Jorf MP - SAP & Energy

Storage area and pipe rack


5
4
3
2
1

27.03.2019 MS for shoring work HS NA GD 0

Date Description – Revision Subject Prepared by Checked by Approved by Rev

DOCUMENT DESCRIPTION & REFERENCES

CLIENT NAME: OCP


PROJECT LOCATION: JORF LASFAR MAROC
PROJECT DESCRIPTION: Jorf MP – SAP & Energy – Q3701XX
JE PROJECT NUMBER: Q3701XX
PURCHASE ORDER REFERENCE: 5451/5425J/16
REQUISITION REFERENCE: -
OTHER REFERENCE (tag, unit): Storage area and pipe rack

DISCIPLINE DOCUMENT TITLE


MS for Excavation work (shoring support)
QUALITY

VENDOR Document Number

02/IV/C01a/12716

JACOBS Document Number


Imm. 5 - ZénithMillenium - Lot. Attaoufik Route Nouaceur-
SidiMâaroufCasablanca-20270Tél:+212
(0)522877000/+212(0)522877150Fax:+212 Q3701XX-02-IV-C01a-12716 (rev 03)
(0)522877234

Jacobs Engineering Group Inc.


Imm.5-ZénithMillenium-Lot.AttaoufikRouteNouaceur-SidiMâaroufCasablanca-20270
Tél:+212(0)522877000/+212(0)522877150Fax:+212(0)522877234
SUBJECT

This method statement describes the methodology of shoring support for trench on Construction site ACID STORAGE
Storage area and pipe rack OCP, Jorf Lasfar.

Contractual documents and technical references

Articles from Technical Specifications Others : Drawings verified and stamped Issued for
 Annex R : Rules of Construction Construction:
 Annex S: Safety Rules

RESOURCES

Company :
Equipment: Furnace Fabrica India Limited
Materials:
 Excavator 
 shovel
Storage :
 Axe

 Steel panels
 Struts support Deposit :

Staff:
 1 site engineer
 1 HSE supervisor
 1 Quality supervisor
 Skilled workers
 Laborers
METHODOLOGY OF WORKS

N° DESCRIPTION

Introduction:
The purpose of this method statement is to provide description of procedure and method for the construction
0 and installation of shoring works when working in excavation for the raft F7 in Pipe rack 027.
Also included are the necessary procdure to ensure health and safety of emplooyees.

Preliminary works :
 Cleaning of work area.
1  Preparation of safe areas for work: barricade the area, proper signage, access platform.
 Provide all necessary material according to drawing.

Works description :

- Implantation of the raft by the survey


- Start the mechanical excavation.
- Install shoring at side once one meter depth is reached
2
- Push the shoring down as the excavation become deeper.
- Once the desired depth (3 meter) is attained fix the shoring to avoid collapse.
- Proceed with construction when the side slope has been stabilized.
- After completion of work, slowly remove the shoring and proceed with backfilling.

JOB SAFETY ANALYSIS

Hazard Prevention and protective measures

Injury Wearing of PPE (gloves, glasses, boots, helmet)

Hearing damage Earplugs or headphones sound absorbing (when using noisy


equipment)

Before starting the shoring work ensure materials are placed safely
Fall of person/material around excavation area
Avoid Walking on the ledge of excavation pit when necessary

Collapse of side walls Provide shoring for depth of every 1 meter


LOCATION OF THE RAFT
SKETCH OF SHORING SUPPORT