Anda di halaman 1dari 13

Survey Harga Dasar - Form.

23 PNPM-Mandiri Perdesaan

HASIL SURVEI HARGA BAHAN/ALAT

Kegiatan : Jemb. Gantung

NAMA DAN ALAMAT TOKO/SUPLIER Ongkos


Unit / Harga rata2 Total Harga
NO. JENIS BAHAN/ALAT Transport ke KET
Satuan SINAR MAKMUR (Rp.) Satuan (Rp.)
BERKAT JAYA lokasi
TERANG JAYA
1 2 3 4 5 6 7 = (4+5+6)/3 8 9 = (7+8) 10

A. BAHAN :
1 Semen sak - - - 65,000 2,000 67,000
2 Pasir Pasang m3 70,000 - 70,000
3 Tanah Urug m3 50,000 - 50,000
4 Kerikil m3 125,000 - 125,000
5 Batu Gunung m3 100,000 - 100,000
6 Kayu, 5/5 cm Ujung 17,500 2,000 19,500
7 Kayu 5/7 Kls II Ujung 24,500 2,000 26,500
8 Kayu kelas I, 8/12 cm Ujung 70,000 2,000 72,000
9 Papan Lantai 5/25 Kls I Ujung 87,500 2,000 89,500
10 Papan Mall Ujung 20,000 2,000 22,000
11 Kabel Utama 1" M 90,000 5,000 95,000
12 Kabel Seling f 1/2 M 40,000 5,000 45,000
13 Warfel Kabel Utama Bh 50,000 - 50,000
14 Warfel Kabel Seling Bh 45,000 - 45,000
15 Katrol Bh 250,000 - 250,000
16 Mur + Baut balok Psg 10,000 - 10,000
17 Kuku Macan Bh 20,000 - 20,000
18 Besi pengantung Ø 16 mm Ujung 20,000 - 20,000
19 Besi Siku, 50,50,5 mm Ujung 400,000 - 400,000
20 Besi dia. 12 mm Ujung 75,000 2,000 77,000
21 Besi dia. 10 mm Ujung 65,000 2,000 67,000
22 Besi dia. 8 mm Ujung 19,000 2,000 21,000
23 Besi dia. 6 mm Ujung 15,000 2,000 17,000
24 Kawat Bendrat kg 20,000 - 20,000
25 Paku campur kg 20,000 - 20,000
26 Cat Kayu kg 37,500 - 37,500
Survey Harga Dasar - Form. 23 PNPM-Mandiri Perdesaan

NAMA DAN ALAMAT TOKO/SUPLIER Ongkos


Unit / Harga rata2 Total Harga
NO. JENIS BAHAN/ALAT Transport ke KET
Satuan SINAR MAKMUR (Rp.) Satuan (Rp.)
BERKAT JAYA lokasi
TERANG JAYA
1 2 3 4 5 6 7 = (4+5+6)/3 8 9 = (7+8) 10

27 Paralon 2 Inchi Ujung 45,000 - 45,000


28 Pelat Klem Besi Bh 2,500 - 2,500
29 Besi angker di las Bh 150,000 - 150,000
- -
B. ALAT : - -
1 Cangkul bh 40,000 - 40,000
2 Linggis Bh 30,000 - 30,000
3 Sekop bh 65,000 - 65,000
4 Kunci Sok Set 250,000 - 250,000
5 Kunci Pas + Ring Set 250,000 - 250,000
6 Gergaji bh 45,000 - 45,000
7 Gergaji Besi bh 45,000 - 45,000
8 Martil bh 40,000 - 40,000
9 Kuas cat tembok bh 13,000 - 13,000
10 Kuas cat kayu bh 6,000 - 6,000
11 Takal Hr 100,000 - 100,000
12 Ember bh 10,000 - 10,000
-
C. UPAH : -
1 Pekerja HOK 35,000 - 35,000
2 Tukang HOK 50,000 - 50,000
Basic Price PNPM-Mandiri Perdesaan

DAFTAR
HARGA SATUAN DASAR UPAH & BAHAN

Desa Jenis Kegiatan : Sarana/Prasarana


Kecamatan Nama Kegiatan : Jembatan Gantung
Kabupaten Volume : 1 Unit

Ongkos Nilai Harga


Unit / Harga Satuan
No Uraian Transport ke Satuan di KET
Satuan (Rp.)
Lokasi (Rp.) Lokasi (Rp.)

