Anda di halaman 1dari 1

C:\Users\BAREZ\Downloads\Building HeaderSS.

png

Mobile Buildingoffice198@Gmail.com
Email: Number:+ 964 750 8620123

DESIGN NOTES
0

DESIGN BASIS
- The design is performed according to ACI 318-14 code requirement complying for designing all concrete members ( foundation, Tie beams and floors).
- Net allowable bearing capacity is assumed to be 150 kN/m2
MATERIALS
CONCRETE STRUCTURE:
- Portland cement ASTM C150 used in the work shall correspond to basis of concrete for designing concrete mixture proportions. Cement must be identified
in its actual service in order to produce concrete with adequate strength and durability.
- Normal weight aggregate ASTM C33 shall conform to the requirements of test to identify actual service and produce concrete with adequate strength and
durability. 1) ALL DIMENSIONS IN MILLIMETERS
EXCEPT MENTIONED.
- Minimum CUBIC compressive strength (Fc') of ALL CONCRETE MEMBERS must be more than 30 MPa for cube tests. 2) CHARACTERISTIC YIELD STRENGTH
OF REINFORCEMENT SHALL BE Fyk =400
MPa.
3) CHARACTERISTIC COMPRESSIVE
- Carbon steel ASTM A615 must be used to requirement specification, minimum tensile strength must be more than 420 MPa for all sizes of steel STRENGTH OF CONCRETE SHALL BE Fc
CUBE=35MPa, Fc cylinderical = 30 MPa
4) CONCRETE COVER FOUNDATION
reinforcement. Cnom=70mm (Top, Nottom, and side)
TIE BEAM
Cnom= 70mm (Top, Nottom, and side)
STRUCTURE
- Foundations should be accommodated safely against all the imposed forces. Attention is requred to the connection between all the member of superstructure
and to the substructure to the anchoring of any holding-down bolts.
- The connection between column- foundation are pinned connection (shear resistance).
DEAD LOAD
The load of the structure and super dead load with 100mm slab thickness have been considered in the design. Moreover, the cladding load has established
on the beam perimeter. On the other hand, the seismic loads is applied according to ASCE7-10 on the structure. Although, the wind load maybe neglected in the design based on
code, it has been applied in order to gain more safety to the building.
LIVE LOAD PROJECT NAME:

-live load for warehouse building is assumed to be 5 kN/m2 for the entire building. For the Roof 2kN/m2 live load is applied.
DURABILITY Warehouse
-The clear cover between lean concrete and bottom reinforcement in the pad foundation should be restricted to 75 mm
-The clear cover between internal form face and closest steel reinforcement in tie beams should be restricted to 75 mm
-The clear cover between internal form face and closest steel reinforcement in walls and slabs should be restricted to 25 mm LAND NO

- Exposure categories such as freezing and thawing, sulfate and chloride attack,requirement for low permeability and reinforcement
LAND AREA
corrosion protection need to be considered precisely due to different weather throughout construction process according to clause 4.1 in ACI318-14
- Any embedment materials such as conduits, pipes and sleeves must not be harmful to endanger concrete components and rebar. BUILT AREA

PRACTICES TO MINIMIZE PLASTIC CRACKS


DRAWING NAME
+ dampen the sub-grade and form works before placing concrete to avoid excessive water loss
+ Place concrete in deep sections first (beams) and let it settle prior to placing and compacting the top layers (slab) to eliminate occurrence GENERAL NOTE
of plastic settlement due to restraining edges of the form works.
+ Precaution needs to be exercised for avoiding damage of bond between rebar and concrete.
JOB NO 1 JOB TYPE STRU.

+ Prevent excessive moisture surface evaporation by providing for sprays or wind breaks.
+ Cover concrete with wet burlaps or polyethylene sheets between finishing operation DESIGNED BY:

+ Use cooler concrete in hot weather and avoid extremely high concrete temperature in cold weather
+ After the excavation of foundation pit shall timely make the foundation construction, no water and exposure. The underground part after the
construction should be timely backfill of pit. Backfill soil shall be compacted, compaction coefficient should be not less than 0.94.
APPROVED

DATE Feb. 2019


SHEET NO SCALE

A 02 N.T.C

Anda mungkin juga menyukai