Page 1 of 13
Issue B
September 1998
SECTION PAGE
SITE TESTING AND COMMISSIONING OF PROTECTIVE
EQUIPMENT 1 4-8
Basic approach of commissioning 1.1 4
Mechanical inspection and ohmmeter checks 1.2 5
Insulation checks 1.3 6
General notes on measuring instruments 1.4 6
DC. Auxiliary Supplies 1.5 6
Test Equipment 1.6 6
Reference results for future maintenance 1.7 7
Faulty Relays 1.8 7
Commissioning flow-chart summary 1.9 8
SECTION PAGE
INITIAL TESTS 23.13 397
INSULATION TESTS 23.14 397
CURRENT TRANSFORMER: 23.15 397/398
Polarity 23.15.1 397
Ratio 23.15.2 397
Magnetisation Curve 23.15.3 397/398
VOLTAGE TRANSFORMER : 23.16 398/399
Polarity 23.16.1 398
Ratio 23.16.2 398
Phasing 23.16.3 398/399
SECONDARY INJECTION : 23.17 399/407
Equipment: Test Block & Plug 23.17.1 399/400
Relays: 0/C & E/F 23.17.2 400/403
Differential 23.17.3 403
Pilot Wire 23.17.4 403/404
Negative Phase 23.17.5 404
Sequence
Directional 23.17.6 404/405
Distance 23.17.7 405/407
DC. Operated 23.17.8 407
PRIMARY INJECTION: 23.18 407/419
General 23.18 407
Relays: O/C & E/F 23.18.1 407/408
Directional 23.18.2 408/411
Generator Diff. 23.18.3 411
Transformer Diff. 23.18.4 412/414
Restricted E/F 23.18.5 414
Pilot Wire 23.18.6 414/416
Busbar 23.18.7 416/418
Negative Phase 23.18.8 419
Sequence
Check for general damage, tightness of connections, correctness of wiring and wire
numbers, according to the relevant schematic diagrams and wiring diagrams.
(See Section 2 for applicable checks on relays).
1.1.3 Insulation resistance tests between all independent circuits and all circuits
to earth.
C.T. ratio, polarity and magnetism - curve checks are normally recommended.
Tests are detailed in Section 23 of "PRAG".
These are designed to prove the basic operation of each relay/relay scheme
independently.
These are designed to prove the scheme stability for external faults and the
effective current setting for internal faults. The directional properties of relays,
where relevant are normally proven with the system on load.
Before removing covers from relays, ensure the area is relatively free from dust - it
can easily jam bearings etc., and destroy contact reliability.
Typical checks that can be carried out prior to serious electrical testing include :
1.2.1 A basic mechanical inspection to ensure freedom from general damage in transit.
1.2.2 A check to ensure the right relay is fitted in the right case - Serial Numbers and
Model Number.
1.2.4 That the correct external resistor is fitted in the right place (where relevant).
1.2.5 The C.T. shorting switches are fitted across all C.T. circuits, and function correctly
when the relay is withdrawn.
1.2.6 That the trip isolating switch works (lower L.H. "red" cradle latch on measuring
relays fitted to the conventional draw-out case only).
1.2.7 That unit contacts wire to the right terminals. Simple ohmmeter checks to the
relevant relay wiring diagram takes little time and may well prove worthwhile.
1.2.8 That contact pressures and follow thoughts are approximately correct. Pressures
can be carefully assessed on accessible units with a probe (screwdriver) and
compared with similar contacts on other such units.
Pressure testing, for example, 2KV rms. for 1 min, has been carried out on each
individual relay on manufacture. Normally insulation checks on site are limited to
DC. insulation resistance checks only. Where pressure tests are required, possibly
by switchgear manufacturers, either static relays should be temporarily removed, or
extreme care should be taken to ensure that the voltage is not suddenly applied.
Solid connections should be made and the voltage slowly increased to the required
(2kV) level - held for a nominal time, then reduced to zero.
In practice, site checks are preferably carried out with a 500V (or 1000V) DC.
insulation tester. Where static circuitry is employed, as is often the case, a
"brushless" type of insulation tester should be used, since worn brushes on the
older forms of testers can promote spikes in excess of 5kV.
Although the resistance of circuits to earth is often only checked, ideally each
electrically separate circuit should also be checked to all other circuits. The
following approach is suggested :
Connect the accessible terminals of each independent circuit together.
