4Vˆw
Dc =
πρ v uˆv
Where Dc is the column diameter in meters, Vˆw is the maximum vapor rate in kg/s.
PRi
t=
2 SE × 0.4 P
3. Tray spacing:
The recommended tray spacing is given by (Treybal, 1980) according to the diameter of the
column.
81
the number of ideal tray
Eo = =0.85
the number of real tray
82
The exchanger area was calculated by using the duty given from UniSIM. The log mean
temperature difference was calculated for each reboiler and condenser.
Example:
∆T1 − ∆T2
∆t =LMTD (log mean temperature difference) =
∆T
ln 1
∆T2
Where, ∆T1 is the temperature difference between the hot inlet stream and cold outlet is stream
and ∆T2 is the difference between the hot outlet stream and the cold inlet stream.
Q
A=
K∆t
The heat exchanger area could then be calculated. The results are shown in Table B.3.
A. Condenser calculation
1. The amount of cooling water needed for the condenser for debutanizer. The sea temperature
used for condense is 10 oC, assume the outlet temperature is 40 oC.
Q 1.133 × 10 7
G H 2O = = = 89920.0kg / h
Cp ⋅ ∆t H 2O 4.2 × (40 − 10)
Q 1.133 × 10 7
A= = = 361m 2
K ∆t 570 × 55
83
The amount of cooling water needed for the condenser for propane column. The sea temperature
used for condense is 10 oC, assume the outlet temperature is 20 oC
Q 4.316 × 10 6
G H 2O = = = 102761.9kg / h
Cp ⋅ ∆t H 2O 4.2 × (20 − 10)
(T 2 − t 1 ) − (T1 − t 2 ) ( 22 .85 − 20 ) − ( 22 .83 − 10 )
∆t = = = 6 .63 ℃
T 2 − t1 22 .85 − 20
ln ln
T1 − t 2 22 .83 − 10
Q 4.316 ×10 6
A= = = 1141m 2
K∆t 570 × 6.63
The amount of cooling water needed for the condenser for butane column The sea temperature
used for condense is 10 oC, assume the outlet temperature is 20 oC
Q 7.257 × 10 6
G H 2O = = = 178725.7 kg / h
Cp ⋅ ∆t H 2O 4.2 × (20 − 10)
(T 2 − t 1 ) − (T1 − t 2 ) ( 30 .36 − 20 ) − ( 30 .17 − 10 )
∆t = = = 14 .72 ℃
T 2 − t1 30 .36 − 20
ln ln
T1 − t 2 30 .17 − 10
Q 7.257 ×10 6
A= = = 864m 2
K∆t 570 × 14.72
B. Reboiler calculation
Assume the temperature of inlet steam is 300℃ and temperature of outlet steam 260℃
The amount of steam need for the reboiler for the deethanizer column
The stream needs to be heated from 193.6℃ to 246.7℃
Q 1.949 × 10 7
G steam = = = 242412.9kg / h
Cp ⋅ ∆t steam 2.01 × (300 − 260)
84
(T 2 − t 1 ) − (T1 − t 2 ) (300 − 246 .7 ) − ( 260 − 193 .6 )
∆t = = = 59 .6 ℃
T 2 − t1 300 − 246 .7
ln ln
T1 − t 2 260 − 193 .6
Q 1.949 × 10 7
A= = = 573.6m 2
K∆t 570 × 59.6
The amount of steam need for the reboiler for the debutanizer column
The stream needs to be heated from 224.7℃ to 252.3℃
Q 1.046 × 10 7
G steam = = = 130099.5kg / h
Cp ⋅ ∆t steam 2.01 × (300 − 260)
(T 2 − t 1 ) − (T1 − t 2 ) ( 300 − 252 .3) − ( 260 − 224 .7 )
∆t = = = 41 .19 ℃
T2 − t1 300 − 252 .3
ln ln
T1 − t 2 260 − 224 .7
Q 1.046 ×10 7
A= = 570 = 445.5m 2
K ∆t 570 × 41.19
The amount of steam need for the reboiler for the propane column
The stream needs to be heated from 73.99℃ to 74.74℃
Q 4.197 × 10 6
G steam = = = 52201.49kg / h
Cp ⋅ ∆t steam 2.01 × (300 − 260)
(T 2 − t 1 ) − (T1 − t 2 ) ( 300 − 74 .74 ) − ( 260 − 73 .99 )
∆t = = = 205 ℃
T 2 − t1 300 − 74 .74
ln ln
T1 − t 2 260 − 73 .99
The amount of steam need for the reboiler for the butane column
85
The stream needs to be heated from 50.02℃ to 50.28℃
Q 7.257 × 10 6
G steam = = = 90261.19kg / h
Cp ⋅ ∆t steam 2.01 × (300 − 260)
(T 2 − t 1 ) − (T1 − t 2 ) ( 300 − 50 .28 ) − ( 260 − 50 .02 )
∆t = = = 229 ℃
T2 − t1 300 − 50 .28
ln ln
T1 − t 2 260 − 50 .02
86
Figure 3.10 – Process Flowsheet Case 1
29