RAB Kolam Koi Taman Kota Bekasi
RAB Kolam Koi Taman Kota Bekasi
I PEKERJAAN PERSIAPAN
1 Pasang Bowplank/Pengukuran 36.00 M' -
2 Bongkar Dinding Bata 196.00 M² -
3 Buang Bongkaran + Pembersihan 29.40 M³ -
4 Lengser Material 1.00 Ls -
SUB TOTAL -
II CORRIDOR -
1 Bongkar jalan aspalt 65.00 m2 -
2 Bongkar dinding bata untuk pintu 8.80 m2 -
3 Galian tanah 3.08 m3 -
4 Pasir urug 10 cm bawah Tie Beam 1.03 m3 -
5 Lantai kerja 5 cm bawah pondasi 0.51 m3 -
6 Strousz pile dia 30 cm L = 4 m, 6 E 12, E 8-150 60.00 m' -
7 Urug tanah kembali 1.23 m3 -
8 Sloof 150/250,4E12,E8-150,K-175 bawah dinding bata 41.00 m' -
9 Lantai Kerja 1:3:5, 5 cm bawah slab 3.25 m3 -
10 Plastik Cor 130.00 m2 -
11 Cor Lantai K-175,T=100,BRC M-6, 1 Lyr 130.00 m2 -
12 Rolaag bata H=15 cm 10.00 m' -
13 Cor Rabat Luar K-175,T=100,BRC M-6, 1 Lyr 10.00 m2 -
14 Trowel finish rabat 10.00 m2 -
15 Kolom Praktis & Ring Balk,120/120,K-175,4E10,E8-150 86.00 m' -
16 Dinding bata 1:5 115.50 M² -
17 Plester Aci 1:5 115.50 M² -
18 Keramik Dinding Roman W-20106 KW-2 115.50 M² -
19 Keramik Lantai Roman 22106 KW-2 20/20 65.00 M² -
20 Ceiling Triplek 4 mm,Kaso 4/6-60cm 65.00 m2 -
21 List Plafon kayu kamper profil 5/5 67.00 m' -
22 Cat Tembok Vinilex Dinding luar & Ceiling 180.50 M² -
23 Kuda-kuda L50.50.5 = 6 set,Jarak 4 m 211.12 kg -
24 Gording CNP 125.50 = 3 brs 378.84 kg -
25 Atap Zinc Alume 0.4 86.80 m2 -
26 Flashing Zinc Alume 0.4 68.40 m' -
27 Siku Dudukan Flashing L30.30.3 16.86 kg -
28 Cat Finish (kg besi),Sincromate 2 lps + Finish Kansai-Ftalit 606.82 kg -
29 BOOT BASIN pasang Pipa PVC E11/2 11.00 m' -
30 BUAT BAK CUCI TANGAN -
Bongkar dinding keramik 5.60 m' -
Cor beton K.175 0.38 m3 -
Pek. Pasang keramik bak 5.04 m2 -
Pek. Pasang buangan air pipa PVC AW E2" 3.00 m' -
SUB TOTAL -
III REPAIR LANTAI RUANG PRODUKSI,GOT & CURBING -
1 Bobok Lantai Lama 50.00 M' -
2 Buang Bongkaran 12.50 M³ -
3 Cor Parit Beton W20 x H50 cm -
-Beton T=10 cm, K-175 site mix 2.50 M³ -
-Besi E8-150, 1 lps 231.48 M³ -
-Bekisting 100.00 M² -
-Pasang Keramik Parit Kia KW2 50.00 M² -
4 Plat Grating T=3mm Galvanize Hot Deep Frame L 40.40.4 50.00 M' -
5 Repair Keramik KIA 40/40 KW-1 + AM 30 565.50 m2 -
6 Repair Nut Keramik AM 55-Epoxy 1,131.00 m2 -
7 Bongkar Ceiling Accoustic lama 1,131.00 m2 -
8 Ceiling Zinc Alume 0.5,Rangka Holo Jarak 60 cm-Cooking Area 259.00 m2 -
Curbing W10xH20 cm,K-175 site mix,2E8,E10-150 SEMUA DINDING
9 PANEL 554.82 m' -
SUB TOTAL -
TOTAL -
(Azwar A) PPN 10% -
Civil Engineer GRAND TOTAL -
CPI-Processing Plant-Cikande DIBULATKAN -
0254 402628 ext.4101 / 0812 948 7152
Unt
Repair lantai bawah pintu Cold storage 7 pintu
PT. Charoen Pokphand Indonesia
Processing Plant - Cikande
1 USD = ### Rp
Charoen Pokphand Indonesia
Chicken Processing Plant
RENCANA ANGGARAN BIAYA PROCESSING PLANT - MEDAN
PONDASI LN2 TANK
No. 04/RAB-CV/EN/FP-MDN/X/08