GRAN TIERRA ENERGY INC.

Daily Drilling Report


Well: PROSPERIDAD 1 Report no.: 2 Report date: 2/11/2019
Wellbore No.: Well Name: PROSPERIDAD 1 Block: EL PORTON Active datum: U @925.0ft (above Ground Level)
Project: EL PORTON Site: PROSPERIDAD 1 Rig Name/No.: Rig #1/5857
Event: ORIG DRILLING Start date: 2/10/2019 End date: Spud date: 2/10/2019
AFE No.: Well.057.0001/DRI AFE Estimator: German Bulla Drilling Supervisor: Eric Pedersen Engineer: German Bulla

COSTS
Authorized cost: 12,791,720.00 Daily cost: 154,187.62 (USD) Cumulative total: 3,011,775.23 (USD) Expenditure: 23.54%
(USD)
DEPTH DAYS
MD: 1,205.0 ft TVD: 1,204.8 ft Progress: 705.0 ft
Avg. ROP: 68.3 ft/hr Rotating hours: 10.32 hr Cum Rot Hrs: 22.32 hr
DFS: 2.00 days Est days: MD auth: 16,289.0 ft
Last Casing: 30.000 in @ 196.0 ft Size: 30.00 Shoe Depth TVD: 196.00 Shoe Depth MD: 196.00
STATUS
Current status: Driling 26-in section with BHA No. 2 into Guayabo Fm. to 1490 ft as follows parameters: Q=1350 gpm, SPP= 2270 psi, WOB= 8-25
Klb, RS= 110 rpm, TQ= 2 -6 Klb-ft.
24 hr summary: Drilled 26-in section with BHA No. 2 into Guayabo Fm. from 500 ft to 1205 ft, as follows parameters: Q=700-1350 gpm, SPP=
1800-2270 psi, WOB= 3-25 Klb, RS= 80-110 rpm, TQ= 2 -6 Klb-ft.
24 hr forecast: To Drill 26-in section with BHA No. 2 into Guayabo Fm. from 1490 ft to 2000 ft. Pooh BHA No. 2 to surface.

WEATHER
Weather: sunny day Temperature: ºF Comments:

SAFETY
Status
Topic: Avg. H2S: %
RID cards: Cum Stop Cards 62.00
Comments:
Inspections/Drills

Last weekly rig check: Daily inspection done: Last fire drill: Last evacuation drill:

Last Csg Press Test: Last Csg Press: Last safety inspection: Last safety meeting:
Last Spill Drill: Last trip drill: Last pit drill: Last diverter drill:
BOP Pressure Tests
Last BOP pressure test: Next test due: Last BOP function test: Last BOP drill:

Standpipe manifold: Kelly hose: Diverter pressure: Annular press:

Lower rams: Kill line: Choke line: Choke manifold:

PERSONNEL
Total No. of People: 96
Company No. People Company No. People
PETREX 40 NOV CS 8
SISAM 1 AXURE 1
SCHLUMBERGER 4 NOV FLUID 5
NOV INSTRUMENTACION 2 ARCO IRIS 2
PROMOVER 2 TECSOTROL 1
FALCK SERVICE 4 MSSP 2
NOV BIT 1 COLVISEG 2
WETHERFORD MUD LOGGING 6 GTEC 9
RAMDE 2 CANAGUARO 4
HOLE SECTIONS
Section Name Section type Effective Hole ID MD (ft) Hole section start Hole section end
Diameter (in) Top Base date/time date/time
(in)

2/12/2019 6:51:59AM version 1.5 www.grantierra.com 1


GRAN TIERRA ENERGY INC.

