PROGRAMA 4 WEEK LOOKAHEAD

OBRAS CONCRETO TÚNEL DE DESVÍO DEL RÍO ASANA


Fecha Corte: Friday, August 10, 2018
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Metrado Fechas AGOSTO AGOSTO AGOSTO AGOSTO
Total Total Total Actual SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 COMENTARIO
ITEM ITEM Descripción de la Actividad
Und Prev. Ejecut. Saldo Saldo Días Rend Inicio Fin S D L M X J V S D L M X J V S D L M X J V S D L M X J V
cant días 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07

T PERFORACIONES
PERF PERF FRENTE 2
PERF PERF PERFORACIONES - JUMBO
PERF PERF02 Perforación Estocada 23 und 75.00 50.00 25.00 25.0 1.0 30.0 13-Aug 13-Aug 0.0 0.0 25.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Perforación Estocada 22 und 75.00 - 75.00 75.0 3.0 30.0 15-Aug 17-Aug 0.0 0.0 0.0 0.0 30.0 30.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Depende del retiro del ventilador
PERF PERF FRENTE 3
PERF PERF PERFORACIONES - JUMBO
PERF PERF02 Perforación Estocada 26 und 75.00 50.00 25.00 25.0 1.0 30.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 25.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Depende del retiro del ventilador
PERF PERF01 FRENTE 1
PERF PERF01 PERFORACIONES - JUMBO -
PERF PERF01 Perforación Estocada 04 und 75.00 - 75.00 75.0 2.0 40.0 21-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 35.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
T RESANE DE MUROS Y JUNTAS
F02 F02 FRENTE 2 - ACABADO DE MUROS
F02 F02 Acabado de muros 3+875 @ 5+940 m 2,064.50 667.90 1,396.60 1,396.6 14.0 100.0 11-Aug 24-Aug 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 96.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 Juntas en muro 3+875 @ 5+940 und 287.00 - 287.00 287.0 36.0 8.0 15-Aug 19-Sep 0.0 0.0 0.0 0.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0
F01 F01 FRENTE 1 - ACABADO DE MUROS
F01 F01 Acabado de muros 3+875 @ 0+015 m 3,860.00 2,334.30 1,525.70 1,525.7 21.0 75.0 11-Aug 31-Aug 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 25.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 Juntas en muro 3+875 @ 0+015 und 537.00 - 537.00 537.0 45.0 12.0 13-Aug 26-Sep 0.0 0.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0
F03 F03 FRENTE 3 - ACABADO DE MUROS
F03 F03 Acabado de muros 7+591.65 - 5+940.00 m 1,652.10 738.00 914.10 914.1 27.0 35.0 20-Aug 15-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0
F03 F03 Juntas en muro 7+591.65 - 5+940.00 und 230.00 - 230.00 230.0 20.0 12.0 25-Aug 13-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0
T LOSA
F02 F02 FRENTE 2
F02 F02 Escarificado para muro intermedio m 2,024.50 742.70 1,281.80 1,281.8 15.0 86.0 11-Aug 25-Aug 86.0 86.0 86.0 86.0 86.0 86.0 86.0 86.0 86.0 86.0 86.0 86.0 86.0 86.0 77.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 Juntas losa und 281.00 - 281.00 281.0 10.0 29.0 26-Sep 5-Oct 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 FRENTE 1
F01 F01 Escarificado para muro intermedio m 3,860.00 1,378.00 2,482.00 2,482.0 21.0 120.0 11-Aug 31-Aug 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 120.0 82.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 Juntas losa und 537.00 - 537.00 537.0 11.0 49.0 25-Sep 5-Oct 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 FRENTE 3
F03 F03 Escarificado para muro intermedio m 1,652.15 - 1,652.15 1,652.2 10.0 170.0 1-Sep 10-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 170.0 170.0 170.0 170.0 170.0 170.0 170.0
F03 F03 Juntas losa und 230.00 - 230.00 230.0 23.0 10.0 30-Aug 21-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
T MURO INTERMEDIO
F02 F02 FRENTE 2
F02 F02 Colocación de acero 5+915 @ 3+875 m 2,024.50 - 2,024.50 2,024.5 9.0 250.0 31-Aug 8-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 250.0 250.0 250.0 250.0 250.0 250.0 250.0 250.0
F02 F02 Vaciado de concreto muro intermedio 5+915 @ 3+875 m 2,024.50 - 2,024.50 2,024.5 9.0 250.0 1-Sep 9-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 250.0 250.0 250.0 250.0 250.0 250.0 250.0
F01 F01 FRENTE 1
F01 F01 Colocación de acero 3+875 @ 0+015 m 3,860.00 - 3,860.00 3,860.0 16.0 250.0 9-Sep 24-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 Vaciado de concreto muro intermedio 3+875 @ 0+015 m 3,860.00 - 3,860.00 3,860.0 16.0 250.0 10-Sep 25-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 FRENTE 3
F03 F03 Colocación de acero 7+592 @ 5+760 m 1,652.15 - 1,652.15 1,652.2 9.0 200.0 15-Sep 23-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Vaciado de concreto muro intermedio 7+591.65 @ 5+760 m 1,652.15 - 1,652.15 1,652.2 9.0 200.0 16-Sep 24-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
T ESTOCADAS
F03 F03 FRENTE 3
F03 F03 29 Estocada 29 7+283 3.0 18-Aug 20-Aug
F03 F03 29 Encofrado Etapa 3 m2 24.00 - 24.00 24.0 1.0 24.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 24.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 29 Concreto Etapa 3 m3 6.00 - 6.00 6.0 1.0 6.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 6.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 29 Inyección glb 1.00 - 1.00 1.0 1.0 1.0 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 28 Estocada 28 7+000 9.0 11-Aug 19-Aug
F03 F03 28 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 11-Aug 11-Aug 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 28 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 2.0 24.0 12-Aug 13-Aug 0.0 24.0 24.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 28 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 14-Aug 14-Aug 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 28 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 28 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 15-Aug 15-Aug 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 28 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 28 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 17-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 28 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 28 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Estocada 27 6+750 13.0 12-Aug 24-Aug
F03 F03 27 Acero Etapa 1 ton 1.40 - 1.40 1.4 1.0 1.4 12-Aug 12-Aug 0.0 1.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 13-Aug 13-Aug 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 2.0 36.0 14-Aug 15-Aug 0.0 0.0 0.0 36.0 36.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 2.0 24.0 17-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 24.0 24.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PROGRAMA 4 WEEK LOOKAHEAD
OBRAS CONCRETO TÚNEL DE DESVÍO DEL RÍO ASANA
Fecha Corte: Friday, August 10, 2018
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Metrado Fechas AGOSTO AGOSTO AGOSTO AGOSTO
Total Total Total Actual SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 COMENTARIO
ITEM ITEM Descripción de la Actividad
Und Prev. Ejecut. Saldo Saldo Días Rend Inicio Fin S D L M X J V S D L M X J V S D L M X J V S D L M X J V
cant días 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07
F03 F03 27 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 27 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Estocada 26 6+534 (SSEE) 19.0 13-Aug 31-Aug
F03 F03 26 Colocación de cable de "Y" a SSEE Estocada 26 glb 1.00 - 1.00 1.0 2.0 0.5 13-Aug 14-Aug 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Retiro de Subestación Eléctrica glb 1.00 - 1.00 1.0 2.0 0.5 15-Aug 16-Aug 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 26 Pernos Estocada 26 und 75.00 45.00 30.00 30.0 2.0 15.0 17-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 15.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Acero Etapa 1 ton 1.40 - 1.40 1.4 2.0 0.7 19-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.7 0.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 1.0 72.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 72.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Desencofrado m2 72.00 - 72.00 72.0 1.0 72.0 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 72.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 1.0 48.0 25-Aug 25-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 26-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 27-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 27-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 29-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 30-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 26 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 31-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 25 Estocada 25 6+250, M108, M378 9 11-Aug 19-Aug