1 2 3 4 5 6=4+5 7

A BAHAN :
1 Semen Zak 65,000 3,000 68,000
2 Batu M3 95,000 - 95,000
3 Psr p M3 100,000 - 100,000
4 Psr U M3 65,000 - 65,000
5 Besi d Ujg 63,000 3,000 66,000
6 Besi d Ujg 47,000 3,000 50,000
7 Besi d Ujg 25,000 3,000 28,000
8 Keriki M3 100,000 - 100,000
9 Bendr Kg 20,000 - 20,000
10 Angkur Bout dia. 10 mm (L=25 cm) Set 10,000 - 10,000
11 Angkur Bout dia. 10 mm (L=15 cm) Set 8,000 - 8,000
12 Paku Kg 20,000 - 20,000
13 Kayu k Lbr 20,000 3,000 23,000
14 Kayu klas II uk. 10/10 cm, L=1.7 m' Bh 30,000 3,000 33,000
15 Kayu klas II uk. 6/10 cm, L=4 m' Ujg 41,500 3,000 44,500
16 Kayu klas II uk. 6/8 cm, L=4 m' Ujg 33,000 3,000 36,000
17 Kayu klas II uk. 5/7 cm , L=4 m' Ujg 24,500 3,000 27,500
18 Kayu k Ujg 17,500 3,000 20,500
19 Kayu papan klas I, uk. 5/25 cm, L=1.5 Bh 33,000 3,000 36,000
20 Kabel M' 93,000 - 93,000
21 Kabel seling penguat angin dia. 1/2" M' 44,000 - 44,000
22 Warfel (pen) pengaku kabel Bh 50,000 - 50,000
23 Kuku Bh 20,000 - 20,000
24 Kausi Bh 30,000 - 30,000
25 Kausi Bh 15,000 - 15,000
26 Katrol Bh 250,000 - 250,000
27 Plamir tembok Kg 10,000 - 10,000
28 Cat t Kg 10,000 - 10,000
29 Cat k Ltr 37,500 - 37,500
30 Cat besi Ltr 37,500 - 37,500
31 Cat Dasar/Meni Ltr 25,000 - 25,000
32 Thinner Ltr 15,000 - 15,000
33 PVC di Ujg 45,000 - 45,000
34 Besi s Ujg 400,000 - 400,000
35 Klem plat besi kabel utama (pengunci) Unit 2,500 - 2,500
36 Jangkar kabel dilas Unit 75,000 - 75,000

B ALAT :
1 Selang air & benang nilon Set 20,000 - 20,000
Basic Price PNPM-Mandiri Perdesaan

Ongkos Nilai Harga


Unit / Harga Satuan
No Uraian Transport ke Satuan di KET
Satuan (Rp.)
Lokasi (Rp.) Lokasi (Rp.)

1 2 3 4 5 6=4+5 7

2 Skop Bh 65,000 - 65,000


3 Cangkul Bh 40,000 - 40,000
4 Ember cor Bh 10,000 - 10,000
5 Linggis Bh 30,000 - 30,000
6 Takle (alat katrol) Hari 100,000 - 100,000
7 Kunci shock Set 100,000 - 100,000
8 Kunci pas+ring Set 100,000 - 100,000
9 Kuas cat tembok Bh 13,000 - 13,000
10 Kuas cat kayu Bh 6,000 - 6,000
11 Kertas pasir lbr 6,000 - 6,000
12 Martil Bh 40,000 - 40,000
13 Gergaji kayu Bh 45,000 - 45,000
14 Gergaji besi Bh 45,000 - 45,000

C UPAH :
1 Pekerja HOK 35,000 - 35,000
2 Tukang HOK 50,000 - 50,000
PNPM - Mandiri Perdesaan 5 / 13

Kabupaten : Jenis : Jemb. Gantung


Kecamatan : Take Of Sheet Lokasi : Dsn.III
Desa : Volume : 1 unit

Gambar Hitungan Volume

Bentang jembatan ( L= 21 m') I. PEKERJAN PERSIAPAN


1.1. Pekerjaan Pembersihan Lokasi&Bowplank 1.00 Ls

II. PEKERJAAN TANAH


2.1. Pekerjaan Galian Tanah STRUKTUR
a. Galian Tnh Pondasi angkur kabel utama :
( 2.50 x 2.50 ) x 3 m' x 2 bh 37.50 m3
b. Galian Tnh Pondasi kabel angin (penguat)
( 2.25 x 2.50 ) x 2 x 4 bh 45.00 m3
c. Galian Tnh Pondasi Tiang Pilon
( 3.50 x 5.40 ) x 3.75 + ( 3.50x5.40 ) x 2.50 118.13 m3
200.63 m3
2.2. Pekerjaan Galian Tanah Biasa
a. Galian Tnh Pondasi talud
( 0.70 x 0.75 x 13 ) x 2 13.65 m3