Daily Drilling Report


Well: PROSPERIDAD 1 Report no.: 2 Report date: 2/11/2019
Wellbore No.: Well Name: PROSPERIDAD 1 Block: EL PORTON Active datum: U @925.0ft (above Ground Level)
Project: EL PORTON Site: PROSPERIDAD 1 Rig Name/No.: Rig #1/5857
Event: ORIG DRILLING Start date: 2/10/2019 End date: Spud date: 2/10/2019
AFE No.: Well.057.0001/DRI AFE Estimator: German Bulla Drilling Supervisor: Eric Pedersen Engineer: German Bulla

HOLE SECTIONS
Section Name Section type Effective Hole ID MD (ft) Hole section start Hole section end
Diameter (in) Top Base date/time date/time
(in)
26 Open Hole 26.00 0.0 2/9/2019 12:00AM

MATERIALS
Product name Weight/Vol. per Usage Quantity end Product name Weight/Vol. per Usage Quantity end
unit unit

MUD
Daily mud: 13,516.39 USD Cum. mud cost: 33,126.02 USD
Mud desc. Density Viscosity Date/Time MD PV YP Cl- Ca+ pH Pm Pf Mf
(ppg) (s/qt) check (cp) (lbf/100f (ppm) (ppm) (cc) (cc)
(ft) t²)
MMH 8.80 51.00 2/11/2019 6:00:00AM 500.0 9.00 41.000 60 10.40 0.23 1.30 1.30
MMH 8.80 49.00 2/11/2019 1:00:00PM 676.0 9.00 42.000 0 60 10.40 0.23 1.30 1.30
MMH 8.80 48.00 2/11/2019 6:00:00PM 832.0 9.00 43.000 0 80 10.50 0.26 1.40 1.40

BHA no.# 1 Bit no.:

Date/Time in: 2/10/2019 9:30PM Date/Time out: Purpose:


BHA Length: 0.00 (ft) Min. ID: 2.750 (in) Weight (Above/Below) Jars:
MD Footage String Wt Drag TQ On/Off
(ft) (ft) Up / Down / Rot (kip) (ft-lbf)
(kip)

Assembly Components
Component type No. Length OD ID Connection Weight Grade Pin Serial no. Left Fish Neck
of (ft) (in) (in) OD Name (ppf) Box or Length OD
joints (in) right (ft) (in)
spiral

PUMP/HYDRAULICS
No. Make/Model Stroke Liner size Efficiency Pressure SPM Output Kill SPM/Pressure/Depth
(in) (in) (%) (psi) (spm) (gpm) (spm/psi/ft)
1 WIRTH / TPK 2200 14.00
2 WIRTH / TPK 2200 14.00
3 WIRTH / TPK 2200 14.00 6.500

MUD SYSTEM
Gas Volumes Losses

Avg. conn. gas (%): Total string vol. (bbl): 0.0 Surface total (bbl) : 660.0
Max. connection gas (%): Total annular vol. (bbl): 0.0 Subsurface total (bbl) :

Avg. trip gas (%): Total pit vol. (bbl): 0.0

Max. trip gas (%): Lines (bbl): 0.0

Avg. background gas (%):

Max. background gas (%): Total system vol. (bbl): 0.0 Total (bbl): 660.0

MUD PRODUCTS
Product Units Used Day cost (USD) Quantity end
AQUA FILM W lb 5.00 200.65 210.00
CARBONATO M 200 lb 40.00 132.00 520.00

2/12/2019 6:51:59AM version 1.5 www.grantierra.com 2


GRAN TIERRA ENERGY INC.

Daily Drilling Report


Well: PROSPERIDAD 1 Report no.: 2 Report date: 2/11/2019
Wellbore No.: Well Name: PROSPERIDAD 1 Block: EL PORTON Active datum: U @925.0ft (above Ground Level)
Project: EL PORTON Site: PROSPERIDAD 1 Rig Name/No.: Rig #1/5857
Event: ORIG DRILLING Start date: 2/10/2019 End date: Spud date: 2/10/2019
AFE No.: Well.057.0001/DRI AFE Estimator: German Bulla Drilling Supervisor: Eric Pedersen Engineer: German Bulla

MUD PRODUCTS
Product Units Used Day cost (USD) Quantity end
CARBONATO M 325 lb 120.00 396.00 240.00
CAUSTIC SODA lb 1.00 24.95 117.00
MMH lb 60.00 6,946.20 40.00
NOV FIBER F lb 50.00 1,363.50 430.00
NOV FIBER M lb 40.00 1,745.20 80.00
NOV GEL lb 175.00 2,362.50 55.00
NOV XAN D lb 3.00 345.39 111.00

