Anda di halaman 1dari 4

Variations in construction contracts - Designing... https://www.designingbuildings.co.uk/wiki/Varia...

We use cookies to ensure we give you the best experience on our website. You can find out about our cookies and how to disable cookies in our
Privacy Policy. If you continue to use this website without disabling cookies, we will assume you are happy to receive them. Close.

Designing Buildings Wiki


Share your construction industry knowledge
www.designingbuildings.co.uk

Last edited 20 Mar 2019

Prefab Buildings For Sale


Variations in construction contracts
Dynamic African Projects

Leaders in Prefabricated Buildings


Contents Design, Supply and Installation

1 Introduction dynamicafrica.co.za
2 Valuation of variations
3 Source of conflict
4 Extension of time OPEN
5 Conclusion
6 Related articles on Designing Buildings Wiki
7 External references

DW Corrugated Plastic
Pipes
Introduction
Corrugated Pipe &Fittings Here
A variation (sometimes referred to as a variation instruction, variation order (VO) or change Economic and powerful. You can use it in
order), is an alteration to the scope of works in a construction contract in the form of an your waste water projects. (100-2400)mm
kuzeyborugroup.com
addition, substitution or omission from the original scope of works.

Almost all construction projects vary from the original design, scope and definition. Whether
OPEN
small or large, construction projects will inevitably depart from the original tender design,
specifications and drawings prepared by the design team.

This can be because of technological advancement, statutory changes or enforcement,


Featured articles and news
change in conditions, geological anomalies, non-availability of specified materials, or simply
because of the continued development of the design after the contract has been awarded. In
Ethics and professionalism
large civil engineering projects variations can be very significant, whereas on small building
contracts they may be relatively minor.

Variations may include:

Alterations to the design.


Alterations to quantities.
Alterations to quality.
Alterations to working conditions.
Alterations to the sequence of work.

Variations may also be deemed to occur if the contract documents do not properly describe
the works actually required.

Variations may not (without the contractors consent):


Modern slavery in the construction sector.
Change the fundamental nature of the works.
1 ofOmit
4 work so that it can be carried out by another contractor. 4/19/19, 4:59 PM
Be instructed after practical completion.
Require the contractor to carry out work that was the subject of a prime cost sum. Contract law
In legal terms,in
Variations a variation is an agreement
construction supported
contracts by consideration to alter some
- Designing... terms of
https://www.designingbuildings.co.uk/wiki/Varia...
the contract. No power to order variation is implied, and so there must be express terms in
contracts which give the power instruct variations. In the absence of such express terms the
contractor may reject instructions for variations without any legal consequences.

Standard forms of contract generally make express provisions for the contract administrator
(generally the architect or engineer) to instruct variations (for example, FIDIC Clause 51.1).
Such provisions enable the continued, smooth administration of the works without the need
for another contract.

Variation instructions must be clear as to what is and is not included, and may propose the
method of valuation.
What to bear in mind when claiming damages
in construction.
Valuation of variations

Variations may give rise to additions or deductions from the contract sum. The valuation of Infrastructure

variations may include not just the work which the variation instruction describes, but other
expenses that may result from the variation, such as the impact on other aspects of the
works. Variations may also (but not necessarily) require adjustment of the completion date.

Variations may be valued by:

Agreement between the contractor and the client.


The cost consultant.
A variation quotation prepared by the contractor and accepted by the client.
By some other method agreed by the contractor and the client.

Valuations of variations are often based on the rates and prices provided by the contractor in
their tender, provided the work is of a similar nature and carried out in similar conditions.
This is true, even if it becomes apparent that the rates provided by the contractor were
How do we achieve sustainable clean-water
higher or lower than otherwise available commercial rates.
infrastructure for all?
The contractor's rates do not become reasonable or unreasonable by the execution of
variations, as stipulated by the ruling in the case of Henry Boot Construction Ltd v Alstom
Appointments
[1999].

If similar types of works to those instructed by a variation cannot be found in the drawings,
specification or bills of quantities, then fair valuation of the contractor's direct costs,
overheads and profit is necessary.

However, NEC contracts do not value variations based on rates in the tender. Guidance on
assessing compensation events states:

'Assessment of compensation events as they affect Prices is based on their effect on


Defined Cost plus the Fee. This is different from some standard forms of contract where
variations are valued using the rates and prices in the contract as a basis. The reason for
this policy is that no compensation event for which a quotation is required is due to the fault
of the Contractor or relates to a matter which is at his risk under the contract. It is therefore What you should know when appointing an
appropriate to reimburse the Contractor his forecast additional costs (or actual costs if the architect.
work has already been done) arising from the compensation event.'