2.3. Pekerjaan Timbunan Tanah


a. Timb. Tnh Pondasi Pilon utama :
Volume galian - volume pasangan
118.1 - 68.60 49.53 m3
b. Timb. Tnh Pondasi angkur kabel utama :
( 0.25 x2 x 3 ) x 2 3.00 m3
(( 0.75+0.25 )/2 x 1x3 ) + ( 0.75x1x3) + (0.5x.50x0.50x3)) x 2 8.25 m3
c. Timb. Tnh Pondasi angkur kabel angin :
( 0.25 x2 x 2 ) x 4 4.00 m3
((0.75+0.25 )/2x1x2) + (0.75x1x2x4) + (0.50x0.50x0.50x2)) x 4 11.00 m3
d. Pekerjaan Timbunan Oprit jembatan
( 2.40+3.30)/2 x 1.80 x 3.825 19.62 m3
95.40 m3

III. PEKERJAAN PASANGAN


3.1. Pek. Pas. Pondasi Batu Kali,
a. Pondasi angkur kabel utama
= ((2.5x0.5x3)+(1.50+2.00)/2x1x3) x 2 18.00 m3
b. Pondasi tiang pilon
= ((3.50x0.75x5.40)+ ((1.5x3.40)+(2.5x4.40))/2x2.50) x 2 68.60 m3
c. Pondasi angkur kabel angin
= (( 2.25x2x 0.5 )+(1.25+1.75)/2x1x2)) x 4 21.00 m3
d. Pondasi talud bangian depan (menghadap sungai)
= ( 0.30+0.75 )/2 x2.70 x 11 + (0.30+0.50)/2x0.70x11 18.67 m3
Pondasi talud pengaman jalan (kanan/kiri)
= (( 0.30+0.50 )/2x 0.50 x8x2 ) x 2 6.40 m3
132.67 m3
3.2 Pekerjaan Plesteran+Acian :
a. Plesteran tiang pilon, uk. 40/40 cm
= (0.40 x 4 x (4+1.5+4) 15.20 m2
b. Plesteran dinding talud bagian atas. lebar = 0.35 m
= ( 16+11) x 2 x 0.40 21.60 m2
36.80 m2
3.3 Pekerjaan Siaran dinding talud
( 11 x 0.30 ) x 2 +( 8 x 2 ) + ( 8 x 0.30 ) 25.00 m2
IV. PEKERJAAN BETON
4.1. Pekerjaan Beton Bertulang
a. Beton Pondasi angkur kabel utama
(( 1 x 1.5) - ( 0.5 x 0.5 x 0.5 )) x 3 x 2 8.25 m3
b. Beton Pondasi dan Tiang pilon
( 1 x 1.5 x 3.40 ) x 2 + ( 0.40 x 0.40 x 9.5) x 2 13.24 m3
c. Beton Pondasi kabel angin
(( 1 x 1.25) - ( 0.5 x 0.5 x 0.5 )) x 2 x 4 9.00 m3
d. Beton pagar, ( 0.20 x 0.20 x 1 ) x 2 x 2 0.16 m3
30.65 m3
4.2 Pekerjaan pembesian
a. Pembesian Beton Pondasi angkur kabel utama
Dia. 8 mm (SNI) :
= (( 19 x 2.9 )+( 14 x 4.5 )) x 2 236.20 m'
b. Pembesian Beton Pondasi tiang pilon
Dia. 8 mm (SNI) :
= (( 20 x 3.5 ) + ( 4.7 x 15 )) x 2 281.00 m'
PNPM - Mandiri Perdesaan 6 / 13

