FOR
THE PROCUREMENT OF
Volume II of V
Book 1 of 4
May 2018
SUMMARY OF DOCUMENTS
2. Specifications
A. General Specifications
100 General Specifications (GS)
101 Application of the General Specification
102 Definitions
103 Mobilization
104 Contractor’s Temporary Facilities
105 Project Information Sign Boards
106 Laboratory
107 Contractor’s Project Organization and
Management
108 Site Offices of the Employer and The Engineer
109 Works in the Vicinity of Existing Operating
Philippine National Railways
110 Detailed Works Program
111 Monthly Progress Report
112 Surveying, Setting Out the Works and Staking
113 Utility Treatment / Utilities Relocation and Protection
114 Traffic Management
115 Quality Assurance and Quality Control Requirements
116 Materials
117 Site Safety
118 Environmental Management
119 Document and Drawing Submittals and Reviews
120 Submission and Response Procedure
121 BIM Requirements
122 Construction Photographs
123 Video Recordings
124 Meeting Requirements
125 Liaison with Others
126 Interface Management
127 Publicity and Public Relations
128 (Not Used)
129 Demobilization and Closing the Works
130 (Not Used)
131 System Assurance
132 Risk Management
133 Requirements Management
134 (Not Used)
135 Integrated Testing and Commissioning
136 Project Management
3. Drawings
May 2018
FOR CP01
1 SCOPE OF WORKS
1.1 Brief Description of Scope of Works
The structure of the North-South Commuter Railway Project (NSCR) is designed
independently from the existing structure of the North Railway project. Total
length of this contract package is 23.6 km (from -2km886 to 20km740) of main
line and the Works include, but not limited to, the following major work items:
1) Embankment Works: 1.8km
2) Viaducts: 21.3km
3) Bridge (River and Road Crossing): 0.5km
4) Stations: 7 elevated stations
5) Ancillary Works (utilities, protection of historical station building, fencing,
etc.)
The new depot is designed near Valenzuela Station and east side of main tracks
line. A part of existing proposed land is previously utilized as a work site for the
Northrail project and the existing Northrail structures will be cleared out by the
DOTr prior to commencement of construction activities. The land area of the new
depot is almost 14.1 ha and has a plan to make 1.0~2.5 m embankment for
preventing flood. The Depot access track allows exiting trains to north bound
(Malolos) and turning back trains from Malolos via a crossover.
Detail Scope of Works is referred to the Specifications and Drawings which shall
be read together with other contract documents.
1.3 Viaducts
The NSCR pass through a relatively densely populated urban area where viaducts
will be the dominant civil and architectural feature in the urban environment.
Some appropriate structural types of viaducts and bridges with alternative options
were evaluated from Cost, Constructability, Environmental impacts and aesthetics,
Structural Characteristics and Maintenance requirement. The following basic
structural forms are employed for the Project:
1) Super structure: Precast pre-stressed concrete segmental box girders erected
by erection gantry with typical spans of 40m
2) Pile Foundation: Multiple-pile foundation-small diameter multiples pile with
SOW- 1
North-South Commuter Railway Project
(Malolos-Tutuban) Part 2 – Works Requirements
CP01: Elevated Structures, 7 Stations and Depot Section VI
CP02: Elevated Structures and 3 Stations Scope of Works
pile caps
3) Sub Structure: Cast-in-place reinforced concrete piers.
1.5 Stations
The NSCR Station buildings are at two (2) or three (3) levels, with a length of 180.0
m by an average width of 30.0 m (corresponding with the minimum available
NSCR ROW); each coach is about 20.0 m long and a train has 8 coaches (for a
total length of 160.0 m); with an extra length of 10.0 m at each end, the NSCR
station measures 180.0 m long.
Platform and roof structures each are supported on integral 3-dimensional moment
frame structure, with the tracks supported on a precast segmental pre-stressed box
girder on cantilever piers. Foundation systems for both the platform and viaduct
consist of pile caps with bored in-situ concrete piles.
The NSCR Stations have either an outboard platform or an island platform. The 2
Station levels (platform level and concourse level) are interconnected by vertical
access systems consisting mainly of stairs and escalators, as well as lifts for select
passengers (disabled, elderly, pregnant women, children, and the like). Ramps also
connect the concourse level and/or FGL on the Station plaza. All gates and ticket
dispensers are at the concourse level.
The enclosed concourse level areas consist of main entry areas, small offices,
elevator lobbies, queue and circulation areas, including stair/ escalator threshold
areas, ticket vending areas, gates/ turnstiles, comfort rooms and utility areas. The
un-enclosed concourse level areas consist of drop-off areas, sidewalks ramps and
steps. The platform level consists of platform and circulation areas, including
stairs/ escalators threshold areas and utility areas.
The electrical and mechanical systems included in the station are as follows, but
not limited to:
1) Power Supply and Distribution System including Grounding and Generator
System
2) Lighting and Emergency Lighting, Socket outlet system;
SOW- 2
North-South Commuter Railway Project
(Malolos-Tutuban) Part 2 – Works Requirements
CP01: Elevated Structures, 7 Stations and Depot Section VI
CP02: Elevated Structures and 3 Stations Scope of Works
The Contractor can utilize the temporary yards of Tayuman Rd. (33,800m2) and
Samson Rd. (39,600m2) as shown table 11.1.3. and figures 11.8.5 and 11.8.6.
The Contractor needs to negotiate a lease fee with the owners of these properties.
The Contractor shall search for lands for the temporary Construction Yards except
for these 2 locations.
SOW- 3
North-South Commuter Railway Project
(Malolos-Tutuban) Part 2 – Works Requirements
CP01: Elevated Structures, 7 Stations and Depot Section VI
CP02: Elevated Structures and 3 Stations Scope of Works
FOR CP02
1 SCOPE OF WORKS
1.1 Brief Description of Scope of Works
The structure of the North-South Commuter Railway Project (NSCR) is designed
independently from the existing structure of the North Railway project. Total
length of this contract package is 14.0 km (from 20km740 to 34km743) of main
line and the Works include, but are not limited to, the following major work items:
1) Embankment Works: 0.4km
2) Viaducts: 13.4km
3) Bridge (River and Road Crossing): 0.1km
4) Stations: 3 elevated stations
5) Ancillary Works (utilities, protection of historical station building, fencing,
etc.)
A detailed Scope of Works is referred to the Specifications and Drawings which
shall be read together with other contract documents.
1.3 Viaducts
The NSCR passes through a relatively densely populated urban area where viaducts
will be the dominant civil and architectural feature in the urban environment.
Some appropriate structural types of viaducts and bridges with alternative options
were evaluated from cost, constructability, environmental impacts and aesthetics,
structural characteristics and maintenance requirements. The following basic
structural forms are employed for the Project:
1) Super Structure: Precast pre-stressed concrete segmental box girders erected
by erection gantry with typical spans of 40m;
2) Pile Foundation: Multiple-pile foundation-small diameter multiple piles with
pile caps;
3) Sub Structure: Cast-in-place reinforced concrete piers.
SOW- 4
North-South Commuter Railway Project
(Malolos-Tutuban) Part 2 – Works Requirements
CP01: Elevated Structures, 7 Stations and Depot Section VI
CP02: Elevated Structures and 3 Stations Scope of Works
1.5 Stations
The NSCR Station buildings are at two (2) or three (3) levels, with a length of 180.0
m by an average width of 30.0 m (corresponding with the minimum available
NSCR ROW); each coach is about 20.0 m long and a train has 8 coaches (for a
total length of 160.0 m); with an extra length of 10.0 m at each end, the NSCR
station measure 180.0 m long.
Platform and roof structure are each supported on integral 3-dimensional moment
frame structure, with the tracks supported on a precast segmental pre-stressed box
girder on cantilever piers. Foundation systems for both the platform and viaduct
consist of pile caps with bored in-situ concrete piles.
The NSCR Stations have either an outboard platform or an island platform. The 2
station levels (platform level and concourse level) is interconnected by vertical
access systems consisting mainly of stairs and escalators, as well as lifts for select
passengers (disabled, elderly, pregnant women, children, and the like). Ramps also
connect the concourse level and/or FGL on the station plaza. All gates and ticket
dispensers are at the concourse level.
The enclosed concourse level areas consist of main entry areas, small offices,
elevator lobbies, queue and circulation areas, including stair/ escalator threshold
areas, ticket vending area, gates/ turnstiles, comfort rooms and utility areas. The
un-enclosed concourse level areas consist of drop-off areas, sidewalks ramps and
steps. The platform level consists of platform and circulation areas, including stair/
escalator threshold areas and utility areas.
The electrical and mechanical systems included in the Station are as follows, but
not limited to:
1) Power Supply and Distribution System including Grounding and Generator
System;
2) Lighting and Emergency Lighting, Socket Outlet System;
3) Fire Alarm and Detection System;
4) Lightning Protection System;
5) Building Automation System;
This contract package includes the construction of three elevated stations;
1) Balagtas Station (2 levels)
2) Guiguinto Station (3 levels)
SOW- 5
North-South Commuter Railway Project
(Malolos-Tutuban) Part 2 – Works Requirements
CP01: Elevated Structures, 7 Stations and Depot Section VI
CP02: Elevated Structures and 3 Stations Scope of Works
SOW- 6