PROYEK : PEMBANGUNAN WORKSHOP FACILITY

PAKET PEKERJAAN : WOSA + PEKERJAAN TAMBAH


LOKASI : PT. PAMAPERSADA NUSANTARA DISTRICT SMMS, SEKAKO - KALIMANTAN TENGAH

REKAPITULASI AKHIR

UNIT PRICE
NO JENIS PEKERJAAN UNIT VOL
(RP)

1 WOSA ls 1 941,324,519.87

2 PEKERJAAN TAMBAH ls 1 471,863,728.94

Sub Total
PPn 10%
Total

Jakarta, 11 Desember 2018

Andy Sugiarto
AKO - KALIMANTAN TENGAH

Rev 2

TOTAL PRICE
(RP)

941,324,519.87

471,863,728.94

1,413,188,248.81
141,318,824.88
1,554,507,073.69
PROYEK : PEMBANGUNAN WORKSHOP FACILITY
PAKET PEKERJAAN : WOSA
LOKASI : PT. PAMAPERSADA NUSANTARA DISTRICT BRCB, BERAU - KALIMANTAN TIMUR

REKAPITULASI AKHIR

UNIT PRICE TOTAL PRICE


NO JENIS PEKERJAAN UNIT VOL
(RP) (RP)

I. BANGUNAN WOSA
1. PEKERJAAN TANAH ls 1.00 11,508,920.00 11,508,920.00
2. PEKERJAAN STRUKTUR ls 1.00 204,298,377.50 204,298,377.50
2. PEKERJAAN BAJA ls 1.00 193,329,657.39 193,329,657.39
3. PEKERJAAN ATAP ls 1.00 104,803,936.68 104,803,936.68
4. PEKERJAAN DINDING DAN PLAFOND ls 1.00 58,895,181.66 58,895,181.66
5. PEKERJAAN PASANGAN PINTU / JENDELA ls 1.00 24,796,168.67 24,796,168.67
II. PEKERJAAN SARANA LUAR ls 1.00 217,226,253.87 217,226,253.87
III. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL ls 1.00 56,466,024.10 56,466,024.10
IV. PEKERJAAN PERSIAPAN ls 1.00 70,000,000.00 70,000,000.00

Sub Total 941,324,519.87


Pembulatan 941,000,000.00
4,278,747.82
PROYEK : PEMBANGUNAN WORKSHOP FACILITY ###
PAKET PEKERJAAN : WOSA
LOKASI : PT. PAMAPERSADA NUSANTARA DISTRICT BRCB, BERAU - KALIMANTAN TIMUR

REKAPITULASI AKHIR
VOL UNIT PRICE TOTAL PRICE
NO JENIS PEKERJAAN UNIT
GP (RP) (RP)

I. BANGUNAN WOSA

1. PEKERJAAN TANAH 11,508,920.00


1 Galian tanah untuk pondasi m³ 19.30 110,000.00 2,123,000.00
2 Urugan tanah kembali m³ 11.44 90,000.00 1,029,420.00
3 Pemadatan tanah m² 220.00 20,000.00 4,400,000.00
4 Pasir urug , t = 10 cm dibawah pondasi & plat lantai m³ 1.93 550,000.00 1,061,500.00
5 Lantai kerja , t = 5 cm dibawah plat lantai m³ 1.93 1,500,000.00 2,895,000.00
###
2. PEKERJAAN STRUKTUR 204,298,377.50
1 Dudukan Tangki m³ 0.64 6,872,409.64 4,398,342.17
2 Pondasi P1-800x800x150 m³ 1.15 5,417,349.40 6,240,786.51
3 Tie beam 15 x 25 m³ 2.85 6,872,409.64 19,586,367.47
4 Slab Lantai dasar t = 15 cm m³ 33.00 3,745,458.88 123,600,143.14
5 Pedestal 200x300 - H=1.5 m m³ 1.08 7,182,891.57 7,757,522.89
6 Ring balok 15 x 15 cm m³ 1.64 6,872,409.64 11,287,932.83
7 Ramp masuk + keluar t = 15 cm m³ 2.25 3,745,458.88 8,427,282.49
8 Floor Hardener m2 200.00 115,000.00 23,000,000.00
###
3 PEKERJAAN BAJA 193,329,657.39
1 Kolom K1 - WF 150.75 kg 554.40 26,325.30 14,594,746.99
2 Kolom K2 - 2xCNP 125.50.20.2.3 kg 39.75 26,325.30 1,046,342.97
3 Balok B1 - 2xCNP 125.50.20.2.3 kg 596.20 26,325.30 15,695,144.58
4 Rafter R1 - WF 150.75 kg 956.62 26,325.30 25,183,329.86
5 Rafter R2 - CNP 125.50.20.2.3 kg 37.41 26,325.30 984,802.65
6 Gording G1 - CNP 125.50.20.2.3 kg 1,491.67 26,325.30 39,268,680.84
7 Rangka Cladding - CNP 125.50.20.2.3 kg 745.25 26,325.30 19,618,930.72
8 Dudukan Listplank - CNP 125.50.20.2.3 kg 218.61 26,325.30 5,754,886.35
9 Trekstang bh 80.00 150,000.00 12,000,000.00
10 Ikatan Angin - Besi Beton dia. 12 bh 4.00 350,000.00 1,400,000.00
11 Base Plate t=10 mm kg 21.41 26,325.30 563,542.43
12 Angkur M16 bh 48.00 350,000.00 16,800,000.00
13 Baut HTB 16 bh 370.00 35,000.00 12,950,000.00
14 Stiffner Plate t=8mm kg 187.00 26,325.30 4,922,831.33
15 Connector Plate t=8mm kg 187.00 26,325.30 4,922,831.33
16 Cat Baja kg 5,035.31 3,500.00 17,623,587.35
###
PROYEK : PEMBANGUNAN WORKSHOP FACILITY ###
PAKET PEKERJAAN : WOSA
LOKASI : PT. PAMAPERSADA NUSANTARA DISTRICT BRCB, BERAU - KALIMANTAN TIMUR

REKAPITULASI AKHIR
VOL UNIT PRICE TOTAL PRICE
NO JENIS PEKERJAAN UNIT
GP (RP) (RP)

3. PEKERJAAN ATAP 104,803,936.68


1 Atap Zincalumn t=0.4 mm m² 316.80 224,238.13 71,039,307.87
2 Penutup Cladding Zincalumn t=0.4 mm m² 87.00 224,238.13 19,508,717.22
3 Nok atap seng m¹ 22.00 200,000.00 4,400,000.00
4 Flashing m¹ 25.71 150,000.00 3,855,911.59
5 Safety Roof ls 1.00 6,000,000.00 6,000,000.00
###
4. PEKERJAAN PLAFOND DAN DINDING 58,895,181.66
1 Pasangan dinding batako m² 73.00 147,349.40 10,756,506.02
2 Plesteran dinding m² 146.00 95,000.00 13,870,000.00
3 Pengecatan dinding bata m² 146.00 40,000.00 5,840,000.00
4 Dinding Kawat Harmonika m² 108.00 116,137.88 12,542,891.57
5 Dinding Partisi Gypsum + GRC 48.00 297,941.77 14,301,204.82
6 Plafond gypsum t= 9mm m² 8.00 151,976.77 1,215,814.19
7 Plafond GRC t= 4mm m² 2.00 184,382.53 368,765.06
###
5. PEKERJAAN PASANGAN PINTU / JENDELA 24,796,168.67
1 Pintu baja type P1 unit 1.00 15,000,000.00 15,000,000.00
2 Pintu P2 unit 1.00 4,207,831.33 4,207,831.33
3 Pintu P3 - PVC unit 1.00 2,559,036.14 2,559,036.14
4 Jendela J3 unit 1.00 3,029,301.20 3,029,301.20
###
II. PEKERJAAN SARANA LUAR 217,226,253.87
1 Grounding Control Box 600x600 unit 4.00 1,500,000.00 6,000,000.00
2 Pembuatan Oil Trap uk 2000x6000x1500 unit 1.00 35,394,586.45 35,394,586.45
3 Rabat keliling t=7 cm m³ 7.60 2,909,302.33 22,110,697.67
4 Gutter dalam Bangunan m' 60.00 1,130,301.25 67,818,074.89
5 Saluran keliling bangunan m' 76.00 1,130,301.25 85,902,894.86
6 Bak Control bh 5.00 1,500,000.00 7,500,000.00
###
III. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 56,466,024.10
A MEKANIKAL
1 Pipa Air Kotor Wavin AW 4" m' 15.00 175,000.00 2,625,000.00
2 Pipa Air Kotor Wavin AW 3" m' 15.00 150,000.00 2,250,000.00
3 Pipa Air Bersih Wavin AW 1" m' 15.00 125,000.00 1,875,000.00
4 Pipa Air Bersih Wavin AW 1/2" m' 15.00 100,000.00 1,500,000.00
5 Fitting & Aksesoris ls 1.00 1,500,000.00 1,500,000.00
6 Kloset Jongkok unit 1.00 641,024.10 641,024.10
7 Kran Air unit 1.00 350,000.00 350,000.00
8 Floor Drain bh 1.00 350,000.00 350,000.00
9 Floor Clean Out bh 1.00 350,000.00 350,000.00
10 Torn Air Bersih kap. 500 liter + Menara + Instalasi ls 1.00 10,000,000.00 10,000,000.00

