Anda di halaman 1dari 10

Fire Safety Journal 58 (2013) 160–169

Contents lists available at SciVerse ScienceDirect

Fire Safety Journal


journal homepage: www.elsevier.com/locate/firesaf

A risk-based method for determining passive fire protection adequacy


Arshad Ahmad n, Siti Ayesah Hassan, Adnan Ripin, Mohamad W. Ali, Saharudin Haron
Institute of Hydrogen Economy, Faculty of Chemical Engineering, Universiti Teknologi Malaysia, 81310 Johor Bahru, Malaysia

a r t i c l e i n f o a b s t r a c t

Article history: A risk-based approach to determine the adequacy of designed safety barriers in process plants is
Received 11 May 2012 proposed and implemented to an offshore gas production platform. The scheme employs quantitative
Received in revised form risk assessment method to assess the impact of selected process hazards and the adequateness of safety
18 October 2012
barriers based on a selected ALARP threshold value. The results obtained are further verified using
Accepted 20 January 2013
emergency evacuation response analysis. Evaluations carried out on the designed fire/blastwalls for the
selected case study confirmed the suitability of the proposed method.
Keywords: & 2013 Elsevier Ltd. All rights reserved.
Risk-based design
Passive fire protection
QRA
Emergency evacuation time
Offshore platform

1. Introduction often not available until the project is well into the detailed design
phase. This entailed simplified and less complex methods so that
Firewall and blastwall are examples of important layers of safety concerns can be identified earlier and embedded inherently
protection in offshore facilities that must be made adequate to throughout the project phases. Krueger and Smith [7] proposed a
satisfy the robust design requirement. This is important because simplified scenario-based methodology for fire risk analysis that
hydrocarbon fires can elevate the temperature of unprotected can be applied early in the design cycle, but their analysis is only
loaded steel structures to 1100 1C within minutes, leading to useful for preliminary purposes. Shetty et al. [8] described a
structural collapse due to loss of strength. In addition to direct scheme that integrates the structural reliability analysis with
damages such as injuries, fatalities and asset losses, accidents QRA. In this work, models and tools on fire and blast loading are
escalation into severe scenarios can have more detrimental effects presented and method for estimation of failure frequencies of
[1,2]. Typically, fire resistance can be established by adding fire/ components and systems for which historical data are not available
blastwall with suitable insulation materials or coatings on struc- is proposed. More detailed analyses using finite elements for
ture surfaces to reduce the rate of heat transfer to steel surfaces structural analysis [9], and CFD to study impact of fire and
and minimize flame propagation [3]. explosions [10–12] on offshore facilities have also been reported,
As part of the safety best practices, API RP 14J recommended but the approach is far too demanding for smaller projects.
that a firewall or adequate space should be considered to separate More recently, a seven step risk-based method to allow a more
living quarters from areas containing hydrocarbon sources and if detailed identification of the reference accident scenarios considered
high risk process spaces are confined, blast protection should be for the identification of fire protection zones has been proposed [13].
considered. However due to limitations such as availability of However, while their conclusion was positive for on-shore facilities,
materials according to the desired specifications as well as time the application to offshore structures with limited space availability
and budget constraints, direct application of the worst case is still uncertain. The aim of this paper is to provide a methodology
scenario requirement is often found to be impracticable to the for making a quick judgment required especially for fast track
overall cost benefit, and some forms of risk assessment are projects. The approach of Dey [14] is adopted with modifications
required. Owing to this need, various risk assessment methodol- to accommodate the needs of offshore facility as opposed to the
ogies have been used throughout the planning and design period nuclear industry. The methodology is demonstrated using a case
[4,5] assisted by commercial software [6]. study involving an offshore gas platform.
While a full blown QRA provides all the necessary insights
required to guide the design, the level of details needed for a QRA is
2. Framework of coarse risk-based method

n
Corresponding author. Tel.: þ607 5535610; fax: þ607 5588166. The proposed framework applies QRA concept to provide
E-mail address: arshad@cheme.utm.my (A. Ahmad). analysis-matching-the-needs requirement for fast-track projects.

0379-7112/$ - see front matter & 2013 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.firesaf.2013.01.020
A. Ahmad et al. / Fire Safety Journal 58 (2013) 160–169 161

Fig. 1. Study methodology (Reproduced from [15]).

