1
Energy in its various forms
• Chemical – in fuels
• Thermal – sensible and
latent
• Mechanical
• Electrical
Energy Equivalents
2
Basic electricity
• Voltage
This is what pushes electricity through a circuit - the
“driving force”
Units are Volts (V)
• Current
This is what is pushed through by the voltage - the “flow”
Units are Amperes (A) (“Amps”, for short)
4
Calculating power
5
Power Factor - lagging current
310 310
220 220
0 0
-310 -310
6
Why should I care about power factor?
7
Power factor correction
• Add capacitance
• At service entrance
• In distribution system
• At point of use – e.g. on motors
9
What is efficiency?
10
Thermal energy units
11
What is energy auditing?
12
How is energy management done?
• Purchase energy
supplies at the lowest
possible price.
• Manage energy use at
peak efficiency.
• Utilize the most
appropriate
technology.
13
Managing Technology
• No cost - housekeeping
measures
• Low cost - some
technology, lots of
people input
• High cost - capital
investment
14
Energy consuming systems in
buildings
Organization /
Site
Building A Building B
Solar
Process Exhaust
Energy Inflow
Boiler Stack Loss Ventilation
Exhaust
Window
Electricity Heat Loss
Energy Inflow
Wall
Heat Loss
16
Two levels of audit
• Preliminary Audit • Detailed Audit
• High level assessment • Greater detail in
• Assesses merits of doing assessment of specific
detailed audit areas
• Identifies areas of focus • Identifies specific EMOs
for detailed audit
• Includes walk-through
and preliminary data
analysis
17
Pre-site inspection data
requirements
• Historical energy and water consumption and billings data
for at least 12 months, preferably multi-year;
• Basic building configuration information, including at least
conditioned floor area;
• Building schedule and occupancy data;
• Breakdown of building uses by area (i.e. general office,
computer facilities, library, cafeteria, etc.);
• Any other energy assessment data that may be available,
including demand profiles, equipment inventories, etc.
• Degree-day information applicable to the building
location.
18
Preliminary data analysis
19
Preliminary Audit
• Purpose • Steps
• historical analysis
• the need for or merits of
a detailed audit, based • collect building data
on performance indices: • demand profile
• consumption index • walk-through
• tariff analysis
• demand index
MJ/m2/year
VAaverage/m2/month
20
Preliminary audit findings
• Building performance
indices
• Demand profile analysis
• Potential savings
opportunities
• Confirmation of tariff
21
Detailed audit
• Purpose • Steps
• identify specific • examine site drawings
measures to reduce • prepare load inventory
consumption, demand, • assess demand profile
cost
• assess all energy load
areas
• provide baseline
criterion
• assess tariff change
opportunity
22
Auditing – the “big picture”
23
Ten Steps
Figure 3.4: Audit Process Flow Chart
Preliminary Client Meeting and
Historical Data Analysis Preliminary Audit Audit Plan Detailed Audit
1. Conduct a Walk-through Initial Client (4) Det ermine (1) Detailed Walk-
24
Planning for the audit
25
Coordination with O&M personnel and
building occupants
26
Step 1: the walk-through
• Where repair or
maintenance work is
(1) Preliminary
needed; Walk-through
• Where capital
investment may be (2) Analyse
needed to improve Energy
Consumption &
energy efficiency. Costs
27
Step 2: Analyse energy
consumption and costs
saved cost
28
Step 3: Comparative analysis
• Two kinds of
(1) Preliminary
comparison: Walk-through
• Internal - period to
period, site to site;
(2) Analyse
• External - to standards Energy
of performance Consumption &
Costs
established in the
buildings sector.
