Labour Requirement for Civil Works

Manpower Requirement

SI Scope of Work Unit Quantity

Excavation Upto 1.5m Depth


1 including disposal of soil lead upto
50m- 28.3Cum - Soft Rock

Mason Nos 0.15

Male Coolie Nos 5

Female coolie Nos 4

Excavation Upto 1.5m Depth


2 including disposal of soil lead upto
50m- 28.3Cum - Soft Rock

Mason Nos 0.15

Male Coolie Nos 6.5

Female coolie Nos 5

Excavation Upto 1.5m Depth


3 including disposal of soil lead upto
50m- 28.3Cum - Soft Rock

Mason Nos 0.2

Male Coolie Nos 8

Female coolie Nos 6

Soil backfilling including watering


4
and rammering - 10 Cum
Male Coolie Nos 1.5

Female coolie Nos 1.35

5 Plain Cement Concrete - 1Cum

Male Coolie Nos 0.7

Female coolie Nos 0.7

Mason Nos 0.13

Foreman Nos 0.13

6 Reinforced Cement Concrete - 1Cum

Male Coolie Nos 1

Female coolie Nos 1

Mason Nos 0.3

Foreman Nos 0.15

Formwork - 11.16 Sqm including


7
fixing and deshuttering

Carpenter Nos 2.25

Foreman Nos 0.2

Helper Nos 2.25

8 Brick Masonry - 1 Cum

Mason Nos 0.4

Male Coolie Nos 0.5

Female coolie Nos 0.5

Waterman Nos 0.2


9 Half Brick Masonry -10 Sqm

Mason Nos 0.9

Male Coolie Nos 0.6

Female coolie Nos 0.4

Waterman Nos 0.2

10 Solid Block Masonry -1.89 Cum

Mason Nos 2.5

Male Coolie Nos 1.75

Female coolie Nos 1.75

Waterman Nos 0.2

Concrete Flooring 25mm Thk 10


11
Sqm

Mason Nos 1

Male Coolie Nos 1

Female coolie Nos 1

Waterman Nos 0.1

Tile Skirting on Steps and dados - 1


12
Sqm

Mason Nos 0.6

Male Coolie Nos 0.5

Waterman Nos 0.25

13 Tile Flooring - 1 Sqm


Mason Nos 0.4

Male Coolie Nos 0.4

Waterman Nos 0.1

Smooth Finish Plastering - 10 Sqm


14
and 12mm Thk

Mason Nos 0.75

Male Coolie Nos 1.5

Female coolie Nos 1.5

Waterman Nos 0.15

Distemper Painting including Prime


15
coat - 10 Sqm

Painter Nos 0.45

Helper Nos 0.45

Steel reinforcement - 100 Kg


16
including cutting and laying

Barbender Nos 0.8

Helper Nos 0.8