PILE INSTALLATION GURANTEE AND RECOMMENDATION 
Project Name    : 8.5 Storey Building Construction, Pile Foundation Work 

Employer Name  : U Aung Naing 
 
Attention to    : U Tun Hla Aung (PE, 3rd Party)  

Date      : 27th February 2019 

Reference    : UAN/LuckyLink/001/2019 

Dear U Tun Hla Aung, 

I would like to submit the method statement, press pile machine converting table to measure the 
building design load.  

The criteria of the building working load are 25tons. According to safety factor 2time load and total 
working load shall be 50tons. Our press pile machine converting table shown as 9Mpa (1,305.34psi) 
is equivalent with the Load 549KN. Thus, we have to press the RC pile with 9Mpa (1,305.34 psi) to 
achieve  50Tons  working  loads  as  per  attached  table.  Penetration  Length  will  be  varied  as  per soil 
condition. 

We will ensure and confirmed with the RC pile installation procedure and method to achieve designed 
criteria of the Building. Should you have any comments, please do let us know. Thank you. 

Prepared and Submit by            Checked and recommended By     

   
_____________________            _________________________ 
MYAT THU YA (PILE ENGINEER)            
PILE INSTALLATION GROUP 