ADICIONAL
PRESUPUESTO DE OBRA (MODIFICACION Nº 01) PRESUPUESTO
POR MAYOR POR PARTIDAS DEDUCTIVO
MODIFICADO
ITEM DESCRIPCION PARCIAL METRADO NUEVAS
00.00 COMPONENTE I: INFRAESTRUCTURA
01.00 OBRAS PRELIMINARES Y COMPLEMENTARIAS 657,698.58 30,553.00 0.00 0.00 688,251.58
02.00 ESTRUCTURAS 4,170,916.11 1,031,978.67 94,187.86 -413,868.06 4,883,214.58
03.00 ARQUITECTURA 4,406,885.68 0.00 0.00 0.00 4,406,885.68
04.00 INSTALACIONES SANITARIAS 379,179.13 0.00 0.00 0.00 379,179.13
05.00 INSTALACIONES ELECTRICAS 1,622,521.68 0.00 0.00 0.00 1,622,521.68
06.00 INSTALACIONES DE COMUNICACIONES 467,870.82 0.00 0.00 0.00 467,870.82
GASTOS DIRECCION TECNICA, SEGURIDAD Y SALUD DE OBRA 1,109,393.84 85,002.53 7,535.03 -33,109.44 1,168,821.96
GASTOS SUPERVISION 416,022.69 31,875.95 2,825.64 -12,416.04 438,308.24
GASTOS LIQUIDACION 138,674.23 10,625.32 941.88 -4,138.68 146,102.75
GASTOS DE GESTION Y ORGANIZACIÓN ADMINISTRATIVA 277,348.46 21,250.63 1,883.76 -8,277.36 292,205.49
TOTAL COSTO PROYECTO 15,808,862.22 16,655,712.91
RESUMEN DE METRADOS POR BLOQUES
Proyecto : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Cadena Funcional : 0004
Obra : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Inspector de Obra : Angel Gallegos Huamán
Ent. Ejec. : UNIVERSIDAD NACIONAL DE MOQUEGUA Residente de Obra: Edgar Henrry Provincia Huanca
Mod. Ejec. : ADMINISTRACION PRESUPUESTARIA DIRECTA Fecha de Inicio : 01 de agosto de 2018
Ger. Ejec. : OFICINA DE INFRAESTRUCTURA Y GESTION DE PROYECTOS Fecha de Término : 24 de setiembre de 2019
Proyecto : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Cadena Funcional : 0004
Obra : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Inspector de Obra : Angel Gallegos Huamán
Ent. Ejec. : UNIVERSIDAD NACIONAL DE MOQUEGUA Residente de Obra: Edgar Henrry Provincia Huanca
Mod. Ejec. : ADMINISTRACION PRESUPUESTARIA DIRECTA Fecha de Inicio : 01 de agosto de 2018
Ger. Ejec. : OFICINA DE INFRAESTRUCTURA Y GESTION DE PROYECTOS Fecha de Término : 24 de setiembre de 2019
02.00 ESTRUCTURAS
RESUMEN DE METRADOS POR BLOQUES
Proyecto : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Cadena Funcional : 0004
Obra : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Inspector de Obra : Angel Gallegos Huamán
Ent. Ejec. : UNIVERSIDAD NACIONAL DE MOQUEGUA Residente de Obra: Edgar Henrry Provincia Huanca
Mod. Ejec. : ADMINISTRACION PRESUPUESTARIA DIRECTA Fecha de Inicio : 01 de agosto de 2018
Ger. Ejec. : OFICINA DE INFRAESTRUCTURA Y GESTION DE PROYECTOS Fecha de Término : 24 de setiembre de 2019
Proyecto : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Cadena Funcional : 0004