Kabupaten : Jenis : Jemb. Gantung


Kecamatan : Take Of Sheet Lokasi : Dsn.III
Desa : Volume : 1 unit

Gambar Hitungan Volume


c. Pembesian Beton Pondasi angkur kabel angin
Dia. 8 mm :
= ( 17 x 1.9) + ( 9 x 3.90 ) 67.40 m'
584.60 m'
d. Pembesian tiang pilon
Dia. 10 mm (SNI) :
= ( 17.80 x 12 ) x 2 + ( 2.3 x 4 x 2 ) x 2 464.00 m'
Dia. 6 mm (SNI) : (sengkang)
= ( 79 x 1.45 ) x 2 229.10 m'
e. Pembesian kolom pagar, 20/20 cm
Dia. 8 mm (1x4x2)x2 16.00 m'
Dia. 6 mm ( 0.65 x 6 ) x 2 x 2 15.60 m'

V. PEKERJAAN LANTAI JEMBATAN & Assesoris


5.1. Pengadaan & Pemasangan lantai kayu uk. 5/25 cm
a. Panjang papan = 1.50 m
= ( 21 / 0.25) 84.00 Bh
b. Balok gelagar melintang, uk. 10/10 cm (L=1.70 cm)
( 21/1.5 ) + 1 15.00 Bh
c. Gelagar memanjang, 6/10 cm
( 21 x 4 ) = 84 m' 22.05 Ujng
d. Tiang pagar kayu, 6/8 cm ( H = 1.25 m' )
( 15 x 1.25 ) x 2 = 37.5 m' 10.31 Ujng
e. Pagar kayu, 5/7 cm
( 21 x 3 ) x 2 = 126 m' 33.08 Ujng
f. Mur bout dia. 10 mm (panjang=25 cm)
( 4 x 15 ) 60.00 Set

5.1. Pengadaan & Pemasangan Besi penggantung, dia. 10 mm


a. ( 3.12+2.81+2.57+2.38+2.23+2.13+2.07)x2x2 + (2.05x2)+(30*0.15)
= 77.84 m' 7.11 Ujng
5.2. Pengadaan & Pemasangan Kuku macan
( 15 x 2 ) x 2 + ( 16 x 2) + ( 6 x 4 ) 116.00 Unit
5.3. Pengadaan & Pemasangan Jarum pengaku
(7x2) 14.00 Unit
5.4 Pengadaan & Pemasangan Kabel Utama dia. 1"
(( 13 x 2 ) + 33) x 2 + ( 33 x 2 ) 184.00 m'
5.5. Pengadaan & Pemasangan Kabel angin dia. 0.5"
( 13 x 4 ) 52.00 m'

V. PEKERJAAN FINISHING
a. Pek. Cat Tembok
Tiang Pilon, 40/40 cm = (1.60 x 10.30 ) x 2 32.96 m2
Tiang Pagar, 20/20 cm = (0.80 x 1 x 2 ) x 2 3.20 m2
36.16 m2
b. Pek. Cat kayu
Tiang Pagar, 6/8 cm (H= 1.25 m) = (0.28 x 18.75 ) x 2 10.50 m2
Kayu pagar, 5/7 cm ( L=126 m) = (0.24 x 63 ) x 2 30.24 m2
40.74 m2
c. Pek. Cat besi
Besi penggantung Ø10 mm, Luas besi = 0.031 2.41 m2

VI. PENGADAAN ALAT2


a. Pengadaan Alat2 Kerja
a. Ember cor 20.00 Bh
b. Sewa alat Takle 2.00 unit
c. Kunci Shock 1.00 Set
d. Linggis 1.00 unit
e. Skop 2.00 Bh
f. Cangkul 2.00 Bh
g. Selang air & benang nilon 2.00 Set
Tanggal Survei :
7 / 13

ANALISA TEKNIK
HARGA SATUAN PEKERJAAN

Propinsi Kecamatan
Kabupaten Desa
Jenis Kegiatan : Jembatan Gantung Jumlah Unit : 1 Unit

Volume Pekerjaan
NO PEKERJAAN Vol Sat
Dana 1 Dana 2 Jumlah
1 2 3 4 5 6 7 = (5+6)
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan & Bowplank 1.00 Unit
0.200 Pekerja HOK 0.200 - 0.200
0.200 Tukang HOK 0.200 - 0.200
2.000 Kayu latah, uk. 5/5 cm Ujng 2.000 - 2.000
0.200 Paku Campur Kg 0.200 - 0.200
Total 2.600 - 2.600
II PEKERJAAN TANAH
1 Galian Tanah 13.65 M3
0.250 Pekerja HOK - 3.413 3.413
Total 2.600 3.413 6.013
2 Galian Tanah Struktur 200.63 M3
0.350 Pekerja 70.219

