UOT FACTOR 1 STANDARD COMPANY NORMS

EARTHWORK
EW-01 excavation m3 0.15 ### DIV
EW-02 rock excavation m3 1.00 ### DIV-2
EW-03 backfilling & compaction m3 0.10 ###
EW-04 thick stone base course m3 0.20 ###
EW-05 termite protection m2 0.80 ###
EW-06 Grading / grubs / shrubs / stumps / hedges / bush m2 0.02 ###
-
CONCRETE WORK -
CONC-01 concrete m3 0.60 ######
FORM-01 forms (erection & stripping) m2 5.00 ###
RB-01 rebar (15kgs/m3) ton 90.00 ###
RB-02 rebar (40kgs/m3) ton 90.00 ###
RB-03 rebar (45kgs/m3) ton 90.00 ### DIV-3
RB-04 rebar (50kgs/m3) ton 90.00 ###
RB-05 rebar (60kgs/m3) ton 90.00 ###
RB-06 rebar (65kgs/m3) ton 90.00 ###
RB-07 rebar (70kgs/m3) ton 90.00 ###
RB-08 rebar (75kgs/m3) ton 90.00 ###
RB-09 rebar (80kgs/m3) ton 90.00 ###
RB-10 rebar (85kgs/m3) ton 90.00 ######
RB-11 rebar (90kgs/m3) ton 90.00 ###
RB-12 rebar (100kgs/m3) ton 90.00 ###
RB-13 rebar (105kgs/m3) ton 90.00 ###
RB-14 rebar (110kgs/m3) ton 90.00 ###
RB-15 rebar (115kgs/m3) ton 90.00 ###
RB-16 rebar (120kgs/m3) ton 90.00 ###
RB-17 rebar (125kgs/m3) ton 90.00 ###
RB-18 rebar (130kgs/m3) ton 90.00 ###
RB-19 rebar (135kgs/m3) ton 90.00 ###
RB-20 rebar (140kgs/m3) ton 90.00 ###
RB-21 rebar (145kgs/m3) ton 90.00 ######
RB-22 rebar (150kgs/m3) ton 90.00 ###
RB-23 rebar (155kgs/m3) ton 90.00 ###
RB-24 rebar (160kgs/m3) ton 90.00 ###
RB-25 rebar (165kgs/m3) ton 90.00 ###
RB-26 rebar (180kgs/m3) ton 90.00 ###
RB-27 rebar (185kgs/m3) ton 90.00 ###
RB-28 rebar (200kgs/m3) ton 90.00 ######
RB-29 rebar (210kgs/m3) ton 90.00 ###
RB-30 rebar (250kgs/m3) ton 90.00 ###
RB-31 rebar (350kgs/m3) ton 90.00 ###
RB-32 rebars ton 90.00 ###
CUR-01 concrete curing m3 0.07 ###
-
ROAD WORK -
RW-01 50mm thick wearing course m3 2.00 ###
RW-02 70mm thick binder course m3 2.00 ###
RW-03 tack coat RC-250 m2 0.02 ###
RW-04 prime coat MCC-70 m2 0.02 ###
RW-05 150mm thick compacted aggregate base course m2 0.20 ######
RW-06 150mm thick sub base coarse m2 0.20 ### DIV-4
RW-07 geotextile fabric (1 layer) m2 0.13 ###
RW-08 curb & gutter incl paint marking LM 0.17 ###
RW-09 traffic road signs ea 2.50 ###
RW-10 road paint and marking m2 0.20 ###
RW-11 road paint and marking (nos) ea 1.00 ###
-
- DIV-5
PRECAST ELEMENTS -
PC-01 precast hollow core slab m2 0.35 ###
PC-02 precast concrete stair ea 7.00 ###
PC-03 precast concrete lintel ea 1.00 ###
PC-04 precast concrete wall panel m2 1.40 ### DIV-7
PC-05 precast concrete beam ea 3.50 ###
PC-06 precast concrete column ea 2.50 ###
PC-07 precast concrete bench ea 2.50 ###
PC-08 precast concrete trash bin ea 2.50 ###
PC-09 supply & install precast splash block ea 1.20 ###
PC-10 supply & install precast scupper drain ea 1.20 ###
PC-11 install precast splash block ea 0.60 ###
-
WATERPROOFING -
WP-01 polythelene sheet (1 layer) m2 0.05 ### DIV-8
WP-02 bitumen coating (1-coat) m2 0.30 ###
WP-03 bitumen coating (2-coats) m2 0.60 ###
WP-04 bitumen coating (3-coats) m2 0.90 ###
WP-05 roof waterproofing (complete) m2 2.72 ###
WP-06 non-woven fabric m2 0.19 ###
WP-07 install water stopper (PVC) LM 1.00 ###
WP-08 Install water proofing membrane EPDM/LDPE m2 0.60 ### DIV-9
-
-
ROOF WATERPROOFING -
RFW-01 woven fabric installation m2 0.19 ###
RFW-02 50mm insulation board m2 0.19 ###
RFW-03 75mm insulation board m2 0.25 ###
RFW-04 roof sheating m2 0.19 ###
RFW-05 parapet flashing m2 0.24 ###
RFW-06 roofing membrane m2 0.32 ###
RFW-07 50mm screed m3 0.90 ###
-
EXPANSION JOINT -
EJ-01 expansion joint filler m2 0.30 ###
EJ-02 joint sealant m 0.20 ###
-
-
FENCE & GATE -
FG-01 installation of fence LM 4.00 ###
FG-02 design & supply LM 1.20 ###
FG-03 install electrically operated gate LS 144.00 ###
-
-
-
-
LANDSCAPING -
LS-01 maintaining, scarifying, soiling, seeding m2 0.65 ###
LS-02 spreading & levelling of gravel/chippings m2 0.10 ###
LS-03 plants shrubs ea 0.33 ###
LS-04 plants trees ea 1.33 ###
LS-05 protect trees ea 0.83 ###
LS-06 irrigation system m2 4.00 ###
LS-07 soil mix m2 0.19 ###
-
-
-
HARDSCAPING -
HS-01 concrete pavers m2 1.25 ###
HS-02 sand base m2 0.20 ###
-
-
MASONRY -
MAS-01 cmu 100mm thk m2 0.95 ###
MAS-02 cmu 150mm thk m2 1.11 ###
MAS-03 cmu 200mm thk m2 1.26 ###
MAS-04 cmu 250mm thk m2 1.28 ###
MAS-05 cmu 300mm thk insulated m2 1.30 ###
MAS-06 cmu 350mm thk insulated m2 1.33 ###
-
DOORS & WINDOWS -
DW-01 wooden door & frame set 2.56 ###
DW-02 door hardware (wood) set 1.06 ###
DW-03 steel door & frame set 20.50 ###
DW-04 door hardware (steel) set 1.06 ###
DW-05 swing glass door set 20.50 ###
DW-06 door hardware (glass) set 2.85 ###
DW-07 aluminum window set 5.47 ###
DW-08 glazing m2 4.10 ###
DW-09 aluminum curtain wall m2 2.37 ###
DW-10 door repaint m2 1.00 ###
DW-11 Installation of rolling shutter incl. frame and accesso m2 8.00 ###
-
FLOOR FINISHES -
FF-01 screed m3 0.90 ###
FF-02 wiremesh kg 0.05 ###
FF-03 marble tiles m2 1.30 ###
FF-04 unglazed ceramic tiles m2 0.95 ###
FF-05 porcelain tiles m2 0.95 ###
FF-06 epoxy paint m2 0.28 ###
FF-07 vinyl tiles m2 0.45 ###
FF-08 vinyl sheets m2 0.30 ###
FF-09 roll carpet with underlay sheeting m2 0.30 ###
FF-10 quary tiles m2 1.20 ###
FF-11 gravel m2 0.65 ###
FF-12 rubber tiles m2 0.95 ###
FF-13 carpet tiles m2 0.45 ###
FF-14 wooden flooring m2 0.40 ###
FF-15 resilient running track finish m2 1.00 ###
-
SKIRTING -
SK-01 marble 20mm thk x 100mm high LM 0.24 ###