The method demonstrates the use of ALARP region as one of the fitted with process facilities and utilities system. The processing
design decision tools in evaluating the safety layer proposed. The units include:
framework is as summarized in Fig. 1. The steps include [15]:

 Separation system;
 System definition with regards to fire and explosion credible  Gas compression system;
hazards on the installation that may be capable of threatening  Fiscal metering facility for sales gas and condensate;
life or platform integrity;  Pig launcher;
 Identification of areas and isolatable segments of hydro-  Condensate export pumps;
carbon inventory in process piping and equipments, i.e. iso-  Fuel gas treatment system;
lated inventories between the Emergency Shutdown Valves  Seal gas system;
(ESDVs);  Flare system; and
 Release or discharge calculation according to probable leak  Diesel storage and distribution system.
sizes (categorized into ‘Small’, ‘Medium’ and ‘Large’);
 Frequency assessment to estimate the initial frequency (i.e.,
hydrocarbon leak/release frequency), which will be used as
key inputs to Event Tree Analysis (ETA); 3.1. Basis of fire/blastwall impairment criteria
 Consequence modeling to analyze fire and explosion impacts
on topsides and riser/pipeline; The following impairment criteria of fire/blast are laid for the
 Carry out fire and explosion probabilistic analysis and Event analyses:
Tree Analysis (ETA);
 Carry out probabilistic impairment assessment against fire
and blast rating (i.e. J15, H60 and 0.4 barg) using second level  Fire wall (J15 and H60 rated)
of Event Tree Analysis (ETA); and
 Results and recommendations of the analysis suggesting 1) Criterion ‘‘FW1’’: The wall is impinged by jet fire for
alternative approach of analysis. continuous 15 min; or the wall is exposed to pool fire
continuously for 60 min;
2) Criterion ‘‘FW2’’: The impairment frequency of the firewall
The results of the analyses are further verified using the Escape (i.e. the total escalation frequencies of the fire events that
and Evacuation Response (EER) methodology. The indicator, the can impinge onto the firewall) is not exceeding 1  10  4
EER time is defined as the required travel time from the working per year [16].
area to a ‘safe place’ during major accident event.
 Fire/blast wall (J15, H60 and 0.4 barg explosion rated)

3. Case study: offshore gas platform 1) Criterion ‘‘FBW1’’: The wall is impinged by jet fire for
continuous 15 min; and the wall is exposed to pool fire
The objective of the case study is to demonstrate the use of the for continuous 60 min; and the wall is exposed to an
proposed framework in a real case situation. As an example, the explosion overpressure of more than 0.4 barg;
adequacy of a proposed fire/blastwall in an offshore gas produc- 2) Criterion ‘‘FBW2’’: The impairment frequency of the
tion platform is investigated. The platform is located in a gas field fire and blastwall (i.e. the total escalation frequencies of
with 60 m water depth, and is meant to export gas and con- the fire and explosion events that can impinge or expose
densate to an onshore reception facility located more than onto the fire and blastwall) is not exceeding 1  10  4 per
100 km away. The platform is equipped with living quarters and year [16].
162 A. Ahmad et al. / Fire Safety Journal 58 (2013) 160–169

Table 1 3.3. Consequence assessment


Release hole sizes.
3.3.1. Assumptions
Release type Hole sizes (mm) Representative hole sizes (mm)
The potential accidental scenarios included in the assessment
Process equipment are jet fire, pool fire and vapor cloud explosion. Since Closed/Open
Small 3–10 10 Drain System has minimal hydrocarbon inventories compared to
Medium 10–50 30 large vessels such as separators and fuel gas scrubbers during
Large 50–150 100
Riser/pipelines
normal operations, it is not assessed in this study. The flare
Small 0–20 10 system is included since it is normally filled up with large amount
Medium 20–80 50 of hydrocarbon in the event of upset or emergency depressuriza-
Large 480 350 tion condition, but is limited to the section from the flare KO
drum to the flare tip. All drain and vent piping from the process
areas are also excluded as they have significantly lower inventory
The acceptance criterion of the fire wall and blast wall is either compared to the KO drum. For the Diesel Storage & Distribution
Criterion 1 or Criterion 2 is met, which in turn, concludes the fire System, since it is a stand-alone system, used for crane operation
rating and blast rating on the fire wall and blast wall as adequate. only consequences from the diesel storage tank are assessed to
provide late pool fire consequence to firewall (H60 rating).
The hydrocarbon fire and explosion outcomes (i.e. flame durations
3.2. Accidental event process releases
and blast effects) are assumed equivalent to the rating of fire proofing
materials established by Underwriter Laboratory (UL), which is an
The statistic report published by UK HSE [17] gives distribu-
independent certification body accredited by the US Occupational
tion for 7 hole size groups (i.e. o10 mm, 10 o25 mm,
Safety & Health Administration (OSHA), the American National
25o50 mm, 50 o75 mm, 75o100 mm, Z100 mm and ‘‘Not
Standards Institute (ANSI), and the Standards Council of Canada
Applicable’’), while CMPT [15] suggests that the typical hole sizes
(SCC). Exceptional to J class division (i.e. jet fire outcome), fire test
are approximately 5 mm, 25 mm and 100 mm for small, medium
is performed based on UK HSE established document (OTI 95634) as
and large releases respectively. For the analysis to be conserva-
this test is more appropriate for intense severe hydrocarbon fires.
tive, calculation for process accidental releases is performed using
The following conditions are used in all analyses:
the representative hole sizes listed in Table 1. In determining the
volume and duration of hydrocarbon releases from isolatable
segments, Emergency Shut Down Valve (ESDV) closure time is
incorporated.
 Isolation and/or blowdown is successful.
 Leaks from both the gas and two-phase segments (e.g. well
fluids) are treated as vapor releases as the lighter hydrocarbon
3.2.1. Release duration has a higher molar volume.
During an accidental release of a leak scenario, pressure inside  Jet fire at immediate ignition. If the jet impinges on a
the vessel or segment is anticipated to reduce with time. Hence, sufficiently large object, e.g. a solid deck/equipment, the
the release of hydrocarbons is modeled as a time-varying dis- momentum in the jet will be wholly or partially lost and a
charge taking into consideration pressure drops and the effect of diffusive fire will occur. If delayed ignition occurs and the gas
blowdown. In order to accurately calculate the release duration release is allowed to accumulate, there is a potential for a flash
that can give significant impact to personnel, releases below fire or explosion. However, no flash fire has been specifically
2 barg are neglected. The limit of 2 barg is selected in line with modeled as the effects of explosion would be more dominant
relief valve back-pressure nominal setting based on API RP 520. in term of consequences due to higher degree of confinement
between the decks.
 Late pool fires at delayed ignition, in which a bigger pool is
3.2.2. ESDV closure time
formed. The pool fire center is assumed to be located at the
It is assumed that the ESDV’s in process lines will close (i.e.
rainout point.
isolation successful) and isolate the hydrocarbon event inventory
 Multi-Energy explosion at delayed ignition, in which considers
on confirmed fire or gas detection. The time required for any
degree on confinement.
safety device to affect component or platform shutdown should
not exceed 45 sec. Whenever, ESDV is activated, process inputs
are shut-off at the primary source (wells, pump, compressor, etc).
3.3.2. Results
This would be repeated for each component back through the
The well fluid produced at the facility contains 0.99 gaseous
process until the primary source is shut in, i.e. via a cascading
fractions of mixture Methane and Ethane components at approx.
flow [18]. In practise, actual timings are expected to be quicker.
22 1C and 92 barg. All the deck floors are plated except at the
lowest level reaching Splash Zone area. The potential fire and
3.2.3. Release calculations explosion scenarios takes into account the well fluid composition
Most of potential jet fire releases in the category of ‘Small’ and equipment arrangement on the platform. The results of the
leaks could result in hydrocarbon discharge at t ¼15 min, while consequence analyses are summarized as follows:
the ‘Large’ releases at t ¼15 min only lead to ‘Flare’ and ‘Riser’
segments. For the liquid segment, the discharge pressure of the
aerosol is according to pumping pressure until the last drop of  Large hydrocarbon leak from the topside riser produces the
liquid, as such, there would be no difference in discharge condi- longest jet flame on the facilities;
tions at 15 or 60 min.  Due to the relatively low inventory within the segment
The size of explosion corresponds to the congestion varies to (exceptional to Riser events), the fire only lasts for less than
the leak module. The volume discharge is taken to be instanta- 5 min for medium and large releases;
neous at ‘delayed’ scenarios. This is defined as ‘Used of Flammable  Most of the medium and large jet fires can lead to 37.5 kW/m2
Mass’, i.e. mass the will be burned out between UFL and LFL. heat radiation level during initial release. However, it should
A. Ahmad et al. / Fire Safety Journal 58 (2013) 160–169 163