(3) Comparative
Analysis
29
Data analysis
• Energy density:
• MJ/m2/year
• Demand density:
• VAaverage/m2/month
• Correlation with
weather - HDD and CDD
30
Performance indices
• Consumption
MJ/m2/year
• Demand
VAaverage/m2/month
31
Energy use drivers
• Climate
• Facility size & Age
• Schedules
• Equipment type
• Building design
• Processes
• Organisational culture
• Behaviour
32
Types of comparisons
• External benchmarks
• Internal benchmarks
• multiple facilities
• Historical consumption
• Trends and patterns
33
Benchmarking is…
34
Selected benchmarks
• Demand intensity
• VA/m2
• relates to size/number of electricity consumers
• Electric energy intensity
• kWhE/m2
• relates to size/number/duration of electricity use
• Cooling or heating energy intensity
• kWhC/m2 or kWhH/m2
• Total energy intensity
• kWhT/m2 = kWh(C or H)/m2 + kWhE/m2
35
Best practices
36
“This facility is different
from those benchmarks!”
• Investigate the
differences
• The opportunities lie in
the differences
37
Step 4: Define the audit
mandate
• Clarification of the goals
Audit Plan
and objectives of the
audit, and the key (4) Determine
constraints that will Audit Mandate
38
Step 5: Define the audit scope
• Specification of
Audit Plan
• The physical extent of
the audit (4) Determine
• The energy inputs and Audit Mandate
outputs
• The sub-systems to be (5) Define Audit
assessed Scope
39
Step 6: Profile energy consumption
40
Step 7: Inventory energy loads
41
Step 8: Identify EMOs
• STEP 2 - Maximise
system efficiencies (8) Identify EMOs
42
Step 9: Assess the costs and
benefits
indicators should be
used (10) Audit Report
for Action
43
Costs and benefits
• Benefits • Costs
• direct energy savings • direct implementation
• indirect energy savings costs
• comfort/productivity • direct energy costs
increases • indirect energy costs
• operating and • O&M cost increase
maintenance cost
reductions
• environmental impact
reduction
44
Step 10: Report for implementation
45
Analyzing performance requires
energy data
G a s E n e r g y v s . W e a t h e r
E n e r gA y B C ( GF a Jc ) i l i t y f o r 1 9 9 9
3 2 0
2 8 0
2 4 0 E l e c t r i c i t y C o s t B r e a k d o w n f o r 1 9 9 9
A B C F a c i l i t y
2 0 0 E n e r g y C o s t D e m a n d C o s t
$ 4 0 , 0 0 0
1 6 0
1 2 0
$ 3 0 , 0 0 0
8 0
4 0
$ 2 0 , 0 0 0
0
0 2 0 0 4 0 0 6 0 0 8 0 0 1 0 0 0
W e a t h e r
$ 1( 0 ,H D
0 D
0 0 )
G J = 0 . 3 9 5 x H D D + 1 2 [ R - s q = 0 . 9 1 ]
$ 0
F e b A p r J u n A u gO c tD e c
J a nM a Mr a y J u lS e p N o v
O n - PO e af k f - DE P en e me a r k ag ny E d n e r g y
46
Data requirements
• Historical energy • building automation system
consumption data (BAS) documentation
• Metered energy • maintenance logs
consumption
• key plans (floor plans)
• Building configuration
• Weather data • contact information for
building operational
• Energy system nameplate personnel or service
data
contractors
• mechanical, electrical,
architectural plans and
specifications
47
Instrumentation for auditing
• Electric Power Meter • Other useful items:
• Combustion Analyzer • A camera
• Digital Thermometer • Binoculars and a small flashlight
• Duct tape & Tie Wraps
• Infrared Thermometer • Multi- screw driver, adjustable