3 Timbunan kembali bekas galian 95.40 M3


0.050 Pekerja HOK 0.250 - 4.770 4.770
Total - 4.770 4.770
III PEKERJAAN PASANGAN
1 Pek. Pas Batu kali, Camp.1 : 5 132.67 M3
1.200 Pekerja HOK - 159.207 159.207
0.600 Tukang batu HOK - 79.604 79.604
1.100 Batu kali M3 - 145.940 145.940
2.470 Semen Zak - 327.701 327.701
0.450 Pasir Pasang M3 - 59.703 59.703
Total - 772.154 772.154

- -
- -
- - -
2 Pek. Pelester+Acian 36.80 M2
0.100 Pekerja HOK - 3.680 3.680
0.070 Tukang HOK - 2.576 2.576
0.130 Semen @ 50 kg Zak - 4.784 4.784
0.015 Pasir pasang M³ - 0.552 0.552
Total - 11.592 11.592
3 Pek. Siaran 25.00 M2
0.220 Pekerja HOK - 5.500 5.500
0.110 Tukang HOK - 2.750 2.750
0.140 Semen @ 50 kg Dos - 3.500 3.500
0.023 Pasir pasang Zak - 0.575 0.575
Total - 12.325 12.325
IV PEKERJAAN BETON
1 Beton bertulang Camp, 1:2:3 30.65 M3
3.000 Pekerja HOK - 91.950 91.950
1.000 Tukang HOK - 30.650 30.650
5.500 Semen @ 50 kg Zak - 168.575 168.575
0.800 Kerikil M³ - 24.520 24.520
0.450 Pasir pasang M³ - 13.793 13.793
42.000 Besi Ø 10mm (SNI), L = 11.50 m' Ujng - 42.000 42.000
62.000 Besi Ø 8mm (SNI), L = 11.50 m' Ujng - 62.000 62.000
28.000 Besi Ø 6 mm (SNI), L = 11.50 m' Ujng - 28.000 28.000
8 / 13

Volume Pekerjaan
NO PEKERJAAN Vol Sat
Dana 1 Dana 2 Jumlah
1 2 3 4 5 6 7 = (5+6)
0.800 Bendrat kg - 24.520 24.520
0.800 Paku campur kg - 24.520 24.520
0.653 Papan mall kayu kelas III Lbr - 20.000 20.000
10.000 Kayu latah, uk. 5/5 cm Ujng 10.000
Total - 530.528 530.528
2 Pek. Pemasangan kabel seling 1 Unit
40.00 Pekerja HOK - 40.000 40.000
20.00 Tukang batu HOK - 20.000 20.000
184.00 Kabel utama, dia. 1" M' 184.000
52.00 Kabel angin, dia. 1/2" M' 52.000
7.11 Besi penggantung seling Ø 10 mm (SNI) Ujung 7.107
14.00 Warfel (jarum pengaku) Bh 14.000
4.00 Katrol Bh 4.000
60.00 Mur+Baut, Ø 10 mm (L=25 cm) Bh 60.000
116.00 Kuku macan Bh 116.000
4.00 Kausing (rumah ikatan) seling utama Bh 4.000
4.00 Kausing (rumah ikatan) seling angin Bh 4.000
8.00 Jangkar (annkur) kabel utama Bh 8.000
4.00 Jangkar (angkur)kabel angin Bh 4.000
4.00 Katrol kabel utama Bh 4.000
4.00 Paralon PVC dia. 2" (pembungkus kabel) 4.000
Total - 60.000 497.107
V PEKERJAAN KAYU
1 Pek. Lantai Jembatan 84.00 Bh
0.100 Pekerja HOK - 8.400 8.400
0.200 Tukang kayu HOK - 16.800 16.800
84.000 Papan kayu, uk. 5/25 cm ( L=1,50 m) Bh - 84.000 84.000
0.020 Paku campur Bh - 1.680 1.680
Total - 110.880 110.880
2 Pek. Gelagar kayu, uk. 10/10 cm 15.00 Bh
0.125 Pekerja HOK - 1.875 1.875
0.250 Tukang kayu HOK - 3.750 3.750
15.000 Kayu klas II, uk. 10/10 cm Bh - 15.000 15.000
22.050 Kayu klas II, uk. 6/10 cm Ujng - 22.050 22.050
30.000 Besi plat pengunci kabel bawah unit - 30.000 30.000
60.000 Besi mur baut Ø 10 mm (L=25 cm) unit - 60.000 60.000
0.100 Paku campur kg 1.500
Total - 132.675 132.675
3 Pek. Pagar kayu 21.00 m'
0.125 Pekerja HOK - 2.625 2.625
0.250 Tukang kayu HOK - 5.250 5.250
10.313 Kayu klas II, uk. 6/8 cm Ujg - 10.313 10.313
33.075 Kayu klas II, uk. 5/7 cm Ujg - 33.075 33.075
0.100 Paku campur kg 2.100
Total - 51.263 51.263
9 / 13