be noted that these events are located within the process area, ii. Early detection. It is assumed that all medium and large
where there is a firewall and/or fire/blastwall that separates releases are successfully detected. The probabilities assumed
the living quarter, enclosure area and process area. Although for medium and large releases are based on a target Safety
there may be escalation within the local area, escalation to the Integrity Level (SIL) of 2 for the detector system, which is the
area behind the firewall and fire/blastwall is not anticipated to minimum requirement as according to IEC 61511. SIL 2 implies
occur immediately; an on-demand failure probability between 0.001 and 0.01. To
 The hazard range for 15 min of jet fires from the gas segments be conservative, a probability of 0.01 has been assumed,
drops significantly due to the effect of blowdown, therefore which is appropriate as it is possible that the release may
most of these releases do not lead to 37.5 kW/m2 heat occur at a location where it is not in the line-of-sight to the
radiation level at 15 min; gas detection, leading in failure to detect the leak.
 Condensate releases from the bottom of Production Separator iii. Explosion overpressure. The explosion probability given a
and condensate piping are modeled as jet fires due to large delayed ignition is calculated by using NOBRA (NOrsok
pressure difference between the pressure inside vessel and BRAnch probabilities). NOBRA is a spreadsheet tool that is
atmospheric pressure, which leads to the flashing of condensate used to provide estimates of exceeding an explosion over-
into vapor form and subsequently turn into jet fire when ignited; pressure given delayed ignition in offshore installations. The
 Pool fire is only anticipated when there is an ignition of diesel effect of key parameters such as release rate, module volume,
near to the diesel storage tank; degree of confinement and degree of congestion are included.
 Immediate ignition due to the rupture of riser or during iv. Isolation/blowdown failure. Should a leak be detected, the
blowouts can result in fireballs, which give significant hazard main process unit will be isolated by closing ESDVs in order to
range and impact to the facilities; limit the release of inventories. The ESDVs are normally fail-
 Explosion due to delayed ignition of large gas releases are close; hence it is assumed that if the ESD control system fails for
possible. Rupture of the riser at the topside gives the worst some reasons, the valve will close automatically. For this reason,
overpressure hazard range on the process facility due to the no common mode failure is assumed whereby all the ESDV fails
higher degree of confinement on topsides, and its large close. However, there is still a possibility having individual ESDV
hydrocarbon inventory. to fail-to-close on demand. The on-demand failure probability of
ESDV used in this analysis is based on OREDA [20], i.e. 0.02 for all
3.4. Frequency analysis sizes. The same reasoning applies to the on-demand failure
probability of blowdown valves for all sizes.
Fire and explosion barriers considered in constructing event
trees for quantifying fire and explosion frequencies are as follows: 3.4.1. Leak frequencies
The leak frequencies are calculated for each isolatable segment
components lined-up according to the number and size of valves,
i. Ignition probability. The probability of ignition is taken from flanges, instrument connections, vessel and piping together with
the Ignition Probability Review, Model Development and dimensions, pressure and phase of the hydrocarbon inventory.
Look-Up Correlations, IP Research Report [19]. This report The data used for process equipment are based on the UK HSE
evaluates the UK offshore industry OIR12 data, as a basis to Hydrocarbon Release Database [17], but for riser/pipeline the data
develop an improved ignition model for use in QRA. are based on PARLOC 2001 data source. The outcomes leak

Table 2
Fire and explosion frequencies.

Process events Event location—Segments Fire frequencies (per year) Explosion frequencies (per year)

S M L S M L

MDP/GMET/G Cellar Deck—Production Manifold 1.37E-06 5.83E-07 4.33E-08 – – 6.56E-09


MDP/INPROD/W Main Deck—Production Manifold 1.99E-07 7.55E-08 1.65E-08 – – 2.90E-09
MDP/PRODSEP/W Main Deck—Production Separator 5.89E-07 3.14E-07 1.87E-08 – – 3.07E-07
MDP/PRODSEP/G Main Deck—Production Separator 8.96E-06 4.56E-06 7.88E-07 – – 1.29E-07
MDP/PRODSEP/O Main Deck—Production Separator 5.85E-07 3.07E-07 - – – –
MDP/GCOMP1/G Main Deck—Gas Compression Train 1 9.21E-06 4.28E-06 4.74E-07 – – 7.37E-08
TD/GCOMP1/G Top Deck—Gas Compression Train 1 2.15E-06 9.94E-07 1.96E-07 – – –
TD/GMET/G Top Deck—Gas Metering Skid 2.49E-06 1.09E-06 1.74E-07 – – –
MDP/GMET/G Main Deck—Gas Metering Skid 1.37E-06 7.97E-07 2.04E-08 – – 2.83E-09
CDP/GMET/G Cellar Deck—Gas Metering Skid 9.62E-07 4.17E-07 7.29E-08 – – 7.89E-09
CDP/EXPORT/G Cellar Deck—Export pipelines 8.60E-06 4.68E-06 6.92E-07 – – 7.78E-08
SCD/EXPORT/G Sub Cellar Deck—Export pipelines 1.83E-06 9.90E-07 3.53E-08 – – 5.03E-10
MDP/COND/O Main Deck—Condensate lines 1.56E-06 8.21E-07 - – – –
CDP/COND/O Cellar Deck—Condensate lines 8.90E-06 5.83E-06 – – – –
MDP/FUELG/G Main Deck—Fuel Gas Skid 1.12E-05 6.37E-06 1.19E-06 – – –
MDP/SEALG/G Main Deck—Seal Gas Scrubber, Filter 1.18E-05 7.61E-06 – – – –
CDP/FLARE/G Cellar Deck—Flare Header, KO Drum 4.16E-06 2.53E-06 – – – –
SCD/GRISER/G Sub-Cellar Deck—Gas Export Riser 1.62E-06 2.37E-07 1.62E-07 – – 1.52E-09
SZ/GRISER/G Splash Zone—Gas Export Riser 3.88E-07 7.42E-08 1.24E-06 – – 8.60E-09
Total frequencies 7.77E-05 4.26E-05 5.12E-06 – – 6.18E-07