SK-02 ceramic 20mm thk x 100mm high LM 0.24 ###
SK-03 porcelain skirting 6mm thk x 100mm high LM 0.24 ###
SK-04 vinyl tile skirting LM 0.24 ###
SK-05 vinyl sheet skirting LM 0.24 ###
SK-06 epoxy paint skirting 100mm high LM 0.15 ###
SK-07 wooden skirting LM 0.24 ###
SK-08 quary skirting 100mm high LM 0.24 ###
SK-09 concrete hardened skirting LM 0.24 ###
SK-10 rubber cove skirting 100mm high LM 0.24 ###
SK-11 terrazo tile 100mm high LM 0.24 ###
SK-12 metal skirting 100mm high LM 0.24 ###
SK-13 paint skirting 100mm high LM 0.24 ###
-
CEILING FINISHES -
CF-01 plastering incl painting m2 1.14 ###
CF-02 gypsum ceiling standard m2 1.14 ###
CF-03 gypsum ceiling moisture m2 1.14 ###
CF-04 aluminum trellis m2 1.14 ###
CF-05 acoustical ceiling m2 1.14 ###
CF-06 ceiling painting m2 0.25 ###
CF-07 concrete trellis m2 0.45 ###
-
WALL FINISHES -
WF-01 wall cement plastering m2 0.45 ###
WF-02 gypsum board m2 1.14 ###
WF-03 glazed ceramic tiles m2 0.95 ###
WF-04 porcelain wall tiles m2 0.95 ###
WF-05 polished marble 20mm thk m2 1.26 ###
WF-06 riyadh stone cladding m2 1.26 ###
WF-07 wall painting m2 0.19 ###
WF-08 wood panel installation m2 1.26 ###
WF-09 glass wall panel installation m2 1.26 ###
WF-10 fire proof paint m2 4.00 ###
-
FURNISHING -
FUR-01 Chair ea 2.00 ###
FUR-02 Table ea 2.00 ###
FUR-03 Bed ea 4.00 ###
FUR-04 Cabinet ea 4.00 ###
FUR-05 Book shelf ea 2.00 ###
FUR-06 storage ea 2.00 ###
FUR-07 marker board ea 2.00 ###
FUR-08 furniture (small) ea 2.00 ###
FUR-09 appliances (small) ea 2.00 ###
FUR-10 furniture (big) ea 4.00 ###
FUR-11 appliances (big) ea 4.00 ###
FUR-12 window blinds m2 0.55 ###
FUR-13 window blinds (mechanically operated) m2 1.50 ###
FUR-14 gym equipment (small) set 2.00 ###
FUR-15 gym equipment (big) set 4.00 ###
-
METAL WORKS -
MW-01 fabrication of stair/ladder ton 50.00 ###
MW-02 fabrication of grating ton 50.00 ###
MW-03 fabrication of steel structure ton 80.00 ###
MW-04 erection of steel structure (201kg/m) ton 30.00 ###
MW-05 erection of steel structure (121 to 200kg/m) ton 40.00 ###
MW-06 erection of steel structure (61 to 120kg/m) ton 35.00 ###
MW-07 erection of steel structure (31 to 60kg/m) ton 30.00 ###
MW-08 erection of steel structure (up to 30kg/m) ton 60.00 ###
MW-09 erection of stair (up to 30kg/m) ton 15.00 ###
MW-10 erection of railings (up to 30kg/m) ton 15.00 ###
MW-11 erection of cladding, roofing, decking (9kg/m2) m2 4.00 ###
MW-12 installation of aluminum cladding m2 0.47 ###
MW-13 installation of aluminum canopy m2 3.00 ###
MW-14 supply and install of play ground shaded area m2 4.50 ###
MW-15 supply and install of PEB m2 16.00 ###