Obra : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Inspector de Obra : Angel Gallegos Huamán
Ent. Ejec. : UNIVERSIDAD NACIONAL DE MOQUEGUA Residente de Obra: Edgar Henrry Provincia Huanca
Mod. Ejec. : ADMINISTRACION PRESUPUESTARIA DIRECTA Fecha de Inicio : 01 de agosto de 2018
Ger. Ejec. : OFICINA DE INFRAESTRUCTURA Y GESTION DE PROYECTOS Fecha de Término : 24 de setiembre de 2019
Proyecto : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Cadena Funcional : 0004
Obra : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Inspector de Obra : Angel Gallegos Huamán
Ent. Ejec. : UNIVERSIDAD NACIONAL DE MOQUEGUA Residente de Obra: Edgar Henrry Provincia Huanca
Mod. Ejec. : ADMINISTRACION PRESUPUESTARIA DIRECTA Fecha de Inicio : 01 de agosto de 2018
Ger. Ejec. : OFICINA DE INFRAESTRUCTURA Y GESTION DE PROYECTOS Fecha de Término : 24 de setiembre de 2019
02.03.06 PLACAS
02.03.06.01 PLACAS: CONCRETO F'C=210 KG/CM2. m3 457.92 33.48 140.89 229.17 46.32 0.00
02.03.06.02 PLACAS: ENCOFRADO Y DESENCOFRADO m2 3,220.47 235.16 1,118.43 1,717.54 387.52 0.00
02.03.06.03 PLACAS: ACERO CORRUGADO F'Y=4200 KG/CM2 GRADO 60 kg 52,663.91 3,334.06 18,341.25 31,992.02 5,086.15 0.00
02.03.07 VIGAS
02.03.07.01 VIGAS: CONCRETO F'C=210 KG/CM2 C/ADITIVO PLASTIF. CARAVIST m3 359.95 16.71 103.41 184.59 31.04 48.33
02.03.07.02 VIGAS: ENCOFRADO Y DESENCOFRADO m2 1,768.01 119.29 651.28 1,309.42 239.39 383.28
02.03.07.03 VIGAS: ACERO CORRUGADO F'Y=4200 KG/CM2 GRADO 60 kg 51,096.28 2,099.17 17,831.11 31,417.59 4,425.55 5,803.71
02.03.08 VIGUETAS DE ARRIOSTRE
02.03.08.01 VIGUETAS DE ARRIOSTRE: CONCRETO F'C=175 KG/CM2 m3 20.83 0.59 7.26 7.40 5.53 1.05
02.03.08.02 VIGUETAS DE ARRIOSTRE: ENCOFRADO Y DESENCOFRADO m2 307.22 8.12 107.70 109.12 81.63 13.97
02.03.08.03 VIGUETAS DE ARRIOSTRE: ACERO CORRUGADO FY=4200 KG/CM2 kg 1,999.89 61.68 696.41 712.58 529.22 131.50
02.03.09 LOSAS ALIGERADAS
02.03.09.01 LOSA ALIGERADA : CONCRETO F'C= 210 KG/CM2 m3 429.53 13.21 147.45 229.46 44.38 0.00
02.03.09.02 LOSA ALIGERADA: ENCOFRADO Y DESENCOFRADO m2 4,046.71 164.13 1,351.44 2,265.95 444.92 0.00
02.03.09.03 LOSA ALIGERADA: LADRILLO HUECO DE ARCILLA 20X30X30 CM. und 27,577.40 0.00 10,841.00 19,740.00 0.00
02.03.09.04 LOSA ALIGERADA: LADRILLO HUECO DE ARCILLA 15X30X30 CM. und 4,960.07 1,358.00 3,304.00 0.00
02.03.09.05 LOSA ALIGERADA: ACERO CORRUGADO F'Y=4200 KG/CM2 GRADO kg 38,015.86 1,063.73 8,927.62 14,220.28 2,813.86 0.00
02.03.10 ESCALERAS
02.03.10.01 ESCALERA : CONCRETO F'C= 210 KG/CM2. m3 23.26 0.00 16.77 17.22 0.00 0.00
02.03.10.02 ESCALERA: ENCOFRADO Y DESENCOFRADO m2 121.86 0.00 71.69 86.38 0.00 0.00