• Psychrometer (Humidity wrench and pliers
Measurement) • Tape measure
• Bucket and stopwatch
• Air Flow Measurement • Safety Glasses, Gloves & Ear Plugs
Devices
• Caution tape
• Tachometer
• Ultrasonic Leak Detector
48
Hand-held wattmeter
49
Single-phase connections
50
3-phase digital power meter
Table 5.14
RECOMMENDED ILLUMINANCE LEVELS,
POWER DENSITIES AND SURFACE REFLECTANCES
Area and Task Illuminance Power Den- Reflectances %
sity
2
W/m Ceiling Walls Floor
Figure 5.24 Infrared Temperature Measuring Devices (Right Hand Photo: OMEGA)
54
Humidity measurement
55
Static pressure
56
Leak detection - ventilation and compressed
air
• Administrative charge
• Demand charge per kVA
• May be time of use – on-
peak/off-peak
• Energy charge per kWh
59
Analysing the electricity billings
Billing Metered Metered Power Billed Energy Daily Load Demand Energy Adjust Sub Total --- Demand Block A
Date kVA kW Factor kW kWh Days kWh Factor Cost Cost (+/-) Total Cost
01/01/99 1,800.0 1,800.0 1,006,703 30 33,557 78% $21,250 $50,365 ($11,147) $71,615 $64,701
02/01/99 1,900.0 1,900.0 1,206,383 31 38,916 85% $22,750 $56,441 ($13,204) $79,191 $70,607
03/01/99 1,400.0 1,400.0 842,286 28 30,082 90% $15,250 $42,144 ($9,263) $57,394 $51,501
04/01/99 1,850.0 1,850.0 1,102,176 31 35,554 80% $22,000 $53,315 ($12,132) $75,315 $67,606
05/01/99 1,870.0 1,870.0 1,213,021 30 40,434 90% $22,300 $56,641 ($13,252) $78,941 $70,287
06/01/99 2,200.0 2,200.0 1,339,599 31 43,213 82% $27,250 $60,438 ($14,716) $87,688 $78,080
07/01/99 1,560.0 1,560.0 850,195 30 28,340 76% $17,650 $42,540 ($9,438) $60,190 $54,304
08/01/99 1,570.0 1,570.0 948,747 31 30,605 81% $17,800 $47,467 ($10,429) $65,267 $58,677
09/01/99 1,950.0 1,950.0 1,213,798 31 39,155 84% $23,500 $56,664 ($13,308) $80,164 $71,536
10/01/99 2,300.0 2,300.0 1,373,054 30 45,768 83% $28,750 $61,442 ($15,111) $90,192 $80,337
11/01/99 2,100.0 2,100.0 1,347,059 31 43,454 86% $25,750 $60,662 ($14,731) $86,412 $76,699
12/01/99 2,400.0 2,400.0 1,024,475 30 34,149 59% $30,250 $50,984 ($11,685) $81,234 $74,418
Totals/Max 2,400.0 2,400.0 13,467,496 364 $274,500 $639,104 ($148,415) $913,604 $818,752
3,000.0 100%
2,500.0
80% 90% 90%
85% 86%
2,000.0 78% 80% 82% 81% 84% 83%
76%
60%
1,500.0 59%
40%
1,000.0
500.0 20%
0.0 0%
20,000 $40,000
10,000 9 $20,000
0 $0
Nov-99
May-99
Mar-99
Sep-99
Apr-99
Dec-99
Oct-99
Feb-99
Aug-99
Jan-99
Jul-99
Jun-99
Feb-99
Dec-99
Sep-99
Oct-99
Apr-99
Aug-99
Jul-99
Jan-99
Jun-99
Nov-99
Mar-99
May-99
60
Electricity Consumption Data Location: ABC Facility
Load factor
dit Manual\Spreadsheets\[Electricity Cost.xls]Electicity Consumption Data ]
tered Metered Power Billed Energy Daily Load Demand Energy Adjust Sub Total
kVA kW Factor kW kWh Days kWh Factor Cost Cost (+/-) Total Cost
1,800.0 1,800.0 1,006,703 30 33,557 78% $21,250 $50,365 ($11,147) $71,615 $64,701
1,900.0 1,900.0 1,206,383 31 38,916 85% $22,750 $56,441 ($13,204) $79,191 $70,607
1,400.0 1,400.0 842,286 28 30,082 90% $15,250 $42,144 ($9,263) $57,394 $51,501
1,850.0 1,850.0 1,102,176 31 35,554 80% $22,000 $53,315 ($12,132) $75,315 $67,606
1,870.0 1,870.0 1,213,021 30 40,434 90% $22,300 $56,641 ($13,252) $78,941 $70,287
2,200.0 2,200.0 1,339,599 31 43,213 82% $27,250 $60,438 ($14,716) $87,688 $78,080
