Anda di halaman 1dari 5

BOQ

Name of work :- AM& R OF IRRIGATION CHANNELS AND FLOOD PROTECTION WORKS OF


CHITRAL IRRIGATION DIVISION,CHITRAL FOR THE YEAR 2018-19.

Sub Work:- AM & R of Flood Protection works for the year 2018-19 in the
jurisdiction of Irrigation Sub Division Chitral(Lower).

E/Cost :- Rs. 4.00 (Million)

E/Money + Rs. 86,250/-


Stamp Duty
S.No. Item of work. Unit Quantity Rate Amount (Rs.)
1 Excavation in foundation, of buildings, bridges etc 350.50 273.34 95805.67
complete in Shingle /Gravel
MRS 2017 (03-23-d)

2 Excavation in shingle or gravel formation & rock not M3 115.50 377.43 43593.17
requiring blast, undressed, 50m lead : Dry
MRS 2017 (03-09-a)

3 Excavation in shingle or gravel formation & rock not M3 85.50 437.02 37365.21
requiring blast, undressed, 50m lead : Wet
MRS 2017 (03-09-b)

4 Excavation in shingle or gravel formation & rock not M3 80.50 556.21 44774.91
requiring blast, undressed, 50m lead :in Flowing water
MRS 2017 (03-09-c)

5 Rock Excavation, dressing & disposal up to 50m M3 195.0 643.35 125453.25


Medium hard rock, requiring occasional blasting
MRS 2017 (03-11-b)
6 Structural backfill using Common Material available at M3 175.0 442.27 77397.25
site. MRS 2017 (03-60-c)

7 Extra for every 25 m extra lead or part thereof for gravel, M3 320.50 7.95 2547.98
shingle or rock. MRS 2017 (03-17-b)

8 Transportation of earth all types beyond 250 m and upto M3 320.5 141.04 45203.32
500 m.MRS 2017 (03-18-a)

9 Transportation of earth all types for every 100m extra M3 320.5 21.85 7002.93
lead beyond 500m upto 1.5 km.
MRS 2017 (03-18-b)

10 Random rubble masonry in foundn. & plinth Dry M3 110 2672.51 293976.10
masonry.
MRS 2017 (08-01-a)
11 Random rubble masonry in foundn. & plinth in cement, M3 15 5384.76 80771.40
sand mortar : Ratio 1:6
MRS 2017 (08-01-d-03)
12 Providing and weave GI Wire netting for wire M3 1400.00 369.52 517328.00
crates 6" x 9" mesh 8SWG
MRS 2017 (19-13-a-03)
13 Supplying stone & stone filling in G.I. Wire M3 385.00 1673.03 644116.55
crates and its sewing, excl: cost of crates.
MRS 2017 (19-26)
14 Supply & fill bricks in wire crates including sewing M3 120.00 1333.84 160060.80
crates, excl cost of crates : Stone or boulder
MRS 2017 (19-18-a)
15 P.C.C. (1:3:6) in mass concrete less form work using M3 90.00 4488.55 403969.50
40% boulders
MRS 2017 (06-36-b)
16 Errecting & removing form work to concrete in any M2 200.00 552.50 110500.00
shape/position (V)
MRS 2017 (06-38-b)
17 Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah M3 22.07 5219.71 115199.00
shingle well graded and cleaned) in foundation & plinth
(Ratio 1:3:6)
MRS 2017 (06-03-a)
18 Provision for Channelization/Clearance of water Hrs 200.0 5000.00 1000000.00
ways/Diversion of flow etc through 200 HP excavator
including cost of POL/M-OIL, operator, Other Staff
required at site, mobilization, demobilization, repair etc
(complete Job).

Less 7% 2608710
Ading area factor 1.15 3000017
Total Adding NSI 4000017.04
Say Rs = 4000000

Contractor Premium ____________________ % above/below

Signature of Contractor.

Sub Divisional Officer(U), Sub Engineer.


1080

#VALUE!
1716.12 1595.99 1835.39
1247.67 1160.33 1334.383