Volume Pekerjaan
NO PEKERJAAN Vol Sat
Dana 1 Dana 2 Jumlah
1 2 3 4 5 6 7 = (5+6)
VI PEKERJAAN FINISHING & ALAT
1 Cat kayu 40.74 Unit
0.020 Tukang cat HOK - 0.815 0.815
0.017 Tinner (minyak cat ) kg - 0.693 0.693
0.045 Cat minyak @ 1 ltr ltr - 1.833 1.833
0.094 Kertas pasir bh 3.830
0.047 Kuas cat bh 1.915
0.024 Cat dasar/meni kg 0.978
Total - 3.341 3.341
2 Pengecatan Tembok, 2 x 36.16 M2
0.010 Tukang Cat HOK - 0.362 0.362
0.072 Plamir tembok Kg - 2.604 2.604
0.075 Cat Tembok Kg - 2.712 2.712
0.036 Kertas pasir Lbr - 1.302 1.302
0.034 Kuas Cat uk. 4" Bh - 1.229 1.229
Total - 8.208 8.208
3 Pengecatan besi, 2x 2.41 M2
0.020 Tukang Cat HOK - 0.048 0.048
0.024 Cat dasar/Meni Ltr - 0.058 0.058
0.045 Cat besi Ltr - 0.109 0.109
0.017 Thinner Ltr - 0.041 0.041
0.034 Kuas Cat bh - 0.082 0.082
Total #REF! #REF! #REF!
4 Alat kerja 1.00 Unit
2.000 Cangkul Bh 2.000
1.000 Linggis Bh - 1.000 1.000
2.000 Sekop Bh 2.000
2.000 Selang air Set 2.000
1.000 Kunci Sok Bh 1.000
1.000 Gergaji Set 1.000
1.000 Gergaji Besi Set 1.000
2.000 Martil Bh 2.000
2.000 Sewa Takle Unit 2.000
20.000 Ember Bh 20.000
Total - 1.000 34.000
PNPM - Mandiri Perdesaan Form.7e.

RENCANA ANGGARAN BIAYA (RAB)


SARANA/PRASARANA : JEMBATAN GANTUNG

Propinsi No. RAB : 1.1


Kabupaten
Kecamatan Jenis Kegiatan : Jemb. Gantung
Desa Ukuran/Dimensi : 21 meter

VOLUME JUMLAH HARGA SATUAN


Harga Satuan
URAIAN Dari Dari Sat Dana 1 Dana 2 Total
Total (Rp.)
Dana 1 Dana 2 ( Rp. ) ( Rp. ) ( Rp. )

