Paper 0414V1-1
Contents
Aim
Learning outcomes
4. Cost–value reconciliation
4.1 Claims, variations and cost–value reconciliation
4.2 Cost–value reconciliation and final accounts
Financial control for contractors Paper 0414 Page 2
Aim
z To introduce some key concepts in post-contract cost control for contractors.
Learning outcomes
After studying this module you should be able to:
z Discuss the main financial ratios used to ascertain the health of a construction
business.
z Explain the importance of accurate cash flow forecasting, discuss the common
forms of cash flow representation and comment upon the ways in which
contractors might improve their cash flow position.
In the construction industry there are big differences between firms, some being
below 5% and others over 40%. The average would appear to be about 15–20%, with
the civil engineering firms being slightly higher than building firms; but these figures
depend upon the state of the various markets and of the economy generally. This
percentage is used to indicate how efficiently funds are used compared with other
firms or other years.
2 Profit on turnover
In the construction industry this figure is likely to vary between 1% and 8%,
depending upon the type of work and the efficiency of the firm. A UK average is
probably about 2–3%, with building firms generally slightly lower than civil
engineering.
If the actual ratios are widely different from what is to be expected in the industry, or
if they do not appear to be moving towards targets set in the company’s policy
statements, the board should investigate, where possible identify the reason for the
deviation, and issue the necessary instructions to rectify the situation.
Financial control for contractors Paper 0414 Page 5
1.5 Budgets
Preparation of the firm’s annual and medium term budgets are an essential part of the
financial control system. For the budget to be an efficient control tool, this means
estimating:
In terms of expenditure, the budget will need to include not only the direct costs of
carrying out the works, but also indirect costs and an allowance for distribution to
shareholders.
1 Indirect costs
Indirect costs may be defined as those costs that the contractor faces whether or not it
actually carries out any work. In crude terms, the commercial value of construction
work will include the total of the direct costs – that is, the net estimate – with
appropriate additions for indirect costs, basically represented by overheads and profit.
On top of this the bid price may then include an adjustment to reflect the perceived
risk, the degree of utility the contractor places on getting the job, here termed the risk
margin, and the contractor’s assessment of the marketplace at the time the bid is
submitted.
Net estimate
+
Overheads (%)
+
Additional project financing costs
+
Required profit (%)
+
Risk margin
+
Market risk allowance (may be negative)
=
Bid price
Each component must be considered separately, and one must be especially careful
not to confuse overheads, profit, additional project financing costs, risk margin and
the market adjustment.
Companies must plan their financial activity for the year, and the annual plan will
therefore include a prediction of the cost of overheads and an assessment of the base
level of profit required to present a reasonable return to the company’s shareholders.
Note that the baseline profit figure will include provision for the cost of normal
finance needed to keep the company afloat, but some projects may require additional
financing.
Overheads, calculation of the base profit margin and some elementary aspects of
supplementary project financing are considered here. The issue of risk margin is
considered in more detail in other papers.
Financial control for contractors Paper 0414 Page 6
2 Overheads
Overheads represent the fixed costs of running the company regardless of whether the
company does any work or not. Costs will therefore include factors such as head
office staff salaries and on-costs, the cost of providing and maintaining company cars,
head office rental or mortgage payments, and operating expenses such as telephones,
heating and lighting.
The plan will therefore include an anticipated overheads component based on the
projected level of activity planned for the year. Most companies will project their
anticipated overhead expenditure for the coming year based on past costs, with
allowances for any additional resources required and for inflation.
3 Baseline profit
Baseline profit is defined here as the amount of money the contractor must make in
order to be able to service its forthcoming projected financial commitments. This
requires an assessment of the basic finance the company will require during the year.
To assess the level of baseline profit required, the contractor must consider:
z the proposed level of activity for the year, usually denoted by projected
turnover;
z the finance necessary to support the proposed level of activity;
z the return that needs to be earned on turnover in order to service the debt.