THRESHOLD -
TH-01 marble threshold LM 1.50 ###
TH-02 aluminum threshold LM 1.50 ###
TH-03 mortar cement m2 0.90 ###
-
-
SPECIALTIES -
SPC-01 phenolic partition LM 2.50 ###
SPC-02 signage m2 20.00 ###
SPC-03 wall cabinet m2 1.50 ###
SPC-04 base cabinet m2 1.00 ###
SPC-05 counter top LM 2.50 ###
SPC-06 corner guard LM 1.20 ###
SPC-07 ablution seat set 5.00 ###
-
DEMOLITION WORK -
DMW-01 demolition reinforced structure/walls (with equipment m2 3.00 ###
DMW-02 demoltion of road paving/aspahalt m2 0.28 ###
-
-
-
-
-

SCAFFOLDING -
SCF-01 erection & dismantling of scaffolding m2 0.50 0.5
SCF-02 erection & dismantling of soffit scaffolding ea 0.50 0.5
-
-
-
-
-

EQUIPMENT
EQ-01 installation of elevator (vertical) ton 75.00 75
EQ-02 Fabrication of Chutes, Bins, Hoppers, Cyclones & T ton 150.00 150 ton
EQ-03 Erection of Chutes, Bins, Hoppers, Cyclones & Trou ton 60.00 60 ton
-
-
-
-

PLUMBING FIXTURES & SPECIALTIES


PFIX-01 Fixing of wash basin (without faucet) nos 5.00 5
PFIX-02 Fixing of waste pipe / wash basin pedestal nos 1.50 1.5
PFIX-03 Fixing of bath room mirror m2 5.56 5.56
PFIX-04 Fixing of soap dish / dispenser / tooth brush holder nos 1.00 1
PFIX-05 Fixing of towel rail nos 1.00 1
PFIX-06 Fixing of toilet paper holder / dispenser nos 1.00 1
PFIX-07 Fixing of W.C. (European type) with flush cistern / t nos 6.00 6
PFIX-08 Fixing of W.C. (Indian type) without flush tank nos 6.00 6
PFIX-09 Fixing of Urinal nos 6.00 6
PFIX-10 Fixing of Faucets nos 1.50 1.5
PFIX-11 Fixing of Shower / Telephone or Muslim Shower nos 1.50 1.5
PFIX-12 Fixing of water heater (Geyser) nos 8.00 8
PFIX-13 Fixing of Fiberglass tank (500 G ~ 2000 G) nos 8.00 8
PFIX-14 Fixing of bathroom shelf nos 1.50 1.5
PFIX-15 Fixing of bathroom Tub, complete with supports nos 10.00 10
PFIX-16 Fixing of hand dryer nos 2.00 2
PFIX-17 Fixing of accessory tray nos 1.00 1
PFIX-18 Fixing of waste receptacle nos 1.00 1
PFIX-19 Fixing of Kitchen Sink nos 8.00 8
PFIX-20 Fixing of Emergency Eye wash / Shower nos 8.00 8
PFIX-21 Fixing of Water filters ( Cartridge style, dirt & dust ty nos 3.00 3
PFIX-22 Cast Iron gate valves dia 1" nos 0.20 0.2
PFIX-23 Cast Iron gate valves dia 1-1/2" nos 0.25 0.25
PFIX-24 Cast Iron gate valves dia 2" nos 0.25 0.25
PFIX-25 Check valves dia 1" nos 0.20 0.2
PFIX-26 Check valves dia 2" nos 0.20 0.2
PFIX-27 Floor trap, gully 3" to 6" P, S or Q type nos 1.25 1.25
PFIX-28 Mixer tap for wash basins nos 1.00 1
PFIX-29 Shower complete set nos 1.50 1.5
PFIX-30 Gas Cock (brass) 3/ 4 " dia nos 0.25 0.25
PFIX-31 Floor drain 3" to 6" dia nos 1.00 1
STANDARD COMPANY NORMS upd as of