F03 F03 25 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 11-Aug 11-Aug 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 25 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 2.0 24.0 12-Aug 13-Aug 0.0 24.0 24.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 25 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 14-Aug 14-Aug 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 25 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 15-Aug 15-Aug 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 25 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 25 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 17-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 25 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 25 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 24 Estocada 24 6+000 (Volteo) 15.0 1-Sep 15-Sep
F03 F03 24 Acero Etapa 1 ton 1.40 - 1.40 1.4 2.0 0.7 1-Sep 2-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.7 0.7 0.0 0.0 0.0 0.0 0.0
F03 F03 24 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 3-Sep 3-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0
F03 F03 24 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 2.0 36.0 4-Sep 5-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 36.0 36.0 0.0 0.0
F03 F03 24 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 6-Sep 6-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0
F03 F03 24 Desencofrado m2 72.00 - 72.00 72.0 1.0 72.0 7-Sep 7-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 72.0
F03 F03 24 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 2.0 24.0 8-Sep 9-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 24 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 10-Sep 10-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 24 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 11-Sep 11-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 24 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 12-Sep 12-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 24 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 12-Sep 12-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 24 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 13-Sep 13-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 24 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 14-Sep 14-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 24 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 15-Sep 15-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 FRENTE 2 32.0 29-Aug 29-Sep
F02 F02 23 Estocada 23 5+770 13.0 13-Aug 25-Aug
PERF PERF02 23 Pernos Estocada 23 und 75.00 50.00 25.00 25.0 1.0 30.0 13-Aug 13-Aug 0.0 0.0 25.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Acero Etapa 1 ton 1.40 - 1.40 1.4 1.0 1.4 14-Aug 14-Aug 0.0 0.0 0.0 1.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 15-Aug 15-Aug 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 1.0 72.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 72.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 17-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Desencofrado m2 72.00 - 72.00 72.0 1.0 72.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 72.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 1.0 48.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 23 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 25-Aug 25-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Estocada 22 5+514 (Ventilador y caja de paso) 16.0 14-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Retiro de ventilador glb 1.00 - 1.00 1.0 2.0 0.5 14-Aug 15-Aug 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Requiere aprobación SSOMA
F02 F02 22 Retiro de caja de paso und 1.00 - 1.00 1.0 1.0 1.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 22 Pernos Estocada 22 und 60.00 - 60.00 60.0 2.0 30.0 17-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 30.0 30.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Acero Etapa 1 ton 1.40 - 1.40 1.4 1.0 1.4 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 1.0 72.0 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 72.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Desencofrado m2 72.00 - 72.00 72.0 1.0 72.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 72.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 1.0 48.0 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 25-Aug 25-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 26-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 27-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 27-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PROGRAMA 4 WEEK LOOKAHEAD
OBRAS CONCRETO TÚNEL DE DESVÍO DEL RÍO ASANA
Fecha Corte: Friday, August 10, 2018
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Metrado Fechas AGOSTO AGOSTO AGOSTO AGOSTO
Total Total Total Actual SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 COMENTARIO
ITEM ITEM Descripción de la Actividad
Und Prev. Ejecut. Saldo Saldo Días Rend Inicio Fin S D L M X J V S D L M X J V S D L M X J V S D L M X J V
cant días 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07
F02 F02 22 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 22 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 29-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 21 Estocada 21 5+250 11.0 11-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 21 Acero Etapa 2 ton 0.90 - 0.90 0.9 2.0 0.5 11-Aug 12-Aug 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 21 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 2.0 24.0 13-Aug 14-Aug 0.0 0.0 24.0 24.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 21 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 21 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 21 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 17-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 21 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 2.0 20.0 17-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 20.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 21 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 21 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 21 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Estocada 20 5+000 (SSEE) 17.0 15-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Retiro de subestación eléctrica glb 1.00 - 1.00 1.0 2.0 0.5 15-Aug 16-Aug 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Acero Etapa 1 ton 1.40 - 1.40 1.4 1.0 1.4 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 2.0 36.0 20-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 36.0 36.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Desencofrado m2 72.00 - 72.00 72.0 1.0 72.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 72.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 1.0 48.0 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 25-Aug 25-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 26-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 27-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 29-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 30-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 20 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 31-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 19 Estocada 19 4+757 8.0 16-Aug 23-Aug
F02 F02 19 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 1.0 48.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 19 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 17-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 19 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 19 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 19 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 19 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 19 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 19 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 18 Estocada 18 4+500 5.0 20-Aug 24-Aug
F02 F02 18 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 18 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 20.0 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 18 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 18 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 18 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Estocada 17 4+242.5 (SSEE) 32.0 29-Aug 29-Sep
F02 F02 17 Retiro de subestación eléctrica glb 1.00 - 1.00 1.0 2.0 0.5 29-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Acero Etapa 1 ton 1.40 - 1.40 1.4 2.0 1.4 10-Sep 11-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Acero Etapa 2 ton 0.90 - 0.90 0.9 2.0 0.9 12-Sep 13-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 4.0 36.0 14-Sep 17-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 18-Sep 18-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 2.0 48.0 19-Sep 20-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 21-Sep 21-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Acero Etapa 3 ton 0.60 - 0.60 0.6 2.0 0.3 22-Sep 23-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 3.0 13.3 24-Sep 26-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 27-Sep 27-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 28-Sep 28-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 17 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 29-Sep 29-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 FRENTE 1 56.0 11-Aug 5-Oct
F01 F01 10 Estocada 10 2+582 (SSEE) 16.0 20-Aug 4-Sep
F01 F01 10 Retiro de subestación eléctrica glb 1.00 - 1.00 1.0 3.0 0.3 20-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.3 0.3 0.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Acero Etapa 1 ton 1.40 - 1.40 1.4 2.0 0.7 23-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.7 0.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 25-Aug 25-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 2.0 36.0 25-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 36.0 36.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 27-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Desencofrado m2 72.00 - 72.00 72.0 1.0 72.0 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 72.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 1.0 48.0 29-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 30-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 31-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 31-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 1-Sep 1-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 2-Sep 2-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0
F01 F01 10 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 3-Sep 3-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0
F01 F01 10 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 4-Sep 4-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0
F01 F01 8 Estocada 08 2+004 (SSEE) 16.0 17-Aug 1-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 Retiro de subestación eléctrica glb 1.00 - 1.00 1.0 3.0 0.3 17-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.3 0.3 0.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Acero Etapa 1 ton 1.40 - 1.40 1.4 1.0 1.4 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PROGRAMA 4 WEEK LOOKAHEAD
OBRAS CONCRETO TÚNEL DE DESVÍO DEL RÍO ASANA
Fecha Corte: Friday, August 10, 2018
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Metrado Fechas AGOSTO AGOSTO AGOSTO AGOSTO
Total Total Total Actual SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 COMENTARIO
ITEM ITEM Descripción de la Actividad
Und Prev. Ejecut. Saldo Saldo Días Rend Inicio Fin S D L M X J V S D L M X J V S D L M X J V S D L M X J V
cant días 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07
F01 F01 8 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 2.0 36.0 22-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 36.0 36.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Desencofrado m2 72.00 - 72.00 72.0 1.0 72.0 25-Aug 25-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 72.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 1.0 48.0 26-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 27-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 29-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 30-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 31-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 8 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 1-Sep 1-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Estocada 07 1+784 11.0 25-Sep 5-Oct 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Acero Etapa 1 ton 1.40 - 1.40 1.4 1.0 1.4 25-Sep 25-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 26-Sep 26-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 1.0 72.0 26-Sep 26-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 27-Sep 27-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Desencofrado m2 72.00 - 72.00 72.0 1.0 72.0 28-Sep 28-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 1.0 48.0 29-Sep 29-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 30-Sep 30-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 1-Oct 1-Oct 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 1-Oct 1-Oct 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 2-Oct 2-Oct 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 3-Oct 3-Oct 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 4-Oct 4-Oct 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 7 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 5-Oct 5-Oct 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 6 Estocada 06 1+556 7.0 25-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 6 Sostenimiento (shotcrete) Glb 1.00 - 1.00 1.0 2.0 0.5 25-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 6 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 27-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 6 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 6 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 29-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 6 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 30-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 6 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 31-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 5 Estocada 05 1+251 1.0 7.0 11-Aug 17-Aug
F01 F01 5 Acero Etapa 3 ton 0.60 - 0.60 0.6 2.0 0.3 11-Aug 12-Aug 0.3 0.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 5 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 2.0 20.0 13-Aug 14-Aug 0.0 0.0 20.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 5 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 5 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 5 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 17-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Estocada 04 1+000 (SSEE) 18.0 18-Aug 4-Sep
PERF PERF01 4 Pernos Estocada 04 und 75.00 - 75.00 75.0 2.0 30.0 21-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 30.0 30.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Retiro de subestación eléctrica glb 1.00 - 1.00 1.0 3.0 0.3 18-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.3 0.3 0.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Sostenimiento (shotcrete) glb 1.00 1.00 1.0 2.0 0.5 21-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Acero Etapa 1 ton 1.40 - 1.40 1.4 1.0 1.4 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Acero Etapa 2 ton 0.90 - 0.90 0.9 1.0 0.9 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Encofrado Etapa 1 m2 72.00 - 72.00 72.0 2.0 36.0 25-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 36.0 36.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Concreto Etapa 1 m3 20.00 - 20.00 20.0 1.0 20.0 27-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Desencofrado m2 72.00 - 72.00 72.0 1.0 72.0 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 72.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Encofrado Etapa 2 m2 48.00 - 48.00 48.0 1.0 48.0 29-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Concreto Etapa 2 m3 15.00 - 15.00 15.0 1.0 15.0 30-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 31-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 31-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 1-Sep 1-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 2-Sep 2-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0
F01 F01 4 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 3-Sep 3-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0
F01 F01 4 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 4-Sep 4-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0
F01 F01 3 Estocada 03 0+739 8.0 11-Aug 18-Aug
F01 F01 3 Encofrado Etapa 1 y 2 m2 120.00 - 120.00 120.0 2.0 60.0 11-Aug 12-Aug 60.0 60.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 3 Concreto Etapa 1 y 2 m3 35.00 - 35.00 35.0 1.0 35.0 13-Aug 13-Aug 0.0 0.0 35.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 3 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 14-Aug 14-Aug 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 3 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 14-Aug 14-Aug 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 3 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 3 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 3 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 17-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 3 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 2 Estocada 02 0+533 10.0 11-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 2 Acero Etapa 1 y 2 ton 3.00 - 3.00 3.0 1.0 3.0 11-Aug 11-Aug 3.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 2 Encofrado Etapa 1 y 2 m2 120.00 - 120.00 120.0 2.0 60.0 12-Aug 13-Aug 0.0 60.0 60.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 2 Concreto Etapa 1 y 2 m3 35.00 - 35.00 35.0 1.0 35.0 14-Aug 14-Aug 0.0 0.0 0.0 35.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 2 Desencofrado m2 48.00 - 48.00 48.0 1.0 48.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 48.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 2 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 2 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 17-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 2 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 2 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PROGRAMA 4 WEEK LOOKAHEAD
OBRAS CONCRETO TÚNEL DE DESVÍO DEL RÍO ASANA
Fecha Corte: Friday, August 10, 2018
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Metrado Fechas AGOSTO AGOSTO AGOSTO AGOSTO
Total Total Total Actual SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 COMENTARIO
ITEM ITEM Descripción de la Actividad
Und Prev. Ejecut. Saldo Saldo Días Rend Inicio Fin S D L M X J V S D L M X J V S D L M X J V S D L M X J V
cant días 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07
F01 F01 2 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 1 Estocada 01 0+250 5.0 19-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 1 Acero Etapa 3 ton 0.60 - 0.60 0.6 1.0 0.6 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 1 Encofrado Etapa 3 m2 40.00 - 40.00 40.0 1.0 40.0 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 1 Concreto Etapa 3 m3 10.00 - 10.00 10.0 1.0 10.0 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 1 Desencofrado m2 40.00 - 40.00 40.0 1.0 40.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 F01 1 Inyeccion glb 1.00 - 1.00 1.0 1.0 1.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
T T TÚNEL SECUNDARIO 20.0 24-Aug 12-Sep
F01 GEO Perforación e inyecciones Túnel Secundario glb 1.00 - 1.00 1.0 20.0 0.1 24-Aug 12-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
T T SISTEMA DE DRENAJE 59.0 11-Aug 8-Oct
F02 F02 FRENTE 2 47.0 11-Aug 26-Sep
F02 F02 INSTALACIÒN DE TUBERÌA PVC DE 6" EN MUROS 47.0 11-Aug 26-Sep
F02 F02 Perforación para colocación de tuberías 3+875 @ 5+940 m 2,064.00 655.20 1,408.80 1,408.8 21.0 68.0 11-Aug 31-Aug 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 68.0 48.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 Tuberías de drenaje 3+458 @ 5+940 ( lado derecho) m 2,064.00 - 2,064.00 2,064.0 42.0 50.0 16-Aug 26-Sep 0.0 0.0 0.0 0.0 0.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0
F02 F02 Tuberías de drenaje 3+458 @ 5+940 ( lado izquierdo) m 2,064.00 - 2,064.00 2,064.0 21.0 100.0 5-Sep 25-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 100.0 100.0 100.0
PERF PERF02 SELLO DE BARBACANAS
PERF PERF02 Sello de barbacanas Pk 4+353@4+374 (21 m) m 21.00 - 21.00 21.0 1.0 40.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 21.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Sello de barbacanas Pk 4+447@4+465 (18 m) m 18.00 - 18.00 18.0 1.0 40.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 18.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Sello de barbacanas Pk 4+491@4+503 (9 m) m 9.00 - 9.00 9.0 1.0 40.0 17-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.0 9.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Sello de barbacanas Pk 4+578@4+617 (39 m) m 39.00 - 39.00 39.0 1.0 40.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 39.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Sello de barbacanas Pk 4+657@4+684 (27 m) m 27.00 - 27.00 27.0 1.0 40.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 27.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Sello de barbacanas Pk 4+810@4+939 (129 m) m 129.00 - 129.00 129.0 3.0 45.0 20-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 45.0 45.0 39.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 PERF02 INSTALACIÓN DE TUBERÍA DE 2" BOVEDA 1.0
F02 PERF02 Instalación de tubería de drenaje Pk 4+353@4+374 (21 m) und 7.00 - 7.00 7.0 3.0 2.5 16-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 2.5 2.5 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 PERF02 Instalación de tubería de drenaje Pk 4+447@4+465 (18 m) und 6.00 - 6.00 6.0 3.0 2.5 19-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.5 2.5 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 PERF02 Instalación de tubería de drenaje Pk 4+491@4+503 (9 m) und 3.00 - 3.00 3.0 2.0 2.5 22-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 PERF02 Instalación de tubería de drenaje Pk 4+578@4+617 (39 m) und 13.00 - 13.00 13.0 6.0 2.5 24-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.5 2.5 2.5 2.5 2.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 PERF02 Instalación de tubería de drenaje Pk 4+657@4+684 (27 m) und 9.00 - 9.00 9.0 4.0 2.5 30-Aug 2-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.5 2.5 2.5 1.5 0.0 0.0 0.0 0.0 0.0
F02 PERF02 Instalación de tubería de drenaje Pk 4+810@4+939 (129 m) und 43.00 - 43.00 43.0 18.0 2.5 3-Sep 20-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.5 2.5 2.5 2.5 2.5
F01 F01 FRENTE 1 59.0 11-Aug 8-Oct
F01 F01 INSTALACIÒN DE TUBERÌA DE 6" PVC EN MUROS m 59.0 11-Aug 8-Oct
F01 F01 Perforación para tubería de drenaje 3+429.3 @ 0+015 m 3,860.00 1,039.60 2,820.40 2,820.4 51.0 56.0 11-Aug 30-Sep 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0 56.0
F01 F01 Colocación de Tuberías de drenaje 3+429.3 @ 0+015 (lado derecho) m 3,860.00 - 3,860.00 3,860.0 26.0 150.0 20-Aug 14-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0
F01 F01 Colocación de Tuberías de drenaje 3+429.3 @ 0+015 (lado izquierdo m 3,860.00 - 3,860.00 3,860.0 23.0 170.0 16-Sep 8-Oct 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F01 PERF INSTALACIÓN DE TUBERÍA DE 2" BOVEDA m 24.0 20-Aug 12-Sep
PERF PERF01 Instalación de tubería de drenaje Pk 3+380 @ 3+447 (67 m) und 24.00 - 24.00 24.0 12.0 2.0 20-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF01 Instalación de tubería de drenaje Pk 1+427@1+377 (50 m) und 17.00 - 17.00 17.0 9.0 2.0 1-Sep 9-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0
PERF PERF01 Instalación de tubería de drenaje Pk 0+882@0+867 (15 m) und 5.00 - 5.00 5.0 3.0 2.0 10-Sep 12-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 FRENTE 3 24.0 28-Aug 20-Sep
F03 F03 INSTALACIÓN DE TUBERÍA PVC DE 6" EN MUROS 6.00 24.0 28-Aug 20-Sep
F03 F03 Perforación para colocación de tuberías 7+591.65 @ 5+939.6 m 1,652.10 1,173.60 478.50 478.5 10.0 48.0 1-Sep 10-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 48.0 48.0 48.0 48.0 48.0 48.0 48.0
F03 F03 Tuberías de drenaje 7+591.65 @ 5+939.6 (lado derecho) m 1,652.10 - 1,652.10 1,652.1 24.0 70.0 28-Aug 20-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0
F03 F03 Tuberías de drenaje 7+591.65 @ 5+939.6 ( lado izquierdo) m 1,652.10 - 1,652.10 1,652.1 24.0 70.0 28-Aug 20-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0 70.0
F03 PERF02 SELLO DE BARBACANAS 1.0
PERF PERF02 Sello de barbacanas Pk 7+546@7+507 (39 m) m 39.00 - 39.00 39.0 1.0 40.0 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 39.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Sello de barbacanas Pk 7+173@7+155 (18 m) m 18.00 - 18.00 18.0 1.0 40.0 29-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 18.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Sello de barbacanas Pk 6+598@6+520 (78 m) m 78.00 - 78.00 78.0 2.0 40.0 30-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 38.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Sello de barbacanas Pk 6+524@6+437 (87 m) m 87.00 - 87.00 87.0 3.0 40.0 1-Sep 3-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 40.0 7.0 0.0 0.0 0.0 0.0
PERF PERF02 Sello de barbacanas Pk 6+443@6+401 (42 m) m 42.00 - 42.00 42.0 2.0 40.0 4-Sep 5-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 2.0 0.0 0.0
PERF PERF02 Sello de barbacanas Pk 6+394@6+382 (12 m) m 12.00 - 12.00 12.0 1.0 40.0 6-Sep 6-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 12.0 0.0
F03 PERF INSTALACIÓN DE TUBERÍA DE 2" BOVEDA 1.0
F03 PERF02 Instalación de tubería de drenaje Pk 7+546@7+507 (39 m) m 13.00 - 13.00 13.0 4.0 4.0 28-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 4.0 4.0 4.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 PERF02 Instalación de tubería de drenaje Pk 7+173@7+155 (18 m) m 6.00 - 6.00 6.0 2.0 4.0 1-Sep 2-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 4.0 2.0 0.0 0.0 0.0 0.0 0.0
F03 PERF02 Instalación de tubería de drenaje Pk 6+598@6+520 (78 m) m 26.00 - 26.00 26.0 7.0 4.0 3-Sep 9-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 4.0 4.0 4.0 4.0 4.0
F03 PERF02 Instalación de tubería de drenaje Pk 6+524@6+437 (87 m) m 29.00 - 29.00 29.0 8.0 4.0 10-Sep 17-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 PERF02 Instalación de tubería de drenaje Pk 6+443@6+401 (42 m) m 14.00 - 14.00 14.0 4.0 4.0 18-Sep 21-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 PERF02 Instalación de tubería de drenaje Pk 6+394@6+382 (12 m) m 4.00 - 4.00 4.0 1.0 4.0 22-Sep 22-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
T T INTERFERENCIAS - PLANCHAS METÁLICAS 23.0 12-Aug 3-Sep
INTERF F02 FRENTE 2 15-Aug 15-Aug
INTERF F02 PROGRESIVA 3+875 a 3+915 (40 m) 15-Aug
INTERF F02 Vaciado de concreto m 40.00 - 40.00 40.0 1.0 50.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F02 PROGRESIVA 4+661 a 4+690 (Ambos lados) 1.0 15-Aug 15-Aug
INTERF F02 Vaciado de concreto m 30.00 - 30.00 30.0 1.0 30.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 30.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 FRENTE 3 23.0 12-Aug 3-Sep
INTERF F03 PROGRESIVA PK 7+228.35 @ 7+213.95 (Hastial izquierdo) 12.0 12-Aug 23-Aug
INTERF F03 Instalación de perfiles en piso m 14.40 - 14.40 14.4 2.0 8.0 12-Aug 13-Aug 0.0 8.0 6.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Colocación de planchas en pared (inc apuntalamiento) und 10.00 - 10.00 10.0 3.0 4.0 14-Aug 16-Aug 0.0 0.0 0.0 4.0 4.0 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Soldadura tapón pared und 43.00 - 43.00 43.0 2.0 25.0 17-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 25.0 18.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Soldadura filete en conexión muro concreto - muro acero m 15.00 - 15.00 15.0 2.0 8.0 19-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 8.0 7.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Arriostramiento de planchas de pared (temporales) und 14.00 - 14.00 14.0 1.0 15.0 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 14.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Vaciado de concreto m3 30.00 - 30.00 30.0 1.0 30.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 30.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Esmerilado y limpieza de planchas de muro m 14.00 - 14.00 14.0 1.0 30.0 25-Aug 25-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 14.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Touch Up paredes m 14.00 - 14.00 14.0 2.0 7.0 26-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 7.0 7.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 PROGRESIVA PK 6+832 @ 6+768 (Hastial izquierdo) 21.0 14-Aug 3-Sep
INTERF F03 Instalación de perfiles en piso m 64.00 - 64.00 64.0 3.0 24.0 14-Aug 16-Aug 0.0 0.0 0.0 24.0 24.0 16.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PROGRAMA 4 WEEK LOOKAHEAD
OBRAS CONCRETO TÚNEL DE DESVÍO DEL RÍO ASANA
Fecha Corte: Friday, August 10, 2018
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Metrado Fechas AGOSTO AGOSTO AGOSTO AGOSTO
Total Total Total Actual SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 COMENTARIO
ITEM ITEM Descripción de la Actividad
Und Prev. Ejecut. Saldo Saldo Días Rend Inicio Fin S D L M X J V S D L M X J V S D L M X J V S D L M X J V
cant días 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07
INTERF F03 Colocación de planchas en pared (inc apuntalamiento) und 45.00 - 45.00 45.0 5.0 9.0 19-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 9.0 9.0 9.0 9.0 9.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Soldadura tapón pared und 180.00 - 180.00 180.0 4.0 50.0 24-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 50.0 50.0 50.0 30.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Soldadura filete en conexión muro concreto - muro acero m 5.00 - 5.00 5.0 3.0 2.0 28-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.0 2.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Arriostramiento de planchas de pared (temporales) und 45.00 - 45.00 45.0 3.0 15.0 31-Aug 2-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0 15.0 15.0 0.0 0.0 0.0 0.0 0.0
INTERF F03 Vaciado de concreto m3 30.00 - 30.00 30.0 1.0 30.0 3-Sep 3-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 30.0 0.0 0.0 0.0 0.0
INTERF F03 Esmerilado y limpieza de planchas de muro m 50.00 - 50.00 50.0 2.0 30.0 5-Sep 6-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 30.0 20.0 0.0
INTERF F03 Touch Up paredes m 50.00 - 50.00 50.0 4.0 15.0 7-Sep 10-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0
INTERF F01 FRENTE 1 31.0 4-Aug 3-Sep
INTERF F01 PROGRESIVA PK 0+467 @ 0+463 (Hastial Izquierdo y Derecho) 20.0 12-Aug 31-Aug
INTERF F01 Instalación de varillas lisa en hastiales und 28.80 - 28.80 28.8 1.0 28.8 12-Aug 13-Aug 0.0 28.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Armado de módulo LAYHER und 1.00 - 1.00 1.0 1.0 1.0 13-Aug 13-Aug 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Colocación y apuntalamiento de perfiles T en hastial (x6m) und 8.00 - 8.00 8.0 1.0 8.0 14-Aug 14-Aug 0.0 0.0 0.0 8.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Soldadura de perfiles T con varilla lisa und 8.00 - 8.00 8.0 1.0 8.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 8.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Instalación de perfiles en piso m 14.40 - 14.40 14.4 1.0 14.4 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 14.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Colocación de planchas en pared (inc apuntalamiento) und 10.00 - 10.00 10.0 3.0 4.0 17-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 4.0 4.0 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Soldadura tapón pared und 43.00 - 43.00 43.0 3.0 20.0 20-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 20.0 3.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Soldadura filete en conexión muro concreto - muro acero m 15.00 - 15.00 15.0 1.0 16.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Arriostramiento de planchas de pared (temporales) und 8.00 - 8.00 8.0 1.0 15.0 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 8.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Vaciado de concreto m3 16.00 - 16.00 16.0 1.0 20.0 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 16.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Curado y desencofrado m 7.20 - 7.20 7.2 1.0 15.0 29-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 7.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Esmerilado y limpieza de planchas de muro m 7.20 - 7.20 7.2 1.0 15.0 30-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 7.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INTERF F01 Touch Up paredes m 7.20 - 7.20 7.2 1.0 15.0 31-Aug 31-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 7.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0
T T INTERFERENCIAS - PICADO EN ZONA 2 31.0 4-Aug 3-Sep
F02 F02 FRENTE 2 24.0 4-Aug 27-Aug
F02 F02 PICADO DE HASTIALES EN ZONA 02 6.0 4-Aug 9-Aug
F02 F02 Picado en zona 2 entre 4+690 @ 4+692 m 2.00 - 2.00 2.0 2.0 1.5 4-Aug 5-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 Picado en zona 2 entre 4+696 @ 4+698 m 2.00 - 2.00 2.0 2.0 1.5 6-Aug 7-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 Picado en zona 2 entre 4+701 @ 4+704 m 3.00 - 3.00 3.0 2.0 1.5 8-Aug 9-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F02 F02 SHOTCRETE 4.0 24-Aug 27-Aug
PERF F02 Shotcrete en zona 2 (picado de hastiales) m 21.00 - 21.00 21.0 4.0 6.0 24-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 6.0 6.0 6.0 3.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 FRENTE 3 28.0 7-Aug 3-Sep
F03 F03 PICADO DE HASTIALES EN ZONA 02 6.0 7-Aug 12-Aug
F03 F03 Picado en zona 2 entre 6+801 @ 6+792 m 9.00 - 9.00 9.0 2.0 5.0 7-Aug 8-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Picado en zona 2 entre 6+408 @ 6+396 m 12.00 - 12.00 12.0 3.0 5.0 9-Aug 11-Aug 5.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Picado en zona 2 entre 6+353 @ 6+348 m 5.00 - 5.00 5.0 1.0 5.0 12-Aug 12-Aug 0.0 5.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 SHOTCRETE 3.0 1-Sep 3-Sep
PERF F03 Shotcrete en zona 2 (picado de hastiales) m 30.00 - 30.00 30.0 3.0 10.0 1-Sep 3-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 10.0 10.0 0.0 0.0 0.0 0.0
T T TÚNEL DESVÍO VENTANA 25.0 23-Aug 16-Sep
F02 GEO Perforaciones e inyecciones Túnel Ventana glb 1.00 - 1.00 1.0 25.0 0.04 23-Aug 16-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
T T PORTAL DE SALIDA 17.0 12-Aug 28-Aug
F03 F03 OBRAS CIVILES - 9.0 12-Aug 20-Aug
F03 F03 LOSA DE PISO EN ZONA PS3-PS2 - 6.0 12-Aug 17-Aug
F03 F03 Instalación de anclajes und 21.00 - 21.00 21.0 1.0 21.0 12-Aug 12-Aug 0.0 21.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Acero de refuerzo ton 2.00 - 2.00 2.0 1.0 2.0 13-Aug 13-Aug 0.0 0.0 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Concreto m3 2.00 - 2.00 2.0 1.0 2.0 14-Aug 14-Aug 0.0 0.0 0.0 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Fraguado de losa día 3.00 - 3.00 3.0 3.0 1.0 15-Aug 17-Aug 0.0 0.0 0.0 0.0 1.0 1.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 MURO LATERAL PAÑO 1055 - 3.0 18-Aug 20-Aug
F03 F03 Acero de refuerzo m 7.20 - 7.20 7.2 1.0 1.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Encofrado m 7.20 - 7.20 7.2 1.0 1.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Concreto m 7.20 - 7.20 7.2 1.0 7.2 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 7.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 MURO DE CANAL - 7.0 22-Aug 28-Aug
F03 F03 Acero de refuerzo ton 0.50 - 0.50 0.5 1.0 1.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Instalación de planchas laterales glb 1.00 - 1.00 1.0 3.0 0.3 22-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.3 0.3 0.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Encofrado m2 18.00 - 18.00 18.0 2.0 9.0 24-Aug 25-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 9.0 9.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Concreto m3 5.40 - 5.40 5.4 1.0 5.4 26-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Desencofrado m2 18.00 - 18.00 18.0 1.0 18.0 27-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 18.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 F03 Instalación de tapa metálica glb 1.00 - 1.00 1.0 1.0 2.5 28-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
T T SISTEMA DE IMPULSIÓN 64.0 28-Jul 29-Sep
PERF F03 PERFORACIÓN DE ALCAYATAS 16.0 28-Jul 12-Aug
PERF F03 Perforación de taladros para soporte de tubería und 763.00 296.00 467.00 467.0 16.0 30.0 28-Jul 12-Aug 30.0 30.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF F03 Perforación de taladros para soporte de tubería en túnel ventana und 244.00 - 244.00 244.0 9.0 30.0 20-Aug 28-Aug
F03 TUBERÍA HDPE 6" (HASTA 5+940) 15.0 12-Aug 26-Aug
F03 Instalación de soportes hasta PK 5+940 und 519.00 280.00 239.00 239.0 12.0 20.0 15-Aug 26-Aug 0.0 0.0 0.0 0.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 19.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Traslado de tubería a interior de túnel und 276.00 - 276.00 276.0 7.0 40.0 12-Aug 18-Aug 0.0 40.0 40.0 40.0 40.0 40.0 40.0 36.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Termofusión de tubería HDPE D=6'' T1(250 m) pega 45.00 - 45.00 45.0 4.0 14.0 15-Aug 18-Aug 0.0 0.0 0.0 0.0 14.0 14.0 14.0 3.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Termofusión de tubería HDPE D=6'' T2 (570 m) pega 100.00 100.00 100.0 8.0 14.0 20-Aug 27-Aug
F03 Termofusión de tubería HDPE D=6'' T3 (820 m) pega 140.00 140.00 140.0 10.0 14.0 29-Aug 7-Sep
F03 Pruebas hidrostáticas ( 1,656 m) Gbl 1.00 1.00 1.0 3.0 0.4 8-Sep 10-Sep
F03 Montaje de tubería HDPE D=6'' (1,656 m) m 1,656.00 1,656.00 1,656.0 9.0 200.0 4-Sep 12-Sep
F03 TUBERÍA HDPE 6" (VENTANA) - 27.0 27-Aug 22-Sep
F03 Instalación de soportes en túnel ventana und 244.00 - 244.00 244.0 25.0 10.0 27-Aug 20-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
F03 Traslado de tubería a interior de túnel und 120.00 - 120.00 120.0 3.0 40.0 8-Sep 10-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Termofusión de tubería HDPE D=6'' (715 m) m 116.00 - 116.00 116.0 12.0 10.0 11-Sep 22-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Pruebas hidrostáticas T4 (715 m) Glb 1.00 1.00 1.0 3.0 0.4 23-Sep 25-Sep
PROGRAMA 4 WEEK LOOKAHEAD
OBRAS CONCRETO TÚNEL DE DESVÍO DEL RÍO ASANA
Fecha Corte: Friday, August 10, 2018
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Metrado Fechas AGOSTO AGOSTO AGOSTO AGOSTO
Total Total Total Actual SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 COMENTARIO
ITEM ITEM Descripción de la Actividad
Und Prev. Ejecut. Saldo Saldo Días Rend Inicio Fin S D L M X J V S D L M X J V S D L M X J V S D L M X J V
cant días 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07
F03 Montaje de tubería HDPE D=6'' (715 m) m 715.00 715.00 715.0 4.0 200.0 26-Sep 29-Sep
F03 MONTAJE DE EQUIPOS (BOMBA) 3.0 18-Aug 20-Aug
F03 Traslado de bomba de ventana a portal de salida und 1.00 - 1.00 1.0 1.0 1.0 18-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Montaje de bomba sumergible und 1.00 - 1.00 1.0 1.0 1.0 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 MONTAJE DE ESTRUCTURAS (PLATAFORMA) 21.0 1-Sep 21-Sep
F03 Suministro de estructuras para cámara de impulsión und 1.00 - 1.00 1.0 1.0 1.0 1-Sep 1-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 Penidente definir ingeniería
F03 Montaje de estructuras en cámara de impulsión glb 1.00 - 1.00 1.0 10.0 0.1 2-Sep 11-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.1 0.1 0.1 0.1 0.1 0.1
F03 Instalación de tubería acero (inc soportes) glb 1.00 - 1.00 1.0 5.0 0.2 12-Sep 16-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Montaje de tableros, glb 1.00 - 1.00 1.0 2.0 0.5 20-Sep 21-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Canalización eléctrica en plataforma de cámara de impulsión glb 1.00 - 1.00 1.0 5.0 0.2 17-Sep 21-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 PLATAFORMA DE GENERADORES 21.0 15-Aug 4-Sep
F03 MOVIMIENTO DE TIERRAS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Plataformado de área glb 1.00 - 1.00 1.0 5.0 0.2 15-Aug 19-Aug 0.0 0.0 0.0 0.0 0.2 0.2 0.2 0.2 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 SISTEMA ELÉCTRICO - MALLA A TIERRA 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Excavación para banco de ductos glb 1.00 - 1.00 1.0 2.0 0.5 20-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Instalación de tubería m 50.00 - 50.00 50.0 1.0 50.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 50.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Vaciado de concreto m 20.00 - 20.00 20.0 1.0 20.0 23-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Relleno m 20.00 - 20.00 20.0 1.0 20.0 26-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Instalación de pozos a tierra und 5.00 - 5.00 5.0 2.0 2.5 27-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.5 2.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Excavación para malla a tierra m 80.00 - 80.00 80.0 2.0 40.0 29-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0 40.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Instalación de cable desnudo (inc soldadura exotérmica) m 80.00 - 80.00 80.0 4.0 20.0 31-Aug 3-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 20.0 20.0 20.0 0.0 0.0 0.0 0.0
F03 Relleno glb 1.00 - 1.00 1.0 1.0 1.0 4-Sep 4-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0
F03 OBRAS CIVILES 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Vaciado de solado m3 4.00 - 4.00 4.0 1.0 4.0 5-Sep 5-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 4.0 0.0 0.0
F03 Colocación de acero ton 1.50 - 1.50 1.5 1.0 1.5 6-Sep 6-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.5 0.0
F03 Encofrado m2 40.00 - 40.00 40.0 1.0 40.0 7-Sep 7-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 40.0
F03 Concreto losa de piso m3 13.00 - 13.00 13.0 1.0 13.0 8-Sep 8-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 OBRAS MECANICAS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
F03 Montaje de Generadores und 2.00 - 2.00 2.0 2.0 1.0 9-Sep 10-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
T T SISTEMA DE VENTILACIÓN
VENT F01 PORTAL DE ENTRADA
VENT F01 OBRAS CONCRETO PORTAL
VENT F01 MURO
VENT F01 Colocación de acero lado izquierdo ton 1.50 1.50 1.5 2.0 1.0 12-Aug 13-Aug 0.0 1.0 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 Encofrado de muros lado izquierdo m2 40.00 40.00 40.0 2.0 30.0 14-Aug 15-Aug 0.0 0.0 0.0 30.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 Vaciado de concreto en muros lado izquierdo m3 10.00 10.00 10.0 1.0 25.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 Colocación de acero lado derecho ton 1.50 1.50 1.5 1.0 2.0 14-Aug 14-Aug 0.0 0.0 0.0 1.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 Encofrado de muros lado derecho m2 40.00 40.00 40.0 2.0 30.0 16-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 30.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 Vaciado de concreto en muros lado derecho m3 10.00 10.00 10.0 1.0 25.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 CÁMARA
VENT F01 Colocación de acero ton 3.30 3.30 3.3 1.0 3.3 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 3.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 Encofrado de muros m2 30.00 30.00 30.0 1.0 30.0 25-Aug 25-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 30.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 Vaciado de cámara 1ra etapa m3 22.00 22.00 22.0 1.0 25.0 26-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 22.0 0.0 0.0 0.0 0.0 0.0
VENT F01 MOVIMIENTO DE TIERRAS
VENT F01 Relleno con concreto lado izquierdo m3 150.00 - 150.00 150.0 1.0 150.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 150.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 Relleno con arena lado izquierdo m3 50.00 - 50.00 50.0 2.0 30.0 20-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 30.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 Relleno con concreto lado derecho m3 150.00 - 150.00 150.0 1.0 150.0 24-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 150.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 Relleno con arena lado derecho m3 50.00 - 50.00 50.0 2.0 30.0 25-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 30.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
VENT F01 TUBERÍA DE VENTILACIÓN
VENT F01 Montaje de tubería ml 20.00 - 20.00 20.0 2.0 10.0 22-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 10.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
T T INSTRUMENTACIÓN 12.0 11-Aug 22-Aug
INST INST PERFORACIÓN DE EM07 y 10 (CELDAS HI) 1.0 11-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST GEO Traslado de Equipos a Celda HI 10 Pk 5+500 Glb 1.00 0.75 0.25 0.3 2.0 0.2 11-Aug 12-Aug 0.2 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST GEO Celda HI 10 Pk 5+500 und 1.00 - 1.00 1.0 3.0 0.4 13-Aug 15-Aug 0.0 0.0 0.4 0.4 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST GEO Traslado de Celda HI 07 Pk 3+250 Glb 1.00 - 1.00 1.0 2.0 0.5 16-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST GEO Celda HI 07 Pk 3+250 und 1.00 - 1.00 1.0 3.0 0.4 18-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.4 0.4 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST GEO Traslado de equipo a túnel secundario Glb 1.00 - 1.00 1.0 2.0 0.5 21-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF INST INSTALACIÓN CELDAS DE CARGA 7.0 12-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Instalación de perno EM 07 Pk 3+250 und 1.00 - 1.00 1.0 1.0 1.0 12-Aug 12-Aug 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Instalación de perno EM 14 Pk 3+443 und 1.00 - 1.00 1.0 1.0 1.0 13-Aug 13-Aug 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Instalación de perno EM 13 Pk 3+900 und 1.00 - 1.00 1.0 1.0 1.0 14-Aug 14-Aug 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Instalación de perno EM 08 Pk 4+027 und 1.00 - 1.00 1.0 1.0 1.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Instalación de perno EM 09 Pk 4+720 und 1.00 - 1.00 1.0 1.0 1.0 16-Aug 16-Aug 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Instalación de perno EM 10 Pk 5+500 und 1.00 - 1.00 1.0 1.0 1.0 17-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PERF PERF02 Instalación de perno EM 12 Pk 7+220 und 1.00 - 1.00 1.0 1.0 1.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
T T CASETA DE MONITOREO 25.0 15-Aug 8-Sep
INST INST CASETA DE MONITOREO (PORTAL DE INGRESO) 16.0 15-Aug 30-Aug
INST F01 OBRAS CIVILES - CASETA MONITOREO PORTAL DE INGRESO
INST F01 LOSA CASETA DE MONITOREO 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Losa
Cimentaciones
de piso - solado
de caseta m3 1.00 - 1.00 1.0 1.0 1.0 15-Aug 15-Aug 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Losa
Cimentaciones
de piso - acero
p/canalización a Túnel ton 1.00 - 1.00 1.0 2.0 0.5 16-Aug 17-Aug 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Losa
Cimentaciones
de piso - Concreto
p/canalización a Túnel m3 20.00 20.00 20.0 1.0 20.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Losa de piso - Concreto de pedestales m3 1.00 1.00 1.0 1.0 1.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 PEDESTALES PARA BANDEJA ELÉCTRICA (hasta Banco de Ducto) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
PROGRAMA 4 WEEK LOOKAHEAD
OBRAS CONCRETO TÚNEL DE DESVÍO DEL RÍO ASANA
Fecha Corte: Friday, August 10, 2018
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Metrado Fechas AGOSTO AGOSTO AGOSTO AGOSTO
Total Total Total Actual SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 COMENTARIO
ITEM ITEM Descripción de la Actividad
Und Prev. Ejecut. Saldo Saldo Días Rend Inicio Fin S D L M X J V S D L M X J V S D L M X J V S D L M X J V
cant días 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07
INST F01 Excavación und 30.00 - 30.00 30.0 8.0 4.0 18-Aug 25-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Prefabricado de concreto (0.01 m3) und 30.00 - 30.00 30.0 6.0 5.0 18-Aug 23-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.0 5.0 5.0 5.0 5.0 5.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Montaje de prefabricados und 30.00 - 30.00 30.0 6.0 5.0 24-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.0 5.0 5.0 5.0 5.0 5.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 BANCO DE DUCTO 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Excavación m 10.00 - 10.00 10.0 3.0 4.0 20-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 4.0 4.0 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Instalación de tubería m 10.00 - 10.00 10.0 2.0 5.0 23-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.0 5.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Concreto m 10.00 - 10.00 10.0 2.0 5.0 25-Aug 26-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.0 5.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Relleno m 10.00 - 10.00 10.0 2.0 5.0 29-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.0 5.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 OBRAS ELECTROMECÁNICAS - CASETA MONITOREO
INST F01 MONTAJE DE EQUIPOS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Montaje
Cimentaciones
de caseta de caseta und 1.00 - 1.00 1.0 2.0 0.5 23-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Montaje
Cimentaciones
de panelesp/canalización
solares a Túnel und 3.00 - 3.00 3.0 3.0 1.0 25-Aug 27-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 1.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Montaje de Cabina de Generación de Solar und 1.00 - 1.00 1.0 2.0 0.5 28-Aug 29-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 CANALIZACIÓN ELECTRICA 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Instalación de bandeja eléctrica en plataforma de monitoreo m 20.00 - 20.00 20.0 4.0 5.0 30-Aug 2-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.0 5.0 5.0 5.0 0.0 0.0 0.0 0.0 0.0
INST F01 Instalación de bandeja eléctrica de plataforma a portal ingreso m 60.00 - 60.00 60.0 6.0 10.0 3-Sep 8-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 10.0 10.0 10.0 10.0
INST F01 CASETA DE MONITOREO (BOCATOMA)
INST F01 OBRAS CIVILES
INST F01 Excavación m3 1.00 - 1.00 1.0 1.0 1.0 18-Aug 18-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Vaciado de solado m3 1.00 - 1.00 1.0 1.0 1.0 19-Aug 19-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Colocación de acero ton 0.50 - 0.50 0.5 1.0 0.5 20-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Encofrado m2 4.00 - 4.00 4.0 1.0 4.0 21-Aug 21-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 4.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Vaciado de concreto m3 2.00 - 2.00 2.0 1.0 2.0 22-Aug 22-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 OBRAS ELECTROMECÁNICAS
INST F01 Sistema malla a tierra glb 1.00 - 1.00 1.0 2.0 0.5 23-Aug 24-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST F01 Montaje de estructura de flujómetro glb 1.00 - 1.00 1.0 4.0 0.3 25-Aug 28-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.3 0.3 0.3 0.3 0.0 0.0 0.0
INST F01 Montaje de panel solar / radio módem und 1.00 - 1.00 1.0 2.0 0.5 29-Aug 30-Aug 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.0
INST F01 Cableado y conexionado glb 1.00 - 1.00 1.0 2.0 0.5 31-Aug 1-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5
T T CABLE MENSAJERO 30.0 11-Aug 9-Sep
PERF PERF PERFORACIONES CABLE MENSAJERO 3.0 11-Aug 13-Aug
PERF PERF02 Frente 02 - Perforación cable mensajero 4+200 @ 5+940 und 86.00 25.00 61.00 61.0 3.0 21.0 11-Aug 13-Aug 21.0 21.0 19.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST INST INSTALACIÓN DE PERNOS CABLE MENSAJERO 3.0 11-Aug 13-Aug
INST INST Frente 03 - Instalación de pernos cable mensajero 7+590 @ 5+940 und 83.00 61.00 22.00 22.0 3.0 8.0 11-Aug 13-Aug 8.0 8.0 6.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST INST Frente 02 - Instalación de pernos cable mensajero 3+470 @ 5+940 und 124.00 - 124.00 124.0 13.0 10.0 14-Aug 26-Aug 0.0 0.0 0.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 4.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST INST INSTALACIÓN DE CABLE MENSAJERO 14.0 27-Aug 9-Sep
INST INST Habilitación de cable mensajero m 7,526.00 - 7,526.00 7,526.0 16.0 500.0 13-Aug 28-Aug 0.0 0.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 26.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST INST Frente 01 - Instalación cable mensajero 1+300 @ 0+015 m 3,443.10 - 3,443.10 3,443.1 12.0 300.0 15-Aug 26-Aug 0.0 0.0 0.0 0.0 300.0 300.0 300.0 300.0 300.0 300.0 300.0 300.0 300.0 300.0 300.0 143.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
INST INST Frente 02 - Instalación cable mensajero 1+300 @ 5+940 m 2,431.10 - 2,431.10 2,431.1 9.0 300.0 27-Aug 4-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 300.0 300.0 300.0 300.0 300.0 300.0 300.0 300.0 31.1 0.0 0.0 0.0
INST INST Frente 03 - Instalación cable mensajero 7+600 @ 5+940 m 1,652.10 - 1,652.10 1,652.1 5.0 350.0 5-Sep 9-Sep 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 350.0 350.0 350.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Fecha Corte: Thursday, August 16, 2018
Metrado Fechas AGOSTO
Total Total Total Actual SEMANA 1
ITEM ITEM Descripción de la Actividad
Und Prev. Ejecut. Saldo Saldo Días Rend Inicio Fin S D L M X J V Metrado
cant días 11 12 13 14 15 16 17 Semanal

T T INSTRUMENTACIÓN 12.0 11-Aug 22-Aug 0.0


INST INST PERFORACIÓN DE EM07 y 10 (CELDAS HI) 1.0 11-Aug 20-Aug 0.0 0.0 0.0 0.0 0.0 0.0
INST GEO Traslado de Equipos a Celda HI 10 Pk 5+500 Glb 1.00 0.75 0.25 0.3 2.0 0.2 11-Aug 12-Aug PLAN 0.2 0.1 0.0 0.0 0.0 0.0 0.0 0.3
REAL 0.2 0.1
INST GEO Celda HI 10 Pk 5+500 und 1.00 - 1.00 1.0 3.0 0.4 13-Aug 15-Aug PLAN 0.0 0.0 0.4 0.4 0.2 0.0 0.0 1.0
REAL
INST GEO Traslado de equipo de 5+500 a 3+250 Glb 1.00 - 1.00 1.0 2.0 0.5 16-Aug 17-Aug PLAN 0.0 0.0 0.0 0.0 0.0 0.5 0.5 1.0
REAL
PERF INST INSTALACIÓN CELDAS DE CARGA 7.0 12-Aug 18-Aug
PERF PERF02 Instalación de perno EM 07 Pk 3+250 und 1.00 - 1.00 1.0 1.0 1.0 12-Aug 12-Aug PLAN 0.0 1.0 0.0 0.0 0.0 0.0 0.0 1.0
REAL 1.0
PERF PERF02 Instalación de perno EM 14 Pk 3+443 und 1.00 - 1.00 1.0 1.0 1.0 13-Aug 13-Aug PLAN 0.0 0.0 1.0 0.0 0.0 0.0 0.0 1.0
REAL 1.0
PERF PERF02 Instalación de perno EM 13 Pk 3+900 und 1.00 - 1.00 1.0 1.0 1.0 14-Aug 14-Aug PLAN 0.0 0.0 0.0 1.0 0.0 0.0 0.0 1.0
REAL 1.0
PERF PERF02 Instalación de perno EM 08 Pk 4+027 und 1.00 - 1.00 1.0 1.0 1.0 15-Aug 15-Aug PLAN 0.0 0.0 0.0 0.0 1.0 0.0 0.0 1.0
REAL 1.0
PERF PERF02 Instalación de perno EM 09 Pk 4+720 und 1.00 - 1.00 1.0 1.0 1.0 16-Aug 16-Aug PLAN 0.0 0.0 0.0 0.0 0.0 1.0 0.0 1.0
REAL 1.0
PERF PERF02 Instalación de perno EM 10 Pk 5+500 und 1.00 - 1.00 1.0 1.0 1.0 17-Aug 17-Aug PLAN 0.0 0.0 0.0 0.0 0.0 0.0 1.0 1.0
REAL
T T CABLE MENSAJERO 30.0 11-Aug 9-Sep 0.0
PERF PERF PERFORACIONES CABLE MENSAJERO 3.0 11-Aug 13-Aug 0.0
PERF PERF02 Frente 02 - Perforación cable mensajero 4+200 @ 5+940 und 86.00 25.00 61.00 61.0 3.0 21.0 11-Aug 13-Aug PLAN 21.0 21.0 19.0 0.0 0.0 0.0 0.0 61.0
REAL 21.0 21.0 17.0
INST INST INSTALACIÓN DE PERNOS CABLE MENSAJERO 3.0 11-Aug 13-Aug 0.0
INST INST Frente 03 - Instalación de pernos cable mensajero 7+590 @ 5+940 und 83.00 61.00 22.00 22.0 3.0 8.0 11-Aug 13-Aug PLAN 8.0 8.0 6.0 0.0 0.0 0.0 0.0 22.0
REAL
INST INST Frente 02 - Instalación de pernos cable mensajero 3+470 @ 5+940 und 124.00 - 124.00 124.0 13.0 10.0 14-Aug 26-Aug PLAN 0.0 0.0 0.0 10.0 10.0 10.0 10.0 40.0
REAL 7.0 23.0 15.0 15.0
INST INST INSTALACIÓN DE CABLE MENSAJERO 14.0 27-Aug 9-Sep 0.0
INST INST Habilitación de cable mensajero m 7,526.00 - 7,526.00 7,526.0 16.0 500.0 13-Aug 28-Aug PLAN 0.0 0.0 500.0 500.0 500.0 500.0 500.0 2500.0
REAL 100.0
INST INST Frente 01 - Instalación cable mensajero 1+300 @ 0+015 m 3,443.10 - 3,443.10 3,443.1 12.0 300.0 15-Aug 26-Aug PLAN 0.0 0.0 0.0 0.0 300.0 300.0 300.0 900.0
REAL 100.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
ACTIVIDADES ACTIVIDADES
ITEM RESPONSABLE PAC
PROGRAMADAS COMPLETADAS
001 DIEGO DIOSES 13.0 7.0 53.8%
002 JHONY HUARCALLA 8.0 6.0 75.0%
003 HUSSEÍN LEÓN 47.0 21.0 44.7%
004 LUIS OBREGON 12.0 6.0 50.0%
005 JHONY CASTILLO 19.0 15.0 78.9%
PAC = 99.0 55.0 55.6%