152.8 61.12
LOKASI : Gg Sindur
PROYEK : KM/WC
LINGKUP : PEKERJAAN SIPIL
LUAS BANGUNAN : 15 M2
TANGGAL :
WAKTU PELAKSANAAN : 60 hari
LOKASI : Gg Sindur
PROYEK :Toilet
A MATERIAL ALAM
1 Batu Kali m3 -
2 Pasir Urug m3 -
3 Pasir Pasang m3 3.00 275,000 825,000
4 Pasir Beton m3 -
5 Split m3 1.00 250,000 250,000
H Sanitair
1 Closet Duduk unit 2.00 1,250,000 2,500,000
2 Closet jongkok unit 3.00 350,000 1,050,000
3 kran air bh 5.00 50,000 250,000
4 Pipa 1/2 btg 5.00 46,800 234,000
5 Pipa 2.5" btg 4.00 65,000 260,000
6 Pipa 4" btg 4.00 150,000 600,000
I Alat Bantu
1 Amplas bh 20.00 5,000 100,000
2 Kuas 2'' bh 2.00 12,500 25,000
3 Kuas Rol bh 1.00 25,000 25,000
4 Bak Cat bh 1.00 10,000 10,000