OPERATION SUMMARY
From To Dur. Phase Code Sub Class MD from MD to Operation
(hr) (ft) (ft)
0:00 0:30 0.50 DRLSUR 02 P 500.00 500.00 Performed preoperational meeting to P/U & M/U Directional BHA
No. 2 led by Schlumberger crew, with BHA No. 2 as follows:

26-in TRC Bit No. 2 (Manufacturer= NOV, Type= ST11, Jets= 4 *


20/32-in, TFA= 1.227 in²) + 25 1/2-in Near Bit String Stabilizer
(w/float valve); 7 5/8 in REG PxB).
0:30 4:30 4.00 DRLSUR 01 P 500.00 500.00 P/U and assy Schlumberger tools from surface to 90 ft. as follows:

Lower Saver Sub (LWD) + LWD - arcVISION 900(GR/Rest) +


Lower Saver Sub (MWD) + MWD - TeleScope 950 High Flow
(DnI / MVC) + Upper Saver Sub (MWD) + 9.5" NonMag Drill
Collar + 25 3/4" String Stabilizer.
4:30 7:30 3.00 DRLSUR 06 P 500.00 500.00 P/U & M/U BHA No. 2 from 90 ft to 374 ft. as follows:

9 5/16-in X-O (S/N= BC41490265682-5, 7 5/8" REG PIN x 6 5/8


REG BOX) + (3) 8-in DC ( 6 5/8"REG PIN x BOX) + 6 ½-in X-O
(S/N= BC41490265682-5, 6 5/8" REG PIN x NC50 BOX) + (3)
6-1/2 in DC (NC50 PIN x BOX) +6 ½-in X-O (S/N=6677344-1,
NC50 PIN x XT57 BOX) + (21) 5 7/8-in HWDP (NC50 PIN x BOX).

Note:
-Tight spot to 260 ft.
- break out single DC 6 1/2".
- M/U stand HWDP 5 7/8".
- Wash down from 246 ft to 338 ft.
7:30 8:00 0.50 DRLSUR P 500.00 500.00 Rack back stand HWDP, RIH single DC 6 1/2" and RIH stand
HWDP to 374 ft.
8:00 9:30 1.50 DRLSUR P 500.00 500.00 Conected TDS and wash down from 374 ft to 500 ft, with Q: 600
gpm, 460 psi. increase pump to 700 gpm, SPP= 620 psi. Note:
Take survey to 454 ft, 1.3° incl, 135° azi.
9:30 16:30 7.00 DRLSUR P 500.00 829.00 Drilled 26- in section from 500 ft to 829 ft. with Q= 1250 gpm,
SPP= 1850 psi, 80 rpm, 4-6 klb-ft Torq, 10-15 WOB, ROP= 75
ft/hr.
Note: Checked annulus level after each connection.
16:30 18:00 1.50 DRLSUR U 829.00 829.00 Performed back reaming with 70 rpm, Q= 1200 gpm, SPP= 1730
psi, from 829 ft to 554 ft. Wash back to 829 ft, with Q= 1200 gpm,
1730 psi.
Note: Greased TDS wash pipe.
18:00 0:00 6.00 DRLSUR P 829.00 1,205.00 Drilled 26-in section with BHA No. 2 into Guayabo Fm. From 829
ft to 1205 ft as follows parameters:

- Between 829 ft and 1014 ft : Q=1100 gpm, SPP= 1520 psi,


WOB= 8 - 20 Klb, RS= 100 rpm, TQ=3- 6 Klb-ft.
- Between 1014 ft and 1205 ft : Q=1350 gpm, SPP= 2240 psi,
WOB= 8-25 Klb, RS= 90-110 rpm, TQ= 2 -6 Klb-ft.
Progress: 376 ft. Avg. Drilling Time= 6 Hrs. Avg. ROP= 62 ft/hr.
Efec. Drilling Time= 4.9 Hrs. Efec. ROP= 76.73 ft/hr.

2/12/2019 6:51:59AM version 1.5 www.grantierra.com 3


GRAN TIERRA ENERGY INC.

