In Pit Survey
Overview:
In-pit Survey: Setting out a point of known rectangular co-ordinate. Control of directions and gradients for inclined
shafts, slopes, levels and tunnels. Maintaining alignments, simple curve laying underground, laying out and fixing of
mine boundaries claims, subsidence surveys on surface and underground. Volume calculations.
1
Mine Surveying In-Pit Survey
Horizontal positions in geographic or plane coordinate systems relative to previously surveyed positions called
control points.
The basic methods of locating position of a point of known coordinates are either by polar coordinates or by
intersection.
(1) From coordinates compute the bearing of line joining points B and A (BA, this bearing may already be known from
the initial control survey computations).
(2) From coordinates compute the horizontal length (L) and bearing of BP (∠NBP).
(3) From the two bearings compute the setting-out angle ∠ABP = Bearing of BA (∠NBA) - Bearing of BP (∠NBP),
i.e. β
(4) Before proceeding into the field, draw a neat sketch of the situation showing all the setting-out data.
Check the data from the plan or by independent computation.
2
Mine Surveying In-Pit Survey
3
Mine Surveying In-Pit Survey
If only one theodolite is available then two pegs per sight line are established, as in Figure 2, and then string
(thread/ rope/ white line) lines connecting each opposite pair of pegs locate position P, as in Figure 2.
2. Control of directions and gradients for inclined shafts, slopes, levels and tunnels
The control of direction and gradient in Inclined shafts, slopes, levels and tunnels involves setting out of
different horizontal and vertical curves or some combinations of it. These curves have
Curve Designation:
Curves are designated/ described either by their radius (R) or Degree of Curvature (D).
Degree of Curvature (D): It is defined as the angle subtended by an arc of 100 m at the centre of the circle.
100 ×180 °
R=
D×π
The difference of the bearings of the straights provides the deflection angles (∆) of the curves which,
combined with the tangent length, enables computation of the curve radius, through chainage and all setting-
out data.
Control of direction:
Methods:
Using a plumb-bob
In low-rise construction a heavy plumb-bob (5 to 10 kg) may be used as shown in Figure 10.13. If the
external wall was perfectly vertical then, when the plumb-bob coincides with the centre of the peg, distance d
at the top level would equal the offset distance of the peg at the base. This concept can be used internally as
well as externally, provided that holes and openings are available.
4
Mine Surveying In-Pit Survey
4. Volume Calculations
Apart from the mine surveying activities discussed in the earlier sections, another important activity usually performed
by the mine surveyor is volume determination. For example, during a tunnel construction, as-built surveys are required
to check tolerances of tunnel structures. Surveys are also carried out in completed tunnels to check if sufficient
clearances are available for the installation of pipelines, lighting, ventilation, and so on. The surveys are to provide a
record of existing structures and the as-constructed condition of the tunnel. As-built surveys of a tunnel should be
implemented in two steps as follows:
(i) Survey the finished tunnel before and after the breakthrough.
(ii) Check if the existing tunnels have been built to within allowable tolerances,
and if the design tolerances are exceeded, to see if it is possible to realign the tunnel without remedial work to the
existing structures. In this case, cross sections at regular intervals along the whole length of the tunnel are surveyed.
Accurate and cost-effective surveying method applied by surveyors in checking profiles is using reflectorless total
stations by which coordinated points on the tunnel surface are automatically recorded, processed, and analyzed on
computers in the field.
All of the field data are stored electronically in the form of three-dimensional coordinates in the total stations, and the
accuracy between 5 and 10 mm is expected. Based on the cross-section database, volume of excavation and materials
are computed.
Whether underground or on the earth surface, mining involves moving volumes of material from one place to another.
Mapping the changes made by the mining activity and determining the volumes moved is a daily job of mining
surveyors. Nowadays, for underground and open-pit operations, laser scanning systems, reflector-less total station
equipment, GPS surveys, and terrestrial photogrammetry are used for daily mine volume determinations. One approach
for volume determination for underground operations can be described as follows:
1. Observe cross-section profiles at measured intervals (with distance between each cross section being d 12, d23, etc.).
5
Mine Surveying In-Pit Survey
2. Determine the cross-sectional areas using coordinate method based on local x–y coordinate system established for
each cross section. A typical cross section with the local x–y coordinate system is shown in Figure 3. The area (A) of
this cross section can be given using coordinate approach as
3. Compute volumes between cross sections as shown in Figure using average end-area method:
4. Compute the total volume (VT) by the sum of the cross-section/end-area volumes: