PROJECT: ANGKOR WATER PARK

Project: Angkor Water Park


To: THAI NERO ( TNR )
ENGINEERING AND MANAGERMENT No. : MKC- RFA - 103
DATE: 13-March-2019
MATERIAL APPROVAL
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK

Tube Steel Material ( CABANA 3m x 3m x 50 set )


Use: Steel Roof Structure
Model : 1- Square Shape 25 x 25 x 2.0mm.thk x 6m. ( 1.36 Kg/m )
Model : 2- Rectangular Shape 80 x 40 x 2.3mm.thk x 6m.
Model : 3- Rectangular Shape 100 x 50 x 3.2mm.thk x 6m.
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK

Steel Paint ( Anti-rush )- DenzoShield


Use: Steel Roof Structure Paint
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK

Painting - TORA SHIELD 100% Acrylic emulsion paint ( for Exterial and Interior )
Use: Finishing Painting

(Catalog Below)
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK

SHERA ( 0.8cm x 10cm x 30cm ) - Smoth surface - Finish Sprat painted wood color.
Use: Interior and Exterior Ceiling

(Catalog Below)
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK

(Catalog Below)
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK

SHERA EAVES ( 15cm x 1.6cm x 30cm ) - Smoth surface - Finish Sprat painted wood color.
Use: Exterior Eaves

(Catalog Below)
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK

BR01
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK
MONG KHUN GROUP. PROJECT: ANGKOR WATER PARK

Submitted by

______________
Mongkhun Group Co., Ltd.
Mr. WICHAI THONGTO
( Project manager )
Date......../........../.........