Connect all circuit groups so formed together and solidly link to earth.
Isolate each circuit group in turn, removing station circuit earth links as necessary,
and test between this group and all the remaining groups still linked to earth.
Having checked the insulation of all circuits, ensure that all station earthing links
are replaced.
Insulation levels vary:- over 100 Mohms may he obtained on a small installation,
but on a few Mohms where wiring is extensive. humidity is a major influencing
factor and should be considered when the results are to be used as a reference for
future insulation checks to detect deterioration.
Care should be taken that all associated circuitry is kept clear of unauthorised
personnel during the insulation tests. It should also be remembered that cubicle
capacitance may maintain a reasonable charge even after the test has finished - a
few seconds should be left before attempting to disconnect leads.
Generally relays are designed to tolerate a maximum ripple content of 12% (peak
to peak ripple as a % of the mean DC. component). Damage to the static circuitry
of some relays may result if a unsmoothed supply is used. Relays should definitely
NOT be energised directly off battery charges without the batteries being
connected.
Test equipment should give sinusoidal outputs and ideally should be a true replica
of system pre-fault and fault conditions, especially when testing the "Distance"
relays. If so, the test set can be used on any such relay with confidence,
irrespective of relay manufacturer. If it does not represent the systems, results
may be incorrect and confusing. The instructions of the relay manufacturer
recommending its use should be followed specifically.
Experience has shown that suspicions of faulty relays are often unfounded. It is
easy to make a simple mistake on testing and one should first suspect the test
equipment, it's wiring, the instruments involved and the method of test, especially
if the latter differs from that recommended. A simple substitution of the "faulty"
relay with a known "good" relay of the same type is often conclusive. Note that
precautions against ESD (Electro Static Discharge) must be taken when handling
the internal circuitry of any relay involving electronic circuitry (see Section 3.7).
Insulation Tests
Stability tests
Directional properties
The integrity of the complete trip circuit, including circuit breaker should be
checked on at least every maintenance outage, but generally as regularly as
practical, or though advisable by the appropriate authorities. The use of trip-circuit
supervision relays reduces the risk of failure being undetected.
Generally recommended maintenance tests are little more than a repeat of the
"secondary injection tests" recommended in the appropriate relay commissioning
instruction. These instructions are generally readily available for all but the
simplest of relays. Maintenance should include the following:
Many solvents are commercially available, but extreme care should be exercised.
Damage to some of the many materials used in the relay construction may result.
Although appearing to solve the immediate problem, long-term chemical reactions
may be promoted and these may easily lead to complete catastrophic failures.
Many solvents MAY BE suitable, but unless LIFE tests, or ACCELERATED LIFE
tests have been carried out on the particular range of relay components, no
guarantees can be given. One solvent has been used on relays for many years at
These are not recommended. Any form of lubricating film will promote the build-up
of dirt and dust that eventually may lead to the complete failure of the contact or
bearing. Relay surfaces should be left dry. Dry lubricants are occasionally used
on some electro-mechanical relays.
The contact burnisher found in the tool-kit available from the company is
recommended. Many contact burnishers commercially available are very abrasive
and leave relatively deep groves in the contact surface (when viewed under a
microscope). the grooves trap dust, and an unreliable contact results. Although
their use may be warranted on a badly pitted "industrial use" type of contact, the
contact should be finally "polished" using the recommended burnishers.
These should be considered critical for correct reliable contact operation. All
adjusted contact settings should remain in the "tolerance bands" laid down for the
particular type of unit. (See servicing data for the particular relay).
3.5 DUST REMOVAL
Compressed air can be used with extreme care. It should be clean and dry (test
on sheet of clean white paper). Ensure that it never gets directed towards delicate
springs or mechanisms. A clean "DUCKS FEATHER" is very useful for wiping or
"flicking" dust off relay surfaces, especially from inverse-time disc relays.
One should first question the reason why the re calibration is necessary. If
successive maintenance tests have shown a progressive trend, it may be that a
component is at the end of its useful life and is gradually failing. The cause may
however be dust or dirt on bearing surfaces that should be removed before re
calibration is undertaken. The suitability and accuracy of the test equipment must
also be queried.
To assure ourselves and the interested authorities, that the overall protective
system functions correctly.
C.T. Ratio
C.T. Polarity C.T. Mag. Curve C.T's still connected to the
(+ C.T. Mag. Curve) relay