B ELEKTRIKAL
1 Lampu TKO V Shape FL 1 x 36watt unit 8.00 550,000.00 4,400,000.00
2 Lampu Fitting + Bohlam 10 Watt unit 3.00 250,000.00 750,000.00
3 STOP KONTAK 1phase 16A Waterproof bh 1.00 150,000.00 150,000.00
4 STOP KONTAK 3phase 32A Waterproof bh 1.00 500,000.00 500,000.00
5 Saklar Waterproof bh 1.00 350,000.00 350,000.00
6 Saklar SAKLAR Engkel bh 1.00 75,000.00 75,000.00
7 Saklar SAKLAR SERI bh 1.00 125,000.00 125,000.00
8 Instalasi Kabel NYM 3x2,5 mm2 + conduit Lampu bh 11.00 475,000.00 5,225,000.00
9 Instalasi kabel stopkontak 1 ph/ 16 A ls 1.00 475,000.00 475,000.00
10 Instalasi Kabel Stopkontak 3phase 32A ls 1.00 475,000.00 475,000.00
11 Material bantu ls 1.00 5,000,000.00 5,000,000.00
12 Panel PP WOSA bh 1.00 17,500,000.00 17,500,000.00

IV PEKERJAAN PERSIAPAN 70,000,000.00


###
PROYEK : PEMBANGUNAN WORKSHOP FACILITY
PAKET
: PEKERJAAN TAMBAH
PEKERJAAN
LOKASI : PT. PAMAPERSADA NUSANTARA DISTRICT BRCB, BERAU - KALIMANTAN TIMUR

REKAPITULASI AKHIR

NO JENIS PEKERJAAN SPESIFIKASI UNIT

I. PEKERJAAN STRUKTUR ls

II. PEKERJAAN ARSITEKTUR ls

III. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL ls

Sub Total

PROYEK : PEMBANGUNAN WORKSHOP FACILITY


PAKET
: PEKERJAAN TAMBAH
PEKERJAAN
LOKASI : PT. PAMAPERSADA NUSANTARA DISTRICT BRCB, BERAU - KALIMANTAN TIMUR

REKAPITULASI AKHIR
NO JENIS PEKERJAAN SPESIFIKASI UNIT

I PEKERJAAN STRUKTUR
1 Siku Pelindung Pelat Lantai L 70.70.5 m'
2 Rangka Atap dan Oil Storage WS m2
3 Rangka Atap dan Atap Oil Storage WOSA CNP 125.50.20.2.3 m2
4 Rabat Beton Oil Storage - t=7cm Uk. 1800x900 m3
5 Menara Air - H=150cm Uk. 100x100 unit
6 Tanki Air 550 liter unit
7 Railing Oil Trap Uk. 5500x1700x1000 m'

II PEKERJAAN ARSITEKTUR
1 Pintu P2 - Uk. 900x2150 unit
2 Pintu J2 - Uk. 1550x1350 unit
3 Pintu J3 - Uk. 800x1350 unit
4 Partisi Gypsum - t=9mm m2
5 Loket - Uk. 700x400 unit
6 Jendela J4 - Uk. 800x800 unit
7 Grounding Bangunan - Uk. 40x40 unit

III PEKERJAAN MEP


1 Stop Kontak 1 gang - 16A bh
2 Stop Kontak UPS 1 gang - 16A bh
3 Stop Kontak Waterproof - 16A bh
4 Instalasi Stop Kontak 1 gang NYM 3x2.5 mm2 ttk
5 Instalasi Stop Kontak UPS 1 gang NYM 3x2.5 mm2 ttk
6 Instalasi Stop Kontak Waterproof NYM 3x2.5 mm2 ttk
7 Outlet Data RJ 45 bh
8 Instalasi Data Belden CAT 6 ttk
9 AC 1/2 PK Panasonic R32 unit
10 Instalasi Pipa Refrigerant & Kabel Power ttk
LIMANTAN TIMUR

VOL UNIT PRICE TOTAL PRICE


AKTUAL (RP) (RP)

1.00 294,365,616 294,365,615.94

1.00 51,828,163 51,828,163.00


-
1.00 125,669,950 125,669,950.00

471,863,728.94
Pembulatan 471,000,000.00

LIMANTAN TIMUR

VOL VOL VOL UNIT PRICE TOTAL PRICE


RAB AKTUAL SELISIH (RP) (RP)

294,365,615.94
60 60 122,850 7,371,000.00
163 163 1,041,773 113,205,996.81
20 20 1,041,773 20,835,459.53
3.78 3.78 2,909,302 10,997,162.79
1 1 7,500,000 7,500,000.00
1 1 10,000,000 10,000,000.00
14.9 14.9 755,034 11,250,000.00

51,828,163.00
18 22 4 3,924,107 15,696,428.00
20 22 2 5,591,690 11,183,380.00
4 5 1 3,529,166 3,529,166.00
650.02 671.02 21 250,000 5,250,000.00
2 2 1,116,666 2,233,332.00
1 1 3,435,857 3,435,857.00
2 5 3 3,500,000 10,500,000.00

125,669,950.00
21 80 59 80,000 4,720,000.00
101 101 175,000 17,675,000.00
5 5 175,000 875,000.00
21 80 59 375,000 22,125,000.00
101 101 375,000 37,875,000.00
5 5 375,000 1,875,000.00
57 57 90,350 5,149,950.00
57 57 375,000 21,375,000.00
2 2 4,800,000 9,600,000.00
2 2 2,200,000 4,400,000.00