Prepare the workshop drawings showing a complete installation along with section details for
coordination with other MEP works.

After approval of shop drawings, prepare the builders work drawings and based on that install
sleeves in basement service walls and beams.

Drawings stamped ³issued for construction´ by the consultant should only be used for site
works.

Install pipe sections which are embedded below ground floor slab.

Check gradients (slope) of all drainage pipes according to requirements. Coordination with the
Main Contractor for installing the drainage pipe under the basement floor slab.

The sewer or drain under test should be left with water for 1-2 hours.

Submit inspection forms for Consultant¶s approval before encasing pipes with concrete.

Fix pipe brackets in basement as approved.

Install main pipe headers in basement.

Plug, test and submit inspection forms for Consultant¶s approval, along with progress of
installation.

Acoustic insulation ± to be provided as per manufacturer recommendation.

Authorized staff of subcontractor to be present on site during concreting and back filling
operations to ensure that the position of pipes is not disturbed by movement of works.

Scale of shop drawings to be as specified or as approval by Consultants.

Large scale of shop drawings for detail section shall be 1:25 or 1:20.

Invert levels and slopes shall be 1:60 up to 4 inches, 1:90 up to 6 inches and 1:120 from 8 inches
and above or as specified of Consultants.

Mock-up for typical shaft to be installed prior to complete installation.


c 

Suitable strutted plugs are inserted at the lower end of the drain or sewer and at the head of any
connections.

a suitable bend together with a vertical length of pipe is fitted at the head of the sewer or drain to
provide the necessary test head. The system is then filled with water.

A test pressure of 1:50 m head above the crown of the pipe is applied at the higher end of the
drain or sewer ensuring that the resultant head at the lower end does not exceed 4.0 m. Where
gradients are steep, it may be necessary to test in sections to avoid exceeding this figure.

The sewer or drain under test should be left filled with water for 1-2 hours.

During the water test, strutting precautions should be taken to prevent any movement of the drain
or sewer.

Once building and making good of service shafts are completed by main contractor, along with
erection of block walls and provision of sleeves in adjacent bathrooms, proceed with installation
of drainage and rain water risers, complete with pipe branches and floor gulley connections.

Plug, test and submit inspection forms to obtain consultants approval.

Install rain water outlets prior to roof¶s waterproofing and connect to adjacent pipe risers.

Install floor grating covers in various bathrooms and kitchen in conjunction with floor tiling.

Final connections to sanitary fixtures.



Prepare the workshop drawings showing a complete installation along with section details for
coordination with other section and plans above false ceiling shop drawings to be submitted.

Approved drawings to be marked ³issued for construction´ by the consultants.

Once the building and making good of service shafts is completed by main contractor, along with
erection of block wall and provision of sleeves in adjacent bathrooms, proceed with

installation of domestic water pipe risers complete with pipe branches distribution in adjacent
bathrooms.

Test, and submit inspection forms to obtain Consultant¶s approval, along with progress of
installations.
Final connections to sanitary fixtures.

Care will be taken to connect all sanitary fixtures in tile centers, or as agreed by the Engineer,
coordinate with the main contractor.

Obtain drawings for the tile lay-out from the civil contractor to position the sanitary fixtures.

Thrust blocks anchored to be provided as shown on drawings.

All gate valves to be installed at accessible locations.

[ Back to top ]



Once building and making good service shafts is completed by main contractor, along with
erection of block walls and provision of sleeves in adjacent bathrooms, proceed with installation
of hot water pipe risers complete with pipe branches distribution in adjacent areas.

Procedure of water supply pipe testing.

Test and submit inspection forms to obtain Consultants approval along with progress of
installations.

Insulate hot water pipes.

Install water heaters.

Test and submit inspection forms to obtain Consultants approval, along with progress of
installations.

Insulate main headers

Final connections to sanitary fixtures.

Install clarifiers, circulating pump sets and connect to supply and return headers.

Installation of hot water piping system. Specially for riser and all pipe branches in shafts to be
completed as per approved shop drawings by the Consultants.

[ Back to top ]
 c 

  

When the system has been fully installed all pipe work and fittings should be visually inspected
and hydraulically tested. Joints should be left exposed until hydraulic testing has been
successfully completed.
! 

During installation the pipeline will be suitably anchored to resist thrust at changes of direction
and fixed points such as branches and hydrant connections.

"!!

The test section should be isolated, where necessary from the rest of the system. A blank end
connection, drilled and tapped for test equipment, will be required and should be installed on a
suitable flange face.
Testing should not be carried out against closed valves. The system should be filled from its
lowest point with all air valves and control valves in the open position. Care should be taken to
avoid pressure surges and to ensure that all air is expelled from the pipeline. Air valves should be
closed as filling proceeds when the air valves are seen to be discharging water free from aeration.

c#

When charging is complete the pressure test equipment should be connected to the system via
the blank flange or stopper. The equipment should consist of a single or double cylinder hand
pump, a pressure gauge suitably graduated and preferably calibrated before use and press hoses
to connect to a water supply and the blank flange or stopper.

The system should be pressurized slowly using the hand pump until the pressure gauge indicates
the required value. The test pressure will be determined by the Engineer responsible but should
not exceed 1½ times the nominal working pressure.

The duration of the test should not less than one hour during which time the system should be
isolated from the test pump.

c 


Builders work drawing to be prepared for the base of equipments with coordination with main
contractor and approval of Engineer.

Place each equipment on its bases wherever required as per approved drawing.

Connect service pipes to relevant equipments such as:


Calorifiers
Water filters and softeners
Pumps
Fuel oil tank
The supporting system for service lines to be painted with protective paint system to withstand
corrosion.

 !$

—? Prepare the submittal for all materials including pumps fittings and accessories complete
in all respect and shall be submitted to Consultants for approval.
—? Prepare shop drawings and submit to Consultants for comments.
—? Prepare builders work drawings for [positioning of sleeves, risers, etc.
—? „evise and submit to civil defense for approval.
—? Provide sleeves/opening in structure work wherever required.
—? Fix pipe brackets as approved.
—? Coordinate with false ceiling layout for sprinkler head location.
—? Submittal for approval of pipe supporting accessories.
—? Install main pipe work as per approved drawings
—? Plug ends and run pipe test.
—? Obtain Consultants approval.
—? Paint pipe work.
—? Pipes to be painted prior to installation.
—? Submit paint system for approval of Consultant.
—? Install Hose „eel & Landing Valve as per approved detail shop drawing for each cabinet.
—? Connect above to pipe work.
—? install sprinkler heads as per approved location and connect to pipe work.
—? Install pumps on foundation as shown on approved drawings.
—? Connect pumps to main supply pipes.
—? Coordination with approved Sub-contractor to check and commission the system for
Civil Defense approval.

c

—? Obtain approval from Civil Defense on working drawings prepared by Approved Sub-
contractor.
—? Install pipe work and branches to equipments through safety valves and devices.
—? Test pipe work against leakage and obtain consultant approval.
—? Paint pipe work and provide labels.
—? Pipes to be painted prior to installations.
—? After fixing fuel oil clarifiers, actual measurement for chimney can be taken.
—? Fabricate the same and install in place.