RESUMEN DE METRADOS POR BLOQUES
Proyecto : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Cadena Funcional : 0004
Obra : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Inspector de Obra : Angel Gallegos Huamán
Ent. Ejec. : UNIVERSIDAD NACIONAL DE MOQUEGUA Residente de Obra: Edgar Henrry Provincia Huanca
Mod. Ejec. : ADMINISTRACION PRESUPUESTARIA DIRECTA Fecha de Inicio : 01 de agosto de 2018
Ger. Ejec. : OFICINA DE INFRAESTRUCTURA Y GESTION DE PROYECTOS Fecha de Término : 24 de setiembre de 2019
02.03.10.03 ESCALERA: ACERO CORRUGADO F'Y=4200 KG/CM2 kg 8,577.91 0.00 1,358.35 1,421.84 0.00 0.00
02.03.11 TANQUE CISTERNA
02.03.11.01 TANQUE CISTERNA: CONCRETO F'C=210 KG/CM2 m3 34.85 0.00 0.00
02.03.11.02 TANQUE CISTERNA: ENCOFRADO Y DESENCOFRADO m2 195.83 0.00 0.00
02.03.11.03 TANQUE CISTERNA: ACERO CORRUGADO F'Y=4200 KG/CM2 GRADO kg 2,564.68 0.00 0.00
02.03.12 RAMPAS DE CONCRETO
02.03.12.01 RAMPAS:CONCRETO F´C=210KG/CM2 m3 383.65 0.00 0.00 65.33
02.03.12.02 RAMPAS:ENCOFRADO Y DESENCOFRADO m2 858.38 0.00 0.00 546.95
02.03.12.03 RAMPAS: ACERO F'Y=4200 KG/CM2 GRADO 60 kg 13,344.83 0.00 0.00 3,409.20
02.03.13 MESON DE CONCRETO
02.03.13.01 MESON DE CONCRETO: CONCRETO F'C= 210 KG/CM2. m3 17.40 0.00 0.00 17.40
02.03.13.02 MESON DE CONCRETO: ENCOFRADO Y DESENCOFRADO m2 97.77 0.00 0.00 97.77
02.03.13.03 MESON DE CONCRETO: ACERO DE REFUERZO F'y=4200 kg/cm2, G kg 1,280.52 0.00 0.00 1,280.52
Proyecto : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Cadena Funcional : 0004
Obra : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua Inspector de Obra : Angel Gallegos Huamán
Ent. Ejec. : UNIVERSIDAD NACIONAL DE MOQUEGUA Residente de Obra: Edgar Henrry Provincia Huanca
Mod. Ejec. : ADMINISTRACION PRESUPUESTARIA DIRECTA Fecha de Inicio : 01 de agosto de 2018
Ger. Ejec. : OFICINA DE INFRAESTRUCTURA Y GESTION DE PROYECTOS Fecha de Término : 24 de setiembre de 2019
02.06.00 VARIOS
02.06.01 CURADO DE ELEMENTOS ESTRUCTURALES C/ADITIVO m2 1,572.10 708.00 3,276.00 4,671.00 1,349.00 2,323.23
02.06.02 CURADO DE LOSA ALIGERADA m2 1,572.10 164.00 1,351.00 2,266.00 445.00 0.00
02.06.03 JUNTA DE CONSTRUCCION CON TEKNOPORT 3" m 1,114.20 76.30 597.40 291.20 225.60 0.00
02.06.04 JUNTA DE SEPARACION SISMICA C/ELASTOMERICO m 132.40 36.30 50.35 45.75 0.00
02.06.05 TAPAJUNTAS DE ALUMINIO m 132.40 36.30 50.35 45.75 0.00
E METRADOS POR BLOQUES
02.00 ESTRUCTURA
02.01 MOVIMIENTO DE TIERRAS
02.01.01 NIVELACION DE TERRENO m2 1,572.10 4.05 6,367.01 703.41
02.01.02 EXCAVACION DE ZANJAS PARA ZAPATAS Y CIMIENTOS C/ MAQUINARIA m3 6,946.79 11.16 77,526.18 342.27
02.01.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 1,968.86 62.90 123,841.29 676.71
02.01.04 RELLENO CON AFIRMADO A-1 COMPACTADO AL 95% P.M., E=0.20m. m3 628.84 39.62 24,914.64
02.01.05 RELLENO MASIVO CON HORMIGON COMPACTADO AL 95% P.M., E=0.20m. m3 314.42 39.62 12,457.32
02.01.06 RELLENO MASIVO CON MATERIAL (50%OVER+30%CONFITILLO+20%ARENA GRUESA) AL 95% P.Mm3 628.84 39.62 24,914.64
02.01.07 ELIMINACION DE MATERIAL EXCEDENTE DISTANCIA 1 KM m3 0.00 12.76 0.00 0.00
02.01.08 ELIMINACION DE MATERIAL EXCEDENTE DISTANCIA 5 KM m3 4,977.93 14.48 72,080.43 194.85
02.01.09 PREPARACION Y ACARREO DE MATERIAL PROPIO PARA RELLENO m3 33.98
02.03.07 VIGAS
02.03.07.01 VIGAS: CONCRETO F'C=210 KG/CM2 C/ADITIVO PLASTIF. CARAVISTA m3 359.95 486.12 174,978.89 24.13
02.03.07.02 VIGAS: ENCOFRADO Y DESENCOFRADO m2 1,768.01 120.09 212,320.32 934.65
02.03.07.03 VIGAS: ACERO CORRUGADO F'Y=4200 KG/CM2 GRADO 60 kg 51,096.28 5.34 272,854.14 10,480.85
02.03.08 VIGUETAS DE ARRIOSTRE
02.03.08.01 VIGUETAS DE ARRIOSTRE: CONCRETO F'C=175 KG/CM2 m3 20.83 376.41 7,840.62 1.00
02.03.08.02 VIGUETAS DE ARRIOSTRE: ENCOFRADO Y DESENCOFRADO m2 307.22 77.47 23,800.33 13.32
02.03.08.03 VIGUETAS DE ARRIOSTRE: ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 kg 1,999.89 5.33 10,659.41 131.50
02.03.09 LOSAS ALIGERADAS
02.03.09.01 LOSA ALIGERADA : CONCRETO F'C= 210 KG/CM2 m3 429.53 472.09 202,776.82 4.97
02.03.09.02 LOSA ALIGERADA: ENCOFRADO Y DESENCOFRADO m2 4,046.71 65.42 264,735.77 179.73
02.03.09.03 LOSA ALIGERADA: LADRILLO HUECO DE ARCILLA 20X30X30 CM. und 27,577.40 4.07 112,240.02 3,003.60
02.03.09.04 LOSA ALIGERADA: LADRILLO HUECO DE ARCILLA 15X30X30 CM. und 4,960.07 4.07 20,187.48
02.03.09.05 LOSA ALIGERADA: ACERO CORRUGADO F'Y=4200 KG/CM2 GRADO 60 kg 38,015.86 4.81 182,856.29
02.03.10 ESCALERAS
02.03.10.01 ESCALERA : CONCRETO F'C= 210 KG/CM2. m3 23.26 486.12 11,307.15 10.73
02.03.10.02 ESCALERA: ENCOFRADO Y DESENCOFRADO m2 121.86 101.93 12,421.19 36.21
02.03.10.03 ESCALERA: ACERO CORRUGADO F'Y=4200 KG/CM2 kg 8,577.91 5.34 45,806.04
02.03.11 TANQUE CISTERNA
02.03.11.01 TANQUE CISTERNA: CONCRETO F'C=210 KG/CM2 m3 34.85 486.12 16,941.28 2.74
02.03.11.02 TANQUE CISTERNA: ENCOFRADO Y DESENCOFRADO m2 195.83 48.61 9,519.30 4.20
02.03.11.03 TANQUE CISTERNA: ACERO CORRUGADO F'Y=4200 KG/CM2 GRADO 60 kg 2,564.68 5.10 13,079.87
02.03.12 RAMPAS DE CONCRETO
02.03.12.01 RAMPAS:CONCRETO F´C=210KG/CM2 m3 383.65 498.42 191,218.83
02.03.12.02 RAMPAS:ENCOFRADO Y DESENCOFRADO m2 858.38 160.08 137,409.47
02.03.12.03 RAMPAS: ACERO F'Y=4200 KG/CM2 GRADO 60 kg 13,344.83 5.04 67,257.94
02.03.13 MESON DE CONCRETO
