects@g
Mumbai mail.com
Ethique ethiquepune@hotmai
Ar. Sanjeev 9820231285 l.com
Mehta, Pune 24333803 ethique@hotmail.co
Mumbai 25004533 25005978 m
P.G. Patki 22047014 9820509309 22047014 pgpatki@vsnl.com
Architects P. Ltd pgpatki@gmail.com
Ar. P.G.Patki,
Mumbai
Ar. Reza Kabul, 26439415 --- --- ---
Mumbai 26430146
Ar.Padalikar, 222940 9823038972 222940 pnpadali@yahoo.com
Alibaugh 9822081003
LANDSCAPE ARCHITECTS :
Vikas & Nilima 25450700 9822012204 25450702 vikasbhosekar@yaho
Bhosekar, o.co.in
Ar. Vikas bhosekar@vsnl.com
Bhosekar, Pune
- 92 -
Hansal Parikh & 25675562 9890046867 25675564 hansal@hansalpari
Asso, Pune kh.com
Arun Gokhale & 24466802 9822033263 24466802 nykochak@vsnl.net
Associates, Pune erang@sancharnet.i
n
Y. S. Sane 24338391 9822013113 24333394 saneasso@ph2.vsnl
Asso., Pune 24336392 A.N. Watwe .net.in
gramo.s@yssa.in
- 93 -
Fire-Fighting Office Mobile No. Fax No. E-mail ID
Consultant Phone No.
Sujay Fire 24263310 9423001051 24263310 jayesh@sujayfire.c
Jayesh om
Phulpajar,Pune
Sumeet 25380170 9822495357 25380170 sumeetenterprises
Enterprises, 25380199 @vsnl.net
Mohan Jadhav,
Pune
- 94 -
IMPORTANT TELEPHONE NUMBERS
AMBULANCE 101
Sai Ambulance 24215208 / 24215308
Nandadeep 25533496 / 25536519
Rugnaseva 24217672
Kolumbus 25531146 / 25532630
Pune Medical Foundation’s (Ruby Hall) 26123391
Deendayal Memorial Hospital 25652497
HOSPITALS
K.E.M. Hospital 26125600 / 26125601
Ruby Hall Clinic 26123391
Jahangir Hospital & Medical Center 26122551 / 26122552
Kulkarni Endo-surgery Institute 25448554
Poona Hospital 24331707
Krishna General Hospital 25460625 / 6 / 7
Joshi Hospital 25676861 / 25672563
Bharati Hospital 24375182
Seventh Day Adventist 24261926
Mission Hospital 24261619
Deendayal Memorial Hospital 25652497 / 25651613
Lokmanya Hospital 27456496 / 7 / 8
Inlax & Budhrani Hospital 26129080 / 82
- 95 -
Doctor Ambedkar Cantonment 26350530
Sasoon General Hospital 26128000
Hardikar Hospital 25535326 / 27
Aditya Birla Memorial Hospital 30717777 / 30717500 / 1 / 2
BLOOD BANKS
Ruby Hall Clinic 26136318
Achrya Aanadrishiji Blood Bank 24337627
Indian Serological Institute 24335244
Indian Red Cross 26120950
Navjeevan 24480341
Lokmanya Hospital 27459222
Inlax & Budhrani Hospital 26129080 / 82
Sasoon General Hospital 26128000 (Ext. 364)
DAY-NIGHT CHEMISTS
Poona Medical Foundation 26123391 (Ext. 263)
(Ruby Hall Clinic) (Ext. 346)
K.E.M. Medical Stores 26133176 / 5600 (Ext. 370)
Krishna Medical stores 25448934
Poona Hospital Medical Stores 24338768 / 24331076 (Ext. 215)
Deendayal Memoriyal Hospital 25652497 / 25651613
- 96 -