The advisory role shall be presented as a technical brochure for the municipality in the
size of A3 containing the following:
1. License application form according to the prepared form data. (Model No. 1
2. Copy of the legal document or the letter of allocation of the General Authority for
Housing or the lease of state property
3. Copy of the design agreement between the owner and the engineering office.
4. An organizational book of transactions requiring the submission of an organizational
opinion by the Department of Organization in the municipality.
5. A two-year insurance policy for the duration of the license and three years for
implementation (for projects).
6. Submit architectural plans approved by the owner of the consulting house containing:
General site layout and construction focus with heights certified by the
Department of Organization.
Concentrate the spaces in each role with a bounce.
Table of percentages and construction areas.
Horizontal projections for each role, indicating the limits of rebounds.
Sectors of the four facets with materials used and colors.
A perspective of the main interfaces.
Decline for building heights.
7. Approval of the General Department of Fire Department (Prevention Department) on
design.
8. The following pledges are made by the owner of the consulting house:
1. Pledge to conform to the plans submitted with the building regulations and the
prescribed ratios (Model No. 2)
2. A commitment to submit the construction plans with a commitment to the
safety of the structural design (Annex 3)
3. Committed to work out plans to meet the requirements of the concerned
authorities to issue the license represented in:
Ministry of Electricity and Water (Electricity Schemes)
Ministry of Public Works (Sewerage)
Ministry of Communications (Telephone Plans)
Environment Public Authority (for factories)
General Directorate of Civil Aviation (for heights) (Annex 4)
1. Study the plans and make sure that they conform to the building regulations and
review the areas and make sure that they are within the permitted proportions of the
building by the architect without the need for the painter.
2. Ensure that all requirements for issuing the license are met through the advisory role.
3. The architect's approval on the brochure.
4. Issuing the license approved by the director of the competent department.
5. The brochure is saved in the technical file of the property
1. Contract between the owner and the contractor (copy of the license of the contractor
by the municipality and the Central Tenders Committee).
2. Amount of insurance for project implementation - or bank guarantee.
3. Supervised supervision by the Municipal Practice Committee.
4. Signature of the form of receipt of the border by the owner, the contractor and the
competent administration.
Advisory role:
The municipality's advisory role at the request phase of the electricity supply is provided by
the following documents:
• Request an electrical current transmission from the owner of the advisory role with the
following: