Protection Coordination
Phase Distance (21) and Voltage-Controlled or
Voltage-Restrained Overcurrent Protection (51V)
NERC Protection Coordination Webinar Series
June 16, 2010
Phil Tatro
Jon Gardell
Disclaimer
2
Other modifications:
• Achieve common usage of terms
• Remove discrepancies between and among Tables 2 and 3 and
the excerpts from these tables
• Correct some figures
• Correct formatting problems
Objective
9
87U
87T 51T
87G
50BF
R
24 27 59 81
59GN/ 51TG
27TH
21
21 32 40 46 50/27 51V
51V 78
System Events that Could Cause Undesired
Operation of These Protection Functions 14
Purpose
Coordination of Generator and Transmission System
• Faults
• Loadability
• Other Conditions, Where Applicable
Considerations and Issues
Coordination Procedure
• Test Procedure for Validation
• Setting Considerations
Examples
• Proper Coordination
• Improper Coordination
Summary of Detailed Data Required for Coordination of the Protection
Function
Table of Data and Information that Must be Exchanged
Purpose – Function 21
19
Faults
• The detection of a fault is most easily demonstrated
by an example.
• In the example, it is assumed that a transmission line
relay failure has occurred and the fault is at the far
end of the protected line.
• The example presents solutions that can be used to
permit tripping for the fault while not tripping for non-
fault conditions when the generator is not at risk.
Coordination of Generator and
Transmission System – Function 21 21
Loadability
• C37.102 presents a range from 150 percent to 200 percent of the
generator MVA rating at rated power factor as settings that will not
operate for normal generator outputs.
• This setting can be restated in terms of impedance as 0.66 – 0.50 per
unit on the machine base.
• This document addresses phase distance relay applications for which
the voltage regulator action could cause an incorrect trip based on a
fixed-field model basis.
To fully address dynamic effects during stressed system conditions, a
conservative load point(s) or a dynamic simulation(s) of the unit and
excitation system is required to properly assess the security of this
protection function.
The SPCS is developing two methods to assess and model these dynamic
effects.
Most exciters have a field forcing function that enables the exciter to go
beyond its full load output.
These outputs can last up to several seconds before controls reduce the
exciter field currents to rated output.
Assessing Generator Relay
Loadability – Method 1 (Under Development) 22
Relays for
this line fail
21
fault
60 Ω Zsys Bus B
Zsys Bus C
40 Ω 20 Ω
Example - Proper Coordination
– Function 21 28
[1] Calculation details are provided in Appendix E of the Technical Reference Document
Example - Proper Coordination
– Function 21 30
The plot shows that the desired reach cannot be achieved with a mho
characteristic.
In this example blinders are utilized to achieve the desired reach for
dependability and to coordinate with the loadability requirement for security.
2.0
1.0
Load
Point Rated Power Factor
0.5 Angle = 31.8º (0.85 pf)
Blinders Applied at
± 0.25 pu at 85º
Function 21 – Methods To
Increase Loadability 31
Zone 2 Blinders
Set at ± 0.4 pu
For System Trip Dependability
(relay failure coverage) Time Coordination Graph 35
Faults:
• Generator Owner(s) and Transmission Owner(s) need to exchange the following
data:
• Generator Owner
Unit ratings, subtransient, transient and synchronous reactance and time constants
Station one line diagrams
51V-C or 51V-R relay type, CT ratio, VT ratio, settings and settings criteria
Protection setting criteria
Coordination curves for faults in the transmission system two buses away from
generator high voltage bus
• Transmission Owner
Protection setting criteria
Fault study values of current and voltage for all multi-phase faults two buses away from
generator high voltage bus. This includes fault voltages at the high side of the
generator step-up transformer.
Relay types and operate times for multi-phase faults two buses away from generator
high voltage bus.
Voltages on the high-side of the generator step-up transformer for extreme system
contingencies. Use 0.75 per unit or power flow results for extreme system
contingencies.
Coordination of Generator and
Transmission System – Function 51V 41
Loadability
• For the 51V-C function:
The voltage supervision must prevent operation for all system loading
conditions as the overcurrent function will be set less than generator full load
current.
The voltage supervision setting should be calculated such that under
extreme emergency conditions (the lowest expected system voltage), the
51V function will not trip. A voltage setting of 0.75 per unit or less is
acceptable.
• For the 51V-R function:
The voltage supervision will not prevent operation for system loading
conditions.
The overcurrent functions must be set above generator full load current.
IEEE C37.102 recommends the overcurrent function to be set 150 percent
above full load current.
• Coordinate with stator thermal capability curve (IEEE C50.13).
• Note that 51V functions are subject to misoperation for blown fuses that
result in loss of the voltage-control or voltage-restraint.
Considerations and Issues – Function 51V
42
Setting Considerations
• For the 51V-C function, the voltage supervision must prevent
operation for all system loading conditions as the overcurrent
function will be set less than generator full load current. A
voltage setting of 0.75 per unit or less is acceptable.
• For the 51V-R function, the voltage supervision will not prevent
operation for system loading conditions. The overcurrent
function must be set above generator full load current. IEEE
C37.102 recommends the overcurrent function to be set 150
percent of full load current. (For some applications a higher
setting may be necessary.)
Example - Proper Coordination
– Function 51V 48
51V-R operating
curve with ≤ 25% For examples with
voltage (fastest 51V-R
operating time) range of 51V-R operating numeric values, see
curve with full
operation
from 100 voltage (slowest
Section 3.10.5 of the
to 25 %
voltage
operating time)
Technical Reference
Document
Time in Seconds
restraint
Phase OC on
Line - 51LINE 0.5 s or
more
margin
Fault Current
on Line
Current in Amperes
Summary of Protection Functions
Required for Coordination – Function 51V 49
Provide settings for pickup and time delay Times to operate, including timers, of
(may need to provide relay manual for transmission system protection None
proper interpretation of the voltage
controlled/restrained function) Breaker failure relaying times
What is Important to Coordination
51