Anda di halaman 1dari 34

500kV GRID STATION NTDC MULTAN

GRID ISSUES
Sr No Equipment Detail of Problems

220KV Bus Bar Protection was blocked in 2010 as per


instructions of CE (System Protection) WAPDA House
Lahore vide letter No.1964-70 dated 29-04-2010 with the
remarks that “Existing Bus Bar protection will have to be
replaced with new numerical low impedance Bus Bar
1 220KV Bus Bar Protection Protection at 500KV G/S Multan”. However the same has not
been replaced and the Bus Bar Protection has been blocked.
The blocking / absence of Bus Bar Protection on a very vital
grid like 500KV G/S Multan cannot be compromised for a
long time. It is therefore requested for the arrangement of new
220KV Bus Bar

Augmentation of one or two 160


Augmentation of one or two 160 MVA transformers into 250
2 MVA transformers into 250 MVA is
MVA is needed.
needed.
TRANSMISSION LINE CONSTRAINTS
Sr No Transmission Line Details
NIL
CONSTRAINTS DUE TO DISCOS
Sr No Description Details
NIL
CIVIL WORK
Sr No Civil Work Remarks
NIL
MISCELLANEOUS
Sr No Description Problems/Remarks
NIL
LTAN

Current Status

Protection scheme for 10 Nos. 220KV Dias.


Letter has been written to CE (Design) NTDC
Lahore by SE 500KV GSO Multan, vide letter
No.2001-03 dated 11-04-2017, for preparation of
bidding documents for procurement of 220KV
Bus Bar Protection Relays for the same. Admin
approval & Technical sanction alongwith
allocation of budget is required by GM GSO
NTDC Lahore.

Not included in any augmentation

NTS
Current Status

S
Current Status

Current Status

Current Status
500kV GRID STATION NTDC YOUSAFWALA
GRID ISSUES
Sr No Equipment Details

At 500 KV Grid Station Yousafwala due to aging factor,


1 Replacement of 220 & 132KV CBs 220KV & 132KV circuit breaker and all allied isolators need
early replacement for the stability of the system.

In hot weather, 3 Nos. 160 MVA Transformers become


2 220/132KV Transformers loaded at 90% to 100%. It is necessary to augment one
or two transformers with 250 MVA transformers.
TRANSMISSION LINE CONSTRAINTS
Sr No Transmission Line Details
NIL
CONSTRAINTS DUE TO DISCOS
Sr No Description Details
NIL
CIVIL WORK
MISCELLANEOUS
Spreading of gravel in switch yard is in process by XEN
1 Spreading of gravel in switch yard
(Civil) GSO Multan
MISCELLANEOUS
Sr No Description Problems/Remarks
NIL
FWALA

Current Status

Included in replacment data

Not included in any augmentation

NTS
Current Status

S
Current Status

Tender in process

Current Status
500kV GRID STATION NTDC MUZAFFARGARH
GRID ISSUES
Sr No Equipment Detail of Problems
Tertiary Bus Bar of 3x200 MVA Auto Transformer T-2 at
Tertiary Bus Bar of 3x200 MVA Auto 500KV grid station Muzaffargarh was repaired which was a
1
Transformer T-2 temporary arrangement. Now, new Tertiary Bus Bar is
required.
TRANSMISSION LINE CONSTRAINTS
Sr No Transmission Line Details
NIL
CONSTRAINTS DUE TO DISCOS
Sr No Description Details

220KV circuit breakers of 500/220KV Transformers TR-1 &


TR-2 are installed in TPS Muzaffargarh switch yard. These
are under the control of TPS. These circuit breakers create
problem in opening & closing during shutdown on TR-1 and
1 220KV CBs at TPS M/Garh
TR-2 due to improper maintenance and testing by TPS staff.
MD NTDC visited 500KV grid station Muzaffargarh on 24-
02-2017 and advised to plan a new 220KV switch yard to
overcome this problem.

CIVIL WORK
Sr No Civil Work Remarks
NIL
MISCELLANEOUS
Sr No Description Problems/Remarks
NIL
ARGARH

Current Status

Request for demand of spare Bus Bar has been


sent to GM (GSO) NTDCL Lahore from this
office through email dated 26-04-2017.

NTS
Current Status

S
Current Status

The matter has been taken up with GM (Power


Planning) NTDC. A visit of Power Planning and
Design. NTDC representatives is scheduled in
next week for this purpose

Current Status

Current Status
500kV GRID STATION NTDC DG KHAN
GRID ISSUES
Sr No Equipment Detail of Problems

After commissioning In/Out arrangement at 500KV DG


Khan, 500KV T/Line Multan-Guddu circuit split into two
sections i.e. Multan- DG Khan and DG Khan -Guddu T/L
1 Shunt Reactor at DG Khan having shunt reactors at Multan and Guddu ends. DG Khan-
Guddu line needs a shunt reactor at 500KV G/S DG Khan
end, its length being 226.9km, in order to avoid trippings due
to over voltage.

TRANSMISSION LINE CONSTRAINTS


Sr No Transmission Line Details
NIL
CONSTRAINTS DUE TO DISCOS
Sr No Description Details

There is possibility of 08 Nos. 132KV Line Bays at 500 KV


Grid Station DG Khan but at present only 04 Nos. circuits are
Non completion of 4 No 132KV
1 in operation. Load on Muzaffargarh 220KV NTDCL system
Trasmission Lines
can be reduced by constructions of the all 132KV bays at 500
KV Grid Station DG Khan.
CIVIL WORK
Sr No Civil Work Remarks
NIL
MISCELLANEOUS
Sr No Description Problems/Remarks
NIL
KHAN

Current Status

The request for installation of shunt reactor at


500KV G/S DG Khan has been sent by XEN P&I
500KV Muzaffargarh to GM (Planning Power)
Lahore for installation of shunt reactor vide his
letter No.3238-44 dated 13-04-2017.

NTS
Current Status

Current Status

No action yet by MEPCO

Current Status

Current Status
500kV GRID STATION NTDC RAHIM YAR KHAN
GRID ISSUES
Sr No Equipment Detail of Problems
The enegization of 500KV RY Khan grid station with 02 Nos.
500KV ATBs of 600 MVA and 02 Nos. 220/132KV ATBs
with 250MVA capacity will share the load of Bahwalpur grid
1 500KV Grid Station Rahim Yar Khan station and voltage problems will be solved in the Southern
Punjab. It will give relief to MEPCO and SEPCO.

TRANSMISSION LINE CONSTRAINTS


Sr No Transmission Line Details
NIL
CONSTRAINTS DUE TO DISCOS
Sr No Description Details
NIL
CIVIL WORK
Sr No Civil Work Remarks
NIL
MISCELLANEOUS
Sr No Description Problems/Remarks
NIL
AR KHAN

Current Status

Grid Station commisioning will be delayed due to


non completion of in & out arrangement

NTS
Current Status

S
Current Status

Current Status

Current Status
220kV GRID STATION NTDC BAHAWALPUR
GRID ISSUES
Sr No Equipment Detail of Problems

1- There are 03 Nos. transformers at Bahwalpur grid


station. 02 No. transformers have already been augmented
from 160MVA to 250MVA each. Whereas 160MVA T-1 can
1 220/132KV Transformer be augmented from 160MVA to 250MVA for which the
foundations have been constructed. This way the load will
be reduced at the grid station.

220KV grid station Lal Sohanra is ready to be


commissioned. It will share the load of 220KV grid station
2 220KV GS Lal Sohanra Bahwalpur. It will be another power source in addition to
TPS Muzaffargarh.

Manufacturiing fault of 220KV and 132KV CB make GEC


Alstom. Crown of sliding contact slips down in few
operations that cause improper connection of contacts and
3 220KV & 132KV Circuit Breakers results in damage of circuit breaker. 13 No. circuit
breakers of this make and type are installed at this grid
stationn. Despite overhauling and modification in crown, 5
circuit breakers got damaged in past few years.

TRANSMISSION LINE CONSTRAINTS


Sr No Transmission Line Details
NIL
CONSTRAINTS DUE TO DISCOS
Sr No Description Details

All 11KV outgoing trolleys have completed their life and


they pose difficulty inproper operation and could be
1 11KV Trolleys dangerous so the replacement of outgoing trolleys is
required.
500 MCM and 4/0 AWG cables are required for outgoing
2 Requirement of Cables feeders.

CIVIL WORK
Sr No Civil Work Remarks
NIL
MISCELLANEOUS
Sr No Description Problems/Remarks
NIL
ALPUR

Current Status

TS
Current Status

Current Status

01 No. incoming and 01 No. outgoing complete


panels are required.
Current Status

Current Status
220kV GRID STATION NTDC MUZAFFARGARH
GRID ISSUES
Sr No Equipment Detail of Problems
1 Battery bank Sulphation and buckling
2 Isolators alignment problem
3 Air Conditioner compressor over heat issue
4 closing and tripping coils spares are not available
03 energy meters are not installed on 03 circuits.digital
5 Energy/Ampere/volt meters
ampere and volt meters need to be installed
TRANSMISSION LINE CONSTRAINTS
Sr No Transmission Line Details
NIL
CONSTRAINTS DUE TO DISCOS
Sr No Description Details

The 132KV T/L Mara Khas controlling circuit breaker E5Q1


is being controlled by line isolator 101 at 132KV Mara Khas
grid station end. Few more grid stations are also fed from this
line by MEPCO every now and then. It has been observed that
1 Mehra Khas
Distance Protection relay installed at 220KV grid station
Muzaffargarh operates in Zone 2/Zone 3 many times. The
frequent tripping of circuit breaker at this grid station is
deteriorating its health.