£150,000
× 100% = 1.5%
£10,000,000
Assume that overheads, based on last year’s costs with additions for inflation etc, are
£500,000. Then the required recovery of overheads, as a percentage of turnover, is:
The combined baseline percentage on turnover required to cover the overheads and
finance the necessary debt is thus 6.5%.
Financial planning also means monitoring the company’s performance and cash flow
and taking remedial action as the year progresses. The baseline percentage required
may therefore change as time goes by. As an example, consider what would happen if
the anticipated turnover were not achieved. Assume that turnover only reaches
£8,500,000. Basic required earnings are still as before, ie £650,000 for profit and
overheads. To earn this level of return on a reduced turnover of £8,500,000 will
therefore require a mark-up of 7.65%.
Financial control for contractors Paper 0414 Page 7
The budgets must be realistic. They must indicate to the directors the amount of
money the firm is likely to require in the budget period, for:
z capital projects – new headquarters, regional offices, new staff cars, furniture
etc;
z working capital to pay wages and subcontractors, purchase building land and
materials etc.
At this level, separate budgets are usually prepared for the different areas in which the
firm is involved – capital budget, maintenance budget, turnover or contracts budget
etc – as well as a general overall budget for the firm. The number and complexity of
the various budgets will depend upon the size and type of firm, but it is essential for
good control that they can be understood easily by those intending to use them. In
general, the simpler the better.
From this information managers can decide whether it is advisable to tender for
certain projects. A high expected outflow of cash on a new project that is likely to
coincide with a high outflow on projects already under way may be disastrous for the
firm. Sufficient overdraft may be difficult or impossible to obtain, and it may be
better to turn down the invitation to tender on what may appear to be a profitable
contract because of the possibility of running into financial difficulties later.
The more reliable the cost information system of the firm, the better the chances of
efficient financial control.
z Contractors’ receipts are received from clients. Small firms involved with
jobbing and maintenance work are often not paid until they have submitted an
invoice. The management of the firm should ensure that invoices are sent out
promptly – though sometimes a short delay between carrying out the work and
submitting the invoice may be felt to enhance public relations.
z Firms involved in jobbing and maintenance are likely to have a large number
of clients, some of whom may take a long time to pay up even after receiving
the invoice. Others may never pay. Management should take all necessary
precautions to avoid bad debts by regular checking and follow-up procedures,
even employing solicitors to take action on long overdue accounts.
z Contractors often make payments some time after work has been carried out.
In the case of the contractor’s own workforce, some will be paid weekly and
others monthly, so that the contractor receives on average half a week’s or half
a month’s credit from these employees.
z Most materials are paid for two to six weeks after delivery, as suppliers usually
only require payment at the end of the month after the delivery date.
z Subcontractors and suppliers are also usually paid about a month or six weeks
after their work has been carried out. These conditions may vary, depending
upon whether the suppliers or subcontractors are nominated or not.
z In the course of carrying out its business, the firm will incur tax liabilities, but
these may not be paid to the government until as much as two years after the
work has been carried out.
z Delays can be built into the process. Receipts for work done may be delayed
by the quantity surveyor if he is slow in sending his valuation to the architect.
z The architect may delay payment still further in communicating his certificate
to the client. The client may delay the payment still further, either intentionally
or because of his system (eg signing most of his cheques on the last day of the
month). Though the contract will lay down certain requirements with regard to
payments, it is unlikely, because of the public relations issues involved that
contractors will take legal action to ensure prompt payment unless the problem
becomes especially serious. The prudent contractor when estimating and
working out his cash flows, will therefore allow for these unfortunate but
common delays.
Financial control for contractors Paper 0414 Page 9
Reducing/delaying expenditure
The basic requirements of the contractor’s cost control system are the same as for the
client. However, the contractor will be trying to juggle numerous projects
simultaneously and looking to maximise his profits. The type of project being
undertaken, its value and duration all influence the way in which the system will
operate. The contractor needs to establish principles and coding systems that are
flexible enough to suit all types of project.
