Anda di halaman 1dari 2

RINCIAN RENCANA ANGGARAN BIAYA

Provinsi Jenis Kegiatan


Kabupaten
Kecamatan
Desa

NO. RAB
Program

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH BIAYA

A UMUM
1 Mobilisasi 1,0 Ls Rp 89.169.000,00 Rp 89.169.000,00

Total A 89.169.000,00
B BAHAN
1 Bahan Timbunan Pilihan 90,0 m3 Rp 92.250,00 Rp 8.302.500,00
2 AGREGAT KELAS A (kondisi lepas) 379,0 m3 Rp 604.000,00 Rp 228.916.000,00
3 Aspal pen. 60 / pen. 70 8911,0 Kg Rp 15.250,00 Rp 135.892.750,00
4 Kerosene/Minyak Tanah 355,0 Liter Rp 11.300,00 Rp 4.011.500,00
5 Agr 5-10 & 10-15 39,0 m3 Rp 553.500,00 Rp 21.586.500,00
6 Agr 0-5 19,0 m3 Rp 553.500,00 Rp 10.516.500,00
7 Pasir Halus 30,0 m3 Rp 123.000,00 Rp 3.690.000,00
Total B 412.915.750,00
C ALAT
1 ASPHALT FINISHER 1,0 Jam Rp 984.600,00 Rp 984.600,00
2 ASPHALT MIXING PLANT 3,0 Jam Rp 8.777.000,00 Rp 26.331.000,00
3 COMPRESSOR 4000-6500 L/menit 1,0 Jam Rp 233.100,00 Rp 233.100,00
4 DUMP TRUCK 3,5 T 80,0 Jam Rp 393.000,00 Rp 31.440.000,00
5 GENERATOR SET 3,0 Jam Rp 608.600,00 Rp 1.825.800,00
6 MOTOR GRADER >100 HP 8,0 Jam Rp 744.900,00 Rp 5.959.200,00
7 TANDEM ROLLER 6-8 T. 2,0 Jam Rp 320.200,00 Rp 640.400,00
8 TIRE ROLLER 8-10 T. 1,0 Jam Rp 722.500,00 Rp 722.500,00
9 VIBRATORY ROLLER 5-8 T. 17,0 Jam Rp 480.700,00 Rp 8.171.900,00

Total C 76.308.500,00
D UPAH
1 Mandor 11,0 HOK Rp 153.750,00 Rp 1.691.000,00
2 Pekerja 8,0 HOK Rp 107.625,00 Rp 861.000,00

Total D Rp 2.552.000,00
Jumlah A+B+C+D Rp 580.945.250,00
Pajak Galian C Rp 11.860.900,00
PPN (10%) Rp 41.291.500,00
PPh (1,5%) Rp -
Biaya Pembangunan (setelah dipotong pajak) Rp 527.792.850,00
Biaya Perencanaan (4%) Rp 23.237.800,00
Biaya Honorarium TPK (3%) Rp 17.428.300,00
Biaya Operasional TPK (2%) Rp 11.618.900,00
TOTAL BIAYA Rp 633.230.250,00

TERBILANG: ENAM RATUS TIGA PULUH TIGA JUTA DUA RATUS TIGA PULUH RIBU DUA RATUS LIMA PULUH RUPIAH

Anda mungkin juga menyukai