Description Acct.# Comodities UOM


SITE WORK / EXTERNAL
2-101 Trench excavation (not exceed 1m deep) LM
2-102 Trench excavation (not exceed 2m deep) LM
2-103 Trench excavation (not exceed 5m deep) LM
2-104 Backfill & compact trench m3

BUILDING STRUCTURE
2-105 Excavation for raft foundation m3
2-106 Excavation for isolated footing m3
2-107 Backfill around footing m3

CONCRETE
3-100 Blinding concrete m2
3-101 Foundation (forms & rebar included)
a. Isolated footing under 0.75m3 m3
b. Isolated footing over 4.0 m3 m3
c. Strip footing m3
d. Mat foundation under 7.5 m3 m3
e. Mat foundation over 15.0 m3 m3
3-102 Retaining wall (forms & rebar included)
a. 1200 mm high m3
b. 3000 mm high m3
3-103 Ground beams m3
3-104 Slab on-grade (forms only / no rebar)
a. 100mm thk m2
b. 150mm thk m2
c. 200mm thk m2
d. 300mm thk m2
3-105 Slab on-grade (forms and rebar included)
a. 100mm thk m3
b. 150mm thk m3
3-106 Columns (forms and rebar included)
a. 300 mm x 300 mm m3
b. 400 mm x 400 mm m3
c. 600 mm x 600 mm m3
d. 900 mm x 900 mm m3
3-107 RC Wall (forms and rebar included)
a. 200 mm thk x 2400 mm high m3
b. 200 mm thk x 4275 mm high m3
c. 300 mm thk x 2400 mm high m3
3-108 Suspended Beams (forms and rebar included)
a. 3.05 meter span m3
b. 7.60 meter span m3
3-108 Suspended Solid Slab (forms and rebar included)
a. 1-way beam & slab m3
b. 2-way beam & slab m3
3-109 Waffle Slab (forms and rebar included)
a. 762 mm dome m3

MASONRY
4-100 100 mm thk CMU m2
4-101 150 mm thk CMU m2
4-102 200 mm thk CMU m2
4-103 250 mm thk CMU m2
4-104 300 mm thk CMU m2

METAL WORKS
5-100 Handrail & Railing (Aluminum) LM
5-101 Ladder (Aluminum/Galvanized) LM
5-102 Metal Decking m2

THERMAL AND MOISTURE


PROTECTION
7-100 Damproofing
a. Below grade, 1-coat m2
a. Below grade, 2-coats m2
7-101

DOORS AND WINDOWS


8-100 Door Frame (Steel) nos
8-101 Door Frame (Wood) nos
8-102 Door Leaf (Steel) nos
8-103 Door Leaf (Wood) nos
8-104 Aluminum Door nos

FINISHES
9-100 Plaster Cement on Wall (interior/exterior) m2
9-101 Plaster Cement on Ceiling (interior/exterior) m2
9-102 Ceramic Wall Tiles m2
9-103 Ceramic Floor Tiles m2
9-104 Stone Wall Finish (Marble/Granite by mechanical fixing) m2
9-105 Riyadh Stone Wall Finish (by mechanical fixing) m2
9-106 Terrazo tiles m2
9-107 Vinyl tiles m2
9-108 Screed under carpet / vinyl tiles m2
9-109 Screed with surface hardener m2
9-110 Acoustic ceiling m2
9-111 Gypsum board suspended ceiling m2
9-112 Painting to walls m2
9-113 Carpet installation m2
Norm Remarks

100.0 1-back hoe operator, 2-dump truck driver, 3 laborer


70.0 1-back hoe operator, 2-dump truck driver, 3 laborer
35.0 1-back hoe operator, 2-dump truck driver, 3 laborer
36.0 1-mini loader operator, 4-laborer

