PILE INSTALLATION GURANTEE AND RECOMMENDATION
Project Name : 8.5 Storey Building Construction, Pile Foundation Work
Employer Name : U Aung Naing
Attention to : U Tun Hla Aung (PE, 3rd Party)
Date : 27th February 2019
Reference : UAN/LuckyLink/001/2019
Dear U Tun Hla Aung,
I would like to submit the method statement, press pile machine converting table to measure the
building design load.
The criteria of the building working load are 25tons. According to safety factor 2time load and total
working load shall be 50tons. Our press pile machine converting table shown as 9Mpa (1,305.34psi)
is equivalent with the Load 549KN. Thus, we have to press the RC pile with 9Mpa (1,305.34 psi) to
achieve 50Tons working loads as per attached table. Penetration Length will be varied as per soil
condition.
We will ensure and confirmed with the RC pile installation procedure and method to achieve designed
criteria of the Building. Should you have any comments, please do let us know. Thank you.
Prepared and Submit by Checked and recommended By
_____________________ _________________________
MYAT THU YA (PILE ENGINEER)
PILE INSTALLATION GROUP