02.03.13.01 MESON DE CONCRETO: CONCRETO F'C= 210 KG/CM2. m3 17.40 486.12 8,458.49 0.00
RESUMEN PRESUPUESTO MODIFICADO Nº 02
Proyecto : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua
Obra : Creación de la infraestructura e implementación de la Sede Central Administrativa de Universidad Nacional de Moquegua
Ent. Ejec. : UNIVERSIDAD NACIONAL DE MOQUEGUA
Mod. Ejec. : ADMINISTRACION PRESUPUESTARIA DIRECTA
Ger. Ejec. : OFICINA DE INFRAESTRUCTURA Y GESTION DE PROYECTOS
02.03.13.02 MESON DE CONCRETO: ENCOFRADO Y DESENCOFRADO m2 97.77 77.41 7,568.38 0.00
02.03.13.03 MESON DE CONCRETO: ACERO DE REFUERZO F'y=4200 kg/cm2, GRADO 60 kg 1,280.52 5.32 6,812.37 0.00
02.06.00 VARIOS
02.06.01 CURADO DE ELEMENTOS ESTRUCTURALES C/ADITIVO m2 1,572.10 2.32 3,647.27 10,755.13
02.06.02 CURADO DE LOSA ALIGERADA m2 1,572.10 1.56 2,452.48 2,653.90
02.06.03 JUNTA DE CONSTRUCCION CON TEKNOPORT 3" m 1,114.20 7.01 7,810.54 76.30
02.06.04 JUNTA DE SEPARACION SISMICA C/ELASTOMERICO m 132.40 20.25 2,681.10
02.06.05 TAPAJUNTAS DE ALUMINIO m 132.40 14.23 1,884.05
02.00.00 ESTRUCTURAS
02.01.00 MOVIMIENTO DE TIERRAS
02.01.09 Preparación y acarreo de material propio para relleno m3 2,645.57
PRESUPUESTO ADICIONAL Nº 02
P.U. PARCIAL
94,187.86
33.98 89,896.47
38.71 4,291.39
94,187.86
7,535.03
2,825.64
941.88
1,883.76
AL Nº 02 POR PARTIDAS NO CONSIDERADAS EN EL EXPEDIENTE TEC 107,374.17
PLANILLA
POR PARTIDAS NO CONSIDERADAS EN EL EXPEDIENTE TECNICO APROBADO
Proyecto : CREACIÓN DE LA INFRAESTRUCTURA E IMPLEMENTACIÓN DE LA SEDE CENTRAL ADMINISTRATIVA DE LA
UNIVERSIDAD NACIONAL MOQUEGUA - MOQUEGUA
Propietario : UNIVERSIDAD NACIONAL DE MOQUEGUA
Residente : Ing. EDGAR HENRRY PROVINCIA HUANCA
Inspector : Ing. ANGEL GALLEGOS HUAMAN
02.00.00 ESTRUCTURAS
02.01.00 MOVIMIENTO DE TIERRAS
02.01.09 Preparación y acarreo de material propio para relleno m3
CANTIDAD
2,645.57
110.86
PRESUPUESTO ADICIONAL Nº 02
POR MAYORES METRADOS
Proyecto : CREACIÓN DE LA INFRAESTRUCTURA E IMPLEMENTACIÓN DE LA SEDE CENTRAL ADMINISTRATIVA DE LA UNIVE
MOQUEGUA
Propietario : UNIVERSIDAD NACIONAL DE MOQUEGUA
Residente : Ing. EDGAR HENRRY PROVINCIA HUANCA
Inspector : Ing. ANGEL GALLEGOS HUAMAN
PRESUPUESTO
PARTIDA DESCRIPCION DE ACTIVIDAD
UND
02.00.00 ESTRUCTURAS
02.01.00 MOVIMIENTO DE TIERRAS
02.01.01 NIVELACION DE TERRENO m2
02.01.02 EXCAVACION DE ZANJAS PARA ZAPATAS Y CIMIENTOS C/ MAQUINARIA m3
02.01.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3
02.01.08 ELIMINACION DE MATERIAL EXCEDENTE DISTANCIA 5 KM m3
02.06.00 VARIOS
02.06.01 CURADO DE ELEMENTOS ESTRUCTURALES C/ADITIVO m2
02.06.02 CURADO DE LOSA ALIGERADA m2
02.06.03 JUNTA DE CONSTRUCCION CON TEKNOPORT 3" m
