Hülya Sokak No: 37 Tel : (312) 445 04 64 (Pbx)

06700 G.O.P./ ANKARA Fax : (312) 445 05 02

Date : 15.04.2016
Number : 4055

WORK EXPERIENCE CERTIFICATE


(Contractor – Work Completion)

1. Employer : AYEN ENERGY CO., INC. / (AYEN ENERJİ A.Ş.)

2. Name of Work TURBINE ACCESS ROAD OF DIDIM AKBUK-2 WIND


POWER PLANT

3. Place of Work DİDİM / AYDIN

4. Building Technique Applied Turbine Access Roads


- Road Pavement: Unpaved, stabilized road
- Road platform / Ditch width: 6.0 m / 1.0 m
- Road length: 6,500 m
- Excavation: 59,874.16 m3

5. Contractor’s Name and Surname and Trade title : AYDINER CONSTRUCTION CO., INC.
(AYDINER İNŞAAT A.Ş.)

6. Tax ID Number : Cumhuriyet Tax Office / 1160008876

7. Partnership Percentage if Joint-Venture : ----

8. Initial Contract Value : TRL 1,570,267.22 (Based on 2013 Unit Prices)

9. Total Contract Value : TRL 1,633,666.16 (Based on 2013 Unit Prices)

10. Amount of Work Performed : TRL 1,633,666.16 (Based on 2013 Unit Prices)

11. Date of Contract : 20.01.2014

12. If contract was transferred,


a) Date of transfer : ---
b) Amount of work as at date of transfer :
---
c) Amount of work following transfer :
---
13. Provisional Acceptance date 31.12.2015

14. Certificate value TRL 1,633,666.16 (Based on 2013 Unit Prices)

AYEN ENERGY CO., INC. Fahrettin Amir ARMAN


(AYEN ENERJİ A.Ş.)
Board Member – General Manager
Capital : TRL 171,042,300
ANKARA (Sealed & Signed)
Hülya Sokak No: 37 Tel : (312) 445 04 64 (Pbx)
06700 G.O.P./ ANKARA Fax : (312) 445 05 02

Date : 15.04.2016
Number : 4053

WORK EXPERIENCE CERTIFICATE


(Contractor – Work Completion)

1. Employer : AYEN ENERGY CO., INC. / (AYEN ENERJİ A.Ş.)

2. Name of Work CIVIL WORKS OF DIDIM - AKBUK 2 WIND POWER PLANT WITH 20 MW
INSTALLED POWER

3. Place of Work DİDİM / AYDIN

4. Building Technique Applied Turbine Foundations (10 units)


- Total foundation excavation (deep excavation): 13,296.59 m3
- Total concrete quantity: 5,056.85 m3
- Total formwork quantity: 747.60 m2
- Total reinforcement assembly: 296.07 tons
- Anchorage cage and buried elements assembly

Turbine Platforms (10 units)


- Total platform excavation: 81,455.99 m3
- Platform area diameter: 55 m
- Platform pavement: Unpaved, stabilized base

Building and Security Building Construction (Rough-Fine)


- C. Building surface area: 13.20 x 18.00 = 237.60 m2
- S. Building surface area: 3.30 x 3.80 = 12.54 m2
- C. Building Concrete/Formwork/reinforcement: 298.26 m3 / 918.38 m2 / 14.57 tons
- S. Building Concrete/Formwork/reinforcement: 17.96 m3 / 77.61 m2 / 1.61 tons

Cable Ducts
- Length: 4510 m
- Cross sectional area: 1.0 m x 1.5 m
- Excavation: 6,765.00 m3

Miscellaneous Works
- Wire fence: 1,219.01 m
- Cesspool
5. Contractor’s Name and Surname and Trade Title: AYDINER CONSTRUCTION CO., INC.
(AYDINER İNŞAAT A.Ş.)

6. Tax ID Number : Cumhuriyet Tax Office / 1160008876

7. Partnership Percentage if Joint-Venture : ----

8. Initial Contract Value : TRL 5,657,880.27 (Based on 2015 Unit Prices)

9. Total Contract Value : TRL 4,552,855.72 (Based on 2015 Unit Prices)

10. Amount of Work Performed : TRL 4,552,855.72 (Based on 2015 Unit Prices)

11. Date of Contract : 25.05.2015

12. If contract was transferred,


a) Date of transfer : ---
b) Amount of work as at date of transfer :
---
c) Amount of work following transfer :
---
13. Provisional Acceptance date: 31.12.2015

14. Certificate value: TRL 4,552,855.72 (Based on 2015 Unit Prices)

AYEN ENERGY CO., INC.


(AYEN ENERJİ A.Ş.)