CIVIL WORK
Sr No Civil Work Remarks
The building of 220 KV Grid Station
is insufficient to accommodate
1 officers and officials. There is no At least 06 number rooms should be built
room for AE (P&I), AE (M), Store,
P&I Lab, Admin and Accounts.

No proper parking shed is


available. The chemical exhaust
2 from TPS Muzaffargarh is parking shed should be built
deteriorating the official/private
vehicles.

Auto-Transformers are placed very


next to Control Room Building and
3 there is no concrete wall between concrete wall should be built
these and Auto-Transformers T1 and
T2.

Proper security check post are not


4 check post should be bulit
available.

The pedestrian/foot path along road


5 from main gate to Control room pedestrian should be built
building is not available

Many of the employees of this grid


station are facing accommodation
6 problem due to limited number of flats should be bulit as sufficient space is available in this grid
house in the nearby 500 KV NTDC
Colony Muzaffargarh

The height of boundary wall (South-


West) of 132 KV Switch yard is low
7 boundry wall height should be increased
posing a constant security threat to
the grid station.
MISCELLANEOUS
Sr No Description Problems/Remarks

There is an acute shortage of class IV


1 shortage of staff
Staff, Fitter, SSA and ASSA.
ARGARH

Current Status
correspondence in progress

analog meters are installed

NTS
Current Status

S
Current Status

Circuit is on Load these days

Current Status
Pending

Pending

Pending

Pending

Pending

Pending

Pending
Current Status
220KV GRID STATION NTDCL KASSOWAL
GRID ISSUES
Sr. No. Equipment Detail of Problems
1 Graveling Gravel in switchyard is required.
220/132 KV 160 MVA Auto
2 SERGI system is non-functional.
Transformer T-1 & T-2
3 D00+C6 Panel Synchro check relay is non-functional.
Fault and event recorder is required as per BOQ item G.8, 9,
4 Fault and Event Recorder
10 & 11.
CVT is out of order duen to which Over Flux Relay is non-
5 T-2 HV Side CVT
functional.

Distance Set-II installed at 220KV Kassowal-Vehari Circuit-I


& II and 220KV Kassowal-Yousafwala Circuit I & II.
6 Non-Functional Relays
Over All Differential installed at 220/132KV 160 MVA Auto
T/F T-1
TRANSMISSION LINE CONSTRAINTS
Sr. No. Transmission Line Details
NIL
CONSTRAINTS DUE TO DISCOS
Sr No Description Details
Power factor at CDP Points 220/132 KV Auto Transformer T-
1 Low Power Factor
1 ans T-2 is low.
CIVIL WORK
Sr. No. Civil Work Remarks
NIL
MISCELLANEOUS
Sr. No. Description Problems/Remarks
There is extreme shortage of staff at the Grid Station. Some
1 Shortage of Staff
staff is at attachment with other Grid Stations.
2 Laptop 01 no. Laptop for Omicron Test Set is required.
3 Desktop Computer 02 nos. Desktop Computers are required.
4 Printer 2 nos. Printers are required.
5 Internet Internet facility is required.
6 Vehicle Vehicle (Gimny/Double Cabin) is required for XEN.
7 School Bus School Bus is required.
8 CCTV Cameras CCTV Camers are required.
9 Weapons Security Staff does not latest weapons.
220KV GRID STATION NTDCL KASSOWAL
GRID ISSUES
Current Status

Issues has been brought into notice of higher


office.

TRANSMISSION LINE CONSTRAINTS


Current Status
NIL
CONSTRAINTS DUE TO DISCOS
Current Status
Issue has been brought into notice of higher
office.
CIVIL WORK
Current Status
NIL
MISCELLANEOUS
Current Status

Issues has been brought into notice of higher


office.
Issues has been brought into notice of higher
office.
220kV GRID STATION NTDC VEHARI
GRID ISSUES
Sr No Equipment Detail of Problems
The existing 220V & 110V DC battery banks installed at
220KV grid station Vehari have completed their useful
1 220V & 110V DC Battery Banks
life and are in bad condition due to which replacement is
required.
TRANSMISSION LINE CONSTRAINTS
Sr No Transmission Line Details
NIL
CONSTRAINTS DUE TO DISCOS
Sr No Description Details
NIL
CIVIL WORK
Sr No Civil Work Remarks
NIL
MISCELLANEOUS
Sr No Description Problems/Remarks
NIL
HARI

Current Status

Higher offices has been approached many


times for allocation/purchase of battery banks
but issue is still unresoloved.