The estimate and the post-contract plan (method statements, resource analysis etc)
should form the basic documents for the financial control of a project, and once the
job is won the estimate then becomes the project budget. The contractor’s rates in the
bill of quantities are normally broken down into labour, plant, materials and on-costs,
including profit. The first three factors are direct costs to the project. The on-costs
provide a contribution towards the general running and profitability of the firm.
By combining the information in the estimate with the post-contract plan, it should be
possible to prepare a week-by-week list of expected expenditures. This is likely to be
exclusive of the work of nominated subcontractors and that covered by provisional
sums.
By using the rates in the bill of quantities and the programme, it is possible to
estimate the amount to be expected in each monthly valuation. From these two
calculations can be calculated a net expected cash flow for the project. If it is found
that the net outflow figure is unacceptably high, it may be possible to adjust the work
so that a more acceptable one can be obtained.
Financial control for contractors Paper 0414 Page 10
Two methods are conventionally used to depict a contractor’s cash flow for a project:
the cumulative S-curve and the Ogee curve (sometimes termed a ‘sawtooth’ diagram).
These can be computer-generated using a formula or by pricing a programme of
work.
Example 1 shows the contractor receiving his payments in line with a JCT 05 type
contract. It is normal for the contractor to operate in a deficit for much of the contract
period, but by good financial management (or by manipulating the prices in his
tender) he may be able to achieve a positive cash flow earlier.
Example 2 shows the Ogee curve (or ‘saw-tooth’ diagram), which shows clearly
when the contractor is in a positive cash flow position and the amount of money that
will need to be financed each month. The vertical lines each month indicate the size
of the payment that has been received from the client.
In each case the deficit between expenditure and income represents the amount of
capital required to service the project, sometimes termed ‘capital lock-up’.
In Example 3 the project lasts six months with a six-months defects period. The
contractor’s capital outlay is repaid three months after it has been incurred. A 10%
profit is built into the project. The retention percentage is 5%.
The programme shows the cost of each activity, with the calculation of the cash
requirement shown below. The cost of each activity is shown per month in £’000s.
The income received takes into account the addition of 10% for profit and the
reduction of 5% for retention on the contractor’s monthly costs. This is then paid two
months in arrears. Half of the retention is released at practical completion and the
other half after the end of the defects liability period.
Payments are likely to be made throughout the defects period as elements of the final
account are agreed, but for simplicity this has not been taken into account here.
Financial control for contractors Paper 0414 Page 12
Monthly expenditure 35 26 13 17 7 6
Income received – – 36.6 27.2 13.6 17.8 7.3 9.2 2.7
Cumulative expenditure 35 61 74 91 98 104 104 104 104
Cumulative income – – 36.6 63.8 77.4 95.2 102.5 111.7 114.4
Cash required each
month
Cumulative deficit 35 61 37.4 27.2 20.6 8.8 1.5 – –
Cumulative profit 7.7 10.4
Example 3 explains the principle used for producing the cash flow. In the example,
the maximum cash required at any time will be £61,000 in Month 2. If this were
funded by a bank overdraft, the overdraft limit would need to be, say, £65,000 to
allow for any undervaluation or over-expenditure.
Financial control for contractors Paper 0414 Page 13
4 Cost–value reconciliation
The contractor must compare his actual expenditure with his predicted cash flow
forecast to ensure that he will eventually make the estimated profit. He should be able
to identify where he has made a profit or a loss and how this compares to the
anticipated expenditure. The procedure carried out by many contractors’ surveyors is
termed cost–value reconciliation. Simple reconciliations will typically be made on a
monthly basis and more detailed analysis on a three-monthly basis.
Standard pro formas are completed to identify expenditure made and monies received
against elements of the project. With the increase of computer-based accounting
systems and sophisticated coding, the contractor can analyse his expenditure
relatively easily in order to compare it with the sums received in an interim valuation.
Cost centres should be established for the project and given a code, decided by the
degree of information required by the management and the available resources
(manpower) to operate the system. There should be enough cost centres to give
adequate and appropriate control, but the system needs to be cost-effective to operate.
There is little use in providing very detailed information, at great expense, too late for
a decision to be made to be effective for control. Variances between actual and
forecast costs need to be analysed and fed back to the estimating departments so that
errors are not repeated.
Example 4 shows a simple form for a contractor’s monthly cost report in which only
nine cost centres have been used. Costs are given in £000s. If there is a problem with
a particular cost centre, there may be enough time to collect further information and
analyse it in more detail.
However, managers often make judgments for corrective action from their experience
because there is not enough time or resources to resort to further analysis. Some
managers in fact prefer to use their judgment, as this is what makes their job
interesting and a challenge.
In Example 4 the contractor has estimated his final costs for the construction of a
series of boathouses as £5,519,000, but anticipates receiving £5,658,000 from the
client, giving him a £139,000 profit. If the losses on general items and in situ concrete
can be reduced, perhaps by more efficient working or cheaper suppliers, the profit
may be increased further.
Financial control for contractors Paper 0414 Page 14
Financial control for contractors Paper 0414 Page 15
If the contractor has tendered for and been successful in several contracts, he should
combine the cash flow charts and, where possible, arrange the programmes so that
high excess of costs over receipts on each project do not coincide. The expected cash
flow information will provide the financial plan against which financial control can
be measured. Each month the actual costs for the contract and the certificates issued
must be compared with the financial plan. If there are any large discrepancies, a
reconciliation statement should be made to indicate where the differences are and
what adjustments are to be made to allow for them and correct them where necessary.
z Estimated value of work less retention may be stated for each month.
z Estimated direct cost of the work before adjusting for payment delays may also
be listed for each month.
z Comparison of actual costs and receipts with the plan is unlikely to be
straightforward, for a variety of reasons, some of which are listed below.
{ The work may not be exactly according to programme.
{ Certificates may be paid faster or slower than anticipated.
{ Variations will affect the figures.
{ True value of fluctuation will be difficult to calculate.
{ Payments for fluctuations may not be based on true fluctuations (eg
formula price method). With other methods, some materials may not be
included in the basic list of materials used to calculate fluctuations.
{ Invoices from suppliers and or subcontractors may be late in arriving.
{ The QS valuation may include the full tender value, whereas there may
still be some further work to do (eg making good defects etc).
Financial control for contractors Paper 0414 Page 16
Financial control for contractors Paper 0414 Page 17
If the discrepancies are due to changes in the cost of the work, compare the cost of
individual bill of quantities items or groups of items with the rates included in the
tender. This may bring to light poor estimating or it may indicate possible errors in
the Bill or client variations. In such cases appropriate corrective action should be
taken. Or it may lead to improvement in the method of working on site, if the high
costs are due to poor management, inefficient operatives, poor utilisation or lack of
plant.
To check this type of detail, it is necessary to receive adequate feedback from site on
the time spent by operatives on different tasks. One person, perhaps a trainee
manager, should be made responsible for compiling and returning this information to
head office. All head office departments must co-operate fully if proper financial
plans are to be prepared and the necessary control data provided. However, the
system used must be relatively simple, otherwise the cost of operating it may exceed
the increased profit that should result from the control.
At the end of a project, a report should be prepared on how accurate the financial
forecasting has appeared to be, with reasons for any discrepancies between forecast
and actual. The report may be broken down into sections, covering:
z own labour;
z subcontract labour;
z materials;
z plant;
z PC sums;
z project on-costs;
z head office expenses.
In some firms separate monthly forecasts are prepared for materials, own labour,
subcontract labour, plant etc on each project. These can then be compared with the
actual expenditure on each item. However, preparing very detailed information for
each month for each project is likely to be time-consuming and expensive. When
setting up any financial control system, bear in mind that the saving resulting from
using the system must be at least as great as the cost of administering and running it.
There is a break-even point at which additional expenditure on the system will result
in a smaller marginal saving than the additional expenditure.
EXAMPLE 6
It is estimated that, under its usual procedures, a firm would incur a direct cost of
£1,750,000 on a project.
Employing an additional materials checker at a cost of £6000 would reduce the direct cost
to £1,740,000 plus cost of checker.