Daily Drilling Report


Well: PROSPERIDAD 1 Report no.: 2 Report date: 2/11/2019
Wellbore No.: Well Name: PROSPERIDAD 1 Block: EL PORTON Active datum: U @925.0ft (above Ground Level)
Project: EL PORTON Site: PROSPERIDAD 1 Rig Name/No.: Rig #1/5857
Event: ORIG DRILLING Start date: 2/10/2019 End date: Spud date: 2/10/2019
AFE No.: Well.057.0001/DRI AFE Estimator: German Bulla Drilling Supervisor: Eric Pedersen Engineer: German Bulla

OPERATION SUMMARY
From To Dur. Phase Code Sub Class MD from MD to Operation
(hr) (ft) (ft)
Last survey to 1159 ft, 1.66° incl, 130.64° azi.
REMARKS
SOLIDS CONTROL EQUIPMENT
------------------------------------------------------------------------------------------------------------------------------------------
NOV
DAILY COST $ 8333.00
CUMM. COST $ 76980
____________________________________________________________________________________________
____________________________________________________________________________________________
INTEGRITY
------------------------------------------------------------------------------------------------------------------------------------------
ROTATING HRS BHA No.2
CUMMULATIVE: 10 hrs
WASHPIPE/SAVERSUB HRS:
DAILY:24 HRS
CUMMULATIV 46.5 HRS
____________________________________________________________________________________________
GEOLOGY
------------------------------------------------------------------------------------------------------------------------------------------
TOP FORMATIONS FOR SECTIONS:
Guayabo Fm top @
GAS
Avg Conn gas: 0% Max Conn gas: 0%
Avg Trip gas: 0% Max trip gas: 0%
Avg BGG: 0% Max BGG: 0%
Daily mud losses: 0 bbl, Total section mud losses: 0 bbl, Total well mud losses: 0 bbl
____________________________________________________________________________________________
____________________________________________________________________________________________
UPDATE
------------------------------------------------------------------------------------------------------------------------------------------
00:00 - 06:00

Drilled 26-in section with BHA No. 2 into Guayabo Fm. From 1205 ft to 1490 ft as follows parameters:

Q=1350 gpm, SPP= 2270 psi, WOB= 8-25 Klb, RS= 110 rpm, TQ= 2 -6 Klb-ft.
Progress: 285 ft. Avg. Drilling Time= 6 Hrs. Avg. ROP= 47 ft/hr. Efec. Drilling Time= 4.78 Hrs. Efec. ROP= 59 ft/hr.
Take survey to 1350 ft, 0.75° incl, 113.19° azi

2/12/2019 6:51:59AM version 1.5 www.grantierra.com 4


PROSPERIDAD 1 WELL
FORMATION TOPS

PREDICTED TOPS (*) TENTATIVE TOPS BY SAMPLES STRUCTURAL DIFFERENCE


MD (TVD) TVDss Tickness Dips MD TVD TVDss Tickness Higher Lower
FORMATION
(FT) (FT) (FT) (FT) (Degs) (FT) (FT) (FT) (FT) (FT) (FT)
RTE 925.0 RTE 925.0
Guayabo 0 0 884.0 0 925.0
Leon fm 9,619.0 9,583 -8,658.0 9,619 925 0 0
Miembro C1 11,297.0 11,216 -10,291 1,678 925 0
Miembro C2 12,175.0 12,070 -11,145 878 925 0
Miembro C3 12,470.0 12,357 -11,432 295 925 0
Miembro C4 12,715.0 12,595 -11,670 245 925 0
Carbonera Fm Miembro C5 12,815.0 12,693 -11,768 100 925 0
Miembro C6 13,541.0 13,405 -12,480 726 925 0
Falla 13,718.0 13,571 -12,676 177 925 0
Miembro C7 13,749.0 13,601 -12,676 31 925 0
Miembro C8 14,156.0 13,997 -13,072 407 925 0
Mirador fm 14,372.0 14,208 -13,283 216 925 0
Barco fm. 14,855.0 14,677 -13,752 483 925 0
Guadalupe fm. 15,080.0 14,896 -13,971 225 925 0
Gacheta fm. 15,579.0 15,380 -14,455 499 925 0
Une fm. 16,114.0 15,899 -14,974 535 925 0
TD 16,289.0 16,068 -15,156 221