NTS
Current Status

S
Current Status

Current Status

Current Status
220kV GRID STATION NTDC OKARA
GRID ISSUES
Sr No Equipment Detail of Problems

The existing 220V & 110V DC battery banks installed at


1
220KV grid station are in poor condition sediments are
220V & 110V DC Battery Banks
present at the bottom and plates are tilted as well. This
point has been included in punch list of the grid station.

2
Supporting insulator for tertiary bushings were damged
220/132KV 250 MVA Auto-Transformers T2 & T-3
on no load condition and have not been repalced yet
Leakage of SF6 gas in almost all of the 132KV circuit
3
breakers is a major issue of this grid station while D4Q1
132KV & 220KV Circuit Breakers
was also decalred faulty after one week of
commissioning due to leakae of SF6 gas

4 Energy Meters Energy Meters have not been installed at grid station

5 Event & Fault recorders Event & fault recorder have not been commssioned
TRANSMISSION LINE CONSTRAINTS
Sr No Transmission Line Details
220KV Okara-Yousafwala II & Proper In out of second circuits of yousafwala and Sarfraz
1 Okara-Sarfraz Nagar II Nagar lines are pending at grid station
CONSTRAINTS DUE TO DISCOS
Sr No Description Details
NIL
CIVIL WORK
Sr No Civil Work Remarks

Filtration plant is not suitable for drinking water at grid


1 Drinking water station. Proper water pipe connection should be provided
through canal
2 Colony Punch List Colony Punch list points have not been attended yet
MISCELLANEOUS
Sr No Description Problems/Remarks
1 Maintenace Workshop No Maintenace Workshop is present at grid
2 P&I Lab NO P&I Lab is present at grid
Current vehicle at grid station is in bad condition a new
3 New Vehicle vehicle should be provided
4 Offices for A.Es There are no offices for A.Es at the grid station
RA

Current Status

TSG has performed the testing on the battery


banks and results are pending at the moment.

Higher ups has been informed time and again


but no action has been taken yet

Higher ups has been informed time and again


but no action has been taken yet

Matter has been informed time and again to


EHV-1
Matter has been informed time and again to
EHV-1
TS
Current Status
Matter is in notice of EHV-I

Current Status

Current Status

Matter has been informed to higher ups


Matter has been informed to higher ups

Current Status
Matter has been informed to higher ups
Matter has been informed to higher ups
Informed to higher ups
Matter has been informed to higher ups
220kV GRID STATION NTDC CHISHTIAN
GRID ISSUES
Sr No Equipment Detail of Problems
NIL
TRANSMISSION LINE CONSTRAINTS
Sr No Transmission Line Details
NIL
CONSTRAINTS DUE TO DISCOS
Sr No Description Details

02 Nos. 160MVA transformers MEPCO authority can shift the load from Yousafwala,
1 are energized but they are not Kassowal and Vehari grid stations to Chishtian grid station. It
fully loaded. will share the load of above mentioned grid stations.

There is a dire need of replacement of defective/faulty


relays under this region. Request for demand of
DEFECTIVE / FAULTY
2 replacement of defective relays has been sent to GM
RELAYS
(GSO) NTDCL Lahore by this office, vide No.2332
dated 14-04-2017.

The 220KV T/L Multan-T.T.Singh CCT-1&2 was


constructed in 1960. The height of these old towers is 85-
feet which is very less as per specification of 220KV
T/Lines. The transmission line is passing through
EXTENTION IN HEIGHT OF
3 populated area. Therefore, extension in the towers height
TOWERS
is necessary. Letter has been written to PD (EHV-II)
Multan vide this office letter No.2585-87 dated 24-04-
2017 for preparation of as-built plan and profile of
subject transmission line.
Requirement of major 500/220KV equipment of grid
stations has been prepared in respect of GSO Region
Multan which includes 500KV, 220KV and 132KV
circuit breakers, CTs, CCVTs, isolators, surge arrestors,
MAJOR SPARE EQUIPMENT
4 220V and 110V DC battery banks
REQUIRED
Requirement of major equipment in spare for GSO
NTDCL region Multan has been sent to GM (GSO)
NTDCL Lahore vide this office letter No.2332 dated 14-
04-2017.

CIVIL WORK
Sr No Civil Work Remarks
NIL
MISCELLANEOUS
Sr No Description Problems/Remarks

01 No. post of XEN P&I at 500KV grid station Yousafwala


and 02 No. posts of Sr. Engineers at 220KV grid station Okara
SHORTAGE OF ENGINEERS and 220KV grid station Chishtian are vacant. Posts of 20 Nos.
1
AND STAFF Assistant Managers / Junior Engineers are also vacant as per
vacancy statement sent to GM (GSO) NTDCL Lahore from
this office, vide No.2124-25 dated 06-04-2017.
HTIAN

Current Status

NTS
Current Status

S
Current Status

In progress
Current Status

Current Status

Anda mungkin juga menyukai