a) SPE-MAS Up line
b) MS-TBM-CGL up line
c) CGL-VM Up line (presently single line)
d) MAS-AJJ up fast line
e) MAS-PER Dn fast line
f) Mandapam – Pamban
g) IGU-CBE Dn line
h) Yard lines of stations where large number of express trains stops and approaches -
to be identified by divisions.
i) Platform lines at stations - to be identified by divisions.
Signature Not j) Any other locations/sections to be decided by Sr.DEN/Co based on measurement of
Verified corrosion and to be approved by CTE.
Digitally signed by
MANOHARAN S
Date: 2018.05.28
17:03:01 IST
1
Reason: IREPS-CRIS
Location: New Delhi
2.1.2 Severe corrosion prone locations:
All sections where liner seat corrosion recorded is between 1mm and 3 mm in 3
years shall be classified under this group. All sections which are not falling under
very severe corrosion prone locations and moderate corrosion prone locations shall
fall under this group. The severe corrosion prone locations in moderate corrosion
prone sections shall be identified periodically and be approved by Sr.DEN/Co of the
divisions.
Any other line constructed as new line or under doubling and gauge converted
sections shall also fall initially under this category.
2.1.4 Classification of the sections based on the corrosion proneness as mentioned above
shall be reviewed every year depending on the corrosion recorded. The locations
classified under each group shall be recorded in the section register being
maintained by each SE/P.Way/incharge
Date of Engine Line Bet. km Location Rail Lowest Lowest Reduction Action
measure run Up/ Stations secti thickness thickness of in width initiated
ment section Dn Hectometer rail flange at of bottom
No.
on of rail the original flange
& flange at liner seat
UTS the present locations after
liner seat shifting/interch
* anging *
From To Left Right Left Right Left Rig
rail rail rail rail rail ht
rail
2
* The reduction in width of bottom flange need not be considered for measurement
of minimum thickness of rail flange.
Corrosion shall be recorded once in a year in very severe corrosion prone locations
and severe corrosion prone locations and once in 2 years in moderate corrosion
prone locations.
3
be done if minimum thickness is between 2 mm and 4 mm to avoid further
corrosion till TRR is done provided the liner seats are not shifted from the
sleepers which can be done only if special care is taken by conducting detailed
survey before doing the work to ensure the same. In curved track while
interchanging rails, the location of liner seating cannot be maintained at any desired
location. Hence, interchanging shall not be resorted to if minimum thickness of
bottom flange is less than 4 mm in curves.
3.2.3 If the reduction in width of bottom flange at any location of liner seat exceed 7
mm, shifting of liner seats or interchanging of rails shall not be resorted to.
Destressing of LWR shall be done by cutting and removing the rails for a length of
150 mm or in multiples of sleeper spacing +150 mm so as to ensure shifting of liner
seat by 150mm uniformly at all locations during the process of destressing.
3.4 Painting of Rails with anti-corrosive bitumen black paint as per IS:9862
3.4.2 Special care should be taken in preparing the surface at the weld collars.
Generally weld collars are considered severe corrosive areas.
4
3.4.4 Painting scheme:
i) 1st coat: Anti corrosive bituminous black paint conforming to IS:9862-1981
ii) 2nd coat: Anti corrosive bituminous black paint conforming to IS:9862-1981.
i) Painting of both inside and outside of the rails shall be done once in a year in
very severe corrosion prone locations.
ii) Painting of inside of rail in severe corrosion prone locations shall be done once in a
year.
iii) Painting of rails on outside of rail in severe corrosion prone locations and both
inside and outside in moderate corrosion prone locations need not be done.
However painting of welds (both SKV & FBW) shall be done on inside of track
once in a year in moderate corrosion prone locations.
3.5 Greasing:
3.5.1 General
(i) DO not use untested grease. Grease must have oxidation stability and rust
inhibitors.
(ii) Apply recommended cleaning agent and rust inhibitors before anticorrosive
treatment.
(iii)Use preferably mechanized cleaning brush to scrap the rusted surface.
(iv) Greasing shall not be done in rainy condition and hot weather conditions.
Graphited grease grade ‘O’ to IS 408 shall be applied on under side of liners as also
the corresponding area of the rail foot in addition to the central leg of elastic rail
clips. To avoid ingress of toilet droppings as well as moisture to the surface of liner
and the rail foot, grease shall also be applied along with the boundary of liner so as
to seal the liner boundary.
5
In severe corrosion prone locations – greasing shall be done once in a year only on
inside of track. Since the corrosion due to toilet droppings is almost ‘nil’ on outside
of track, greasing on outside of track may be done only along with destressing, TFR
etc.
In moderate corrosion prone locations, greasing of inside of track may be done once
in 2 years and greasing of outside of track need be done along with destressing
and/or TFR.
3.5.4 Greasing of plate screws at points & xings and at guard rails of bridges shall be done
at the time of initial laying and also during maintenance once every six months, one
year and 2 year in very severe, severe and moderate corrosion prone locations
respectively.
6
4.0 Schedule of preventive measures to reduce corrosion of rails is summarised
and given below:
Classification criteria
* Shifting of liner seat from the insert location shall not be done if the minimum
thickness of flange anywhere at liner seat is less than 4mm.
5. The requirement of grease grade ‘O’ to IS 408 and anti corrosive bituminous black
paint to IS 9862-1981 shall be estimated by each division and the estimated annual
requirement (EAR) shall be advised to COS though the concerned divisional stores depot
for procurement and supply.
(Dani Thomas)
Chief Track Engineer.
|ÉvÉÉxÉEòɪÉÉDZɪÉ/Headquarters Office,
ºÉÆEò®ú¨É ¶ÉÉJÉÉ/Works Branch,
{ÉÉEäò ]õÉ=xÉ/Park Town,
SÉäxxÉè-3/ Chennai 600 003.
****
CE Circular No.01/2011 was issued vide letter No.W.506/14/Circular dt.10.01.2011.
Following is the correction slip no.1 to the above circular.
----------------------------------------------------------------------------------------------
email : cte@sr.railnet.gov.in Rly Ph: 22543 BSNL:Tele/Fax 044-2535 1157