Note:
‘‘S’’, ‘‘M’’ and ‘‘L’’ denote ‘‘Small’’, ‘‘Medium’’ and ‘‘Large’’ accidental leak sizes.
‘‘–’’ is denoted for explosion scenario which are not anticipated in some event scenarios due to open nature and limited equipment available on platform’’.
Explosion scenarios are not anticipated in some of event scenarios due to the open nature and limited equipment available on the platform.
164 A. Ahmad et al. / Fire Safety Journal 58 (2013) 160–169

frequencies serve as an input to First Level of Event Tree, which is CDP/INPROD/W Small release) has a fire frequency of 1.08E-06
used for quantification of fire and explosion frequencies. per year. The results show that ‘Small’ leak size are dominating
the total leak frequencies, and the cumulative leak frequencies
3.4.2. Fire and explosion frequencies estimated for process/topsides and riser/pipeline events are
The fire and explosion frequencies are estimated using ETA 6.72E-02, 4.02E-02 and 4.56E-03 per year for Small, Medium
and presented in Table 2. For each event, the fire and explosion and Large leaks respectively.
frequencies are the summation of frequencies resulting from In this study, the ETA conducted at this stage is referred to as
Isolation Successful (denotes ‘IO’) and Blowdown Successful First Level ETA. Summing up all events, the total fire frequencies
(denotes ‘BO’). For example as displayed in Fig. 2, the (Event estimated for the platform are 7.77E-05, 4.26E-06 and 5.12E-06

Description

Frequency
Immediate

Blowdown
Explosion
Frequency

Detection

Outcome
Isolation
Ignition

Delayed

Possible ?

Failure
Early
Leak

Ignition

Failure
8.79E-09 Jet Fires Intermediate 8.79E-09
Y 0.02
4.40E-07
Y 0.1
4.31E-07 Jet Fires Intermediate 4.31E-07
N 0.98
4.40E-06
Y 1.00E-03
7.91E-08 Jet Fires Intermediate 7.91E-08
Y 0.02
3.96E-06
N 0.9
3.88E-06 Jet Fires Intermediate 3.88E-06
N 0.98

4.40E-03 4.35E-03 4.35E-03 Unignited Release 4.35E-03


Y 0.99

2.81E-07 2.81E-07 Explosion Delayed 2.81E-07


Y 0.2675

1.54E-09 Jet/Flash Fires Delayed 1.54E-09


4.39E-03 1.05E-06 Y 0.02
N 9.99E-01 Y 0.0239 7.69E-08
Y 0.1
7.53E-08 Jet/Flash Fires Delayed 7.53E-08
N 0.98
7.69E-07
N 0.7325
1.38E-08 Jet/Flash Fires Delayed
1.38E-08
4.39E-05 Y 0.02
N 0.01 6.92E-07
N 0.9
6.78E-07 Jet/Flash Fires Delayed
6.78E-07
N 0.98

4.29E-05 4.29E-05 Unignited Release 4.29E-05


N 0.9761
Fig. 2. Fire and explosion frequencies (Sample for Event CDP/INPROD/W Small Release).
A. Ahmad et al. / Fire Safety Journal 58 (2013) 160–169 165

Fig. 3. Second level firewall event tree (Sample for Event MDP/GMET/G Small Release).

Table 3
Impact assessment results.