In other words, the contractor can ignore their tender pricing and claim cost plus on Standards

variations. However, there may be disagreements about items such as factory overheads
and management which are very hard to evaluate. In addition, given the complexity and
length of the supply chain in major building works, getting forecast pricing from all the parties
affected takes time, often beyond the date by which the contract administrator has to make
the decision as to whether or not to instruct the variation.

They may then have to decide whether or not to proceed with a variation based on estimates
from the cost consultant which in due course get replaced by the actual cost. It has been
argued that this practicality defeats the some of the rationale of the NEC contracts in relation
2toof 4 control and decision making.
cost 4/19/19, 4:59 PM
A brief history plus some new developments.
Variations in construction contracts - Designing... https://www.designingbuildings.co.uk/wiki/Varia...
Design
Source of conflict

Conflict can arise when work is not mentioned in the bills of quantities, drawings or
specifications. In common law this silence does not mean the contractor has an automatic
right to claim for extra payment. The client is not bound to pay for things that a reasonable
contractor must have understood were to be done but which happen to be omitted from the
bills of quantities.

Where there are items that, whilst they are not expressly mentioned, are nonetheless
How computational fluid dynamics (CFD) helps
required in order to complete the works, then the contractor should have included them in
building design.
their price. The bills of quantities and specification do not necessarily have to include 'every
nail to be punched in'. For example, in fixing GRC façades it is necessary to have steel
supports, and a reasonably experienced contractor must make provision for this in the Infrastructure
contract price. Unless expressly excluded, such supports are not paid for as a variation.

Conflict can also arise when a sub-contractor qualifies that, for example, 'Supply & Fixing of
Door is included' but 'Supply & Fixing of Ironmongery is excluded'. A reasonable sub-
contractor should foresee that a door cannot be fixed without hinges – which is a part of the
ironmongery. So even if ironmongery is excluded, the sub-contractor cannot expect a
variation for any of the items required to fix the doors.

Also, under the pretext of variation, the contract administrator cannot change the nature of
works. For example, if the contract provides for secant pile shoring, they cannot ask for
diaphragm wall shoring as it will entirely change the nature of the work.
The Hong Kong Harbour Area Treatment
Further, if the contract administrator omits work from contractor’s scope, such an omission Scheme (HATS).
must be genuine: that is, the work omitted must be omitted from the contract entirely, it
cannot be used to take work away from the contractor to give it to another (for example, see
Appointments
FIDIC Clause 51.1). Similarly, the contract administrator is not empowered to order
variations to help the contractor if the contract works are proving too difficult or expensive for
them.

Extension of time

Many construction contracts allow the construction period to be extended where there are
delays that are not the contractor's fault. This is described as an extension of time (EOT).

Variations may (but do not necessarily) constitute relevant events that can merit an
'Expressions of interest' for construction
extension of time and so adjustment of the completion date. See Extension of time for more
information. contracts.

Quality in Construction Summit


Conclusion

Variations are often sources of dispute, either in valuing the variation, or agreeing whether
part of the works constitute a variation at all, and can cost a lot of time and money during the
course of a contract. Whilst some variations are unavoidable, it is wise to minimise potential
variations and subsequent claims by ensuring that uncertainties are eliminated before
awarding the contract.

This can be done by:

Undertaking thorough site investigations and condition surveys.


Ensuring that the project brief is comprehensive and is supported by stakeholders.
Dame Judith Hackitt confirmed as keynote
Ensuring that legislative requirements are properly integrated into the project.
Ensuring that risks are properly identified. speaker – one year on from the Hackitt Report.
Ensuring that designs are properly coordinated before tender. Save £100 on tickets.
Ensuring the contract is unambiguous and explicit.
Ensuring the contractor's rates are clear.
3 ofPreparing
4 concise drawings, bills of quantities and specifications, providing for all 4/19/19,
Click here for more Featured 4:59
articles and PM
situations which are reasonably foreseeable.
news.
Variations in construction contracts - Designing... https://www.designingbuildings.co.uk/wiki/Varia...

Related articles on Designing Buildings Wiki

Extension of time EOT in construction contracts


Architect's instruction
Campaign for cash retentions reform.
Change order for construction contracts
Alterations to existing buildings
Prime cost sum
Liquidated damages in construction contracts
Construction contract
Change control procedure for building design and construction
Compensation event
Abortive work in building design and construction
Payment for extra work
Bill of quantities BOQ
Confirmation of verbal instruction
Scope of work
Dayworks in construction
How to prepare a claim for an extension of time
Contract sum
FIDIC
Loss and expense
Contract documents for construction
Relevant event
Fluctuations in construction contracts
Valuation
Valuation of interim payments

External references

The JCT 05 Standard Building Contract: Law and Administration By Issaka Ndekugri,
Michael Rycroft.

© Designing Buildings Ltd. 2019

4 of 4 4/19/19, 4:59 PM

Anda mungkin juga menyukai