1 2 3=4+5 4 5 6 7 8=4*7 9=5*7 10=8+9

I. BAHAN
1 Semen 505.00 25.00 480.00 sak 68,000 1,700,000 32,640,000 34,340,000
2 Pasir Pasang 75.00 25.00 50.00 m3 100,000 2,500,000 5,000,000 7,500,000
3 Plat besi pengunci kabel 30.00 10.00 20.00 set 2,500 25,000 50,000 75,000
4 Kerikil 25.00 0.50 24.50 m3 100,000 50,000 2,450,000 2,500,000
5 Batu Gunung 146.00 26.00 120.00 m3 95,000 2,470,000 11,400,000 13,870,000
6 Kayu, 5/5 cm 12.00 2.00 10.00 Ujung 20,500 41,000 205,000 246,000
7 Kayu 5/7 Kls II 33.00 3.00 30.00 Ujung 27,500 82,500 825,000 907,500
8 Kayu kelas I, uk. 10/10 cm, L=1.7 m 15.00 - 15.00 Bh 33,000 - 495,000 495,000
9 Kayu kelas I, uk. 6/10 cm 22.00 2.00 20.00 Ujung 44,500 89,000 890,000 979,000
10 Kayu kelas I, uk. 6/8 cm 10.00 2.00 8.00 Ujung 36,000 72,000 288,000 360,000
11 Papan Lantai, uk.5/25 Kls I 84.00 4.00 80.00 Bh 36,000 144,000 2,880,000 3,024,000
12 Papan Mall kayu klas III 20.00 - 20.00 Ujung 23,000 - 460,000 460,000
13 Kabel Utama dia. 1" 184.00 - 184.00 M 93,000 - 17,112,000 17,112,000
14 Kabel Seling dia. 1/2" 52.00 - 52.00 M 44,000 - 2,288,000 2,288,000
15 Kausing kabel Utama 8.00 - 8.00 Bh 30,000 - 240,000 240,000
Kausing kabel angin 8.00 - 8.00 Bh 15,000 - 120,000 120,000
16 Warfel (jarum) besi penggantung 14.00 - 14.00 Bh 50,000 - 700,000 700,000
17 Katrol 4.00 - 4.00 Unit 250,000 - 1,000,000 1,000,000
18 Mur+Baut besi 10mm (L=25 cm) 60.00 - 60.00 Psg 10,000 - 600,000 600,000
19 Kuku Macan 116.00 - 116.00 Bh 20,000 - 2,320,000 2,320,000
20 Besi pengantung Ø 10 mm 7.00 - 7.00 Ujung 66,000 - 462,000 462,000
21 Besi dia. 10 mm (SNI) 42.00 - 42.00 Ujung 66,000 - 2,772,000 2,772,000
22 Besi dia. 8 mm (SNI) 62.00 - 62.00 Ujung 50,000 - 3,100,000 3,100,000
23 Besi dia. 6 mm (SNI) 28.00 - 28.00 Ujung 28,000 - 784,000 784,000
24 Kawat Bendrat 25.00 - 25.00 kg 20,000 - 500,000 500,000
25 Paku campur 30.00 - 30.00 kg 20,000 - 600,000 600,000
26 Cat Kayu 2.00 - 2.00 kg 37,500 - 75,000 75,000
27 Paralon 2 Inchi 4.00 - 4.00 Ujung 45,000 - 180,000 180,000
28 Besi angker di las 12.00 - 12.00 Bh 75,000 - 900,000 900,000
###
Sub Total. I 7,173,500 91,336,000 98,509,500
PNPM - Mandiri Perdesaan Form.7e.

VOLUME JUMLAH HARGA SATUAN


Harga Satuan
URAIAN Dari Dari Sat Dana 1 Dana 2 Total
Total (Rp.)
Dana 1 Dana 2 ( Rp. ) ( Rp. ) ( Rp. )

1 2 3=4+5 4 5 6 7 8=4*7 9=5*7 10=8+9

###
II. ALAT
1 Cangkul 2.00 2.00 - bh 40,000.00 80,000 - 80,000
2 Linggis 2.00 2.00 - Bh 30,000.00 60,000 - 60,000
3 Sekop 2.00 2.00 - bh 65,000.00 130,000 - 130,000
4 Kunci Sok 1.00 1.00 - Set 100,000.00 100,000 - 100,000
5 Kunci Pas + Ring 1.00 1.00 - Set 100,000.00 100,000 - 100,000
6 Gergaji 1.00 1.00 - bh 45,000.00 45,000 - 45,000
7 Gergaji Besi 1.00 1.00 - bh 45,000.00 45,000 - 45,000
8 Martil 2.00 2.00 - bh 40,000.00 80,000 - 80,000
9 Kuas cat tembok 1.00 - 1.00 bh 13,000.00 - 13,000 13,000
10 Kuas cat kayu 2.00 - 2.00 bh 6,000.00 - 12,000 12,000
11 Sewa Takle 2.00 2.00 - Hr 100,000.00 200,000 - 200,000
12 Ember 20.00 10.00 10.00 bh 10,000.00 100,000 100,000 200,000
13 Logo/Relief PNPM 1.00 - 1.00 bh 343,650.00 - 343,650 343,650
Sub Total. II 940,000 468,650 1,408,650
###
III. UPAH ###
1 Pekerja 392.00 - 392.00 HOK 35,000.00 - 13,720,000 13,720,000
2 Tukang 163.00 - 163.00 HOK 50,000.00 - 8,150,000 8,150,000

Sub Total. III - 21,870,000 21,870,000

TOTAL BIAYA ( Dana 1 + Dana 2 ) 8,113,500 113,674,650 121,788,150

Dari Dana 1 8,113,500


Sumber Dana
Dari Dana 2 113,674,650
PNPM-Mandiri Perdesaan Form. 8b

REKAPITULASI RENCANA ANGGARAN BIAYA (R-RAB)