‘Target’ Summation of fire Summation of blast Criterion ‘‘FW1’’ Criterion ‘‘FW2’’ Fire/blast rating adequate?
impairment frequencies impairment frequencies (See Section 3.1) (See Section 3.1)

Firewall at living quarter and main deck 1.2E-07 0.0E þ00 N N Y


‘Target’ Summation of fire Summation of blast Criterion ‘‘FBW1’’ Criterion ‘‘FBW2’’ Fire/blast rating adequate?
impairment frequencies impairment frequencies (See Section 3.1) (See Section 3.1)
Fire/blastwall at main deck 1.4E-07 1.4E-08 Y N Y
Fire/blastwall at cellar deck 6.1E-07 1.4E-08 Y N Y

Fig. 4. Location of points (A)–(D).


166 A. Ahmad et al. / Fire Safety Journal 58 (2013) 160–169

for Small, Medium and Large leaks respectively. This is higher For the blast wall, the Second Level ETA is generated by
than the expected total explosion frequency, which is in the integrating an overpressure level of 3 barg where deck flooring
magnitude of 10  7 per year. and pipe works/supports are considered blown-off, thus creating
missile effects. The purpose is to estimate the likelihood of
impairment for the firewall and blastwall and whether or not it
3.5. Impairment assessment meets the impact assessment criteria laid in Section 3.1. The
results are presented in Table 3, and based on these values, the
The impairment assessment only takes into account events fire and blast ratings on fire/blastwall are deemed adequate.
with resulting consequences that exceed the acceptance criteria,
i.e. leak duration beyond 15 min and 60 min for jet fire and pool
fire events respectively, and event resulting in explosion over- 3.6. EER analysis
pressure of more than or equal to 0.4 barg. At this step, ETA is
used again (referred to as Second Level ETA) to screen events that The proposed simplified QRA based method presented in the
meet the criteria. An example of a Second Level ETA showing the above has proved that the PFP ratings are in line with ALARP
event (MDP/GMET/G Small Release) is depicted in Fig. 3. It is requirements. In this section, the PFP ratings are compared with an
developed based on information derived from flame length or alternative assessment known as the EER Analysis. The key vari-
pool diameter or explosion radii reaching the ‘target’, obstruction able, i.e., EER time is defined as the time required to execute safe
of other equipment or decks floor and flame width or diameter evacuation operation during emergency. It is the time required to
according to 3601 radius direction of impingement. get to a ‘safe place’ from the working area. Depending on the
location of the event, the ‘safe place’ can be either (see Fig. 4):

 Point (A)—Firewall segment at Frame 2B


 Point (B)—Fire/blastwall segment at Frame 2A
 Point (C)—Firewall segment at Frame 1B
 Point (D)—which is at the survival craft muster area (primary
evacuation)

The EER time is computed from the furthest point of manning


area in each deck (i.e. from Helideck, above Air Cooler Top Deck,
Crane Cabin, Gas Turbine Package Main Deck, Pigging Area Cellar
Deck and Drain Area Sub Cellar Deck) to reach primary muster
area within the area of survival craft, identified as (D) in Fig. 4.
The EER analysis is simulated according to the flow as depicted in
Fig. 5 and the EER time is computed according to site specific
basis of emergency system activation, procedural response plan
and offshore worker movement speed, based on real-time drill
exercises. In all cases, conservative estimates that consider
possible congestions during evacuations are used. Note that in
mapping the activities to the classification of evacuation phases
Fig. 5. Sequence of evacuation (Reproduced from [21]). as defined in Fig. 5, some of the steps required may involve more

Fig. 6. Top deck (Evacuation flow No. 1, 2, 3).


A. Ahmad et al. / Fire Safety Journal 58 (2013) 160–169 167

Fig. 7. Main deck (Evacuation Flow no. 4) and Continuation of Flow no. 1, 2, 3, 5 and 6.

than one phase, For example, the time required to make the work Deck, and proceed to the escape routes at the north part of
area safe involves tA (Awareness Phase) and tEv (Evaluation platform area to the stairs reaching Main Deck, and finally
Phase). The estimations are as follows: to primary master area (D)

ii. Main Deck (see Fig. 7)


 0.5 min to sound alarm (i.e. t1);
 3.0 min to make work area safe, i.e. tA and tEv;  Flow no. 4 (from Gas Turbine Package)—Personnel located
 1.0 m/s on level walkways or corridors, i.e. tEv and tEg; at Gas Turbine Package may progress to the escape route at
 0.8 m/s on changing decks using stairs, i.e. tEv and tEg; eastern part of the platform, and followed the escape route
 0.3 m/s on ladders (allows for the time taken on and off the at the southern along the perimeter to the primary muster
ladder), i.e. tEv and tEg; area (D) located at the west part of platform area.
 10.0 min for decision making, roll-call and don lifejackets (only  Flow no. 1, 2 and 3—Continuation of evacuation process
applicable during mustering) i.e. tEv; for personnel located at Top Deck, to primary muster
 3.0 min to board the life raft or survival craft and confirm area (D).
whether everybody is on-board, i.e. tR; and  Flow no. 5—Continuation of evacuation process for per-
 10.0 min to launch the life raft or survival craft, which includes sonnel located at Cellar Deck, to primary muster area (D).
time release break, lower and release, falls, and move away  Flow no. 6—Continuation of evacuation process for per-
from the platform, i.e. tR. sonnel located at Sub-Cellar Deck, to primary muster
area (D).
The procedural evacuation flow for EER time simulations
using primary escape routes are strategized on simplified decks iii. Cellar Deck (see Fig. 8)
diagram shown below:
 Flow no. 5 (from Pigging Area)—Personnel located at
Pigging Area within the eastern platform area may proceed
i. Top Deck (see Fig. 6) to the southern part of platform area, walking up to Main
Deck via stairs and finally to the primary muster area (D) at
 Flow no. 1 (from Helideck)—Personnel located helideck the western part of platform area.
walking down via stairs located southern part of the
platform to reach Main Deck and finally proceed to primary iv. Sub-Cellar Deck (see Fig. 9)
muster area (D).
 Flow no. 2 (from above Air Cooler Top Deck)—For person-  Flow no. 6 (from Drain Area)—Personnel located here may
nel who are performing maintenance or inspection above proceed toward southern part of the platform area, to the
Air Cooler Top Deck, they may proceed to escape route at ladder in the midst of the escape path. Then, they may
the southern part of the platform, walking down stairs to proceed to upper level decks (i.e. Cellar Deck and Main
Main Deck and proceed to primary muster area (D). Deck). From Main Deck, they may just follow the escape
 Flow no. 3 (from Crane Cabin)—Crane operator escaping route perimeter to the western part of platform area
down via ladder connected to pedestal tower to reach Top (primary muster area (D)).
168 A. Ahmad et al. / Fire Safety Journal 58 (2013) 160–169

Fig. 8. Cellar deck (Evacuation Flow no. 5).

Table 4
Time to safety from furthest working area at each deck.

No. Work area Total time (min)

Work Work Work Work area-


area-A area- area-A- A-B-C-D
A-B B-C

1 Helideck 0.0 0.0 0.0 5.2


2 Top of air cooler 4.2 4.2 4.4 5.5
(Top Deck)
3 Crane cabin 4.2 4.2 4.5 5.5
4 Gas turbine 4.2 4.2 4.4 4.8
package (Main
Deck)
5 Pigging area (Cellar 3.7 4.2 4.4 5.0
Deck)
6 Drain area (Sub- 4.4 4.8 4.9 5.5
cellar Deck)

Fig. 9. Sub cellar deck (Evacuation Flow no. 6).

of platform abandonment is needed. Therefore, an additional time


Based on the procedural evacuation flows as shown in Figs. 6–9, of 23 min (from the maximum 6 min resulted in Table 4) is
the simulated EER time are computed and shown in Table 4. On assumed needed to complete an evacuation process. This gives a
average, 3.7–5.5 min are allowed for the first level firewall failure cumulative of 28.5 min needed for the complete recovery process.
(i.e. at locations (A) and (B)). This is the maximum duration that the With redundancy of another firewall protecting living quarters,
firewall is able to maintain its integrity as a barrier to the generated additional amount of survival time can be considered. Complete
fire event in 15 min jet fire and 60 min pool fire. evacuation is therefore successful, assuming no double jeopardy
This EER analysis also assumed that no escalation from failures event and the platform structural integrity is retained.
of deck floors and other structural components, safety equipment
and hydrocarbon vessels, i.e. no double jeopardies. Credit is taken
as if the deck floors and other structural components, safety 4. Conclusions
equipment and hydrocarbon vessels managed to fully maintain its
integrity at minimum of 15/60 min, which is at the firewall The proposed method is an important tool for design
exposure rating time due to jet/pool fire. verification to justify the adequacy of safety barriers used in
In order to complete an evacuation process to a place of safety offshore platforms as well as other similar process facilities.
from the survival craft muster area, an amount of additional time While not involving high degree of complexities, the method
A. Ahmad et al. / Fire Safety Journal 58 (2013) 160–169 169

incorporates important items that influence the safety of the [7] J. Krueger, K.J. Smith, A practical approach to fire hazard analysis for offshore
proposed installation. This has been illustrated by the case structures, J. Hazardous Mater. 104 (1-3) (2003) 107–122.
[8] N.K. Shetty, C.G. Soares, P. Thoft-Christensen, F.M. Jensen, Fire safety assess-
study presented here and can be conveniently adopted for ment and optimal design of passive fire protection for offshore structures,
other cases. Reliab. Eng. Syst. Saf. 61 (1–2) (1998) 139–149.
The case study presented here shows that the fire rating J15 [9] J.W. Boh, L.A. Louca, Y.S. Choo, Numerical assessment of explosion resistant
and H60 firewalls located in the facility is deemed adequate based profiled barrier, Mar. Struct. 17 (2) (2004) 139–160.
[10] J.K. Paik, J. Czujko, B.J. Kim, J.K. Seo, S.R. Han, C.H. Yeon, P. Janiszewski,
on EER time of worker to be able to muster at survival craft area at P. Musial, Quantitative assessment of hydrocarbon explosion and fire risks in
Main Deck assuming no double jeopardy events, i.e. escalation offshore installations, Mar. Struct. 24 (2011) 73–96.
events due to failure of deck floors and other structural compo- [11] B.J. Kim, J.K. Seo, J.H. Park, J.S. Jeong, B.K. Oh, S.H. Kim, C.H. Park, J.K. Paik,
nents, safety equipments and hydrocarbon vessels. This result is Load characteristics of steel and concrete tubular members under jet fire: an
experimental and numerical study, Ocean Eng. 37 (13) (2010) 1159–1168.
also consistent with ALARP principal applied as an input to [12] J.K. Paik, B.J. Kim, J.S. Jeong, S.H. Kim, Y.S. Jang, G.S. Kim, CFD simulations of
design. The results also proved the adequacy of the proposed gas explosion and fire actions, Ships Offshore Struct. 5 (2010) 3–12.
course risk-based methodology in determining PFP (fire/blast- [13] A.D. Padova, A. Tugnoli, V. Cozzani, T. Barbaresi, F. Tallone, Identification of
fireproofing zones in oil and gas facilities by a risk-based procedure, J.
wall) adequacy.
Hazardous Mater. 191 (2011) 83–93.
[14] M.K. Dey, An evaluation of risk methods for prioritizing fire protection
References features: a procedure for fire barrier penetration seals, Nucl. Eng. Des. 232
(2004) 165–171.
[15] J. Spounge, A guide to quantitative risk assessment of offshore installations,
[1] F.I. Khan, S.A. Abbasi, An assessment of the likelihood of occurrence, and the CMPT, 1999.
damage potential of domino effect (chain of accidents) in a typical cluster of [16] UKOOA, Fire and Explosion Guidance Part 2: Avoidance and Mitigation of
industries, J. Loss Prev. Process Ind. 14 (2001) 283–306.
Fires. Revision 2, 2006.
[2] V. Cozzani, A. Tugnoli, E. Salzano, Prevention of domino effect: from active
[17] UK HSE. Offshore Hydrocarbon Releases Statistics and Analysis, UK HSE,
and passive strategies to inherently safer design, J. Hazardous Mater. 139
2002.
(2006) 209–219.
[18] API, Recommended Practice for Analysis, Design, Installation, and Testing of
[3] T.A. Roberts, L.C. Shirvill, K. Waterton, I. Buckland, Fire resistance of passive
Basic Surface Safety Systems for Offshore Production Platforms, API RP 14C,
fire protection coatings after long-term weathering, Process Saf. Environ.
Prot. 88 (2010) 1–19. 7th Edition, 2001.
[4] A. Brandsæter, Risk assessment in the offshore industry, Saf. Sci. 40 (2002) [19] UKOOA, Ignition Probability Review and Model Development—Phase 2 Look-
231–269. Up Correlation Report Look-up Correlations, 2004.
[5] A. Falck, E. Skramstad, M. Berg, Use of QRA for decision support in the design [20] DNV, Offshore Reliability Data Handbook (OREDA), DNV, 2002.
of an offshore oil production installation, J. Hazardous Mater. 71 (1–3) (2000) [21] D.G. DiMattia, F.I. Khan, P.R. Amyotte, Determination of human error
179–192. probabilities for offshore platform musters, Journal of Loss Prevention in
[6] S. Lewis, An Overview of Leading Software Tools for QRA, in: Proceedings of the Process Industries 18 (2005) 488–501.
the 7th Professional Development Conference and Exhibition. March 18–22,
2005, Kingdom of Bahrain.

Anda mungkin juga menyukai