Anda di halaman 1dari 2

SPEC F025

December, 2005

DC “Hi-Pot” Testing Guidelines for MV Cables

DC High Potential (HI-POT) Testing of Medium-Voltage Power Cable

Overview Before performing any dc HI-POT TESTING PROCEDURES


This procedure is intended to provide overpotential tests: Normally this requires only a few
general guidelines for high potential • All equipment must be discon- seconds unless cable circuits of
dc testing of power cables. nected from the cable circuit, i.e. high capacitance are involved.
disconnect transformers, switch Record leakage current at each
All tests made after cable installation taps, motors, circuit breakers, step.
and during the guarantee period shall surge arrestors, etc. This will pre-
be made in accordance with applica- clude damage to such equipment Maintain the test voltage at the
ble specifications. and will prevent test interruptions prescribed value for the time des-
All safety precautions must be due to flashovers and/or trip-outs ignated in applicable specifica-
observed during testing at resulting from excessive tions. The following times are
leakage current. usually considered adequate: at
high voltage.
• Establish adequate clearance the end of the test period, set the
Read and understand and follow the between the circuit test ends and test set voltage control to zero,
Operator’s Manual for the particular any grounded object, and to
test set being used! allow the residual voltage on the
other equipment not under test
circuit to decay, then ground the
(about 2.5 feet).
• Ground all circuit conductors not conductor just tested.
Test Equipment
under test with all cable shields
Direct current test equipment is including nearby equipment. CAUTION
available commercially with a • Consult termination manufactur- It should be recognized that dc
wide range of voltages. ers for maximum test voltage charges on cable can build up to
Accessory equipment necessary recommendations and potentially dangerous levels if
to safely conduct high voltage time limitations. grounds are removed too quickly.
tests—such as safety Maintain solid grounds after the test
barriers, rubber gloves and The direct current test voltage on the cable for at least 4 times the
nonconducting hard hats—must may be applied either continu- duration of the test. On exceptionally
be used; consult appropriate ously or in predetermined steps long cable lengths, it may be neces-
safety officer. to the maximum value in sary to increase the grounding time. It
accordance with applicable is advantageous to maintain these
specifications.
Test Procedures grounds longer and while reconnect-
• Continuous Method – Apply test ing circuit components.
See IEEE Standard 400 (page 105).
voltage at an approximate rise • Acceptance Testing – After
Acceptable procedures, although
rate of 1 kV per second or 75% installation and before the cable is
varying slightly in technique, have
of the rated current output of the placed in regular service, the
more or less been standardized specified test voltage shall be
equipment, whichever is less.
as either a “withstand test” or a applied for 15 consecutive min-
Some equipment will take longer
“time-leaking current test.” to reach the maximum test volt- utes.
age because of the amount of • Proof Testing – At any time dur-
charging current. ing the period of guarantee, the
• Step Method – Apply test volt- cable circuit may be removed
age slowly in 5 to 7 increments of from service and tested at a
equal value to the maximum reduced voltage (normally 65 per-
specified. Allow sufficient time at cent of the original acceptance
each stop for the leakage current
value) for 5 consecutive minutes.
to stabilize.
• Record the leakage current at
one minute intervals for the dura-
tion of the test time involved.

Phone: 888-593-3355
www.generalcable.com
SPEC F025
December, 2005

DC “Hi-Pot” Testing Guidelines for MV Cable

DC High Potential (HI-POT) Testing of Medium-Voltage Power Cable

Comments This results in an increase of coro- Testing Problems


DC overpotential testing of medi- na. It is most desirable to reduce or
eliminate corona current at the bare Extra Leakage Current:
um-voltage power cables is usually
performed with negative polarity metal extremities of cable or termi- • Failure to guard against corona
connected to the nations. This may be accomplished • Failure to clean insulation surface
conductor. by covering these areas with plastic • Failure to keep cable ends dry
envelopes, plastic or glass contain- • Failure to provide adequate
DC overpotential testing is a tool
ers, plastic wrap (e.g. “Saran” or clearance to ground
only for determining insulation
“Handiwrap®”) or suitable electrical • Improper shield termination
resistance at higher voltages.
putty.
Effective insulation resistance of the
cable system may be calculated by Routine periodic dc maintenance Erratic Readings:
means of Ohms Law: testing of cable for the evaluation of
the insulation strength is not a com- • Fluctuating voltage to test set
R = V/I. The relation is:
mon practice. Some power cable • Improper test leads
users have adopted a program of
Megohms = Kilovolts x 1000 testing circuits during planned out- Environmental influences:
Microamperes ages, preferring possible break- • High relative humidity
downs during testing rather than
• Dampness, dew, fog
experiencing a service outage. It is
Insulation resistance may also be nearly impossible to recommend • Wind, snow
measured with standard instru- test voltage values for those main-
ments which give a direct reading tenance tests with the history of the Results vs. Cable Life
at 500 volts (or higher, depending cable circuit. An arbitrary test volt-
on the model). IR in general has lit- To date there is no bases for
age level could break down a cable correlation between dc test
tle or no direct relationship to circuit that would otherwise render
dielectric or breakdown strength. results and cable life expectancy.
long trouble-free service at normal
The significance of conducting dc operating ac voltage.
high-voltage tests on nonshielded, The main usefulness of dc high- Partial Listing of Equipment
nonmetallic-sheathed cable is voltage testing is to detect con- Suppliers
dependent upon the environment in ducting particles left on the creep- J.G. Biddle Company
which it is installed because the age surface during splicing or ter- Blue Bell, PA 19422
characteristics of the return circuits mination.
are unknown. The environment
Test equipment should be supplied Hipotronics
must be carefully considered or test
results may not be significant. In from a stable, constant voltage Brewster, NY 10519
fact, these tests can result in dam- source. Do not use the same
age to the cable insulation. source that is supplying arc welders Associated Research Inc.
or other equipment causing line Chicago, IL 60648
Humidity, condensation and actual voltage fluctuations. The output
precipitation on the surface of a voltage of the test set must be fil-
cable termination can increase the Von Corporation
tered and regulated. Consider using
leakage current by several orders of a portable, motor-driven alternator Birmingham, AL 35211
magnitude. Humidity also increases to energize test set.
the corona current, which indication
is included in the total leakage cur- The gradual decrease or non-
rent. Wind prevents the accumula- increase of leakage current with
tion of space charges at all bare respect to time at maximum test
energized terminals. voltage is the acceptance criteria
for dc hi-pot testing.

Phone: 888-593-3355
www.generalcable.com

Anda mungkin juga menyukai