Jenis Prasarana : Jembatan Gantung

Propinsi : Kecamatan
Kabupaten : Desa
Jenis Kegiatan : Jemb. Gantung Jenis Kegiatan
Ukuran/Dimensi : ( 1.5 x 21 ) meter Ukuran/Dimensi
No. URAIAN Bobot (%) Bobot (%) JUMLAH TOTAL Bobot (%)
Jumlah : 1 Unit Jumlah
No. RAB : 1.1. No. RAB
1 2 Dana 2 Dana 1 Dana 2 Dana 1 Dana 2 Dana 1

I BAHAN -
( Tidak dirinci ) 91,336,000.00 7,173,500.00 80.89 91,336,000.00 7,173,500.00 80.89

II PERALATAN
( Tidak dirinci ) 468,650.00 940,000.00 1.16 468,650.00 940,000.00 1.16

III UPAH
( Tidak dirinci ) 21,870,000.00 - 17.96 21,870,000.00 - 17.96

JUMLAH 113,674,650.00 8,113,500.00 100.00 - - - 113,674,650.00 8,113,500.00 100.00

JUMLAH (Dana 1 + Dana 2) 121,788,150.00 - 121,788,150.00


JADWAL PELAKSANAAN PEKERJAAN

Propinsi : Kecamatan
Kabupaten : Desa
Jenis Kegiatan : Pemb. Jemb. Gantung Jumlah Unit : 1 Unit

JADUAL WAKTU PELAKSANAAN


NO URAIAN PEKERJAAN VOLUME SAT BOBOT JULI AGUSTUS SEPTEMBER OKTOBER KET.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I PEKERJAAN PERSIAPAN 100


1 Pembersihan Lokasi 1.00 Ls 0.11 0.11

2 Pengadaan tenaga, alat & bahan 1.00 Ls 0.11 0.05 0.05

II PEKERJAAN TANAH
1 Galian Tanah 214.28 M3 22.90 1.00 2.00 4.00 6.00 6.00 3.90
80
2 Urugan tanah kembali 95.40 M3 10.20 0.50 1.00 2.00 3.00 3.70

III PEKERJAAN PASANGAN


1 Pas. Batu kali 132.67 M3 14.18 1.00 1.25 1.50 1.50 4.00 4.93

2 Pek. Plester+acian 36.80 M2 3.93 1.00 2.93

3 Pek. Siaran 25.00 M2 2.67 0.50 1.50 0.67


60
IV PEKERJAAN BETON
1 Beton bertulang, camp. 1:2:3 30.65 M3 3.28 0.50 0.75 1.00 1.03

V PEKERJAAN JEMBATAN
1 Pengadaan&pemasangan Kabel Utama dia. 1" 184.00 M' 19.67 4.00 8.00 6.00 1.00 0.67
40
2 Pengadaan&pemasangan Kabel angin dia. 0.5" 52.00 M' 5.56 1.00 1.00 1.00 1.75 0.81

3 Pek. Lantai Jembatan 31.50 M2 3.37 0.50 1.00 1.87

4 Pek. Pagar Jembatan 21.00 M' 2.24 0.5 0.75 1.00

5 Pek. Besi penggantung 30.00 Bh 3.21 0.25 0.75 1.00 1.21

VI PEK. PENYELESAIAN
20
1 Pengecatan Tembok 36.16 M2 3.86 1.00 2.00 0.86

2 Pengecatan Kayu 40.74 M2 4.35 1.00 1.00 2.35

3 Pengecatan besi 2.41 M2 0.26 0.26

VII MDST 1.00 Ls 0.11 0.11 0


Jumlah 935.61 100.00

Rencana Kemajuan Pekerjaaan 0.16 1.05 3.00 5.75 8.50 10.00 11.65 11.13 10.46 9.67 8.75 7.00 6.95 3.20 2.61 0.11

Kumulatif Rencana Kemajuan Pekerjaan 0.16 1.21 4.21 9.96 18.46 28.46 40.12 51.24 61.70 71.37 80.12 87.12 94.08 97.28 99.89 100.00

Realisasi Kemajuan Pek. di lapangan


Kumulatif Realisasi Kemajuan Pek. Di Lapangan

Anda mungkin juga menyukai