Capital : TRL 171,042,300


ANKARA

Fahrettin Amir ARMAN

Board Member – General Manager

(Sealed & Signed)


Hülya Sokak No: 37 Tel : (312) 445 04 64 (Pbx)
06700 G.O.P./ ANKARA Fax : (312) 445 05 02

Date : 15.04.2016
Number : 4052

WORK EXPERIENCE CERTIFICATE


(Contractor – Work Completion)

1. Employer : AYEN ENERGY CO., INC. / (AYEN ENERJİ A.Ş.)

2. Name of Work ACCESS ROAD OF AKBUK 2 WIND POWER PLANT


WITH 20 MW INSTALLED POWER

3. Place of Work DİDİM / AYDIN

4. Building Technique Applied High Standard Type (B) Forest Road


- Road Pavement: Unpaved, stabilized road
- Road platform / Ditch width: 6.0 m / 1.0 m
- Road length: 11,600 m
- Excavation: 62,336.54 m3

5. Contractor’s Name and Surname and Trade Title : AYDINER CONSTRUCTION CO., INC.
(AYDINER İNŞAAT A.Ş.)

6. Tax ID Number : Cumhuriyet Tax Office / 1160008876

7. Partnership Percentage if Joint-Venture : ----

8. Initial Contract Value : TRL 1,855,805.60 (Based on 2012 Unit Prices)

9. Total Contract Value : TRL 1,706,287.41 (Based on 2012 Unit Prices)

10. Amount of Work Performed : TRL 1,706,287.41 (Based on 2012 Unit Prices)

11. Date of Contract : 06.03.2013

12. If contract was transferred,


a) Date of transfer : ---
b) Amount of work as at date of transfer :
---
c) Amount of work following transfer :
---
13. Temporary acceptance or housing date 01.10.2013

14. Certificate value TRL 1,706,287.41 (Based on 2012 Unit Prices)

AYEN ENERGY CO., INC. Fahrettin Amir ARMAN


(AYEN ENERJİ A.Ş.)
Board Member – General Manager
Capital : TRL 171,042,300
ANKARA (Sealed & Signed)
Hülya Sokak No: 37 Tel : (312) 445 04 64 (Pbx)
06700 G.O.P./ ANKARA Fax : (312) 445 05 02

Date : 15.04.2016
Number : 4054

WORK EXPERIENCE CERTIFICATE


(Contractor – Work Completion)

1. Employer : AYEN ENERGY CO., INC.


(AYEN ENERJİ A.Ş.)

2. Name of Work : DIDIM – AKBUK 2 WPP 154 KV


SWITCH YARD CIVIL WORKS

3. Place of Work : DIDIM / AYDIN

4. Building Technique Applied : 154 kV Switch Yard Construction


- Excavation: 4,136.12 m3
- Pylon Foundation: 22 units
- Circuit breaker foundations: 5 units
- Voltage transformer foundations: 13 units
- Current transformer foundations: 12 units
- Surge arrester foundation: 6 units
- Disconnecter switch foundations: 10 units
- Cable ducts: 304.90 m
- Power transformer foundations: 2 units
- Fire wall: 1 unit
- Oil pit and oil siphon: 1 unit
- Concrete roads: 532.71 m2
- Panel fence: 253.70 m
- Draining all the plant, spreading lime, nylon and
stone chips (2,195.50 m2)

Akbük 1 Control Building Refurbishment


- Brick wall, sand-cement screed, ceramic tile, raised
flooring, plaster board suspended ceiling, paint,
etc.. works
5. Contractor’s Name and Surname and Trade Title: AYDINER CONSTRUCTION CO., INC.
(AYDINER İNŞAAT A.Ş.)

6. Tax ID Number : Cumhuriyet Tax Office / 1160008876

7. Partnership Percentage if Joint-Venture : ----

8. Initial Contract Value : TRL 768.413,88 (Based on 2015 Unit Prices)

9. Total Contract Value : TRL 752.137,81 (Based on 2015 Unit Prices)

10. Amount of Work Performed : TRL 752.137,81 (Based on 2015 Unit Prices)

11. Date of Contract : 30.06.2015

12. If contract was transferred,


a) Date of transfer :
b) Amount of work as at date of transfer :
---
c) Amount of work following transfer : ---
---
13. Provisional Acceptance date: 31.12.2015

14. Certificate value : TRL 752.137,81 (Based on 2015 Unit Prices)

AYEN ENERGY CO., INC.


(AYEN ENERJİ A.Ş.)

Capital : TRL 171.042.300


ANKARA

Fahrettin Amir ARMAN

Board Member – General Manager

(Sealed & Signed)