TOTAL COSTO DIRECTO
GASTOS DIRECCION TECNICA, SEGURIDAD Y SALUD OCUPACIONAL
GASTOS DE SUPERVISION
GASTOS DE LIQUIDACION
GASTOS DE GESTION Y ORGANIZACIÓN ADMINISTRATIVA
TOTAL PRESUPUESTO ADICIONAL Nº 02 POR MAYORES METRADOS
UPUESTO ADICIONAL Nº 02
R MAYORES METRADOS
LEMENTACIÓN DE LA SEDE CENTRAL ADMINISTRATIVA DE LA UNIVERSIDAD NACIONAL MOQUEGUA -
PRESUPUESTO ADICIONAL Nº 02
30,553.00
1,031,978.67
PRESUPUESTO ADICIONAL Nº 02
PRESUPUESTO ADICIONAL Nº 02
02.00.00 ESTRUCTURAS
02.01.00 MOVIMIENTO DE TIERRAS
02.01.01 NIVELACION DE TERRENO
02.01.02 EXCAVACION DE ZANJAS PARA ZAPATAS Y CIMIENTOS C/ MAQUINARIA
02.01.03 RELLENO COMPACTADO CON MATERIAL PROPIO
02.01.08 ELIMINACION DE MATERIAL EXCEDENTE DISTANCIA 5 KM
02.06.00 VARIOS
02.06.01 CURADO DE ELEMENTOS ESTRUCTURALES C/ADITIVO
02.06.02 CURADO DE LOSA ALIGERADA
02.06.03 JUNTA DE CONSTRUCCION CON TEKNOPORT 3"
PLANILLA
R MAYORES METRADOS
URA E IMPLEMENTACIÓN DE LA SEDE CENTRAL ADMINISTRATIVA DE LA UNIVERSIDAD
UND CANTIDAD
m2 35.11
m2 46.00
m2 38.50
m2 7.16
m2 300.11
mes 2.00
mes 2.00
mes 2.00
m3 28.75
m3 28.75
m2 703.41
m3 342.27
m3 676.71
m3 194.85
m2 432.19
m2 127.85
m2 127.85
m3 347.38
m2 327.88
kg 13,093.69
PLANILLA
R MAYORES METRADOS
URA E IMPLEMENTACIÓN DE LA SEDE CENTRAL ADMINISTRATIVA DE LA UNIVERSIDAD
UND CANTIDAD
m3 28.38
m2 230.49
kg 15,468.01
m3 0.02
m2 22.30
kg 661.02
m3 101.46
m2 867.48
kg 20,076.93
m3 4.59
m2 12.85
kg 741.13
m2 238.18
kg 6,089.57
m3 24.13
m2 934.65
kg 10,480.85
m3 1.00
m2 13.32
kg 131.50
m3 4.97
m2 179.73
und 3,003.60
m3 10.73
m2 36.21
PLANILLA
R MAYORES METRADOS
URA E IMPLEMENTACIÓN DE LA SEDE CENTRAL ADMINISTRATIVA DE LA UNIVERSIDAD
UND CANTIDAD
m3 2.74
m2 4.20
und 348.00
und 12.00
pto 16.00
m2 10,755.13
m2 2,653.90
m 76.30
PRESUPUESTO DEDUCTIVO Nº 02
02.00.00 ESTRUCTURAS
02.01.00 MOVIMIENTO DE TIERRAS
02.01.04 RELLENO CON AFIRMADO A-1 COMPACTADO AL 95% P.M., m3 628.84
02.01.05 RELLENO MASIVO CON HORMIGON COMPACTADO AL 95% P. m3 314.42
02.01.06 RELLENO MASIVO CON MATERIAL (50%OVER+30%CONFITIL m3 628.84
PRESUPUESTO DEDUCTIVO Nº 02
413,868.06
39.62 24,914.64
39.62 12,457.32
39.62 24,914.64
226.83 2,032.40
77.47 1,512.99
486.12 3,918.13
4.07 1,213.14
4.81 52,863.68
5.34 30,959.82
5.10 494.96
498.42 158,657.05
160.08 49,853.71
5.04 50,075.58
413,868.06
33,109.44
12,416.04
4,138.68
8,277.36
471,809.58
PLANILLA DEDUCTIVO Nº 02
02.00.00 ESTRUCTURAS
02.01.00 MOVIMIENTO DE TIERRAS
02.01.04 RELLENO CON AFIRMADO A-1 COMPACTADO AL 95% P.M., m3 628.84
02.01.05 RELLENO MASIVO CON HORMIGON COMPACTADO AL 95% P. m3 314.42
02.01.06 RELLENO MASIVO CON MATERIAL (50%OVER+30%CONFITIL m3 628.84