d. Product Requirements
a. Project Charter
b. Requirements Document
a. Collect requirements
b. Define Scope
c. Create WBS
4. If the project is terminated early, the level and extent of completion should be documented. This is
done as a part of:
a. Define Scope
b. Create WBS
c. Validate Scope
d. Control Scope