60.0 1-back hoe operator, 2-dump truck driver, 3 laborer


45.0 1-back hoe operator, 2-dump truck driver, 3 laborer
14.0 1-mini loader operator, 4-laborer

34.0 2-rough carpenter, 2-mason, 3-laborer

19.0 1-foreman, 6-rough carpenter, 2-steelfixer, 1-mason, 4-laborer


40.0 1-foreman, 6-rough carpenter, 2-steelfixer, 1-mason, 4-laborer
31.0 1-foreman, 6-rough carpenter, 2-steelfixer, 1-mason, 4-laborer
19.0 1-foreman, 6-rough carpenter, 2-steelfixer, 1-mason, 4-laborer
28.0 1-foreman, 6-rough carpenter, 2-steelfixer, 1-mason, 4-laborer

33.0 1-foreman, 18-rough carpenter, 2-steelfixer, 1-mason, 2-laborer


62.0 1-foreman, 18-rough carpenter, 2-steelfixer, 1-mason, 2-laborer
7.7 1-foreman, 16-rough carpenter, 4-steelfixer, 1-mason, 2-laborer

207.0 1-foreman, 6-mason, 2-laborer


202.0 1-foreman, 6-mason, 2-laborer
192.0 1-foreman, 6-mason, 2-laborer
165.0 1-foreman, 6-mason, 2-laborer

34.0 1-foreman, 2-rough carpenter, 4-steelfixer, 1-mason, 3-laborer


51.0 1-foreman, 2-rough carpenter, 4-steelfixer, 1-mason, 3-laborer

5.0 1-foreman, 6-rough carpenter, 2-steelfixer, 1-mason, 4-laborer


6.3 1-foreman, 6-rough carpenter, 2-steelfixer, 1-mason, 4-laborer
8.8 1-foreman, 6-rough carpenter, 2-steelfixer, 1-mason, 4-laborer
11.6 1-foreman, 6-rough carpenter, 2-steelfixer, 1-mason, 4-laborer

23.0 1-foreman, 14-rough carpenter, 6-steelfixer, 1-mason, 2-laborer


13.1 1-foreman, 14-rough carpenter, 6-steelfixer, 1-mason, 2-laborer
32.0 1-foreman, 14-rough carpenter, 6-steelfixer, 1-mason, 2-laborer

7.8 1-foreman, 12-rough carpenter, 4-steelfixer, 1-mason, 2-laborer


9..2 1-foreman, 12-rough carpenter, 4-steelfixer, 1-mason, 2-laborer

10.2 1-foreman, 16-rough carpenter, 4-steelfixer, 2-mason, 2-laborer


12.0 1-foreman, 16-rough carpenter, 4-steelfixer, 2-mason, 2-laborer

18.4 1-foreman, 16-rough carpenter, 4-steelfixer, 2-mason, 2-laborer


18.0 3-mason, 2-laborer
16.5 3-mason, 2-laborer
13.5 3-mason, 2-laborer
10.0 3-mason, 2-laborer
10.0 3-mason, 2-laborer

27.0 3-subcon installer


17.0 3-subcon installer
83.0 1-foreman, 3-installer

41.0 1-laborer
31.0 1-laborer

4.0 2-finishing carpenter


4.0 2-finishing carpenter
6.0 2-finishing carpenter
6.0 2-finishing carpenter
2.0 2-subcon installer (aluminum)

20.0 2-mason plaster, 1 laborer


12.0 2-mason plaster, 1 laborer
10.0 2-mason tile setter, 1 laborer
8.0 2-mason tile setter, 1 laborer
3.0 1-mason stone installer, 1 laborer
3.0 1-mason stone installer, 1 laborer
7.0 1-mason tile setter, 1 laborer
25.0 1-mason tile setter, 1 laborer
30.0 1-mason tile setter, 1 laborer
25.0 1-mason tile setter, 1 laborer
12.0 1-finishing carpenter, 1 laborer
8.0 1-finishing carpenter, 1 laborer
88.0 1-painter
35.0 1-carpet installer, 1 laborer