If security guards were also employed, pilfering would be reduced and materials costs
would be £15,000 less. The cost of the proposed guards would be £12,000.
It is estimated that additional forecasting of costs and cost checking by the accounts
department would reduce the materials costs still further by £7000, but this would involve
extra head office staff costs of £5500.
By using a computer and extra feedback from site, more materials and labour savings of
approximately £9000 could be made. The cost of using the computer is estimated at £6000
and the additional labour necessary to provide feedback on site is £3500.
When expressed like this, it is obvious which measures are going to benefit the firm. In
practice, many elaborate schemes are brought into operation which cost more to run than
the benefits in savings which they achieve. In this example, the materials checker would
result in a net saving of £4000, the security guard £3000, and the accounts department
£1500, but the use of the computer system would result in a net extra expense of £500.
The first three therefore might be introduced, but the fourth would probably not be. As the
figures are only estimates, the likely prediction errors and the social effects of introducing
the procedures should also be considered by the management.
This point raises a number of potential problem areas from an accounting point of
view, problems which have become more evident in the case of recent high profile
company failures. In essence, including optimistic values will result in the
contractor’s financial position appearing to be better than it may be, and pessimistic
projections will have the reverse effect.
Issues such as these are closely bound up with the company’s management
philosophy. If the surveyor believes, for example, that he will be held accountable in
some way for unprofitable projects, then his behaviour will be influenced
accordingly. Both approaches however have the potential to cause serious problems
for the contractor’s consolidated accounts, and a consistent policy must be adopted
for the calculation of all cost–value reconciliations.
Financial control for contractors Paper 0414 Page 19
The following measures may go some way to ensure that the figures are accurately
presented:
z making the quantity surveyor and project manager jointly responsible for the
cost–value reconciliation;
z disclosure by the quantity surveyor of supporting documents used;
z disclosure of a preliminary valuation of the work in progress prior to the
release of the cost information, which will prevent the quantity surveyor
manipulating the reported income to suit the reported costs for the accounting
period;
z meetings between the contractor’s quantity surveyor, accountants and middle
management to probe and examine the project cost variation reports.
Further problems arise with the reporting of likely profits and losses. Fluctuations in
profitability will inevitably arise from estimating errors, non-recoverable costs (eg for
remedial work) and other variable risks. A sensible approach might be to take profit
as work proceeds on the basis of a proportion of the anticipated final out-turn.
How then should the contractor deal with variations which have not been agreed?
Clearly, some form of conservative estimate of the amount likely to be received has
to be made. Once again, this is a matter of the contractor’s quantity surveyor applying
professional judgment.
Settlement of contractual claims for delay, disruption, acceleration and other causes
of loss and expense may take many years. Differences of opinion between the
contractor and the contract administrator as to entitlement, liability and/or quantum
with respect to a particular claim creates a high degree of uncertainty as to the final
out-turn, and this can cause severe problems for contractors when preparing the year-
end or other financial accounts that have to be independently audited.
Financial control for contractors Paper 0414 Page 20
It has therefore been suggested that the cost–value reconciliation should separately
identify:
‘The settlement of claims arising from circumstances not envisaged in the contract
or arising as an indirect consequence of approved variations is subject to a high
level of uncertainty relating to the outcome of future negotiations. In view of this,
it is generally prudent to recognise receipts in respect of such claims only when
negotiations have reached an advanced stage and there is sufficient evidence of
the acceptability of the claim principle to the purchaser, with an indication of the
amount involved also being available.’
Similarly, the International Accounting Standard 11: Construction Contracts (IAS 11)
states:
‘A claim is an amount that the contractor seeks to collect from the customer or
another party as reimbursement for costs not included in the contract price. A
claim may arise from, for example, customer-caused delays, errors in
specifications or design, and disputed variations in contract work. The
measurement of the amounts of revenue arising from claims is subject to a high
level of uncertainty and often depends on the outcome of negotiations. Therefore,
claims are only included in contract revenue when: