STANDARD CHECKLIST

PROJECT : NMDC 3.0MTPY STEEL PLANT (NAGARNAR)

REF: PUMP HOUSE/415V PANEL NO: MCC Date:25/10/2018

CONTROL TRANSFORMER
LOCATION- Raw Water Pump House
FEEDER NAME:3F4
1. NAME PLATE DETAILS:
REFERENCE DETAILS
3.INSULATION
RATIO 415/240V RTESISTANCE
INS CLASS F IN(Ω)
KVA 2.5
Make REF VALUE
Pri-Earth -500V >1GΩ
Pri- Sec-500V >1GΩ
Sec –Earth-200V >1GΩ
4.MEASUREMENT OF RESISTANCE IN (Ω)

REF VALUE
Primary 4.7Ω
Secondary 1.10Ω

5.RATIO TEST

INJECTED
ACTUAL VALUE IN
REF VOLTAGE IN PRY VOLTAGE MEASURED IN SEC.(V)
SEC (V)
(V)
1 227.5 131.5 141.3

6.INSTRUMENT DETAILS
INSTRUMENT SERIAL NO MODEL VALID UPTO
MULTIMETER FLUKE 34630115WS 17B 19-06-2019

INSULATION TESTER E0023218 KEW 3125A 19-06-2019

SIGNATURE: SIGNATURE: SIGNATURE: SIGNATURE:

NAME: NAME: NAME: NAME:


DESIGN: T&C ENGG. DESIGN: SITE ENGG. DESIGN: DESIGN:
COMPANY: COMPANY: SRI RAM COMPANY: MECON COMPANY: NMDC
STANDARD CHECKLIST

PROJECT : NMDC 3.0MTPY STEEL PLANT (NAGARNAR)

REF: PUMP HOUSE/415V PANEL NO: MCC Date:25/10/2018

MICRO OHM METER 01A 030500 19-06-2019

7. OBSERVATION:
Control transformer is Found Healthy .

SIGNATURE: SIGNATURE: SIGNATURE: SIGNATURE:

NAME: NAME: NAME: NAME:


DESIGN: T&C ENGG. DESIGN: SITE ENGG. DESIGN: DESIGN:
COMPANY: COMPANY: SRI RAM COMPANY: MECON COMPANY: NMDC