1,560.0 1,560.0 850,195 30 28,340 76% $17,650 $42,540 ($9,438) $60,190 $54,304
kWh used in period
Load Factor (%) =
1,570.0 1,570.0 948,747 31 30,605 81% $17,800 $47,467 ($10,429) $65,267 $58,677
1,950.0 1,950.0 1,213,798 31 39,155 84% $23,500 x 100
$56,664 ($13,308) $80,164 $71,536
2,300.0
2,100.0
2,300.0
2,100.0
1,373,054 30
1,347,059 31
Peak kW x 24 hr per day x # days in period
45,768
43,454
83%
86%
$28,750
$25,750
$61,442
$60,662
($15,111)
($14,731)
$90,192
$86,412
$80,337
$76,699
2,400.0 2,400.0 1,024,475 30 34,149 59% $30,250 $50,984 ($11,685) $81,234 $74,418
2,400.0 2,400.0 13,467,496 364 $274,500 $639,104 ($148,415) $913,604 $818,752
60%
cost. 59%
40%
20%
0%
$40,000
Graphical analysis of historical energy
use
Building "A" Building "B"
Gas Space Heat & Gas Domestic Hot Water, Electric A/C Electric Space Heat, Electric A/C, Gas Domestic Hot Water
16,000 18,000
14,000 16,000
14,000
Equivalent kWh
Equivalent kWh
12,000
12,000
10,000
10,000
8,000
8,000
6,000 6,000
4,000 4,000
2,000 2,000
0 0
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
Monthly Electricity Consumption Monthly Gas Consumption Monthly Electricity Consumption Monthly Gas Consumption
10,000 10,000
Equivalent kWh
Equivalent kWh
8,000 8,000
6,000 6,000
4,000 4,000
2,000 2,000
0 0
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
Monthly Electricity Consumption Monthly Gas Consumption Monthly Electricity Consumption Monthly Gas Consumption
62
Calculating degree-days
63
Correlation of energy consumption to
degree-days
64
Hourly Demand Profile
140
120
100
80
60
40
20
0
2 4 6 8 10 12 14 16 18 20 22 24
1 3 5 7 9 11 13 15 17 19 21 23
Hour of the Day
65
Patterns Revealed
• Peak Demand • Loads that Cycle
• Night Load • Interactions
• Start-Up • Occupancy Effects
• Shut-Down • Production Effects
• Weather Effects • Problem Areas
66
Analyzing the Profile
67
Obtaining a Demand Profile
L1
L2
L3
CLIP-ON AMMETER
STOP
POWER
OFF
phase measurement:
ON
DC
69
3 phase measurement
70
Daily or monthly
1200
1000
800
600
400
71
Meter response
Typical Meter Response
Load
Each type has adisconnected
different response - contact your utility.
Load
connected
72
What the demand meter sees
20
15
10
73
Savings opportunities
74
Peak demand control
75
Power factor correction
76
Lighting system
Ballast
Lamps (light source)
Ceiling
Fixture
Lens or Diffuser
Switch
Walls
The Requirement Work Surface
Floor
77
Lighting considerations
78
Lighting quality
• Illumination level
• Uniformity
• Absence of glare
• Colour temperature
• Colour rendition index (CRI)
79
Colour rendering index (CRI)
82
EMOs for lighting
84
Electric motors
• First, reduce
unnecessary use
• Ensure proper operating
conditions
• Provide good
maintenance
• Consider an energy The motor is not the end-
efficient motor use; consider what is being
driven.
85
Imbalance = Inefficiency!
Increase in Losses (%)
100
80
60
40
20
0
0 2 4 6 8 10
Voltage Im balance (%)
86
Match the motor to the load
87
Operating conditions
88
Watch your speed!
89
Fans & pumps
• Comprise significant
load in buildings
• Typically oversized
• Misapplication is
common
• Proper flow control can
yield large savings
90
Assessing fans & pumps
91