CLIENT: KNOWLES ELECTRONICS PHILS.

Date : Mar 16, 2019


Cebu Light Industrial Park, Lapu-Lapu City QTN # LC19_092

ATTENTION: Ms. Erna Enderes


Facilities Department

SUBJECT: Quotation for the Design and Build Project for New Motorcycle Parking Canopy

Dear Maam,

We are pleased to submit below our proposal for your requirement for Supply of materials and labor for the Design and
Build Project for New Motorcycle Parking Canopy.

Terms and Condition

Price Offer : ₱1,875,332.29


Terms of Payment : 30% Down Payment and 60% Progress Billing 10% Retention
Completion : As per Agreement
Validity of offer : 30 days

Thank you for giving us the opportunity to quote and we look forward to receive your approval soon.

Very Truly Yours,

Antero Loreno Jr
General Manager
Design and Build Project for New
PROJECT : Motorcycle Parking Canopy DATE : 16-Mar-2019
LOCATION QUOTATION
: Cebu Light Industrial Park NO. LC19_092

CONTACT : Ms. Erna Enderes REF. NO.

PROJECT COST ESTIMATE


BID FORM base on estimate
R A T E S
ITEM DESC RIPTION QTY UNIT MATERIALS LABOR TOTAL TOTAL AMOUNT QTY UNIT MATERIALS
A General Design Services 15,000.00
Provision of design details services of Parking Roof including
1.0 1.00 lot 15,000.00 15,000.00 1.00 lot
production of drawings for presentation and permits
Supply of Materials and Labor for Construction of
B Concrete Foundation and necessary accessories to 218,330.84
complete the job
Site Works (Excavation and Backfilling)including hauling and
1.0
disposal
Concrete 4.23 cu.m. 2,500.00 2,500.00 10,584.00 3.53 cu.m.
Soil 21.17 cu.m. 1,500.00 1,500.00 31,752.00 17.64 cu.m.
2.0 Steel Works convert to kg add 10% price per kg(net) base price
12mm diameter reinforcement bar 375.94 kgs 49.08 14.72 63.80 23,985.05 384.00 Lm 65.00 341.76 375.936 37.18 40.898
10mm diameter reinforcement bar 261.89 kgs 44.99 13.50 58.48 15,316.29 384.00 Lm 55.00 238.08 261.888 37.18 40.898
#16 G.I Tie Wire 30.00 kgs 50.00 12.50 62.50 1,875.00 25.00 kgs 50.00
12mm diameter x 150mm Anchor Bolt with Nut and washer 300.00 pcs 125.00 31.25 156.25 46,875.00 288.00 pcs 220.00
3.0 Formworks
4'' x 8' x 1/2"thk. Marine Plywood 15.00 shts 850.00 255.00 1,105.00 16,575.00 12.00 shts 850.00
2" x 2" x 8' Coco Lumber 144.00 Lm 50.00 15.00 65.00 9,360.00 115.20 Lm 50.00
2" CWN 27.60 kgs 80.00 12.00 92.00 2,539.20 23.00 kgs 80.00
4" CWN 20.40 kgs 80.00 12.00 92.00 1,876.80 17.00 kgs 80.00
4.0 Concreting Works
Portland Cement 67.00 bags 215.00 64.50 279.50 18,726.50 56.00 bags 215.00
Washed Sand 3.60 cu.m. 1,700.00 425.00 2,125.00 7,650.00 3.00 cu.m. 1,500.00
Gravel 9.60 cu.m. 1,700.00 510.00 2,210.00 21,216.00 8.00 cu.m. 1,500.00
5.0 Consumables 1.00 lot 10,000.00 10,000.00 1.00 lot
Supply of Materials and Labor for Fabrication and
C Installation of Parking Roof and necessary accessories to 1,106,631.80
complete the job
1.0 Post and Roofing Installation canvassed price per Lm or pc
10mm thk. Base Plate and Gusset Plates 4.90 sqm 4,083.33 1,225.00 5,308.33 25,989.60 4.08 sqm 3,888.89 11,200.00 3888.888889
6" diameter B.I. Pipe Post 162.00 Lm 1,750.00 525.00 2,275.00 368,550.00 144.00 Lm 1,666.67 10,000.00 1666.666667
4" diameter B.I. Pipe Rafter 162.00 Lm 444.50 133.35 577.85 93,611.70 144.00 Lm 423.33 2,540.00 423.3333333
2" diameter B.I. Pipe Horizontal Support 288.00 Lm 92.75 27.83 120.58 34,725.60 263.60 Lm 88.33 530.00 88.33333333
2" x 4" C-Purlins 720.00 Lm 159.25 47.78 207.03 149,058.00 658.00 Lm 151.67 910.00 151.6666667
M6 G.I. Turnbuckle 220.00 pcs 510.30 153.09 663.39 145,945.80 184.00 pcs 486.00 486.00 486.00
GA#20 Pre-Painted Longspan Rib-Type Roofing 434.94 Lm 441.00 132.30 573.30 249,351.10 395.40 Lm 420.00 420.00 420.00
2" Texscrew 6,000.00 pcs 2.00 0.40 2.40 14,400.00 5,000.00 pcs 2.00 1.75
2.0 Consumables 1.00 lot 25,000.00 25,000.00 1.00 lot
Supply of Materials and Labor for Paintworks and
D 183,641.32
necessary accessories to complete the job
Supply of Materials and Labor for Paintworks on steel
1.0 materials with 1-coat Epoxy Primer and 2-coats Epoxy 343.54 sqm 325.00 195.00 520.00 178,641.32 312.31 sqm 325.00
Enamel and necessary accessories to complete the job
2.0 Consumables 1.00 lot 5,000.00 5,000.00 1.00 lot
Supply of Materials and Labor for Electrical Works and
E necessary accessories to complete the job (tap to nearest 121,424.36
EE Room)
1.0 Supply and installation of lighting fixtures canvassed price add 10%
18W T-8 LED Light 48.00 sets 660.00 99.00 759.00 36,432.00 48.00 sets 600 660
3.5 mm2 3-Core Royal Cord 4.80 rolls 9,005.70 200.00 9,205.70 44,187.36 4.00 8,187.00 8,187.00 9005.7
G.I Junction Box with cover 72.00 pcs 53.90 13.48 67.38 4,851.00 60.00 49.00 49.00 53.9
3.5 mm2 Cable Gland 216.00 pcs 101.20 25.30 126.50 27,324.00 180.00 92.00 92.00 101.2
1/2" diameter 2-hole Metal Clips 120.00 pcs 13.20 3.30 16.50 1,980.00 100.00 12.00 12.00 13.2
15 AT Bolt-on Circuit Breaker (Schneider Brand) 2.00 sets 660.00 165.00 825.00 1,650.00 2.00 600.00 600.00 660
2.0 Consumables 1.00 lot 5,000.00 5,000.00 1.00 lot
Sub Total : 1,645,028.32
S U M M A R Y
ITEM DESCRIPTION COST
A Total Materials and Labor Cost 1,645,028.32
B Mobilization & Demobilization 49,350.85
C Miscellaneous, Overhead, PPE & Equipments 49,350.85
D Supervision 82,251.42
E Engineering Plans, As- Built Plans, PEZA Permits 49,350.85
Sub-Total 1,875,332.29
TOTAL CONTRACT PRICE 1,875,332.29

Note:
Lead-time : As per agreement
Quotation Validity : 30 days
Terms of payments : 30% Down Payment and 60% Progress Billing 10% Retention

Thank you very much for giving us the chance to quote. We hope this offer would merit your immediate approval.

Respectfully yours,

Antero Loreno Jr.


GENERAL MANAGER

F Supply of Materials and Labor for Plumbing Works and 5,000.00


necessary accessories to complete the job (tap to nearest
1.0 Supply and installation of roof gutter and downspouts
drain only)
GA#20 Pre-Painted Box-Type Roof Gutter 0.00 Lm 225.00 67.50 292.50 0.00
2" diameter PVC Downspout including fittings 0.00 Lm 225.00 67.50 292.50 0.00
2.0 Consumables 1.00 lot 5,000.00 5,000.00